Skip to main content
19 min readReviewed August 7, 2026Method framework

Delay analysis methods

A delay analysis method is the technique used to prove that a qualifying event delayed contractual completion. The SCL Delay and Disruption Protocol, 2nd Edition (February 2017) names six. AACE International RP 29R-03 (rev. 25 April 2011) names nine. Which of them you can run is decided by the records you kept, not by the facts you want to prove.

Delay analysis methods, at a glance
The question it answers
Which forensic technique can be run on this project's record set to connect a qualifying event to critical delay, and which techniques the record set has already ruled out.
The controlling constraint
The method available to you is a function of the records you kept. A method whose data requirements the project record cannot meet is not an option, however well it suits the facts.
The two frameworks
SCL Delay and Disruption Protocol, 2nd Edition (February 2017): six methods, strategic frame. AACE International RP 29R-03, Forensic Schedule Analysis, rev. 25 April 2011: nine method implementation protocols, technical taxonomy.
The mapping is not a translation
The gaps run both ways. SCL's Retrospective Longest Path has no dedicated AACE MIP. AACE's MIP 3.4 contemporaneous split has no SCL analogue. Writing as though the two taxonomies are equivalents is an error.
The distinction most often got wrong
Impacted as-planned (MIP 3.6) inserts delay fragnets into the original baseline. Time impact analysis (MIP 3.7) inserts them into the baseline updated to the point of impact. The difference is the base, not the fragnet, and TIA therefore needs a contemporaneous update series that impacted as-planned does not.
What the 2nd edition changed
The 1st edition's preference for time impact analysis was removed for retrospective work. TIA is now positioned as the contemporaneous, prospective tool under Core Principle 4 and is not endorsed for time-distant analysis under Core Principle 11.
Methodology is not a rule of law
White Constructions Pty Ltd v PBS Holdings Pty Ltd [2019] NSWSC 1166: method must be driven by the factual evidence and the SCL Protocol is not a rule of law. Thomas Barnes & Sons plc (in administration) v Blackburn with Darwen Borough Council [2022] EWHC 2598 (TCC): experts are not confined to one SCL method.
What tribunals actually punish
Not method choice, data quality. Missing baselines, absent updates, percentage progress instead of actual dates, and unexplained schedule logic changes. No US decision 2023–2026 condemns a named forensic delay methodology.

Almost everything written about delay analysis presents the methods as a menu the analyst picks from on the merits, as though the facts of the delay select the technique. They do not. The records select the technique, and the record set was closed months or years before anyone thought about a claim.

A method whose data requirements your project record cannot meet is not an option. It does not matter that time impact analysis fits the fact pattern if the monthly updates were never statused, or that a collapsed as-built would be devastating if the as-built dates exist only as percentage complete. What is left after the record set has done its filtering is usually two methods, sometimes one, and occasionally none that a tribunal will accept.

So the order of the questions is: what do we have, then what can be run on it, then which of those survives cross-examination. Not the reverse. Delay analysis proves element two of the four-element test every extension of time claim has to satisfy (causation) and a method that cannot be run on the available data proves nothing at all.

Which methods can your records actually support?

Work from the record set inward. A baseline and an as-built alone support only the as-planned versus as-built family. A reliable series of contemporaneous updates supports windows analysis, which is the best-evidenced position available. Missing or corrupt updates push the analyst into recreated schedules or an as-built-only method, both of which are expensive and both of which invite attack. The table below is the whole practical payload of this subject.

What the record set containsMethod it supportsAACE MIPThe exposure
Baseline plus as-built onlyAs-planned versus as-built, gross or windowed3.1 / 3.2The floor. Fact-rooted and defensible, if unsophisticated. Does not show the critical path shifting
Reliable contemporaneous updates: dated, statused, with data dates, logic changes and narrativesSCL Time Slice Windows3.3 / 3.4The best-evidenced position. Requires clean statused updates, which is exactly what most projects lack
Updates missing or corruptRecreated updates, or SCL Retrospective Longest Path3.5 (no dedicated MIP for Retrospective Longest Path)Recreation invites the "reconstructed for litigation" attack. A last resort
Good baseline, poor as-builtModelled additive: impacted as-planned, time impact analysis3.6 / 3.7Weak. Fragnet construction and insertion point are both contestable
Rich as-built, weak baselineCollapsed as-built (but-for)3.8 / 3.9The inserted retrospective logic is the vulnerability, and it is always the first thing attacked
No accepted baseline at allNone reliablyImpacted as-planned and time impact analysis become unavailable in practice. The float argument collapses for both sides (SCL Protocol 2nd Edition (February 2017), Core Principle 9)

Two dependencies in that table are worth stating in their own right, because they are where most projects actually fail. First, no accepted baseline means no datum. The opponent attacks the baseline as unrealistic, and the employer's standing defence (the baseline was never accepted, so the contractor's own plan proves nothing) has no answer. Second, the loss of contemporaneous updates is the single largest evidential loss available on a construction project. It removes the entire dynamic family in one move and leaves only static methods that cannot show the critical path as it actually shifted.

SCL Delay and Disruption Protocol, 2nd Edition (February 2017), Core Principle 1 recommends that the parties agree the record regime in writing at or before the outset: types, who produces and checks them, frequency, format, ownership and storage. Almost nobody does it. It remains the cheapest risk mitigation available on any project, and it is the only point at which the method question is genuinely open. The full record-category analysis, and what each absence forecloses, sits in the records that decide whether you have a claim at all.

One contract override sits above all of this. If the contract mandates a method, it governs regardless of technical preference. NEC4 ECC clause 63.5 effectively mandates a prospective impact assessment against the Accepted Programme, and many US and Middle East EPC contracts mandate time impact analysis by name. A mandated method whose data requirements the project cannot meet is a contractual problem, not merely a forensic one.

How the methods sort: three axes, not a list of six

The six methods in the SCL Delay and Disruption Protocol, 2nd Edition (February 2017) are not a flat list. They sort on three axes that decide everything about how an analysis behaves: whether it is prospective or retrospective, whether the critical path is treated as static or dynamic, and whether it reasons cause to effect or effect to cause. Learn the axes and the six methods stop needing to be memorised.

#SCL methodStanceCausal directionCritical path determined byData required
1Impacted As-PlannedProspective, hypotheticalCause → effectAs-planned CPM onlyBaseline plus event list
2Time Impact AnalysisProspectiveCause → effectBaseline updated to the point of impact, fragnet insertedBaseline, contemporaneous updates, logic
3Time Slice WindowsRetrospective, dynamicEffect → causeContemporaneous updates sliced into windows. Critical path re-determined each windowFull set of contemporaneous updates plus records
4As-Planned versus As-Built WindowsRetrospectiveEffect → causeFact-based comparison per window. Less CPM-dependentAs-built records, as-planned, diaries, photos, correspondence
5Retrospective Longest PathRetrospective, staticEffect → causeSingle as-built longest path traced back from actual completionAs-built programme
6Collapsed As-Built (but-for)Retrospective, subtractiveEffect → causeAs-built with delay events extractedAs-built plus inserted retrospective logic

Read from the SCL Protocol 2nd Edition (February 2017). The three-axis sort is inferential: the corpus's own, not a classification the Protocol itself states.

The static/dynamic axis is the one that decides credibility on a real project. "The" critical path is a false singular: multiple critical paths, near-critical paths compressed to within days of criticality, and paths that become critical mid-project are all normal. Any analysis premised on a single fixed critical path across a whole project is either describing a very simple project or producing a modelling artefact. That is precisely why the dynamic methods: SCL Time Slice Windows, AACE MIP 3.3 and 3.4, exist: they re-determine the critical path in each window instead of assuming it.

The prospective/retrospective axis is set by the Protocol's own hinge. Core Principle 4 tells the parties not to "wait and see" and to deal with Employer Risk Events as the work proceeds. Core Principle 5 states the prospective test, grant an extension to the extent the event is reasonably predicted to prevent completion by the then prevailing date. Core Principle 11 is the hinge: where assessment occurs after completion or well after the event, "the prospective analysis of delay referred to in the guidance to Core Principle 4 may no longer be appropriate."

The choice of stance is itself a contested issue, and it moves the day count. Fluor Ltd v Shanghai Zhenhua Heavy Industry Co Ltd [2018] EWHC 1 (TCC) held that "a prospective analysis … does not necessarily produce the same answer as an analysis carried out retrospectively", expressly qualifying the suggestion in Walter Lilly & Co Ltd v Mackay [2012] EWHC 1773 (TCC) that a properly performed analysis of either kind should reach the same result. Where the contract picks a stance, it governs: NEC4 ECC clause 63.5 mandates a prospective assessment, and JCT's "fair and reasonable" assessment is prospective. An adjudicator revising a JCT extension of time must perform the contract's prospective assessment rather than a purely retrospective one (Mace Construct Ltd v Baltic Investment Holdings Ltd [2026] EWHC 976 (TCC)).

As to which method persuades: SCL method 4, as-planned versus as-built windows, is the one courts most often find persuasive, because it is fact-rooted rather than model-rooted. Methods 1 and 6 (impacted as-planned and collapsed as-built) are the most attacked. Method 5 is rarely used.

How the SCL methods map onto AACE 29R-03, and where they do not

They map, but they are not translations of each other, and the gaps run both ways. AACE International RP 29R-03, Forensic Schedule Analysis (rev. 25 April 2011) has no dedicated method implementation protocol for the SCL Protocol's Retrospective Longest Path. The SCL Delay and Disruption Protocol, 2nd Edition (February 2017) has no analogue for MIP 3.4, the contemporaneous split, or for MIP 3.5, recreated updates. Anyone writing as though the two taxonomies are a one-to-one dictionary is wrong in both directions.

SCL methodAACE MIPAACE taxonomyStanceData requiredVulnerability
As-Planned vs As-Built3.1Observational / Static / GrossRetrospectiveBaseline plus as-builtDoes not identify the shifting critical path
As-Planned vs As-Built Windows3.2Observational / Static / PeriodicRetrospectiveAs-built records, as-planned, diaries, photos, correspondenceWindow selection can be argued as self-serving
Time Slice Windows3.3 / 3.4Observational / Dynamic / Contemporaneous As-Is. Contemporaneous SplitRetrospective, dynamicFull set of contemporaneous updates plus recordsRequires clean, statused updates, which is exactly what most projects lack
Impacted As-Planned3.6Modelled / Additive / Single BaseProspective, hypotheticalBaseline plus event listIgnores as-built reality entirely. Heavily attacked
Time Impact Analysis3.7Modelled / Additive / Multiple BaseProspectiveBaseline, contemporaneous updates, logicFragnet construction and insertion point are both contestable
Collapsed As-Built (but-for)3.8 / 3.9Modelled / Subtractive / Single Simulation. Multiple BaseRetrospective, subtractiveAs-built plus inserted retrospective logicThe inserted logic is the vulnerability, and it is always the first thing attacked
Retrospective Longest Pathno dedicated MIPMaps loosely to as-built critical path analysisRetrospective, staticAs-built programmeRarely used. No AACE analogue to cite
no SCL analogue3.4Observational / Dynamic / Contemporaneous SplitRetrospectiveUpdates separable into progress and non-progress revisionsThe "half-step", isolates non-progress revisions from progress variance. Useful for concurrency, and with no SCL equivalent
no SCL analogue3.5Observational / Dynamic / Modified or RecreatedRetrospectiveReconstructed updatesRecreation invites the "reconstructed for litigation" attack. A last resort

Inferential where the taxonomies do not meet: the pairings follow Popescu's harmonisation, and the "no analogue" rows are the corpus's reading of the gaps, not a published concordance.

The mapping is drawn from Anamaria Popescu (Ankura), Harmonizing SCL D&D2 and AACE 29R-03 (5 November 2025, 11th International SCL Conference, Seoul), whose thesis is worth carrying whole: SCL supplies the strategic and principled frame, 29R-03 supplies the technical protocol, and a competent expert uses both. (The first row is worth a flag on the fact-versus-inference line: the Protocol's six-method table names the windowed variant. Treating the single gross comparison as the same family run once is an inference from the mapping, not a statement in the Protocol.)

Cite the AACE layers, not just the number. The useful part of 29R-03 is the taxonomy, which lets an expert say exactly what was done. The basic method is Observational (examine the schedules as they are) or Modelled, insert or extract delays and re-run CPM. Observational sub-layers are Static (single fixed critical path) versus Dynamic (critical path tracked as it shifts), and Gross (one analysis) versus Periodic (segmented). Modelled sub-layers are Additive (insert delay fragnets) versus Subtractive (extract them), and Single Base / Multiple Base / Single Simulation. Stating "MIP 3.3, observational / dynamic / contemporaneous as-is" tells a tribunal precisely what was done. Stating "a windows analysis" does not.

MIP 3.4, the gap on the SCL side, is not an academic curiosity. It isolates non-progress revisions (logic changes, calendar changes, re-sequencing) from actual progress variance, which is exactly the separation a concurrency argument needs to be tested properly. 29R-03's own commentary treats MIPs 3.1 to 3.5 as generally inadequate for rigorous concurrency and pacing analysis. That usually requires a modelled or split approach plus factual records. And 29R-03 is not the whole of AACE's claims guidance: AACE International RP 130R-23, Demonstrating Entitlement to Cumulative Impact Claims in Construction (15 May 2023) covers the cumulative-impact side and is frequently missed.

Time impact analysis or impacted as-planned?

Both are prospective, both reason from cause to effect, and both work by inserting delay fragnets into a schedule and re-running CPM. The difference is the base. Impacted as-planned inserts the fragnets into the original as-planned baseline: one base for every event, which is why AACE International RP 29R-03 (rev. 25 April 2011) classifies it as MIP 3.6, Modelled / Additive / Single Base. Time impact analysis inserts each fragnet into the baseline as updated to that event's point of impact: a different base per event, hence MIP 3.7, Modelled / Additive / Multiple Base.

Impacted as-planned: SCL method 1, AACE MIP 3.6
Time impact analysis: SCL method 2, AACE MIP 3.7
The base the fragnet enters
The original as-planned baseline, unchanged, for every event.
The baseline updated for actual progress to the point of impact, event by event.
AACE taxonomy
Modelled / Additive / Single Base.
Modelled / Additive / Multiple Base.
Records required
Baseline plus a list of events. Nothing else.
Baseline, the contemporaneous update series, and the logic in each update.
Relationship to as-built reality
None. The as-built record does not enter the calculation at all.
Enters through the update series, up to the point of impact only.
Principal line of attack
It ignores as-built reality entirely. The most heavily attacked of the six SCL methods.
Fragnet construction and the choice of insertion point are both contestable.

That distinction has a hard practical consequence, and it is the records point again in a different costume: a project with no reliable contemporaneous updates cannot run time impact analysis at all. It will be pushed down to impacted as-planned, the method with the lowest data requirement and the worst reputation. The choice between MIP 3.6 and MIP 3.7 is very rarely a free one.

The SCL Protocol's 2nd Edition changed its own position here, and the change is under-reported. The 1st edition (October 2002) expressed a preference for time impact analysis. The 2nd Edition (February 2017) removed that preference for retrospective work. Time impact analysis is now positioned as the contemporaneous, prospective tool under Core Principle 4, and is expressly not endorsed for time-distant analysis under Core Principle 11. Citing the Protocol as authority for running a TIA years after completion is citing a superseded edition.

One further trap for prospectively-assessed forms. Under NEC4 ECC, the assessment stands or falls on the Accepted Programme, and nobody can invent one: in Premier Modular Ltd v Maidstone and Tunbridge Wells NHS Trust [2026] EWHC 1404 (TCC) an NEC4 adjudication decision was refused enforcement in part because the adjudicator relied on an "updated" Accepted Programme when both parties agreed the programme had not been updated.

Is a named method a rule of law?

No. Three common-law jurisdictions have said so within the last seven years, in three different ways, and none of them treats either the SCL Delay and Disruption Protocol, 2nd Edition (February 2017) or AACE International RP 29R-03 (rev. 25 April 2011) as binding. What each requires instead is that the method be driven by the factual evidence, that the analyst say what was done, and that every departure from the named method be explained.

ForumPosition
AustraliaWhite Constructions Pty Ltd v PBS Holdings Pty Ltd [2019] NSWSC 1166: methodology must be driven by the factual evidence, and the SCL Protocol is not a rule of law. Both parties' delay experts were rejected
English TCCThomas Barnes & Sons plc (in administration) v Blackburn with Darwen Borough Council [2022] EWHC 2598 (TCC): "it would be wrong to proceed on the basis that, because the SCL Protocol identifies six methods, an expert is only allowed to choose one." Establish the as-built critical path, then find the effective cause. Departures are fatal only when "manifestly inappropriate" or unexplained
CanadaWalsh Construction v Toronto Transit Commission, 2024 ONSC 2782: departures from AACE 29R-03 are tolerable because the recommended practice itself "allows for various adjustments and options" and "usually requires subjective decisions by the expert", provided they are explained and grounded in contemporaneous records
US boards and courts[Negative finding] No decision 2023–2026 condemns a named methodology. The attack is always on inputs and contemporaneity
International arbitration29R-03 vocabulary is expected. Tribunals want the taxonomy label stated
Statutory adjudicationWhatever can be explained and tested in 28 days, which excludes most full CPM analyses

Jurisdictional. White Constructions (NSWSC), Thomas Barnes (TCC) and Walsh (ONSC) are all first instance. No appellate authority on method choice was located in any of them.

Two negative findings belong here, stated plainly rather than hedged, because knowing what cannot be argued is worth more than a paragraph of speculation.

There is no US decision between 2023 and 2026 condemning a named forensic delay methodology. Not time impact analysis, not collapsed as-built, not windows. A cross-examination premised on the proposition that a named method is discredited as such has no authority behind it in US practice.

There is no reported judgment deciding a case on "float suppression" as a named doctrine. Float suppression: artificial constraints, excessive lags, preferential logic dressed as physical logic, duration padding, open ends, resource-levelling artefacts, quiet baseline re-sequencing: is real, and it is run against baselines and updates by both sides. But it operates as an evidential and credibility attack, not a cause of action. Pleading it as though it were a freestanding wrong invites a strike-out of the label and loses the substance with it.

The convergent rule across every forum: pick the method the records support, state the taxonomy label, state the assumptions, and explain every departure from the named method.

What tribunals actually punish

Data quality, not method choice. The recurring findings across US, English and Canadian decisions are about missing baselines, absent updates, progress recorded as percentages rather than actual start and finish dates, and schedule logic that the contemporaneous documents do not support. A modest windows analysis run on clean statused monthly updates beats a methodologically orthodox analysis run on reconstructed or re-logicked schedules, every time.

Alares Construction, Inc. v Department of Veterans Affairs, CBCA 6149, 7071, 7597 (21 March 2025) is the sharpest recent demonstration of what that costs. The contractor claimed the Department of Veterans Affairs had caused all 765 days of delay. The Board found 218 days of VA-responsible compensable delay, adopting the owner's expert's critical-path analysis and drawing adverse inferences from unexplained schedule logic changes in the contractor's monthly updates. The contract required monthly updates reflecting activity and event changes and accurate actual-versus-planned progress. The failure to maintain them cost the contractor the benefit of the doubt on every contested period.

765Days of delay claimed against the VA
218Days found VA-responsible and compensable
28%Of the claimed delay, awarded

The older US authority is to the same effect. In George Sollitt Construction Co. v United States, 64 Fed. Cl. 229 (2005) the expert's analysis was discounted for missing baseline schedules, absent monthly updates during startup and completion, progress reported as percentages rather than actual start and finish dates, and inaccurate critical-path activity dates. None of those findings is about the technique the expert selected. They are all about the contemporaneous record the technique was run on.

How the delay analysis dies

  • The method presupposes records that do not exist. A time impact analysis run where the update series was never statused is a set of fragnets inserted into a baseline nobody accepted, dressed as MIP 3.7.
  • Unexplained logic changes. Alares Construction, Inc. v Department of Veterans Affairs, CBCA 6149, 7071, 7597 (21 March 2025): schedule logic "unsupported or contradicted by contemporaneous project documentation", and adverse inferences drawn. Keep a narrative with every update.
  • Recreated updates presented as contemporaneous ones. AACE MIP 3.5 is legitimate and sometimes unavoidable, but it must be labelled as recreation. Unlabelled, it becomes the "reconstructed for litigation" cross-examination.
  • Percentage progress instead of actual start and finish dates. George Sollitt Construction Co. v United States, 64 Fed. Cl. 229 (2005). The analysis was discounted on exactly this.
  • A programme asserted to be updated that was not. Premier Modular Ltd v Maidstone and Tunbridge Wells NHS Trust [2026] EWHC 1404 (TCC): an NEC4 adjudication decision refused enforcement in part for reliance on an "updated" Accepted Programme both parties agreed had not been updated.
  • The method is named but not labelled. "A windows analysis" is not a method statement. "MIP 3.3, observational / dynamic / contemporaneous as-is" is.
  • The departure is real but unexplained. Under Thomas Barnes [2022] EWHC 2598 (TCC) and Walsh Construction v Toronto Transit Commission, 2024 ONSC 2782, departures are survivable when reasoned and grounded in the contemporaneous record, and fatal when silent.
  • Programme issued as PDF. A PDF of a programme cannot be interrogated for logic, constraints or float. Issue and retain native schedule files.

Which edition are you citing?

Cite both frameworks with their dates, every time, because readers assume there is a newer one and because one of them has not been revised in fifteen years. As at August 2026 the SCL Delay and Disruption Protocol is in its 2nd Edition, February 2017, superseding the 1st edition (October 2002) and Rider 1 (July 2015). AACE International RP 29R-03, Forensic Schedule Analysis, stands at rev. 25 April 2011.

Both of those statements carry a qualification that ought to travel with them into an expert report.

AACE 29R-03. The public table of contents still shows rev. 25 April 2011. A draft revision circulated around 2023: regrouping the methods into four groups, with a public critique arguing that collapsed as-built should be moved to "available but not recommended", and no published revision has been located. AACE's member catalogue was not accessible for this note, so treat rev. April 2011 as current but check the AACE library before citing the revision date in an expert report. Citing 29R-03 undated reads as though the writer does not know it has not been revised in fifteen years.

SCL Protocol. No 3rd edition exists and no revision programme is announced. That finding rests on the absence of any 3rd edition on the SCL site and in 2025–26 commentary, and SCL International's protocols page was not retrievable. High confidence, not certainty.

One thing not to do: do not quote a paragraph number for the Protocol's six-method table. It is variously cited between 11.5 and 11.7 across published commentary, and the discrepancy is not resolved here. Cite the Protocol, the edition and the method by name. Leave the paragraph number out unless you have the PDF open in front of you. The same discipline applies to every clause citation in a delay report: form, edition and clause travel together or the citation is not a citation.

Choosing between the methods your records will support

The real choice is narrower than the literature suggests. You are not choosing among six SCL methods or nine AACE method implementation protocols. You are choosing among the two or three that your record set can carry, filtered further by whatever the contract mandates and by whether the assessment is contemporaneous or time-distant. Run those filters honestly and the decision usually makes itself.

The filters, in the order they actually bite:

  1. What does the record set contain? An accepted baseline with logic, constraints and calendars? A complete statused update series with narratives? Native schedule files or PDFs? Daily reports, and RFI and submittal logs dated on both sides? Answer this before naming a method, not after.
  2. Does the contract mandate a method or a stance? NEC4 ECC clause 63.5 effectively mandates a prospective impact assessment against the Accepted Programme. Many US and Middle East EPC contracts mandate time impact analysis by name. A mandated method governs regardless of technical preference.
  3. Is the assessment contemporaneous or time-distant? SCL Delay and Disruption Protocol, 2nd Edition (February 2017), Core Principles 4 and 5 govern while the works are live. Core Principle 11 is the hinge to retrospective analysis once the assessment is time-distant.
  4. Is concurrency in issue? If so, note that AACE International RP 29R-03 (rev. 25 April 2011) treats MIPs 3.1 to 3.5 as generally inadequate for rigorous concurrency and pacing analysis without a modelled or split approach plus factual records.
  5. Have you stated the taxonomy label and explained every departure? Name the SCL method and the AACE MIP with its full taxonomy string, then justify each departure: reasoned and grounded in contemporaneous records under Thomas Barnes & Sons plc (in administration) v Blackburn with Darwen Borough Council [2022] EWHC 2598 (TCC) and Walsh Construction v Toronto Transit Commission, 2024 ONSC 2782. Fatal when silent.

If the filters leave nothing (no accepted baseline, no update series, no individuated causal links) what is left is a total time claim: the extension asserted as actual completion minus contractual completion, against a bundle of employer events with no critical-path attribution. It is the weakest form of extension of time claim there is, and SCL Delay and Disruption Protocol, 2nd Edition (February 2017), Core Principle 17 discourages exactly that practice. Advanced as a first resort it reads as a concession that the records were not kept, and tribunals read it that way.

Which returns the whole subject to where it started. The method is not chosen when the dispute starts. It is chosen when the record regime is set, or allowed to drift, at the outset of the works. By the time anyone is arguing about MIP 3.6 versus MIP 3.7, that decision was taken months or years earlier by people who were not thinking about a claim at all.

Authorities

  1. Society of Construction Law, Delay and Disruption Protocol, 2nd Edition (February 2017) 2nd Edition, February 2017, superseding the 1st edition (October 2002) and Rider 1 (July 2015)The six-method framework and the Core Principles that decide the stance: Core Principles 4 and 5 while the works are live, Core Principle 11 as the hinge to retrospective analysis, Core Principle 9 on float where there is no accepted baseline, and Core Principle 17 discouraging total time claims.Do not quote a paragraph number for the six-method table. It is variously cited between 11.5 and 11.7 across published commentary and the discrepancy is not resolved in this corpus, so no paragraph number is published here. Separately, the finding that no 3rd edition exists rests on the absence of any 3rd edition on the SCL site and in 2025–26 commentary, and SCL International's protocols page was not retrievable. High confidence, not certainty.Protocol
  2. Fluor Ltd v Shanghai Zhenhua Heavy Industry Co Ltd [2018] EWHC 1 (TCC), Technology and Construction Court"A prospective analysis … does not necessarily produce the same answer as an analysis carried out retrospectively", expressly qualifying Walter Lilly. The choice of stance is itself a contested issue and it moves the day count.Find Case Law
  3. Walter Lilly & Co Ltd v Mackay [2012] EWHC 1773 (TCC), Technology and Construction CourtSuggested that a properly performed analysis, prospective or retrospective, should reach the same result, the suggestion qualified in Fluor.The global-claims synthesis is commonly cited at ¶486. That paragraph number is taken from secondary sources and is not verified in this corpus.Find Case Law
  4. Mace Construct Ltd v Baltic Investment Holdings Ltd [2026] EWHC 976 (TCC), Technology and Construction CourtAn adjudicator revising a JCT extension of time must perform the contract's prospective "fair and reasonable" assessment rather than a purely retrospective one.Find Case Law
  5. AACE International Recommended Practice No. 29R-03, Forensic Schedule Analysis rev. 25 April 2011The nine method implementation protocols and the taxonomy (observational or modelled, static or dynamic, gross or periodic, additive or subtractive) that let an expert state exactly what was done. Its own commentary treats MIPs 3.1 to 3.5 as generally inadequate for rigorous concurrency and pacing analysis.The public table of contents still shows rev. 25 April 2011. A draft revision circulated around 2023: regrouping the methods into four groups, with a public critique arguing that collapsed as-built should move to "available but not recommended", and no published revision has been located. AACE's member catalogue was not accessible for this corpus, so treat rev. April 2011 as current but check the AACE library before citing the revision date in an expert report.Table of contents
  6. AACE International Recommended Practice No. 130R-23, Demonstrating Entitlement to Cumulative Impact Claims in Construction 15 May 2023AACE's cumulative-impact guidance, which sits outside 29R-03 and is frequently missed when 29R-03 is treated as the whole of AACE's claims material.Table of contents
  7. Premier Modular Ltd v Maidstone and Tunbridge Wells NHS Trust [2026] EWHC 1404 (TCC), Technology and Construction CourtAn NEC4 adjudication decision refused enforcement in part because the adjudicator relied on an "updated" Accepted Programme when both parties agreed the programme had not been updated.Find Case Law
  8. White Constructions Pty Ltd v PBS Holdings Pty Ltd [2019] NSWSC 1166, Supreme Court of New South WalesMethodology must be driven by the factual evidence and the SCL Protocol is not a rule of law. Both parties' delay experts were rejected.Find on AustLII
  9. Thomas Barnes & Sons plc (in administration) v Blackburn with Darwen Borough Council [2022] EWHC 2598 (TCC), Technology and Construction Court"It would be wrong to proceed on the basis that, because the SCL Protocol identifies six methods, an expert is only allowed to choose one." Establish the as-built critical path, then find the effective cause. Departures are fatal only when manifestly inappropriate or unexplained.Find Case Law
  10. Walsh Construction v Toronto Transit Commission 2024 ONSC 2782, Ontario Superior Court of JusticeDepartures from AACE 29R-03 are tolerable because the recommended practice itself "allows for various adjustments and options" and "usually requires subjective decisions by the expert", provided they are explained and grounded in contemporaneous records.Find on CanLII
  11. Alares Construction, Inc. v Department of Veterans Affairs CBCA 6149, 7071, 7597 (21 March 2025), Civilian Board of Contract Appeals218 of the 765 claimed days were found VA-responsible and compensable. The Board adopted the owner's expert's critical-path analysis and drew adverse inferences from unexplained schedule logic changes in the contractor's monthly updates.Not a release case. The Board upheld the reservation of rights in modification P00005. The claim then failed on concurrency, an independent ground.CBCA
  12. George Sollitt Construction Co. v United States 64 Fed. Cl. 229 (2005), United States Court of Federal ClaimsThe expert's analysis was discounted for missing baseline schedules, absent monthly updates during startup and completion, progress reported as percentages rather than actual start and finish dates, and inaccurate critical-path activity dates. None of the findings is about the technique selected.Court of Federal Claims