EOT claim checklist: is your extension of time claim ready to submit?

An extension of time claim is ready when a stranger to the project could check every assertion in it against a dated record. That means seven things are in place: the contract basis, a notice served in time to the right person, the records, a critical-path causation case, an honest account of concurrency and float, a net count of days (and cost, if claimed), and a document that ties them together. Notice is the only one you cannot repair later.

Reviewed Oct 13, 202611 min read8 sources

At a glance

General practice
Last reviewed
27 September 2026
Class
Practical page. A readiness checklist for project managers and contract administrators
Jurisdiction
Neutral, with pointers for FIDIC 2017, CCDC 2 – 2020 and AS 4000
Not legal advice
A working checklist. The executed contract, its amendments and the governing law decide what your claim needs
§ 00

Key facts

  1. 01

    When to run it

    Twice. Groups 1 to 3 the week the delay starts, because the notice clock is already running. All eight groups before the claim goes out.

  2. 02

    The check you cannot fix later

    Notice. Under FIDIC 2017 Sub-Clause 20.2.1 and CCDC 2 – 2020 GC 6.5.4 a late notice can bar the extension outright. In Panther [2022] DIFC CA 016 (on the 1999 form) the contractor lost its extension although all but 19 of the 325 days of delay were attributed to the employer.

  3. 03

    The earliest clock

    CCDC 2 – 2020 GC 6.5.4: 10 Working Days after the commencement of the delay, to the Consultant. Commencement, not awareness.

  4. 04

    The record that carries the claim

    The statused schedule update series, in native files, with a narrative for every logic change. In Alares a mid-project logic revision was rejected as making "no sense"; the VA was found responsible for 218 of the 765 days Alares attributed to it.

  5. 05

    The test causation must pass

    Delay to completion, not delay to progress. Delay to non-critical activities gives no extension, however well documented.

  6. 06

    The quantum rule

    Days are counted net, added to the previously fixed completion date, and money does not follow time automatically.

  7. 07

    The FIDIC 2017 second deadline

    The fully detailed Claim under Sub-Clause 20.2.4 is due within 84 days of awareness, as published commentary summarises it. Without the statement of contractual or legal basis in that period, the Notice of Claim is deemed to lapse (subject to the Engineer notifying the lapse within 14 days).

An extension of time claim is ready to submit when every statement in it points to a dated record, the notice was served in time to the right person, and the days claimed come from a critical-path analysis rather than from the completion date. Below is the checklist that tests that, in eight groups a project manager can tick off, plus the red flags that mean it is not ready yet.

Run it twice: groups 1 to 3 the week a delay starts, because the notice clock is already running, and all eight before the claim goes out. A tick means the document exists, you have found it, and you can cite its reference. Each group maps onto the four elements every extension of time claim must establish; the law sits on the linked pages, not here.

This is a working checklist, not legal advice. The executed contract, its amendments and the governing law decide what your claim needs. Each form's own vocabulary is used: Engineer under FIDIC, Consultant under CCDC, Superintendent under AS 4000.

§ 01

1. Contract and entitlement

The qualifying event is rarely where claims die, but it decides which clause you claim under, who you write to, and whether money follows.

§ 02

2. Notice

Notice is the only element you cannot rebuild afterwards, and the cheapest to get right. The letters, with placeholders and send-by rules, are on delay notice templates for AS 4000, FIDIC 2017 and CCDC 2; the law is on notice and time bars.

§ 03

3. Records

The records decide which analysis you can run, and that set closes long before the dispute. This group follows the SCL record categories and the dependency table on records and evidence. Under FIDIC 2017 the contemporary records relied on form part of the claim (Sub-Clauses 20.2.3 and 20.2.4, as commentary summarises them).

§ 04

Where Storia fits

Most ticks in the records group fail for the same reason: the document exists somewhere, but nobody can find the dated version that proves when the delay commenced. Storia turns drawings, RFIs, schedules, correspondence and field reports into one source-linked project record, built as the work happens, so every entry in the claim traces back to the document it came from. Teams can resolve the delay in coordination, or move from records to a claim-ready case in days instead of rebuilding the timeline months later.

§ 05

4. Causation and critical path

The question is whether the event delayed completion, not some work. Choosing the method is covered on delay analysis methods compared.

§ 06

5. Concurrency and float

The other side's first two arguments. Find them first. See concurrent delay.

§ 07

6. Quantum: the days, and the money if claimed

§ 08

7. The document

The drafting, step by step, is on how to write an EOT claim. This group checks the finished draft.

§ 09

8. After submission

§ 10

The checklist on one screen

GroupThe questionReady whenRead
1. ContractWhich clause, which gateway?Qualifying clause named, conditions provedExtension of time
2. NoticeIn time, to the right person, in the right form?Notice, proof of service, any money notice on fileNotice templates
3. RecordsCan each fact be proved from a dated record?Baseline, native updates with narratives, dailies, registers, photosRecords
4. CausationDid the event move completion?Critical-path chain, per event, by a method the records supportMethods
5. Concurrency and floatWhat were you and the float doing?Own delays and float addressedConcurrent delay
6. QuantumHow many days, what money?Net days; cost for the impact weeksProlongation
7. DocumentCan a stranger check it?Basis, notices, cited chronology, analysis, reservationsHow to write
8. After submissionWhat happens next, and when?Deadlines diarised, records continuing, no unreserved releasesNotice and time bars
§ 11

Frequently asked questions

What should an EOT claim include?

The qualifying event and clause; the notices already given; a dated chronology citing a record for every fact; a critical-path analysis showing delay to completion; the net days; any cost, priced for the weeks the effect was felt; reservations; and a records schedule. Under FIDIC 2017, commentary reports the fully detailed Claim must include a statement of contractual or legal basis within 84 days.

When should I submit an EOT claim?

Serve the notice first, within the contract's period: 28 days from awareness under FIDIC 2017 Sub-Clause 20.2.1, 10 Working Days from commencement of the delay under CCDC 2 – 2020 GC 6.5.4. Then submit the detailed claim within the contract's second deadline, and as close to the event as possible (SCL Core Principle 4).

What records do I need for an extension of time claim?

An accepted baseline, statused updates in native files with narratives for logic changes, daily reports, labour and plant records, the correspondence and notices register, RFI and submittal logs dated on both sides, and timestamped photographs. The records you hold decide which delay analysis methods you can run.

What if I missed the notice deadline?

Serve the notice now, state that it is late and why, and take advice. Under FIDIC 2017 the Engineer has 14 days to object to a late Notice, failing which it is deemed valid, though the Employer can still dispute it at the determination stage (Sub-Clause 20.2.5). Rescue arguments such as waiver or the owner's actual knowledge are fact-heavy, and in Panther the contractor lost its extension although all but 19 of the 325 days were attributed to the employer.

Notes

Sources and authorities

8 cited
  1. 1
    Steria Ltd v Sigma Wireless Communications Ltd[2007] EWHC 3454 (TCC), Technology and Construction Court

    The notice "must emanate from Steria" (at [82]): a minute prepared by the other side's representative would not by itself be valid notice.

    Find Case Law

  2. 2
    FIDIC Conditions of Contract for Construction (Red Book), 2nd Edition 2017, reprinted 2022Sub-Clause 8.5 (Extension of Time for Completion), Sub-Clauses 20.2.1 to 20.2.6 (Claims for payment and/or EOT)

    As published commentary summarises the 2017 form: Notice of Claim to the Engineer within 28 days after the Party became aware or should have become aware (20.2.1), with an express bar; the Engineer has 14 days to say a Notice is late, otherwise it is deemed valid (20.2.2); contemporary records (20.2.3); a fully detailed Claim within 84 days, and if the statement of contractual or legal basis is not given in that period the Notice of Claim is deemed to have lapsed (20.2.4); interim claims at monthly intervals and a final claim within 28 days of the end of the effects where the event has a continuing effect (20.2.6).

    Fenwick Elliott commentary

  3. 3
    CCDC 2 – 2020 Stipulated Price ContractCanadian Construction Documents Committee, GC 6.5 (Delays) and GC 6.6 (Claims for a Change in Contract Price)

    GC 6.5.4 bars any extension for delay unless Notice in Writing of the cause of delay is given to the Consultant not later than 10 Working Days after the commencement of the delay. GC 6.6.1 separately requires timely Notice in Writing of intent to claim money. GC 6.5.3 delays give time only.

    CCDC

  4. 4
    Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC[2022] DIFC CA 016 (judgment 12 May 2023), DIFC Court of Appeal

    The 28-day notice under Sub-Clause 20.1 of an amended FIDIC 1999 Red Book was a condition precedent: the contractor lost its extension of time although all but 19 of the 325 days of delay were attributed to the employer. A valid notice may be short, provided it reaches the Engineer in time.

    DIFC Courts

  5. 5
    Society of Construction Law, Delay and Disruption Protocol, 2nd Edition (February 2017)2nd Edition (February 2017), Society of Construction Law

    Core Principle 1: the programme should be updated to record actual progress, variations, changes of logic and any extensions granted, and the parties should agree the record regime at the outset. Core Principle 4: applications should be made and dealt with as close in time as possible to the delay event. Core Principle 5: an extension is granted to the extent the employer risk event is reasonably predicted to prevent completion by the then prevailing completion date, in general where it impacts the critical path. Core Principle 8: absent contrary provision, an extension is granted only to the extent employer delay is predicted to reduce total float on the critical path below zero. Core Principle 17 discourages global claims.

    Protocol

  6. 6
    Alares Construction, Inc. v Department of Veterans AffairsCBCA 6149, 7071, 7597 (21 March 2025), Civilian Board of Contract Appeals

    Alares attributed all 765 days of delay to the VA and sought extended general conditions for 653. The Board found the VA responsible for 218 days of critical path delay and Alares for the rest, and rejected a mid-project logic revision in Alares's schedule as making "no sense".

    CBCA

  7. 7
    George Sollitt Construction Co. v United States64 Fed. Cl. 229 (2005), United States Court of Federal Claims

    Delay affecting only non-critical activities does not delay completion. The expert's analysis was discounted for, among other things, progress reported as percentages rather than actual start and finish dates.

    Court of Federal Claims

  8. 8
    Walter Lilly & Co Ltd v Mackay[2012] EWHC 1773 (TCC), Technology and Construction Court (Akenhead J)

    No rule of law bars a claim that does not allocate loss to each event: the global approach goes to proof. The claimant must still comply with notice requirements, prove the events and causation, and support it with contemporaneous evidence.

    Find Case Law

General information, not legal advice. Reviewed Oct 13, 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…

Each issue links to the full articles in the Storia Library.