01Progress report
Which owner decisions are holding the job?
Late decisions counted in days, tied to the critical path.
2 owner decisions sit on the critical path.
| Item | Waiting on | Days | Impact |
|---|---|---|---|
| CR-014 Level 3 lab layout change | Owner | 108 d | +73 d |
| RFI-088 Roof exhaust routing | Owner's engineer | 104 d | +22 d |
2 items on the critical path3 waiting more than 60 days
Notes
- Days: from submission to the end of the period, 02 Nov 2026. Impact: variance on the activity each item blocks, from the latest schedule.