The Storia Library
All articles
92 articles
Sort
Extension of time72
- Extension of timeA contractual instrument that moves the completion date because the works were delayed by an event that was not the contractor's risk, relieving liability for late-completion damages. Whether the same event also pays for the…Reviewed Oct 13, 2026
- Concurrent delayConcurrent delay is where an employer-risk event and a contractor-risk event both drive the same period of critical overrun. It is settled law nowhere. On one four-week fact pattern the answer runs from four weeks of time and no…Reviewed Oct 13, 2026
- Notice and time barsA notice clause is a time bar where the contract makes the extension of time conditional on serving notice within a stated period. Under FIDIC 2017 Sub-Clause 20.2.1 and NEC4 clause 61.3 failure forfeits entitlement outright.…Reviewed Oct 13, 2026
- Delay analysis methods compared: which one your records can supportA delay analysis method is the technique used to prove that a qualifying event delayed completion. The SCL Delay and Disruption Protocol, 2nd Edition (February 2017) tabulates six commonly used methods at paragraph 11.5: impacted…Reviewed Oct 13, 2026
- Prolongation and delay costsAn extension of time and compensation are separate gateways: winning the time does not win the money. Prolongation cost is assessed for the period when the effect of the employer risk event was actually felt, not the overrun at…Reviewed Aug 7, 2026
- Records and evidence for an EOT claimThe records a project keeps decide which delay analysis methods it can run, and that set closes long before anyone knows there is a dispute. The SCL Delay and Disruption Protocol, 2nd Edition (February 2017) names six record…Reviewed Oct 13, 2026
- Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay, the work, and that you claim the time. AS 4000 wants a prompt cl 34.2 delay notice, then a written cl 34.3 claim within 28 days of…Reviewed Oct 13, 2026
- How to write an EOT claim, step by stepAn extension of time claim succeeds when it proves, on the contract's own terms and inside its deadlines, four things: a qualifying cause of delay that was not the contractor's risk, that it delayed completion and not merely…Reviewed Oct 13, 2026
- EOT claim checklist: is your extension of time claim ready to submit?An extension of time claim is ready when a stranger to the project could check every assertion in it against a dated record. That means seven things are in place: the contract basis, a notice served in time to the right person,…Reviewed Oct 13, 2026
- Extension of time in QuebecIn Quebec there is no statutory completion date, no statutory extension-of-time mechanism, and no "time at large". Time is entirely a creature of contract, and when a Quebec court relieves a contractor of delay consequences it…Reviewed Aug 8, 2026
- Quebec vs common-law Canada: what a common lawyer gets wrong about delayQuebec is a civil-law jurisdiction inside a common-law federation, and the delay doctrines a Canadian practitioner relies on mostly do not exist there. There is no time at large, no concurrent-delay doctrine, no imprévision and…Reviewed Aug 8, 2026
- The Civil Code framework for delay in QuebecThe Code civil du Québec contains no provision on time for completion, delay or extension of time. Arts 2098–2129 were read individually. Time appears once, at art 2102, as a pre-contractual disclosure duty on the contractor.…Reviewed Aug 8, 2026
- Notice and time bars in QuebecQuebec enforces contractual claim time bars strictly: a missed notice or claim deadline normally forfeits the entitlement, whatever the merits. Only three arguments defeat one: waiver, breach of the owner's obligation de…Reviewed Aug 8, 2026
- Concurrent delay in QuebecQuebec has no doctrine of concurrent delay. No Quebec authority, doctrine or professional commentary on « délais concomitants » as a distinct doctrine was located. Where two causes operate on the same overrun, a Quebec court…Reviewed Aug 8, 2026
- Delay penalties and the clause pénale in QuebecQuebec has no penalty versus liquidated-damages distinction. A clause pénale is valid under art 1622 C.c.Q. and enforceable without proof of loss under art 1623 para 1. The remedy is reduction, not nullity: art 1623 para 2 allows…Reviewed Aug 8, 2026
- Extension of time in CanadaCanadian delay and extension-of-time law is almost entirely common law and contract. No province or territory has a statute addressing construction delay as such. On procedure Canada is close to England and strict, on remedy it…Reviewed Sep 10, 2026
- Delay regimes by Canadian province: what changes at the borderNo Canadian province or territory has a statute addressing construction delay as such, so delay law is common law and contract everywhere. What changes at the border is the machinery around the claim: whether a limitation period…Reviewed Sep 8, 2026
- Notice and time bars in CanadaCanadian courts enforce construction notice clauses as conditions precedent, and the owner need not prove prejudice. Under CCDC 2 – 2020 GC 6.5.4 the contractor has 10 Working Days from the commencement of the delay not from its…Reviewed Sep 10, 2026
- Concurrent delay in CanadaCanadian courts treat delays as concurrent where delays to co-critical and co-controlling activities overlap, and they apportion time and money alike. On remedy that is closer to the United States than to England, which awards a…Reviewed Oct 13, 2026
- Liquidated damages and the penalty rule in CanadaCanada has not adopted Cavendish Square v Makdessi. A delay liquidated damages clause is enforceable only if the rate is a genuine pre-estimate of loss, and is separately vulnerable to an unconscionability challenge. Where the…Reviewed Sep 8, 2026
- Prevention principle and time at large in CanadaIn Canada an owner that has prevented the contractor from completing on time cannot insist on liquidated damages, and where no extension is granted the completion date can fall away. Perini Pacific is the anchor, but the domestic…Reviewed Sep 10, 2026
- Prolongation and delay costs in CanadaCanadian law compensates delay through two routes: the contract's own reimbursement clause and damages for breach. Extended site overhead, unabsorbed head-office overhead, equipment standby and acceleration are all recoverable in…Reviewed Sep 8, 2026
- Extension of time in OntarioOntario is the only Canadian jurisdiction where an extension of time is adjudicable, and the only one where a commercial contract may lawfully shorten or exclude a limitation period. Both turn on the contract date. A delay claim…Reviewed Sep 10, 2026
- Ontario delay claim clocksOntario runs five independent clocks on a delay claim: contractual notice, adjudication, lien, holdback and limitation. Each has a different trigger, a different character in law and a different consequence for being missed, and…Reviewed Sep 10, 2026
- Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is gone, and the owner need not prove prejudice. Content counts as much as timing. An insufficient claim submission is treated as no notice…Reviewed Sep 10, 2026
- Prompt payment and adjudication in OntarioSince 1 January 2026 Ontario is the only Canadian jurisdiction where an extension of time can be adjudicated. And only as an ancillary head, only where reasonably necessary to a money determination, not on P3 projects, and not on…Reviewed Sep 10, 2026
- Limitation periods and claim accrual in OntarioOntario gives a delay claim two years from discovery under the Limitations Act, 2002, with a fifteen-year long-stop. Uniquely in Canada, section 22 lets commercial parties to a business agreement extend, shorten, suspend or…Reviewed Aug 8, 2026
- Liens, holdback and security for a delay claim in OntarioAn Ontario construction lien secures a delay claim only in part. The line is price versus damages: extended-duration equipment and extra labour caused by owner default are lienable. Overhead, lost profit on other jobs and general…Reviewed Sep 10, 2026
- Extension of time in England and WalesEnglish law gives a contractor more time through the contract's own machinery: a Relevant Event under JCT, a compensation event under NEC4. The prevention principle is a default rule the parties can displace, concurrent delay is…Reviewed Oct 13, 2026
- Concurrent delay in England and WalesIn England and Wales the working default on concurrent delay is time yes, money no: where a Relevant Event and a Contractor-risk event are both effective causes of the same critical delay, the Contractor gets a full extension of…Reviewed Oct 13, 2026
- Notice and time bars in England and WalesIn English law a notice clause bars a claim only if, on its true construction, it makes the relief conditional on the notice. Disclosure and Barring Service v Tata Consultancy Services Ltd [2025] EWCA Civ 380 sets out five…Reviewed Oct 13, 2026
- Prevention principle and time at large in England and WalesIn England and Wales the prevention principle is a default rule of risk allocation that clear words displace, not an overriding rule of law. An employer act that in fact delays completion sets time at large only where the…Reviewed Oct 13, 2026
- Adjudicating extensions of time in England and WalesUnder the Housing Grants, Construction and Regeneration Act 1996 either party to a construction contract can refer an extension of time dispute to adjudication at any time, and the adjudicator can open up, revise and review the…Reviewed Oct 13, 2026
- Delay notice templates for JCT 2024 and NEC4 (England and Wales)A delay notice puts the cause, the date and the claim on the record before the other side can say it never heard of them. Under JCT Design and Build 2024 the Contractor notifies delay to progress "forthwith" once it is…Reviewed Oct 13, 2026
- Extension of time in AlbertaAlberta is the best Canadian forum for a late-crystallising private delay claim and the worst for a public one. Private-sector adjudication runs post-completion and alongside litigation, on provincial Crown public works delay is…Reviewed Aug 9, 2026
- Alberta delay claim clocksAlberta runs six clocks on a delay claim, contractual notice, adjudication, lien, holdback, limitation and prosecution of the action itself. Which of them exist at all depends on which Act you are on: on a provincial Crown public…Reviewed Aug 9, 2026
- Prompt payment and adjudication in AlbertaAlberta runs two payment regimes. In the private sector it is the most claim-friendly adjudication forum in Canada a consent catch-all, referral up to 30 days after final payment, concurrent with litigation, and no cap. On…Reviewed Aug 9, 2026
- Notice and time bars in AlbertaOn an Alberta provincial public work the notice that matters is statutory: Public Works Act s 14(3) requires registered mail within 45 days, strictly enforced. On private work CCDC 2 – 2020 GC 6.5.4 gives 10 Working Days from…Reviewed Sep 10, 2026
- Limitation periods and claim accrual in AlbertaAlberta gives a delay claimant two years from knowing the injury occurred, was attributable to the defendant and warrants a proceeding, and ten years from the first actionable breach. Under s 7(2) a limitation period may be…Reviewed Aug 9, 2026
- Liens, the lien fund and trust in AlbertaAn Alberta lien secures delay damages only where they relate directly to the liened work lost productivity on that project, not inability to work elsewhere. And the lien fund is not the trust: PPCLA s 22 bites only on payments…Reviewed Aug 9, 2026
- Arbitration and forum for Alberta delay claimsThe real Alberta risk in a delay claim is the forum, not the doctrine. An arbitral finding on delay causation is effectively unappealable, the courts have no construction list, expert evidence is capped at one expert per subject…Reviewed Sep 10, 2026
- Oil, gas and industrial delay claims in AlbertaAlberta's oil, gas and industrial construction is the highest-value, least-precedented delay environment in Canada. There is no standard EPC or EPCM form, no turnaround authority, no winter authority and no regulatory-delay…Reviewed Aug 9, 2026
- Extension of time in British ColumbiaBritish Columbia is the birthplace of Canadian delay doctrine and the jurisdiction that has done least with it since. It supplies the national anchors on prevention, notice, acceleration and total cost, then goes quiet for twenty…Reviewed Sep 8, 2026
- British Columbia Delay Claim ClocksEvery deadline that can end a British Columbia delay claim, grouped by the clock it belongs to and by its character in law, contractual condition precedent, statutory precondition, limitation period, or condition of a security…Reviewed Sep 8, 2026
- Notice and Time Bars in British ColumbiaBritish Columbia enforces construction notice provisions purposively rather than mechanically. A BC court asks what the clause was for and whether the owner was actually deprived of it, in substance and in good time. That is…Reviewed Sep 10, 2026
- Prevention and Time at Large in British ColumbiaBritish Columbia supplies both Canadian prevention anchors and the strongest candidate for a Canadian judgment actually finding time at large, Hawl-Mac (1985). That proposition contradicts most national commentary, rests on a…Reviewed Sep 8, 2026
- Concurrent Delay and Apportionment in British ColumbiaBritish Columbia apportions concurrent delay as a damages exercise rather than an entitlement exercise. There is no Malmaison, no dominant cause and no first-in-time in BC. The province has both precise day-by-day apportionment…Reviewed Sep 8, 2026
- Prolongation, Acceleration and Quantum in British ColumbiaBritish Columbia's delay-quantum philosophy is actual cost, proved. Head-office overhead runs on Shore & Horwitz rather than a formula, total cost is available as a last resort through the W A Stephenson gateway, and the province…Reviewed Sep 8, 2026
- Limitation Periods and Claim Accrual in British ColumbiaIn British Columbia the deadline that kills a delay claim is almost always a Builders Lien Act deadline, not a Limitation Act one. The Act gives two years from discovery, the lien, holdback and trust clocks expire far sooner, and…Reviewed Sep 8, 2026
- Liens, Holdback and the Statutory Trust in British ColumbiaBritish Columbia's Builders Lien Act creates two trusts, a 10% holdback, a 45-day lien filing period and a separate lien on the holdback fund. Together they, not the Limitation Act, set the deadlines that decide whether a delayed…Reviewed Sep 8, 2026
- Prompt Payment and Adjudication, British ColumbiaBritish Columbia has no prompt payment and no construction adjudication. The Construction Prompt Payment Act received Royal Assent on 27 November 2025 and is not in force as at 8 September 2026, no adjudication authority has been…Reviewed Sep 8, 2026
- Arbitration, Experts and Forum in British ColumbiaBritish Columbia decides most large delay disputes in confidential arbitration, and the Arbitration Act permits appeal only on a question of law. Because contract interpretation is mixed fact and law, an arbitrator's reading of…Reviewed Sep 8, 2026
- Public Works and Infrastructure, British ColumbiaBritish Columbia's public construction owners allocate delay differently from one another and from CCDC 2. The MOTI Major Works General Conditions give time but not money for abnormal weather, the Site C contract excludes flood…Reviewed Sep 8, 2026
- Extension of time in United States construction claimsIn US construction, there is no single EOT rule: federal contracting, private AIA-form work, and each state's law on no-damage-for-delay clauses can give materially different answers on the same facts, and critical-path proof is…Reviewed Sep 1, 2026
- Extension of time: the claim clocks in US constructionA 'claim clock' is a contractual or statutory deadline that can extinguish or cap a US construction delay claim if missed. US practice layers three kinds: AIA's 21-day Claim window, FAR's stacked notice/cost-cutoff/proposal…Reviewed Sep 1, 2026
- The Claim-Within-a-Claim Trap in US Notice MachineryNotice-and-time-bar mechanics in US construction turn on structural questions a deadline calendar can't answer: whether a bare time request is itself a Claim, why owner LD assessment skips the Claims machinery entirely, and why a…Reviewed Sep 1, 2026
- There Is No Prevention Principle in US Construction LawUS law has no doctrine called "the prevention principle" and no concept of "time at large." A practitioner trained in English law looking for either will find neither. The same commercial result, that an owner who caused delay…Reviewed Sep 1, 2026
- Concurrent Delay: Why the Contractor's Burden Is the TrapIn US federal practice, concurrent delay is a rule of proof, not substantive law: where both parties contribute to a delay, neither recovers unless the evidence permits clear apportionment, and it is the contractor, not the…Reviewed Oct 6, 2026
- No-Damage-for-Delay Clauses: Enforceable in Texas, Void in OhioA no-damage-for-delay (NDFD) clause limits a contractor's delay remedy to a time extension only. US enforceability is not uniform: it turns on state law, judicially created exceptions, and, in a minority of states, statutory…Reviewed Sep 1, 2026
- Constructive Acceleration: A Claim Parasitic on the EOT ClaimConstructive acceleration is a US claim theory arising when an owner refuses or fails to act on a valid extension-of-time request and instead insists on the original completion date, forcing the contractor to expend extra…Reviewed Sep 1, 2026
- Extension of time in AustraliaAustralian delay and extension-of-time law runs on one common law and eight statutory regimes. Doctrine. Prevention, penalties, concurrency, global claims, delay analysis. Does not change at the state line. What changes is the…Reviewed Sep 26, 2026
- Prevention principle and time at large in AustraliaIn Australia the prevention principle has been largely displaced by the Superintendent's unilateral power to extend time, which must be exercised honestly and fairly. A principal that will not use it for delay it caused loses its…Reviewed Oct 13, 2026
- Concurrent delay in AustraliaAustralia has no judicial default on concurrent delay. The answer is set entirely by contract. AS 4000-1997 cl 34.4 apportions overlapping delay. AS 2124-1992 cl 35.5 denies an extension of time for the concurrent period…Reviewed Sep 1, 2026
- Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the Superintendent's duty to act honestly, waiver, and the weak Gaymark argument. Since 15 April 2026, Victoria joins Western Australia as the…Reviewed Sep 26, 2026
- Liquidated damages and penalties in AustraliaAustralia runs its own penalties doctrine, wider than England's at the gateway and narrower nowhere. Andrews v ANZ [2012] HCA 30 lets a stipulation be struck even without breach. Paciocco [2016] HCA 28 sets an "out of all…Reviewed Sep 1, 2026
- Prolongation and delay costs in AustraliaAustralian law lets a delayed contractor recover extended site overhead, actual off-site overhead, plant standby, escalation and lost profit or opportunity, but by proof of actual cost, not by formula. No Australian decision has…Reviewed Sep 1, 2026
- Global claims and total cost in AustraliaA global (or total cost) claim lumps prolongation losses together instead of linking each loss to a specific compensable event. Australian law permits this only where apportionment is proved impracticable, and unlike England or…Reviewed Oct 13, 2026
- Acceleration in Australian Construction ClaimsConstructive acceleration is not a recognised doctrine in Australian law. Contractors instead recover acceleration costs as damages for breach of the Superintendent's duty to administer the extension-of-time machinery honestly…Reviewed Sep 1, 2026
- Delay analysis methods in AustraliaAustralian courts choose delay-analysis methodology from the facts, not from a protocol. White Constructions [2019] NSWSC 1166 held the SCL Delay and Disruption Protocol is not a rule of law and rejected both parties' experts.…Reviewed Sep 1, 2026
- Records and expert evidence in AustraliaAustralian delay claims are won or lost on contemporaneous records and on an expert who can expose their reasoning under Makita. Concurrent evidence. "hot-tubbing". Is an Australian invention now used worldwide, but no located…Reviewed Sep 1, 2026
- Limitation and Long-Stops: AustraliaAustralian breach-of-contract claims carry a six-year limitation period, except the Northern Territory's three years. Five states and territories also run a building-action long-stop of about ten years. Absent in Queensland and…Reviewed Sep 1, 2026
- Security of Payment and Adjudication: AustraliaEvery Australian jurisdiction now lets an adjudicator value a delay or prolongation claim, on a payment-claim timetable measured in business days. No statute names extension of time, so it arrives through valuation,…Reviewed Sep 26, 2026
Variations20
- VariationsA change to the contract scope, instructed under the contract's own change power, valued by the contract's pricing machinery. Whether an item is a variation is a question of contract construction, not of fairness, and proving it…Reviewed Oct 13, 2026
- What counts as a variationA variation is a change to the design, quality or quantity of the works as defined by the contract documents, instructed under the contract's change mechanism. Whether an item qualifies is a question of construing the contract,…Reviewed Oct 13, 2026
- Written instruction and waiverA variation is compensable only if instructed, in writing, by the named person, before the cut-off. Whether an unwritten instruction can still be paid for depends entirely on the regime: England enforces the formality, Australia…Reviewed Oct 13, 2026
- Constructive and deemed variationsConstructive change is a United States doctrine: work beyond the contract requirements, ordered expressly or impliedly by the government. No doctrine of that name exists elsewhere: England, Canada, Australia and FIDIC use deemed…Reviewed Oct 13, 2026
- Valuation and the pricing ladderAlmost every construction contract values a variation by climbing a ladder (contract rates, then adjusted rates, then a fair valuation, then daywork) and a party may not skip a rung because it prefers the answer further up. NEC4…Reviewed Sep 26, 2026
- Change order releases and reservation of rightsElement 5 of the variation claim, and the one with no extension-of-time analogue: the impact claim you meant to bring at the end has already been released by the change orders you signed along the way. Impact claims die in signed…Reviewed Oct 6, 2026
- Change orders in the United StatesAmerican change-order practice runs on two doctrines no other jurisdiction this site covers has by name, constructive change and cardinal change, and the most common way a sound change claim dies is not a lost argument about…Reviewed Sep 22, 2026
- Written instruction and waiver in the United StatesWhether a contractor recovers for a change performed without a signed change order depends first on who the owner is. On private work a written-change-order requirement is a contract term the owner can waive by conduct. On state…Reviewed Sep 22, 2026
- Constructive change in the United StatesA constructive change is work beyond the contract requirements that the owner ordered, expressly or impliedly, without issuing a formal change order. On federal construction, FAR 52.243-4(b) treats such an order from the…Reviewed Sep 22, 2026
- Cardinal change in the United StatesA cardinal change is an alteration so drastic that it effectively requires the contractor to perform duties materially different from those originally bargained for. It falls outside the changes clause, so it is a breach of…Reviewed Sep 22, 2026
- Change order releases and reservation of rights in the United StatesA change order release is wording in an executed change order or bilateral modification by which the contractor accepts the stated adjustment as full compensation and gives up further claims arising from the change. Tribunals…Reviewed Oct 6, 2026
- Change orders in CaliforniaCalifornia change-order practice runs on the general US framework, the private/public split on who can bind the owner, and the federal-style doctrines carried into state courts, with one statutory addition: from 1 January 2026,…Reviewed Sep 22, 2026
- California SB 440: the change-order payment statuteFor contracts entered into on or after 1 January 2026, Cal. Civ. Code §§ 8850–8851 (added by SB 440) give contractors and subcontractors on most private California work a statutory claim procedure for time extensions and…Reviewed Sep 22, 2026
- Variation claims in Australia: AS 4000, AS 2124 and the 2026 changesAn Australian variation claim is won or lost on three things: who directed the work, in writing, and before when; whether the work was really outside the contract; and, since 15 April 2026, where the claim is going to be decided,…Reviewed Sep 26, 2026
- Oral variations in Australia: why Rock Advertising never crossedIn Australia a clause requiring variations to be in writing does not stop the Principal and Contractor agreeing a variation orally or by conduct, and it does not defeat an estoppel. Liebe v Molloy (1906) still governs and Rock…Reviewed Sep 26, 2026
- AS 4000 deemed variations and latent conditions in AustraliaAustralia has no doctrine called constructive change. Work nobody formally directed reaches the variation account by four other routes: an express deeming provision in the contract (under AS 4000:2025, bill of quantities items…Reviewed Sep 26, 2026
- AS 4000 variation pricing: how to value a variation in AustraliaUnder AS 4000 (and, as summarised, AS 4902) a directed variation is priced down a fixed order: prior agreement, then rates or prices in the Contract, then rates in a priced schedule even if it is not a Contract document, and only…Reviewed Sep 26, 2026
- Variation notice templates for AS 4000 and AS 2124A variation notice puts one fact on the record: that a direction changed the work, given to the right person, in writing, in time. Under AS 4000 (1997 and 2025) the variation itself must be directed in writing by the…Reviewed Oct 6, 2026
- Variations in Victoria: security of payment after 15 April 2026Victoria used to be the one Australian jurisdiction where a disputed variation on most large contracts could not be adjudicated. On 15 April 2026 it repealed the "claimable variation" and "excluded amounts" regime (ss 10A–10B of…Reviewed Sep 26, 2026
- Variation claims in Victorian adjudication: ss 10A–10B gone, s 13A inSince 15 April 2026 a disputed variation can go into a Victorian payment claim and to adjudication like any other amount: the "claimable variation" and "excluded amounts" regime in ss 10A–10B of the Security of Payment Act was…Reviewed Sep 26, 2026
The notice brief
One email a month on claims, notices and the cases that decided them.
The notice briefIssue 01 · sample
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.