Is the contractor's schedule real?
Milestones against the contract baseline, and how old the last update is.
IFC, lab wing: +73 days. Last schedule update 22 Apr.
| Milestone | Baseline | Forecast | Variance |
|---|---|---|---|
| IFC package, lab wing | 14 Aug | 26 Oct | +73 d |
| Level 3 slab, first pour | 02 Feb | 16 Mar | +42 d |
- Baseline: contract schedule rev. 0. Forecast: latest dates stated in minutes and correspondence where no update was issued.
- Schedule updates received: last 22 Apr 2026, counted to 02 Nov 2026.