There are four kinds of deadline in a British Columbia delay claim, and they do four different things. Some destroy your entitlement, some destroy your security, and one merely bars the proceeding. Confusing them is how BC delay claims are lost, and the one that usually runs out first is not the limitation period.
This page is a register of every deadline the corpus holds for a BC delay claim, grouped by the clock it belongs to. Each carries its character in law: a contractual condition precedent, a statutory precondition to suing, a limitation period, or a condition of a security remedy. That distinction is not academic. It determines what survives when the date passes, what the argument for relief looks like, and. For a practitioner arriving from Ontario, Alberta, England or the United States, which diary entry is actually the dangerous one.
Two rules of provenance govern what follows. The Builders Lien Act, the Crown Proceeding Act and the Supreme Court Civil Rules were obtained from BC Laws, so those section and rule numbers are primary-verified. The MOTI Major Works General Conditions, the Site C Main Civil Works Contract and the Penticton Regional Hospital Project Agreement were obtained as primary documents, so those clause numbers are primary-verified too. The Limitation Act, the Construction Prompt Payment Act and the Local Government Act were not obtained, and every figure attributed to them rests on secondaries. And no BC judgment was read in original text (CanLII and bccourts.ca blocked automated retrieval) so every case proposition below rests on two or more independent secondary sources and carries no paragraph pinpoint. For the rest of the province's delay law, see the British Columbia extension-of-time hub.
Which clock kills a British Columbia delay claim first?
Almost always a Builders Lien Act clock. The 45-day lien filing period, the 55-day holdback period, the hard one-year trust period and the one-year action period the owner can compress to 21 days all expire long before the Limitation Act's two years from discovery. A BC claimant who diarises the limitation period first has diarised the least urgent date on the file.
That ordering is the whole point of this page. On a P3 the shortest clock is five Business Days and it starts when you first Have Knowledge of an entitlement, on a MOTI highway job it is 14 days. And on any project the statutory security clock is 45 days from an event that may have nothing to do with your own progress. The limitation period is a distant fourth. The corpus's earlier record of a "45 or 46 day" BC lien period is resolved: 45 days is lien filing under s 20, and the 46 days is the future holdback period under the unproclaimed Construction Prompt Payment Act, down from 55. Never present 46 as a lien filing period.
Four characters, and why the distinction decides your argument
A BC deadline is one of four things, and what you lose on missing it differs in each case. A condition precedent goes to entitlement, miss it and there is no claim to bring. A statutory precondition goes to the right to sue at all, in BC, against the Province, there is none. A limitation period bars the proceeding but not the debt. A condition of a security remedy destroys the security while leaving the underlying claim intact.
| Character | What missing it destroys | The BC instances | What survives |
|---|---|---|---|
| Contractual condition precedent | Entitlement, the claim itself | P3 s 8.2(a) five Business Days, MOTI GC 44.03 14 days. MOTI GC 41.01 and GC 37.07 seven days, the GC 44.02 mitigation condition | Nothing on that event, subject to waiver, estoppel and the purposive BC reading of notice |
| Statutory precondition to suing | The right to bring the proceeding | None against the Province. Possibly Local Government Act s 736 against a municipality, unresolved | The claim, in BC, is unaffected. There is no such precondition to clear |
| Limitation period | The proceeding, not the debt | Limitation Act s 6 two years from discovery, s 21 ultimate 15 years. BLA s 14 one-year trust period. BLA s 33 one year to sue and register | A defence must be pleaded. The obligation is not extinguished |
| Condition of a security remedy | The security only | BLA s 20 45-day filing, extinguished under s 22, BLA s 8 holdback period, the Shimco holdback lien | The delay claim in debt and damages, and the s 10 trust claim |
Layer: inferential, the four-way classification is this corpus's framework, not a statement any BC court has made. The instances in each row are drawn from the primary statute tier (BC Laws) and the primary contract-form tier (documents obtained), except the Local Government Act row, which is unverified.
The fourth row is the one that changes conduct. Losing the 45-day lien does not lose the delay claim. It loses the security for it, which on a distressed or terminated project is often the only thing that was going to produce payment. It also explains why the s 10 trust matters so much in BC: it is the fallback that survives loss of the lien.
Contractual notice, the condition-precedent clocks
These are the shortest clocks on any BC project and the only ones that go directly to entitlement. The three BC public forms obtained as primary documents set five Business Days, 14 days and seven days respectively, the private-work default is CCDC 2 – 2020 GC 6.5, for which the corpus's BC notes fix no day count. Whether any of them operates as a condition precedent is governed by Doyle Construction and Northland Kaska.
| Form | Period | Trigger | Provision |
|---|---|---|---|
| Infrastructure BC project agreement (Penticton Regional Hospital, 2016) | 5 Business Days | from "Has Knowledge" that a supervening event has caused an entitlement, a defined term | s 8.2(a) |
| Same, supporting details | 10 Business Days | after delivery of the notice | s 8.2(b) |
| Same, meeting and escalation | 15 Business Days to meet, then 10 Business Days to dispute resolution | – | s 8.2(h) |
| MOTI Major Works, extension of time | 14 days | from the "occurrence or the detection" of the event | GC 44.03 |
| MOTI Major Works, changed condition | 7 days | – | GC 41.01 |
| MOTI Major Works, default | 7 days | where no specific period is stated | GC 37.07 |
| BC Hydro Site C Main Civil Works | Not extractable | – | Schedules 2, 11 and 14 were not in the retrieved document |
| CCDC 2 – 2020 (private work) | Not fixed by this corpus | – | GC 6.5, events limb at GC 6.5.3 |
The three public forms in that table were obtained as primary documents for this corpus, so their clause numbers and periods are primary-verified: the MOTI Major Works General Conditions, version 2026-04-01, the Penticton Regional Hospital Patient Care Tower Project Agreement, dated 6 April 2016 and the Site C Clean Energy Project Main Civil Works Contract, dated 18 December 2015. The CCDC 2 – 2020 Stipulated Price Contract was not: like every copyright form in this corpus, its clause numbers are verified against publicly available contents pages and its wording is reconstructed from converging secondary sources rather than quoted.
Layer: form-default. Rows one to seven rest on the primary contract-form tier, the CCDC row rests on the standard-document position just described.
Three things about that table are worth more than the numbers in it.
The P3 trigger is the most aggressive delay-notice regime in BC public contracting. Five Business Days keyed to a defined "Has Knowledge" standard is dramatically shorter than MOTI's 14 days and shorter than most CCDC forms, and on a P3 it cascades down to the design-builder and its subcontractors through the construction sub-agreement. Notice discipline on a BC P3 is a function, not a task. The caveat is real, though: this is one project agreement dated 2016, and Infrastructure BC agreements follow a family resemblance rather than a published standard form, so as a generalisation across the portfolio.
The MOTI trigger is disjunctive, and that is a gift. "Not later than fourteen (14) days after the occurrence or the detection" supports a discoverability argument for latent or creeping delay events, the productivity-sapping condition you only recognise in retrospect. Alongside it sits GC 44.02, which conditions time relief on the Contractor having diligently proceeded and applied all reasonable means to complete. That is a mitigation condition precedent to time relief, and it means re-sequencing decisions have to be documented contemporaneously or the Ministry has a standing disentitlement argument.
On Site C the notice clock could not be found at all. The extension-of-time, notice and liquidated-damages provisions sit in Schedule 2 and Schedule 11, with a Dispute Notice defined in Schedule 14, and those schedules were not in the retrieved document. No general BC Hydro standard-form set of construction general conditions for non-Site-C work was located either. A claimant on a BC Hydro job cannot work from a published default and must read its own schedules. See BC public works and infrastructure contracts.
There is also a clock hiding above these. The MOTI dispute machinery runs GC 58.00 Dispute Resolution, GC 59.00 Formal Claim, GC 60.00 Appeal and GC 61.00 Arbitration. , the full text was truncated in retrieval, and the inference that it operates as a staged, condition-precedent-style escalation should be verified clause by clause on any live matter. If it does, it is a time bar layered on top of the 14-day GC 44.03 notice.
Enforceability is where BC departs from Ontario. Doyle Construction Co v Carling O'Keefe Breweries, 1988 CanLII 2844 (BCCA) treats notice as a condition precedent to maintaining the claim, and Northland Kaska Corp v R, 2001 BCSC 929, (2001), 10 CLR (3d) 190 holds that a contractor's grumblings are not notice, and, more precisely, that an owner's knowledge of difficulty is not knowledge of an intention to claim. Northland Kaska was itself a claim against the Crown, which makes it the most on-point authority for a GC 44.03 dispute. But BC reads notice purposively: it asks what the clause was for and whether the owner was actually deprived of it. That is meaningfully less strict than Ontario's line, and it is worth saying plainly that the governing BC notice authorities are from 1988 and 2001, see notice and time bars in British Columbia.
The Builders Lien Act clocks: conditions of a security remedy
These are the clocks that actually end BC delay claims, and they are conditions of a security remedy rather than limitation periods: missing them destroys the lien, not the debt. Four matter under the Builders Lien Act, SBC 1997, c 45 45 days to file, 55 days of holdback, one year to sue and register, and the owner's right to compress that year to 21 days. All of them can be started by an event on someone else's contract.
| Clock | Period | Runs from | Consequence of missing | Section |
|---|---|---|---|---|
| File a claim of lien | 45 days | a certificate of completion. Or the head contract completed, abandoned or terminated. Or the improvement completed or abandoned | Lien extinguished (s 22) | s 20 |
| Holdback period | 55 days now, 46 after proclamation | certificate of completion, otherwise head contract or improvement completion | Payment out discharges liens unless a lien was filed or proceedings commenced | s 8 |
| Certificate of completion | certifier has 10 days to issue on request, copies out in 7 days | the request | The court may declare completion. The certifier is personally liable | s 7 |
| Commence the action and register a CPL | 1 year | the date the lien was filed | Lien lost | s 33 |
| Owner's notice to commence | 21 days | service, and mailed notice is conclusively deemed served on day 8, leaving roughly 13 real days | Lien extinguished | s 33 |
Layer: jurisdictional. Every row rests on the primary statute tier, the Act's text was obtained from BC Laws, so the section numbers are primary-verified. The characterisation of these periods as conditions of a security remedy is this corpus's framework, not a statement of any BC court.
The trigger everyone gets wrong. Absent a certificate of completion, a subcontractor's 45 days does not run from the day it finished its own scope. It runs from the head contract being completed, abandoned or terminated, or from the improvement being completed or abandoned. The corpus records this as the single most-missed feature of the BC Act, and it cuts both ways on a delayed project. Favourably: a subcontractor that finished long ago on a late job still has live lien rights, because the head-contract clock has not started delay preserves lien rights. Adversely: because termination is a trigger, and termination is a common consequence of severe delay, a sudden termination starts a 45-day clock against every subcontractor on the project simultaneously, often without their knowledge.
The escape hatch is s 7. Apply for a certificate of completion for your own subcontract: it starts your clock deliberately, releases your holdback and does not wait on the head contract. The certifier has 10 days to issue on request and is personally liable for failures causing loss.
Two further Builders Lien Act provisions are clocks in disguise, and both bear directly on a delay dispute. Section 6 prohibits the required holdback from being applied to completion, to the payment of damages, or to any other purpose while the possibility of a lien survives. A statutory bar on setting liquidated damages off against the statutory 10%, though excess retention remains fair game. Section 34 fixes the lien fund and provides that the amount owing is not reduced by counterclaims, by payments made in bad faith, or by payments made after a lien was filed with actual notice. Between them they defeat the archetypal owner position on a late job. There is nothing left, we are claiming liquidated damages.
Every one of these figures now has a second value, because the Construction Prompt Payment Act, Bill 20 (2025), Royal Assent 27 November 2025 is enacted and not in force as at 10 August 2026. Read the date before you read the rule.
Layer: jurisdictional and dated. The left column rests on the primary statute tier for the Builders Lien Act sections and on the secondary tier for the case law. The right column rests entirely on secondary sources: unlike the Builders Lien Act, the CPPA text was not obtained from BC Laws, so its figures should be checked against the statute before they are relied on.
The Shimco Metal Erectors Ltd v Design Steel Constructors Ltd, sub nom Shimco Metal Erectors Ltd v North Vancouver (District), 2003 BCCA 193 lien is a separate lien on the holdback fund, distinct from the lien against the land, and it is good law on 10 August 2026, Kingdom Langley Project LP v WQC Mechanical Ltd, 2025 BCCA 169 reaffirmed it, saying that disagreement with the decision did not warrant overturning it and that legislative intervention rather than judicial action is required. Reports that it has been abolished are wrong: the CPPA will abolish it, and the CPPA is not in force.
On adjudication, the position is unusually stark. There is no adjudication clock in BC today, and no BC decision on delay in an adjudication or prompt-payment context exists, and none is possible, because the Act is not in force. No adjudication authority has been designated and the regulation consultation closed 7 July 2026. When it is proclaimed it will apply only to contracts entered into after commencement, so essentially every BC contract live today will never be subject to BC adjudication. And whether a BC adjudicator could grant time is unresolved: delay is adjudicable in substance through the change-order and valuation heads: s 16 expressly covers approved and proposed change orders, which is wider than Ontario, but declaratory time relief is uncertain. See prompt payment and adjudication in British Columbia.
The trust clock, a one-year limitation that runs from an event you may not hear about
This one is a true limitation period, and it is the answer for a claimant whose lien has gone. Builders Lien Act ss 10 to 14 create a statutory construction trust, s 14 gives one year to bring a trust action, running from the head contract being completed, abandoned or terminated. It is hard, not a discovery period, and it can expire before the claimant knows the triggering event happened.
The proposition that BC has no statutory construction trust is wrong, and this corpus previously carried the error. It has one, at ss 10 to 14, with a second trust at s 5(2) over the holdback account. Three limits define its reach and each one bites on a delay claim:
- The res is money actually received, not money received or receivable, so the fund exists only to the extent the payer was in fact paid.
- One tier only, the trust runs against the party that directly engaged you, not up the chain.
- A hard one-year limitation at s 14, from head-contract completion, abandonment or termination, not from discovery.
And on a public project there may be no second trust at all: s 5(7) exempts government entities and contracts under $100,000 from the holdback-account requirement, so on a BC public job there is typically no holdback account and no s 5(2) trust. Your cash security is the s 10 trust and a timely lien. The mechanics are worked through in liens, holdback and the statutory trust in British Columbia.
The scheduling consequence is the point for this page. The s 14 clock and the s 20 lien clock run from the same class of event, head-contract completion, abandonment or termination, so a single termination can start a 45-day security clock and a one-year trust clock at the same moment, and both can be running before the subcontractor is told the head contract has ended.
The Limitation Act, the clock that almost never bites, and the accrual date nobody knows
Two years from discovery, 15 years ultimate, under the Limitation Act, SBC 2012, c 13. It is the least urgent date on a BC delay file and, on the corpus's evidence, the least certain: there is no BC authority on when a delay or prolongation claim accrues. Not the delaying event, not completion, not the final certificate no BC court has said.
| Provision | Rule | Status |
|---|---|---|
| s 6 | Basic limitation, two years from discovery | Verified at two independent secondary sources |
| s 8 | Discovery: four elements, of which element four, appropriateness, does most of the work in construction | Verified at two independent secondary sources |
| s 21 | Ultimate limitation, 15 years | Verified at two independent secondary sources |
| s 24 | Acknowledgment and part payment restart the clock | |
| Contractual variation | No express provision. No BC equivalent of Ontario's s 22(5) | |
| Accrual of a delay claim | No BC authority. The most defensible candidate is the certifier's or owner's refusal of the claim |
Layer: jurisdictional, but the whole table rests on the secondary tier. Unlike the Builders Lien Act, this Act was not obtained from BC Laws for this corpus retrieval was blocked, so every section number and figure in it comes from secondary sources. The accrual row is a searched negative finding, and the candidate accrual date is opinion.
Two practical consequences follow. First, because there is no accrual rule, diarise every candidate date, not one: the refusal of the claim, the last day of the delaying event, completion, and the final certificate. Second, BC has no express statutory provision permitting contractual variation of a limitation period, which makes it the least certain major Canadian jurisdiction on the question. Rosas v Toca, 2018 BCCA 191 proceeded assuming without deciding that variation is possible, and required clear language describing a limitation period. That is obiter, and it is all there is.
Keep two categories apart, because they are routinely conflated. A notice condition precedent ("no claim unless notice within 10 days") is a substantive condition on entitlement, governed by contract law and Doyle, and the variation debate is irrelevant to it. A clause shortening the period in which to commence proceedings engages the variation question and is unsettled in BC.
Statutory preconditions to suing. The ones British Columbia does not have
State this one flat, because it is a searched finding and it changes how a public job is run. There is no BC Public Works Act, and the Crown Proceeding Act, RSBC 1996, c 89 contains no pre-suit notice provision. A contractor suing the Province of British Columbia for delay faces no statutory notice precondition at all.
| British Columbia | Alberta | |
|---|---|---|
| Public works statute | None | Public Works Act |
| Notice to the Crown before suing | None, the Crown Proceeding Act has no pre-suit notice provision | 45 days, by registered mail |
| Delay in adjudication on provincial public works | No adjudication at all until the CPPA is proclaimed, and then new contracts only | Expressly excluded by name: schedule changes, milestone dates, relief events, changes in law and force majeure |
Layer: comparative and jurisdictional. The BC row rests on the primary statute tier, the Crown Proceeding Act having been obtained from BC Laws, and the negative finding is recorded at two independent sources. The Alberta column rests on the corpus's comparative material only. No Alberta statutory text was obtained, and the chapter citation is not held.
That contrast is the single sharpest divergence between the two western provinces on delay procedure, and it runs in BC's favour. Alberta's Public Works Act, s 14(3), s 14.3(2) requires notice to the Crown within 45 days by registered mail, and separately excludes schedule changes, milestone dates, relief events, changes in law and force majeure from adjudication on provincial public works by name. An Alberta contractor that misses the registered-mail notice has a problem no amount of contractual argument fixes, a BC contractor has no equivalent trap. See notice and time bars in Alberta for the other side of it.
The exception, and it is unresolved, is the municipal owner. Local Government Act, RSBC 2015, c 1, s 736 is reported to bar a claim for damages against a municipality in the absence of written notice within two months. One BC firm has published pieces with directly opposing titles on whether it is a limitation period or a notice condition, the reported cases are personal injury and tort, and whether it reaches a contract or delay claim is unresolved. On the language recorded, it probably does not. A two-month notice requirement, if it applied, would be catastrophic on a delay claim. Verify it before advising on any claim against a BC municipality.
The procedural clocks, and how the whole set interacts
Once proceedings are on foot a fourth set of dates applies under the Supreme Court Civil Rules, Rules 11-6, 15-1, 22-4 and 22-7 none of them fatal to entitlement, but two of them capable of ending the action. Expert reports go in 84 days before trial and responding reports 42 days before trial under Rule 11-6. A proceeding in which no step has been taken for one year cannot proceed without notice under Rule 22-4(4), and can be dismissed for want of prosecution under Rule 22-7(7).
| Clock | Period | Rule |
|---|---|---|
| Serve expert report | 84 days before trial | Rule 11-6 |
| Serve responding expert report | 42 days before trial | Rule 11-6 |
| Number of experts | No limit, Rule 11-8 is repealed | |
| Dormancy | 1 year with no step taken, notice required before proceeding | Rule 22-4(4) |
| Want of prosecution | On application, at any time | Rule 22-7(7) |
| Fast track, examination for discovery | 2 hours, against 7 ordinarily | Rule 15-1, |
Layer: jurisdictional, resting on the primary statute tier, the rules text was obtained from BC Laws and the rule numbers are primary-verified. The one exception is the fast-track discovery figure, which is unverified.
The repeal of Rule 11-8 is a genuine advantage on a delay claim: BC imposes no cap on the number of experts, the opposite of Alberta's one per subject matter. Fast track is the trap in the other direction. Its two-hour discovery limit makes a multi-year as-built chronology unexaminable, so it is unsuitable for a real delay claim, but builders lien claims are expressly eligible, which gives an owner facing a modest lien inflated by a delay allegation a tactical interest in getting the matter into it.
Now the interaction, which is what makes BC different. A single event, the head contract being completed, abandoned or, most often on a delayed project, terminated, starts three clocks at once: the 45-day lien filing period under s 20, the 55-day holdback period under s 8 (46 days after proclamation), and the hard one-year trust period under s 14. None of them is keyed to your own progress, and nobody is obliged to tell you the event has happened. The contractual notice clocks run on a different trigger entirely, your knowledge of the delaying event: and will usually have started, and often expired, months earlier. The Limitation Act runs on a third trigger, discovery, from a date no BC authority identifies. They are not a sequence. They are four independent timers on the same file.
Five Business Days on an Infrastructure BC project agreement, 14 days on MOTI Major Works from occurrence or detection, seven days for a MOTI changed condition or where the contract states no period. It is almost certainly the shortest clock you have, and it is the only one that goes to entitlement.
That date, not your own last day on site, starts the 45-day lien clock, the 55-day holdback period and the one-year trust period. Find it and record it. On a terminated project all three are already running against every subcontractor at once.
Apply under s 7 for a certificate of completion for your own subcontract. It starts your clock deliberately, releases your holdback and does not wait on the head contract. The certifier has 10 days, and is personally liable for failures causing loss.
Section 33 gives a year from filing to commence the action and register a certificate of pending litigation, and the owner can compress it to 21 days on notice. Mailed notice is conclusively deemed served on day 8, so the real window is about 13 days.
It is a hard one-year period from head-contract completion, abandonment or termination (not from discovery) and it is what survives loss of the lien. On a public job it may be all you have, because s 5(7) exempts government entities and contracts under $100,000 from the holdback account.
There is no BC authority on when a delay claim accrues. Diarise two years from the refusal of the claim, and diarise the earlier candidates as well. On a multi-year project, get a tolling agreement rather than relying on the question being answered in your favour.
Check Local Government Act s 736 immediately. Two months, unresolved as to whether it reaches a contract claim, and catastrophic if it does.
Which leaves the order to work in, and it is not the order most practitioners arrive with. Diarise the contractual notice clock first, it is the shortest and the only one that destroys entitlement rather than security. Diarise the head-contract status second, because that single unknown date controls three statutory clocks you cannot influence. Diarise the s 14 trust date third and separately, because it is the fallback that survives everything else and it runs hard. The Limitation Act comes fourth. On a BC delay claim the two-year period is not the deadline. It is the one you will still have when the others are gone.
Authorities
- Builders Lien Act SBC 1997, c 45Sets a 45-day period to file a claim of lien (s 20) with extinguishment as the consequence of missing it (s 22), a 55-day holdback period (s 8), a certificate-of-completion procedure (s 7), a one-year period to commence an action and register a certificate of pending litigation which the owner may compress to 21 days on notice (s 33), a trust over contract money received (s 10) with a hard one-year limitation (s 14) and a second trust over the holdback account (s 5(2)), an exemption for government entities and contracts under $100,000 (s 5(7)), a prohibition on applying the required holdback to damages (s 6), and a lien fund that is not reduced by counterclaims (s 34).The statutory text was obtained from BC Laws, the section numbers are primary-verified. The application of each provision to a delay claim rests on secondary commentary.Find on CanLII →
- Construction Prompt Payment Act Bill 20 (2025), Royal Assent 27 November 2025Once proclaimed, reduces the holdback period from 55 days to 46, abolishes the Shimco holdback lien, expands "improvement" to include demolition and removal, and introduces adjudication. With s 16 extending to approved and proposed change orders. It applies only to contracts entered into after commencement.Not in force as at 10 August 2026. No adjudication authority has been designated and the regulation consultation closed 7 July 2026. Unlike the Builders Lien Act, the text of this Act was not obtained from BC Laws for this corpus, so its section numbers and figures rest on secondary sources and should be checked against the statute before they are relied on.Find on CanLII →
- Limitation Act SBC 2012, c 13A basic limitation period of two years from discovery (s 6), a four-element discovery rule (s 8), an ultimate period of 15 years (s 21), and a restarting effect for acknowledgment and part payment (s 24). The Act is silent on contractual variation of a limitation period.Unlike the Builders Lien Act, the text of this Act was not obtained from BC Laws for this corpus (retrieval was blocked) so every section number and figure attributed to it rests on secondary sources. The s 24 acknowledgment and part-payment rule is recorded as . The silence on contractual variation is a recorded negative finding.Find on CanLII →
- Crown Proceeding Act RSBC 1996, c 89The statute governing proceedings against the Province. It contains no pre-suit notice provision, and there is no BC Public Works Act.The statutory text was obtained from BC Laws. The absence of a pre-suit notice provision is a searched negative finding recorded at two independent sources, not an inference from silence in commentary.Find on CanLII →
- Local Government Act RSBC 2015, c 1, s 736Reported to bar a claim for damages against a municipality in the absence of written notice within two months. and . The text was not obtained. One BC firm has published pieces with directly opposing titles on whether the provision is a limitation period or a notice condition, and the reported cases are personal injury and tort. Whether it reaches a contract or delay claim is unresolved and, on the language recorded, it probably does not. Verify before advising on any claim against a BC municipality.Find on CanLII →
- Supreme Court Civil Rules Rules 11-6, 15-1, 22-4 and 22-7Expert reports are served 84 days before trial and responding reports 42 days before trial (Rule 11-6). A proceeding in which no step has been taken for one year requires notice before it can proceed (Rule 22-4(4)), and may be dismissed for want of prosecution on application (Rule 22-7(7)). Rule 11-8, which capped expert evidence, is repealed.The rules text was obtained from BC Laws, the rule numbers are primary-verified. The two-hour examination-for-discovery limit under the fast-track rule, Rule 15-1, is recorded as . The application of these rules to a delay claim rests on secondary commentary.
- British Columbia Ministry of Transportation and Infrastructure, Major Works General Conditions Version 2026-04-01, GC 37.07, GC 41.01, GC 44.02, GC 44.03, GC 58.00–61.00An extension-of-time notice must be submitted not later than 14 days after the occurrence or the detection of the qualifying event (GC 44.03), a changed-condition notice runs to 7 days (GC 41.01), and 7 days is the default where no period is stated (GC 37.07). GC 44.02 conditions time relief on the Contractor having diligently proceeded and applied all reasonable means to complete.This document was obtained as a primary document for this corpus and is current as at the statement date, so the clause numbers and periods are primary-verified. The GC 58.00 to 61.00 dispute-resolution ladder is , the full text was truncated in retrieval, and whether it operates as a staged condition precedent is an inference to be checked clause by clause on any live matter.
- Penticton Regional Hospital Patient Care Tower Project Agreement Dated 6 April 2016, ss 8.2(a), 8.2(b), 8.2(h)Notice of a supervening event must be given within five Business Days after the applicant Has Knowledge that the event has caused an entitlement, additional details within 10 Business Days after delivery of the notice, and the parties meet within 15 Business Days, with dispute resolution available if the matter is unresolved 10 Business Days after that meeting.This document was obtained as a primary document for this corpus, so the clause numbers and periods are primary-verified for this project agreement. It is one project agreement dated 2016. Infrastructure BC project agreements follow a family resemblance rather than a single published standard form and drafting has evolved, notably on pandemic and climate risk after 2020, so treating these clause numbers as a BC standard form is as a generalisation.
- Site C Clean Energy Project, Main Civil Works Contract Dated 18 December 2015The BC Hydro form for the largest recent BC civil project. Its force majeure definition expressly excludes extreme or abnormal weather and flood, including any overtopping of the cofferdams.This document was obtained as a primary document for this corpus, so what was retrieved is primary-verified. The extension-of-time, notice and liquidated-damages provisions sit in Schedule 2 and Schedule 11, with a Dispute Notice defined in Schedule 14, and those schedules were not in the retrieved document, no notice period or time limit could be extracted. No general BC Hydro standard-form set of construction general conditions for non-Site-C work was located.
- CCDC 2 – 2020 Stipulated Price Contract GC 6.5, GC 6.5.3The private-work default. Delay and extension of time sit at GC 6.5, with the events limb at GC 6.5.3 covering labour disputes, fire, unusual delay by common carriers and any cause beyond the Contractor's control.The CCDC document was not obtained as a primary text for this corpus. Clause numbers are verified against publicly available contents pages and converging secondary sources, operative wording is reconstructed from those sources rather than quoted. The corpus's British Columbia notes do not fix a notice period or day count for GC 6.5. They say only "see the form" so no CCDC day count is stated on this page. Supplementary conditions almost universally amend GC 6.5 and must be read first.
- Doyle Construction Co v Carling O'Keefe Breweries 1988 CanLII 2844 (BCCA)Notice is a condition precedent to maintaining the claim.No BC judgment was read in original text for this corpus, the citation and holding rest on two or more independent secondary sources. It remains the governing BC authority on whether a contractual notice period is a condition precedent, and it is a 1988 decision. Verify on CanLII before pleading.Find on CanLII →
- Northland Kaska Corp v R 2001 BCSC 929, (2001), 10 CLR (3d) 190The grumblings of a contractor are not sufficient to constitute notice, and more precisely, an owner's knowledge of difficulty is not knowledge of an intention to claim.No BC judgment was read in original text for this corpus, the citation and holding rest on two or more independent secondary sources. The case is also styled v Yukon Territory and v Canada. It was itself a claim against the Crown, which makes it the most on-point BC authority for a public-works notice dispute. Verify on CanLII before pleading.Find on CanLII →
- Shimco Metal Erectors Ltd v Design Steel Constructors Ltd, sub nom Shimco Metal Erectors Ltd v North Vancouver (District) 2003 BCCA 193The Builders Lien Act creates a lien on the statutory holdback fund that is separate from and independent of the lien against the land, so a claimant may assert a claim against the holdback fund even where the land lien has been lost.No BC judgment was read in original text for this corpus, the citation and holding rest on two or more independent secondary sources. The style of cause conflicts between sources, CanLII styling it v North Vancouver (District) and the BC Appeal Cases report using v Design Steel Constructors Ltd, the neutral citation is verified. The claim that this dual-lien model is unique in Canada is as an exhaustive comparative statement. Verify on CanLII before pleading.Find on CanLII →
- Kingdom Langley Project LP v WQC Mechanical Ltd 2025 BCCA 169The Shimco holdback lien survives. Disagreement with the decision did not warrant overturning it, and legislative intervention rather than judicial action is required.No BC judgment was read in original text for this corpus, the citation and holding rest on two or more independent secondary sources. It is the authority for the statement that the Shimco lien is good law on 10 August 2026. Verify on CanLII before pleading.Find on CanLII →
- Rosas v Toca 2018 BCCA 191Proceeded on the basis that a limitation period may be varied by contract assuming without deciding the point, and required clear language describing a limitation period.No BC judgment was read in original text for this corpus, the citation and holding rest on two or more independent secondary sources. The proposition that parties may contract out of a BC limitation period is available on obiter and first-instance dicta only. Verify on CanLII before pleading.Find on CanLII →
- Public Works Act (Alberta) s 14(3), s 14.3(2)Alberta requires notice to the Crown within 45 days by registered mail (s 14(3)) and excludes schedule changes, milestone dates, relief events, changes in law and force majeure from adjudication on provincial public works by name (s 14.3(2)).An Alberta statute, recorded in this corpus at comparative level only. The section numbers are held in the corpus's Alberta material, the chapter citation is not, and no Alberta statutory text was obtained. It appears here solely as the contrast that makes the British Columbia negative finding legible, and should be checked against the Alberta statute before it is relied on.
About this material Library content is general information about construction claim practice, not legal advice. Entitlement, deadlines and procedure are governed by your own contract and by the law of the place the work is performed. Reviewed August 10, 2026 · Report a correction
In this article
- Which clock kills a British Columbia delay claim first?
- Four characters, and why the distinction decides your argument
- Contractual notice, the condition-precedent clocks
- The Builders Lien Act clocks: conditions of a security remedy
- The trust clock, a one-year limitation that runs from an event you may not hear about
- The Limitation Act, the clock that almost never bites, and the accrual date nobody knows
- Statutory preconditions to suing. The ones British Columbia does not have
- The procedural clocks, and how the whole set interacts