Skip to main content

Privacy

A note about cookies

Essential cookies keep this site running. Optional analytics help us understand what's working, only enabled if you accept.

LIBRARY
QuebecExtension of timeJurisdiction article

The Civil Code framework for delay in Quebec

The Code civil du Québec contains no provision on time for completion, delay or extension of time. Arts 2098–2129 were read individually. Time appears once, at art 2102, as a pre-contractual disclosure duty on the contractor. Time in Quebec is entirely a creature of contract, and a prolongation claim is pleaded as the owner's fault under art 1458.

Reviewed Aug 8, 202616 min read18 sources

At a glance

Quebec
Class
Framework
Jurisdiction
Quebec, Canada, civil law
Scope
Quebec only
Primary instrument
Code civil du Québec, arts 2098–2129
§ 00

Key facts

  1. 01

    The short answer

    The Code civil du Québec supplies no completion date, no extension mechanism, no list of excusable events, no delay-notice regime and no delay-damages regime for the contrat d'entreprise. Every article from 2098 to 2129 was read individually.

  2. 02

    The single mention of time

    Art 2102 C.c.Q., a pre-contractual disclosure duty on the contractor as to « le temps nécessaire ». It is not a completion obligation and it does not run the other way.

  3. 03

    Where the extension comes from

    Entirely from the form. CCDC 2CcQ – 2024 GC 6.5 on private and institutional work, the MTMD Cahier des charges et devis généraux on provincial roadworks, which has no dedicated extension-of-time clause at all, Ville de Montréal CCAG art 5.1.9 on municipal work.

  4. 04

    How the claim is pleaded

    As fault, in contractual liability under art 1458 C.c.Q., not as an entitlement to additional payment under the contract.

  5. 05

    Why not as entitlement

    On a forfait contract, art 2109 C.c.Q. para 2 refuses a price increase for changes in the cost of labour or materials and para 3 holds the price unchanged notwithstanding modification of the conditions d'exécution. The only exit is agreement, an avenant.

  6. 06

    The burden on the contractor

    Meeting the completion date is an obligation de résultat. The contractor must positively prove force majeure or the owner's fault. Proving the absence of its own fault is not enough (Ville de Pointe-Claire, 2023 QCCA 1565).

  7. 07

    What "completion" means

    Fin des travaux is statutory: art 2110 C.c.Q., the work executed and fit for its intended use, and the court determines it, not the certifier. Substantial performance and Ready-for-Takeover are not Quebec concepts.

  8. 08

    No hardship relief

    Quebec has no imprévision. The Supreme Court said so expressly in Churchill Falls, 2018 SCC 46. France codified hardship at art 1195 Code civil in 2016. Quebec did not follow.

The Code civil du Québec says nothing about time for completion. That single absence explains almost everything that surprises a common-law practitioner about a Quebec delay claim: why the extension mechanism is whatever the form happens to supply, why the claim is pleaded as fault rather than as entitlement, and why the contractor carries a burden of proof that its Ontario counterpart does not.

Every article of the contrat d'entreprise chapter, arts 2098–2129 C.c.Q.1, was read individually for this corpus. There is no default completion date, no extension-of-time mechanism, no enumerated list of excusable or compensable events, no delay-notice regime and no delay-damages regime. Time is mentioned exactly once, at art 2102 C.c.Q.2, and it points the wrong way for a delay claim: it is a pre-contractual disclosure duty on the contractor to tell the client, before the contract is made, what the task involves and « le temps nécessaire » to perform it.

This page works out the consequences of that absence. It is the foundation for the rest of the Quebec material at the extension-of-time hub for Quebec.

§ 01

What the Civil Code of Québec provides on time for completion

Nothing. Arts 2098–2129 C.c.Q., the entire contrat d'entreprise chapter, contain no default completion date, no extension mechanism, no list of qualifying events, no notice regime and no delay-damages regime. Time appears once, at art 2102 C.c.Q., as a pre-contractual disclosure duty owed by the contractor to the client. This is a recorded negative finding, not an inference from silence.

Question a delay practitioner asks of the CodeAnswer
Is there a default rule fixing when the work must be completed?No
Is there a statutory extension-of-time mechanism?No
Is there a statutory list of excusable or compensable delay events?No
Is there a statutory notice regime for delay or extension of time?No in this chapter
Is there a statutory liquidated-damages or delay-penalty regime?No in this chapter. The general law of the clause pénale applies
Is time mentioned at all in arts 2098–2129?Once: art 2102, a pre-contractual disclosure duty on the contractor

Layer: jurisdictional, and it rests on the Code itself. Arts 2098–2129 C.c.Q. were verified against LégisQuébec in French and in the official English. Nothing in this table depends on case commentary.

Several articles in the chapter sit adjacent to time without creating a time obligation, and it is worth naming them so that they are not pressed into service as one. Art 2100 C.c.Q. imposes prudence and diligence: a conduct standard, not a deadline. Art 2110 C.c.Q.3 defines fin des travaux, the end point of the work, not the date by which it must be reached. Art 2117 C.c.Q. obliges the client not to hinder progress. None of these supplies a completion date or a mechanism for moving one.

One consequence follows immediately and should be stated before anything else. "Time at large" does not exist in Quebec. No statutory, judicial, doctrinal or professional source uses the concept. Where a term is left indeterminate, art 1512 C.c.Q.4 requires the court, on the application of either party, to fix the term having regard to the nature of the obligation and the situation of the parties. That is the opposite of the common-law consequence: Quebec fills the gap rather than dissolving the obligation.

§ 02

Where the extension actually comes from, if the Code supplies none

From the contract, and from nowhere else. Because the Code civil du Québec contains no extension-of-time machinery, the mechanism on any Quebec project is whatever the executed form supplies. On private and institutional work that is normally CCDC 2CcQ – 2024 GC 6.5, on provincial roadworks the MTMD Cahier des charges et devis généraux, which has no dedicated extension clause at all, on municipal work the Ville de Montréal CCAG.

SectorFormThe extension provision
Private and institutionalCCDC 2CcQ – 20245, released 21 May 2024GC 6.5 Delays, same number and heading as CCDC 2 – 2020. The operative CcQ wording is not publicly available and is unverified, including whether the 10 Working Days notice period is retained
Provincial roadworksMTMD CCDG6, Construction et réparation, édition 2026None. There is no dedicated extension-of-time clause and no express delay-penalty clause. Extensions run, if at all, through the avenant machinery at art 8.4. The claim procedure is at art 8.8 in editions from 2017
Municipal (Montréal)Ville de Montréal CCAG7, rév. 2022-12-13Art 5.1.9 Modification apportée aux délais, with penalties at art 5.1.12 and claims at art 4.3.11

Layer: form-default. Clause numbers and headings are verified. The CCDC 2CcQ – 2024 GC 6.5 operative text is not, and CCDG numbering is edition-sensitive. Read the executed contract and its supplementary conditions before relying on any row.

The MTMD position deserves to be said without hedging, because practitioners lose time looking for a clause that is not there. The CCDG has no dedicated extension-of-time clause and no express delay-penalty clause. That is a recorded negative finding. A contractor on a provincial roadworks contract that expects to find a "CCDG EOT clause" will not find one. The penalty, if there is one, is in the devis spécial, and the route to more time is a contract amendment.

The practical corollary for anyone drafting or reviewing in Quebec is that an omission that would be survivable elsewhere is not survivable here. In a common-law jurisdiction, a contract with a completion date and a defective or missing extension mechanism produces time at large. In Quebec it produces art 1512 C.c.Q. (a judicially fixed term) and a penalty that is defeated on the merits or reduced, not voided.

§ 03

Why a Quebec prolongation claim is pleaded as fault, not as entitlement

A Quebec prolongation claim is a claim in contractual liability under art 1458 C.c.Q.8 for the owner's fault. It is not a claim for additional payment under the contract, because on a forfait (fixed-price) contract, art 2109 C.c.Q.9 says the price does not move. This is the single most important structural difference from a common-law lump sum, and the reason common-law variation instincts mislead in Quebec.

Art 2109 C.c.Q. does two separate things in its second and third paragraphs, and both matter to delay.

Paragraph 2 refuses the contractor an increase in the price for the opposite reason to the one that would let the client claim a reduction: in practice, changes in the cost of labour or materials. Steel, fuel, lumber and wage escalation are the contractor's risk on a forfait, absolutely.

Paragraph 3 is the one that bites on a delay claim. In the official English: "Unless otherwise agreed by the parties, the price fixed by the contract remains unchanged notwithstanding any modification of the original terms and conditions of performance." The French is « les conditions d'exécution initialement prévues »: the conditions of performance, which on their face embrace sequence, method, working conditions and timing. A change to them does not move the price.

The error to avoid: pleading a Quebec prolongation claim as an "entitlement to additional payment under the contract" when the contract is forfait and contains no such entitlement. It meets art 2109 C.c.Q. head-on and fails.

Art 2109 C.c.Q. supplies its own exit, and only one: "unless otherwise agreed by the parties". That agreement is an avenant, a contract amendment. Procureur général du Québec c. Opron inc.10 2022 QCCA 98 is reported as holding that the CCDG claim procedure is an exception to the rule that a forfait contractor performs at a profit or a loss, that it must be interpreted narrowly, and that it does not apply where the claim arises under an avenant, which may be verbal. The practical instruction is unglamorous and reliable: if the parties agree a way forward during the works, write the agreement up the same day.

Where there is no avenant, the claim must be re-characterised as fault. The dominant route is contractual fault of the client under art 1458 C.c.Q., with breach of the duty to inform and abuse of right as the supporting theories. The consequence for pleading is that the elements are the civil-law elements (fault, causation, injury) and not the four elements a common-law form builds around a qualifying event.

§ 04

The completion date is an obligation de résultat, and the burden sits on the contractor

Meeting the completion date in Quebec is an obligation de résultat. An obligation of result rather than of means. Per Ville de Pointe-Claire c. Asphalte Béton Carrières Rive-Nord inc.11 2023 QCCA 1565, the contractor must positively prove force majeure or the owner's fault. Proving the absence of its own fault is not enough. Delay presumes contractor responsibility, and that presumption is the thing being displaced.

This is a genuine allocation of risk, not a rhetorical one. In a jurisdiction where the completion obligation is one of means, a contractor that shows it behaved reasonably has answered the case. In Quebec it has not: it has to identify the excusing cause, prove it, and prove the causal link between it and the failure to complete on the contractual date.

For a compensable delay (one where the contractor seeks money as well as time) the burden is heavier still. The contractor must additionally prove the causal link to the critical path, the quantum, and its compliance with the contractual claim procedure. None of those requirements comes from the Code. The first two are ordinary civil-law causation and proof. The third is a creature of the form.

Layer note: the obligation de résultat characterisation rests on secondary law-firm commentary reporting Ville de Pointe-Claire, 2023 QCCA 1565. No Quebec judgment was read in original text for this corpus, and no paragraph pinpoint is available.

§ 05

The three-category delay taxonomy: same shape, different proof rules

Quebec practice sorts delay into three categories (retards inexcusables, retards compensables and retards excusables non compensables) and that is the same shape the common-law standard forms use. The divergence is in the proof rules and the causation test, not in the taxonomy. A reader who recognises the categories will otherwise assume more similarity than exists.

CategoryCauseTimeMoney
Retards inexcusablesThe contractor's own default: defective work, poor planning, resourcing, late ordering, subcontractor failureNoThe contractor pays the owner's damages or the penalty
Retards compensablesThe owner's acts: change orders, suspensions, late site delivery, late approvals, deficient designExtensionExtension and compensation
Retards excusables (non compensables)Force majeure, strikes, lock-outs, abnormally adverse weather, third-party acts meeting the doctrinal cause étrangère (external cause) test, the Code's own term at art 1470 C.c.Q. being superior forceExtensionNo compensation, the contractor bears its own extended general conditions

Layer: jurisdictional as to the burden allocation, which rests on the Code and on secondary case commentary. Form-default as to the time and money columns, which are supplied by the contract and not by the C.c.Q. The categories have no statutory source in arts 2098–2129 C.c.Q.

Three differences make the taxonomy behave differently from its common-law twin.

The burden runs the other way at the outset. Delay presumes contractor responsibility. The contractor moves a delay from the first row to the second or third by proving owner fault or force majeure. It does not start in a neutral position and argue about which list an event falls into.

There is no concurrent-delay doctrine to fall back on. No Quebec authority, doctrine or professional commentary on « délais concomitants » as a distinct doctrine was located. Where two causes operate, Quebec apportions fault. A submission built on dominant cause, or on the English default that true concurrency yields time but not money, has no Quebec footing to stand on.

Nothing in the Code says force majeure suspends an obligation or extends time. That is a further recorded negative finding. The suspensive effect a contractor relies on is doctrinal and contractual. It comes from the form's own delay clause, and the Code's own language on force majeure is extinctive rather than suspensive.

The structural point is worth stating for readers arriving from the neutral extension-of-time material. The common-law four-element test (qualifying event, causation to completion, notice and procedure, extent) is a test of entitlement under a contractual mechanism. A Quebec prolongation claim is a claim in liability for fault. Elements one and four have no Quebec statutory content at all, element two becomes ordinary civil-law causation under the damages articles, and only element three survives intact, because the claim procedure is contractual in both systems. Mapping the four elements onto a Quebec claim will produce a pleading that asks the wrong questions in the wrong order. The row-by-row account is at Quebec vs common-law Canada on delay.

§ 06

Fin des travaux is statutory, and the court determines it

Completion in Quebec is defined by statute, not by certificate. Art 2110 C.c.Q. provides that the client is bound to accept the work at the end of the work (la fin des travaux) which occurs when the work has been executed and is fit for its intended use. It is an objective factual state, and the court determines it, not the certifier. Substantial performance and Ready-for-Takeover are not Quebec concepts.

Fin des travaux is not merely a definition. It is the pivot on which several time limits turn.

Prescription. Art 2116 C.c.Q.12 is a deferral provision, not a warranty provision. Prescription of remedies between the parties does not begin to run until fin des travaux (the contractor's prolongation claim and the owner's delay-damages claim alike) and the deferral applies even to items reserved at acceptance. It does not run from acceptance, and it does not run from the delaying event. Commentary describing art 2116 C.c.Q. as a warranty provision running from acceptance is wrong on both counts.

The statutory liabilities. Arts 2118 and 2120 C.c.Q.13 use different triggers and different forms of liability, and the difference is deliberate. Art 2118 C.c.Q. (the five-year liability for loss of the work) runs from fin des travaux, and the liability is solidaire. Art 2120 C.c.Q. (the one-year garantie contre les malfaçons, the warranty against defects of workmanship) runs from réception, acceptance, and the liability is conjointe. Art 2118 C.c.Q. was amended on 24 September 2020 to add le technologue professionnel to the list of persons solidarily liable, a change that post-dates most practitioner texts.

The drafting consequence is direct, and it is the most common defect in a common-law contract used on a Quebec job. Completion triggers written for lien statutes and substantial-performance certification do not engage the Quebec machinery. CCDC 2CcQ – 2024 addresses this by replacing the single CCDC 2 – 2020 milestone with a two-milestone structure, GC 12.1 Ready for Acceptance With Reservation and GC 12.3 Ready for Acceptance Without Reservation, keyed to réception avec réserve and sans réserve under art 2110 C.c.Q. Any delay analysis, penalty calculation or float assessment on that form must be run to the CcQ milestone. Note that neither "Substantial Performance" nor "Ready-for-Takeover" is a defined term in CCDC 2CcQ – 2024.

§ 07

Quebec rejected imprévision, and a reader reasoning from French law will get this wrong

Quebec has no doctrine of imprévision, and it is not the French position. In Churchill Falls (Labrador) Corp v Hydro-Québec14 2018 SCC 46 the Supreme Court of Canada held that the doctrine is not recognised in Quebec civil law, and that any development of analogous concepts must take account of the legislature's deliberate choice not to make it a universal rule. France codified hardship at art 1195 Code civil15 in 2016. Quebec did not follow.

The legislative history is part of the reason the position is stable. The Office de révision du Code civil recommended incorporating imprévision into the recodified Code. The legislature declined, and Quebec courts have relied on that deliberate choice since.

Churchill Falls also fixes the ceiling on what good faith can do. Good faith may serve to protect the equilibrium of a contract but cannot be used to change that equilibrium and impose a new bargain. Good faith in Quebec is a conduct standard governing how a right is exercised. It is not a hardship doctrine and it does not rewrite the bargain.

For a construction delay claim, the rejection of imprévision and art 2109 C.c.Q. are mutually reinforcing. A Quebec contractor cannot obtain relief for cost escalation, materials shortage or extraordinary inflation on a forfait contract by invoking hardship: para 2 of art 2109 C.c.Q. shuts the contractual door and Churchill Falls shuts the equitable one. The only available routes are contractual (an escalation clause negotiated in advance, or an avenant agreed at the time) or fault-based under art 1458 C.c.Q. The industry has responded by drafting: model price-revision clauses circulate in Quebec precisely because the Code supplies none.

§ 08

What is recoverable: art 1613, and the articles that are not the damages articles

Remoteness in Quebec runs on art 1613 C.c.Q.16, not on Hadley v Baxendale. In contractual matters the debtor answers only for damages that were foreseen or foreseeable at the time the obligation was contracted, and even then only for what is « une suite immédiate et directe » of the non-performance. Art 1607 C.c.Q. supplies the causation filter and art 1611 C.c.Q. the two heads, the loss sustained and the profit deprived.

The carve-out inside art 1613 C.c.Q. has no common-law analogue and is worth pleading where the facts support it. Where the failure to perform is due to intentional fault or gross fault (faute lourde), the foreseeability filter falls away entirely. The debtor then answers for all immediate and direct consequences, however unforeseeable they were at formation. At common law, the Hadley limbs are not disapplied for deliberate breach. On a delay file this is a real strategic lever: an owner that deliberately withholds access, or a contractor that abandons the site, is exposed to the full unfiltered chain of direct loss. The « suite immédiate et directe » limit survives gross fault. Only the foreseeability gate falls.

Two articles are routinely misdescribed in delay-claim commentary and should not be cited for quantum. Arts 1612 and 1614 C.c.Q.17 are not general damages provisions: art 1612 C.c.Q. is the trade-secret article, with no application to a construction delay claim, and art 1614 C.c.Q. fixes the discount rate for prospective bodily-injury damages, irrelevant to construction quantum. The general assessment provisions are arts 1607, 1611 and 1613 C.c.Q. The heads of loss themselves (extended site overhead, head-office overhead, finance and plant) are worked in the neutral prolongation and delay costs material, subject throughout to the art 1613 C.c.Q. filter rather than to Hadley.

Two structural limits then close off routes a common-law practitioner would expect to have.

No suing in tort as an alternative. Art 1458 C.c.Q. para 2 is the rule of non-cumul: co-contractants may not opt into the extracontractual regime. There is no Quebec equivalent of concurrent liability in contract and tort between the parties to the construction contract, and no possibility of reframing a contractual delay claim extracontractually because the extracontractual rules produce a better outcome on remoteness, prescription or apportionment.

The claim can be cut short by resiliation. Art 2125 C.c.Q.18 gives the client a statutory unilateral right to resiliate the contract, without cause, even after the work has been begun. Termination for convenience in Quebec is not a matter of contractual grant. Where it is exercised, a live delay claim converts from contractual damages to the compensation measure in arts 2126–2129 C.c.Q. State the limit of what can be said here honestly: the article numbers and subject matter are correct, but the verbatim text of arts 2126–2129 C.c.Q. was not retrieved for this corpus, and whether future profit is recoverable under art 2129 C.c.Q. on a client's unilateral resiliation is unresolved. Read the articles before advising on the measure.

Notes

Sources and authorities

18 cited
  1. *
    Verification, unless noted

    No form text was read in original for this corpus. Clause numbering and content rest on independent secondary sources. Check the executed contract and its supplementary conditions.

  2. 1
    Code civil du Québec, arts 2098–2129, Du contrat d'entreprise ou de serviceC.c.Q., arts 2098–2129

    The whole contract-of-enterprise chapter. It contains no completion date, no extension-of-time mechanism, no list of excusable or compensable delay events, no delay-notice regime and no delay-damages regime. Every article was read individually and the absence is a recorded negative finding.

    LégisQuébec

  3. 2
    Code civil du Québec, art 2102C.c.Q., art 2102

    The contractor or provider of services is bound, before the contract is entered into, to provide the client with any useful information concerning the nature of the task and « le temps nécessaire » to perform it. This is the only place time is mentioned in arts 2098–2129, and it is a pre-contractual disclosure duty on the contractor.

    LégisQuébec

  4. 3
    Code civil du Québec, art 2110, fin des travauxC.c.Q., art 2110

    The client is bound to accept the work at the end of the work. The end of the work occurs when the work has been executed and is fit for its intended use. It is an objective factual state.

    LégisQuébec

  5. 4
    Code civil du Québec, art 1512C.c.Q., art 1512

    Where the parties have agreed to delay the determination of the term and a reasonable period has expired without their doing so, the court may, on the application of either of them, fix the term having regard to the nature of the obligation, the situation of the parties and any appropriate circumstances. The consequence of temporal indeterminacy is judicial gap-filling.

    LégisQuébec

  6. 5
    CCDC 2CcQ – 2024, GC 6.5 DelaysCCDC 2CcQ – 2024 (released 21 May 2024), GC 6.5

    The first CCDC contract designed for the Code civil du Québec. GC 6.5 Delays carries the same number and heading as CCDC 2 – 2020. The operative wording of the CcQ clause is not publicly available and could not be verified, including whether it retains the 10 Working Days notice period. Read the executed contract.

    CCDC

  7. 6
    MTMD, Cahier des charges et devis généraux: Infrastructures routières, Construction et réparationCCDG, édition 2026 (reissued annually) · structure verified from the édition 2024

    Contains no dedicated extension-of-time clause and no express delay-penalty clause. Extensions are handled, if at all, through the contract-amendment machinery at art 8.4 (avenant au contrat). The claim procedure is at art 8.8 in editions from 2017 and was art 9.7 in the December 2000 edition. Clause numbering is edition-sensitive.

  8. 7
    Ville de Montréal, Cahier des clauses administratives généralesVille de Montréal CCAG, rév. 2022-12-13, art 5.1.9 Modification apportée aux délais

    The municipal general conditions carry an express provision on modification of the contract periods at art 5.1.9, with penalties at art 5.1.12 and claims at art 4.3.11.

  9. 8
    Code civil du Québec, art 1458, contractual liability and non-cumulC.c.Q., art 1458

    Every person has a duty to honour the undertakings contracted by them and is liable for injury caused to the other contracting party by failure to do so. Para 2 provides that neither party may then opt to be governed by the rules of extracontractual liability, the rule of non-cumul.

    LégisQuébec

  10. 9
    Code civil du Québec, art 2109, the forfait ruleC.c.Q., art 2109

    Where the contract is a fixed-price (forfait) contract, the client pays the price agreed and the contractor may not claim an increase for the opposite reason (para 2). Unless otherwise agreed by the parties, the price fixed by the contract remains unchanged notwithstanding any modification of the original terms and conditions of performance (para 3).

    LégisQuébec

  11. 10
    Procureur général du Québec c. Opron inc.2022 QCCA 98, Court of Appeal of Quebec

    The CCDG claim procedure is an exception to the rule that on a forfait contract the contractor must perform at a profit or at a loss, and is to be interpreted narrowly. It does not apply where the claim arises under an avenant, which may be written or verbal.

    Find on CanLII

  12. 11
    Ville de Pointe-Claire c. Asphalte Béton Carrières Rive-Nord inc.2023 QCCA 1565, Court of Appeal of Quebec

    Meeting the completion date is an obligation de résultat. The contractor must positively prove force majeure or the owner's fault. Proving the absence of its own fault is not enough.

    Find on CanLII

  13. 12
    Code civil du Québec, art 2116C.c.Q., art 2116

    A deferral provision, not a warranty provision. Prescription of remedies between the parties does not begin to run until fin des travaux, the contractor's prolongation claim and the owner's delay-damages claim alike. The deferral applies even to items reserved at acceptance, and it does not run from acceptance.

    LégisQuébec

  14. 13
    Code civil du Québec, arts 2118 and 2120C.c.Q., arts 2118 and 2120

    The two articles use different triggers and different forms of liability, and the difference is deliberate. Art 2118 imposes the five-year liability for loss of the work on the contractor, architect, engineer, technologue professionnel and subcontractor. That liability is solidary and it runs from fin des travaux. Art 2120 imposes the one-year garantie contre les malfaçons. That liability is joint and it runs from réception, acceptance. Art 2118 was amended on 24 September 2020 to add le technologue professionnel.

    LégisQuébec

  15. 14
    Churchill Falls (Labrador) Corp v Hydro-Québec2018 SCC 46, Supreme Court of Canada

    The doctrine of imprévision is not recognised in Quebec civil law, and any development of analogous concepts must take account of the legislature's choice not to turn the doctrine into a universal rule. Good faith may serve to protect the equilibrium of a contract but cannot be used to change that equilibrium and impose a new bargain.

    SCC

  16. 15
    Code civil (France), art 1195, imprévisionCode civil (France), art 1195, introduced by the 2016 reform of the law of obligations

    Permits a party to request renegotiation where an unforeseeable change of circumstances makes performance excessively onerous, with judicial revision or termination if renegotiation fails. Quebec maintains its pre-reform position and rejects that approach. France is not a guide to Quebec here.

  17. 16
    Code civil du Québec, arts 1607, 1611 and 1613, the damages provisionsC.c.Q., arts 1607, 1611 and 1613

    Art 1607 confines damages to « une suite immédiate et directe » of the fault. Art 1611 gives the two heads, the loss sustained and the profit deprived. Art 1613 confines contractual damages to those foreseen or foreseeable at formation, except where the failure to perform is due to intentional or gross fault, in which case the foreseeability filter falls away and only the immediate-and-direct limit survives.

    LégisQuébec

  18. 17
    Code civil du Québec, arts 1612 and 1614, two articles routinely misdescribedC.c.Q., arts 1612 and 1614

    Art 1612 is the trade-secret article and has no application to a construction delay claim. Art 1614 fixes the discount rate for prospective bodily-injury damages and is irrelevant to construction quantum. Neither is a general damages provision.

    LégisQuébec

  19. 18
    Code civil du Québec, arts 2125 and 2129C.c.Q., arts 2125 and 2129

    Art 2125 gives the client a unilateral right to resiliate the contract even after the work has been begun. Compensation follows arts 2126–2129. The article numbers and subject matter are correct, but the verbatim text of arts 2126–2129 was not retrieved for this corpus, and whether future profit is recoverable under art 2129 is recorded as unresolved.

    LégisQuébec

General information, not legal advice. Reviewed Aug 8, 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…

Each issue links to the full articles in the Storia Library.

The Civil Code framework for delay in Quebec · Storia