Valuation and the pricing ladder
Almost every construction contract values a variation by climbing a ladder (contract rates, then adjusted rates, then a fair valuation, then daywork) and a party may not skip a rung because it prefers the answer further up. NEC4 is the exception: it prices every compensation event as forecast Defined Cost plus Fee.
At a glance
- Doctrine
- valuation rules · pricing hierarchy · star rates · fair rates and prices
- Element 4 of the variation claim
- General practice · JCT, NEC4, FIDIC, AIA, FAR, CCDC, AS 4000
Key facts
- 01
The four rungs
Similar character, similar conditions, no significant quantity change → contract rates. Similar character but changed conditions or quantity → rates as the basis plus a fair allowance. Not of similar character → fair rates and prices. Cannot properly be valued by measurement → daywork.
- 02
You fall to a rung. You do not elect one
Daywork is a residual rule. The employer's standard and usually successful answer to a daywork account is that the work could have been measured, so rung 4 was never reached.
- 03
NEC4 has no ladder
NEC4 ECC clause 63.1 assesses every compensation event on Defined Cost plus Fee: actual for work done by the dividing date, forecast for work not done. Even under Option B the bill rates price the works as originally described and are not a valuation mechanism for change.
- 04
Rates are sacrosanct
Henry Boot Construction Ltd v Alstom Combined Cycles Ltd [2000] BLR 247 (CA): contract rates are not subject to correction merely because a party is dissatisfied. A mistaken rate must be used. The rule binds an under-priced contractor exactly as it binds an over-charged employer.
- 05
A numeric gate and a judgment standard
FIDIC Red Book 2017 clause 12.3 gates a new rate behind four cumulative arithmetic conditions. JCT and AS 4000 use evaluative language: "similar character", "changed conditions", "reasonably applicable". A 9% quantity change is arguable under JCT and hopeless under FIDIC limb (a).
- 06
Fair valuation carries profit
Weldon Plant Ltd v The Commission for the New Towns [2000] EWHC Technology 76 at [18]: "an employer must pay profit in valuations made under any rule". Head office overhead enters as a percentage from the contractor's accounts. Site overheads must be proved as incurred.
- 07
FIDIC "Cost" excludes profit
FIDIC 2017 clause 1.1.19 defines Cost as expressly excluding profit. Clause 1.1.20 "Cost Plus Profit" is Cost plus 5% unless otherwise stated. Writing it the other way round is a real-money error and it is made constantly.
- 08
The valuation prices the changed work only
Prolongation, disruption and thickened preliminaries travel by a different route: loss and expense under JCT Section 4, an Article 15 claim under AIA A201–2017, equitable adjustment for impact under FAR, a clause 20.2 claim under FIDIC 2017. NEC4 is the sole exception.
Valuation is where variation money is actually won and lost, and it runs on a hierarchy that is routinely misapplied. Four rungs (contract rates, adjusted contract rates, a fair valuation, daywork) applied in order, with each rung available only because the one above it has failed. The recurring mistake is treating the ladder as a menu.
Two things make this harder than it looks. The first is that the rungs are triggered by different tests in different forms: FIDIC gates the move off contract rates behind arithmetic, JCT behind judgment, AS 4000 behind reasonableness. The second is that one major form has no ladder at all, and practitioners who learned their valuation on JCT or FIDIC routinely misprice NEC4 work as a result.
Everything below assumes the scope question is already settled. If it is not (if the argument is still about whether the work was inside the original scope at all) valuation is premature, and the wider machinery is set out in the variation claims pillar.
What the pricing ladder is, and why you fall to a rung rather than pick one
The pricing ladder is the sequence of valuation rules almost every measurement-based construction contract applies to a variation: contract rates where the work is of similar character executed under similar conditions without significant change in quantity, contract rates as the basis with a fair allowance where character is similar but conditions or quantities have changed, fair rates and prices where the work is not of similar character, and daywork where the work cannot properly be valued by measurement. You do not elect a rung. You fall to it.
The sequence is not a modern invention and it has been construed judicially. In Weldon Plant Ltd v The Commission for the New Towns1 [2000] EWHC Technology 76, [2001] 1 All ER (Comm) 264, HHJ Humphrey Lloyd QC read ICE clause 52(1) as three sequential rules, bill rates for work of similar character and conditions, bill rates "so far as may be reasonable" as the basis for dissimilar work, and "failing which a fair valuation shall be made". The modern JCT, FIDIC and AS drafting is the same structure with different words.
The practical consequence of "fall, don't elect" is asymmetric and it favours whoever is defending the account. A contractor arguing for a fair valuation must first defeat the contract rate. A contractor running a daywork account must first show the work could not properly have been measured. In both cases the burden sits on the party climbing down the ladder, which is almost always the contractor.
Where each contract form puts the ladder
Every form in common use puts the ladder somewhere different, calls the rungs something different, and hands the fallback determination to a different person. The table below is the ladder as each form actually writes it. Note that two entries are not ladders at all: NEC4 ECC prices from first principles, and the FAR equitable adjustment is a single compensatory measure with no rung hierarchy. Every table in this article states form-default positions: bespoke amendment to valuation provisions is normal on major projects, and the executed contract governs.
| Form and location | Rung 1 | Middle rungs | Last rung | Who decides if not agreed |
|---|---|---|---|---|
| JCT DB 2024: cl 5.4 Measurable Work, cl 5.5 Daywork, cl 5.6 change of conditions for other work | Contract Sum Analysis / Priced Document rates for work of similar character, similar conditions, no significant change in quantity | Similar character but changed conditions or quantity (rates as the basis plus a fair allowance. Not of similar character) a fair valuation | Daywork (cl 5.5) where the work cannot properly be valued by measurement | Employer's Agent's valuation, then the dispute machinery |
| JCT SBC 2024, Valuation Rules cl 5.6–5.10 | Same-rate rule for measurable work | Pro-rata / fair-allowance rule, then fair rates and prices. Cl 5.9 values other work affected by the Variation | Daywork (cl 5.7) | Quantity Surveyor's valuation |
| NEC4 ECC, cl 63.1 | No ladder. Change to the Prices is the effect on Defined Cost plus Fee: actual for work done by the dividing date, forecast for work not done | Rates and lump sums only by agreement (cl 63.2) | – | Project Manager's own assessment, cl 64, and only through the gateways cl 64 specifies |
| AIA A201–2017: §7.3.3 methods, §7.3.4 default | Mutual acceptance of a lump sum with substantiating data | Unit prices, or cost determined in an agreed manner plus a mutually acceptable fixed or percentage fee | – | Architect's determination under §7.3.4 on a closed cost list, plus a reasonable allowance for overhead and profit |
| FAR 52.243-4 | Equitable adjustment. The difference between what the work would reasonably have cost as originally required and what it reasonably cost as changed, plus profit on the increase | Allowability governed by the FAR Part 31 cost principles. Profit negotiated under the FAR 15.404-4 weighted guidelines | – | Contracting Officer's unilateral determination, then a claim under the Contract Disputes Act |
| CCDC 2 – 2020: GC 6.2 Change Order, GC 6.3 Change Directive | GC 6.2 contains no valuation methodology at all. A Change Order is pure agreement | – | GC 6.3 Change Directive: actual cost of the listed items plus a percentage fee | Consultant's finding |
| AS 4000:2025, cl 36 | Prior agreement between Principal and Contractor | Applicable rates in the Contract. Then rates in a priced bill, schedule of rates or schedule of prices even though not Contract documents, so far as reasonable | Reasonable rates or prices, including a reasonable amount for profit and overheads | Superintendent's determination |
| FIDIC Red Book 2017: cl 12.3, applied by cl 13.3 | The rate or price for the item in the Bill of Quantities or Schedules | A rate derived from a comparable item with reasonable adjustments. Then a new rate where the cl 12.3 conditions are met | Reasonable Cost of executing the work together with Profit | Engineer's cl 3.7 determination, then DAAB |
Form-default. The rungs and clause locations are read off the published forms. Bespoke amendment is normal on major projects, and the executed contract governs.
Five caveats belong on the face of that table rather than in a footnote.
The AIA number is §7.3.4, and it is not a cost-plus-percentage provision. In AIA A201–2017 the Architect's determination and its cost list sit at §7.3.4. That provision was §7.3.7 in A201–2007, and commentary still citing §7.3.7 is working from the superseded edition. Nor is §7.3.4 a percentage default: it is a closed cost list, framed in "shall be limited to" language, with a reasonable allowance for overhead and profit added on an increase only. The percentage-fee concept sits one level up at §7.3.3 and is a consensual method, not the fallback. The enumerated cost categories in §7.3.4 were not read verbatim for this article and are therefore not reproduced here. Read them off the printed form before you plead them.
JCT SBC 2024 sub-clause numbers. The sequence of the SBC 2024 Valuation Rules at clauses 5.6–5.10 is verified. The sub-clause numbers commonly quoted for the three measurable-work limbs (5.6.1.1, 5.6.1.2, 5.6.1.3) were carried forward from JCT SBC 2016 and not read from the 2024 text. Cite the rule, not the decimal, unless you have the printed form in front of you.
AS 4000:2025 sub-clause numbers are not given here. The standard is paywalled. For the 1997 edition the clause 36 numbering is confirmed from a public amended copy (36.1 Directing Variations, 36.2 Proposed Variations, 36.3 Variations for convenience of Contractor, 36.4 Pricing); summaries that put pricing at 36.2 are wrong for 1997. The four-limb hierarchy is reported by firm summaries for AS 4000 and AS 4902, but it is not verified from an unamended standard: the amended AS 4000-1997 copy read has had its last limb deleted, and the one AS 4902-based contract read (in Kaloriziko) orders its limbs differently and fixes margin by Annexure percentages. It is not confirmed against the 2025 text either. Nothing in the 2025 commentary suggests the hierarchy changed. Cite "AS 4000:2025 clause 36" and check the sub-number against the standard before pleading it.
CCDC 2 – 2020 has a percentage problem. The form values a Change Directive as actual cost plus a percentage fee for overhead and profit. Two independent sources report a 10% allowance where not otherwise agreed. A competing reading of GC 6.3 is that the form specifies no percentage at all and defers entirely to the Contract Documents or the parties' agreement, so that on an unsupplemented CCDC 2 with a blank fee entry the percentage is undefined and becomes a live dispute in every Change Directive. Sub-paragraph numbering within GC 6.3 is unverified. Fill the fee in at tender and the question never arises.
FIDIC's Yellow and Silver Books have no Clause 12. They are lump-sum contracts with no remeasurement, and variations are valued entirely within Sub-Clause 13.3.1. A Schedule of Rates and Prices applied so far as relevant, and otherwise Cost plus Profit. In the Silver Book the Employer performs the valuation function directly, so there is no neutral determiner at all and disputes go straight to the DAAB.
Why NEC4 has no ladder at all
NEC4 ECC rejects the pricing ladder entirely. NEC4 ECC clause 63.1 assesses the change to the Prices for a compensation event as the effect on actual Defined Cost of work done by the dividing date, forecast Defined Cost of work not yet done, and the resulting Fee. There is no rung 1, no contract-rate presumption, and no fair valuation. Every compensation event is priced from first principles, whether it is worth GBP 500 or GBP 5 million.
That design decision does something no other form does: it makes rate abuse structurally impossible. There is no rate to be front-loaded, no windfall to be captured by a quantity increase, and no argument about whether the work is of similar character. Even under Option B, priced with a bill of quantities, the bill rates price the works as originally described and are not a valuation mechanism for change. The one qualification is clause 63.2, new in NEC4 and elevated to a core clause: the Project Manager and Contractor may agree to use rates and lump sums to assess the change. It is optional and agreement-based (neither party can impose it) and it is the most underused provision in clause 63, because it short-circuits Defined Cost forensics on low-value and repetitive changes.
NEC4 removes the rate as a thing to argue about, and relocates the dispute to Defined Cost: forecast assumptions, disallowed cost and the Fee percentage. That is not a smaller fight.
The dividing date under clause 63.1 is the date of the Project Manager's or Supervisor's instruction or communication where the compensation event arises from one, and the date of notification for everything else. Work before it is valued on actual Defined Cost. Work after it on forecast Defined Cost, and the forecast is not revisited when the outturn is known, implementation is final under NEC4 ECC clause 66. Which cost schedule applies inverts most people's expectation: Options A and B, the priced options, use the Short Schedule of Cost Components, because there is no ongoing open-book regime and a simplified basis reduces argument. Options C, D and E, the cost-based options, use the full Schedule of Cost Components, because Defined Cost is already being administered open-book for payment.
Northern Ireland Housing Executive v Healthy Buildings (Ireland) Ltd2 [2017] NIQB 43 remains the leading decision on the resulting tension. Where quotations were never agreed contemporaneously, the court permitted retrospective assessment using actual cost records, invoking the mutual trust and co-operation obligation. It is Northern Irish and not binding in England, but it is universally cited and it cuts both ways: a contractor that never submitted quotations cannot insist on a generous forecast when the actuals say otherwise, and an employer that never assessed cannot complain when actuals are used. Beyond it there is very little: no published English authority on NEC4 compensation-event valuation disputes exists, because they are overwhelmingly resolved in adjudication and are therefore structurally unreported. That absence is a feature of the regime, not a gap in the research.
When does a contract rate stop applying?
A contract rate stops applying when the valuation rules themselves say so, and not before. Every form draws that line differently, and the difference decides how the argument has to be run: FIDIC 2017 uses a numeric gate, JCT uses a judgment standard, and AS 4000:2025 uses a reasonableness standard. A numeric trigger and a judgment standard are different animals to argue, and they reward completely different evidence.
FIDIC Red Book 2017, clause 12.3, four cumulative conditions. A new rate is appropriate for a Bill item on the arithmetic route only where all four are satisfied: the measured quantity has changed by more than 10% from the Bill quantity, that change multiplied by the Bill rate exceeds 0.01% of the Accepted Contract Amount, that change directly changes the Cost per unit quantity by more than 1%, and the item is not specified as a fixed-rate item.
Those four conditions are reported consistently across the commentaries, but the verbatim text of FIDIC 2017 clause 12.3 was not read, run the arithmetic from the printed form before you build a case on it. The alternative route is clause 12.3's second limb: work instructed under Clause 13 for which no rate is specified and no specified rate is appropriate, because the work is not of similar character or not executed under similar conditions. That limb is evaluative, and it is where a contractor whose arithmetic fails must go.
JCT DB 2024 clause 5.4 and JCT SBC 2024 clauses 5.6–5.10: judgment. The triggers are "similar character", "similar conditions" and "significant change in quantity", and the remedy where character is similar but conditions or quantity have changed is contract rates as the basis plus a fair allowance for the difference. There is no threshold, no percentage and no arithmetic. There is also, and this is worth stating plainly, no case law construing what a "fair allowance" means where quantities have changed under the JCT Valuation Rules. That is a real gap in English authority, not an omission from this article.
AS 4000:2025 clause 36: reasonableness, twice over. The Superintendent applies contract rates, then rates in a priced bill or schedule of rates even though not Contract documents, "to the extent that it is reasonable to use them" (the wording of the public amended AS 4000-1997 copy read; the 2025 text was not read), and only then, as firm summaries report it, reasonable rates including profit and overheads. The middle limb is unusually wide and it is a trap: a tender-stage rate build-up submitted for evaluation is capable of being used against the contractor in variation pricing even though it never became a contract document. Assume anything priced and handed over is reachable.
The practical consequence of the FIDIC/JCT divide is easy to state and expensive to learn. A contractor with a loss-making rate and a 9% quantity change has no route at all under FIDIC's first limb and an arguable one under JCT. Under FIDIC, run the arithmetic before you write anything else. If it fails, the only argument left is character and conditions.
The sacrosanct rate cuts both ways
Contract rates are, in the English formulation, "sacrosanct, immutable, and not subject to correction" merely because a party is dissatisfied with them. Henry Boot Construction Ltd v Alstom Combined Cycles Ltd3 [1999] BLR 123 (TCC), affirmed [2000] BLR 247 (CA), is the authority. Boot had mis-priced temporary sheet piling, variations increased the quantity and generated a windfall, Alstom argued for a fair revaluation and the Court of Appeal refused. A mistaken rate must be used to value the variation.
The rule is defensible precisely because it is symmetrical. An under-priced rate binds the contractor exactly as an over-priced rate binds the employer, and that is the price of a bargain in which rates are fixed at tender and both parties price the risk of being wrong. Contractors discover this on the loss-making side far more often than they enjoy it on the windfall side, because the quantities that grow are rarely the ones that were priced generously.
The front-loading defence. An employer facing a windfall claim on an inflated rate has three moves, in descending order of strength.
- Attack scope, not rate. Argue the work is not of similar character, so the rate does not apply at all and the fair-valuation rung governs. This is far stronger than asking a tribunal to correct a rate it has just been told is sacrosanct, and it is the argument employers most often fail to run.
- Attack conditions. Show the work was not executed under similar conditions, which moves the valuation to rates-as-basis-plus-fair-allowance and reopens the number legitimately.
- Argue the fair allowance can adjust downwards. Whether a "fair allowance" can be used to reduce an over-generous rate where conditions have changed is contested and undecided: no authority on the point was located, and it is framed as an open question in practitioner commentary. Two counterweights sit against it: Henry Boot itself is against reopening rates on grounds of dissatisfaction, since the fair allowance adjusts for the difference in conditions rather than for the rate's inherent generosity, and Van Oord UK Ltd v Dragados UK Ltd4 [2021] CSIH 50 is adverse to an employer whose change of conditions was self-inflicted. There, Dragados moved a third of the works elsewhere and then relied on the reduced volume to argue the rate should fall from GBP 7.48/m³ to GBP 3.80/m³, the court held that a compensation event which is a breach of contract does not reduce total Defined Cost, and that the mutual trust obligation prevents a party enforcing terms arising from its own breach.
For a contractor sitting on a bad rate, the corollary is that the evidence which wins is evidence about conditions (access, sequence, working hours, weather window, plant availability, gang size) recorded contemporaneously. Comparing your cost to your rate proves only that you priced it badly, which is the one thing Henry Boot says is irrelevant. The "rates are wrong" argument is the single most-attempted and least-successful move in variation valuation. Budget accordingly.
Overhead and profit: three structural models, and what a fair valuation must contain
Standard forms pay overhead and profit on a variation in one of three structurally different ways, and confusing them is how margin gets left on the table. Percentage addition: CCDC 2 – 2020 GC 6.3 adds a percentage fee to the listed actual costs of a Change Directive, and FIDIC 2017 adds a default 5%. Fee percentage: NEC4 ECC carries all overhead and profit inside the Fee applied to Defined Cost, so there is no separate claim for either. Open valuation, JCT's fair valuation and AIA A201–2017 §7.3.4's reasonable allowance for overhead and profit both require the number to be built and justified rather than read off a rate.
| Form | Site overhead / preliminaries | Head office overhead | Profit |
|---|---|---|---|
| JCT DB 2024 / SBC 2024 | Adjusted where the Change affects preliminary items. SBC cl 5.9 values other work affected | Not in the valuation, loss and expense under Section 4 | Included in a fair valuation |
| NEC4 ECC | Inside Defined Cost, per the applicable Schedule of Cost Components | Inside the Fee percentage | Inside the Fee percentage |
| AIA A201–2017 | Within the §7.3.4 cost determination | Only through the overhead-and-profit allowance, home office is not in the §7.3.4 cost list | "As set forth in the Agreement", or a reasonable amount. Only on an increase |
| FAR 52.243-4 | Allowable field overhead per FAR Part 31 | Unabsorbed overhead by Eichleay5, and only on government-caused standby, on strict prerequisites | Negotiated, weighted guidelines |
| CCDC 2 – 2020 | Actual cost of the listed items under GC 6.3 | Within the percentage fee | Within the percentage fee. Added on a net increase, not deducted on a net decrease |
| AS 4000:2025 | Reasonable rates under the last limb of cl 36 | Reported as excluded from deductions on omissions, unverified against the standard | Yes, expressly, under the last limb |
| FIDIC 2017 | In the rate, or in the new rate | Depends on the Cost definition and the Particular Conditions | 5% default under cl 1.1.20 |
Form-default, with the AS 4000:2025 head-office entry unverified against the standard. Bespoke amendment is normal on major projects, and the executed contract governs.
The FIDIC definition that gets written backwards. FIDIC 2017 clause 1.1.19 defines "Cost" as expressly excluding profit. Clause 1.1.20 defines "Cost Plus Profit" as Cost plus 5% unless otherwise stated in the Particular Conditions. Every entitlement in the form that gives "Cost" alone gives no margin, and every entitlement that gives "Cost Plus Profit" gives 5%. Practitioners routinely assert that FIDIC "Cost" includes profit. It does not, and the difference is 5% of every Cost-based head on the project.
Fair valuation includes profit. It does not include head office overhead as a prolongation claim. Weldon Plant Ltd v The Commission for the New Towns [2000] EWHC Technology 76 is the authority, and it holds three things, all load-bearing. Profit must be included: "a contractor is in business to make profit on costs of deploying resources, and accordingly an employer must pay profit in valuations made under any rule" (at [18]). The arbitrator's exclusion of profit was an error of law. Overheads split in two and are proved differently: time-related and site overheads must be proved as actually incurred, or shown to have been denied recovery. Contribution to fixed head office overheads need not be individually proved, but must be included via a reasonable percentage derived from the contractor's accounts (at [19]). And the governing principle is restorative: a fair valuation puts the contractor in the financial position it would have occupied had the variation not been instructed, provided the costs were reasonably and properly incurred.
One asymmetry worth carrying: on deleted work, AIA A201–2017 §7.3.8 measures the credit as actual net cost, so the Contractor keeps its overhead and profit on the deletion, and where a change bundles additions with credits for related work, overhead and profit are figured on the net increase only. CCDC 2 – 2020 GC 6.3 reaches the same commercial result by a different route, reducing the price on a net decrease without adjusting the percentage fee. AS 4000 is reported to run the opposite way on deductions (profit but not overheads) but that limb is unverified against the standard and should be checked before it is relied on either way.
Dayworks is the last rung, and it fails on records rather than on principle
Daywork is available only where the work cannot properly be valued by measurement. It is a residual rule, not an election, and a contractor cannot choose daywork over measurement because it is easier or because the daywork rates are better. JCT DB 2024 clause 5.5 and JCT SBC 2024 clause 5.7 compute it by reference to the RICS Definition of Prime Cost of Daywork carried out under a Building Contract6, or the specialist-trades equivalent, plus the percentage additions stated in the Contract Documents. FIDIC 2017 clause 13.5 runs a Daywork Schedule with a daily record discipline attached: the Contractor must submit quotations, invoices, vouchers and accounts for goods, and priced statements each day.
Daywork claims fail because the records will not carry the account.
One structural point about the rates themselves. Daywork percentage additions are set for a general case and rarely reflect the actual cost of a disruptive, small-quantity, out-of-sequence operation, which is exactly the kind of work that reaches rung 4. Daywork is attractive to contractors because it converts a valuation argument into an arithmetic one, and attractive to employers for the same reason, because the arithmetic is usually low.
The valuation clause prices the changed work only
Under almost every form, the valuation clause prices the changed work and nothing else. Prolongation, disruption and thickened preliminaries travel by a different route with its own trigger, notice and proof: loss and expense under JCT Section 4 (JCT DB 2024 clauses 4.19–4.23), a claim under Article 15 of AIA A201–2017, equitable adjustment for impact under FAR, and a clause 20.2 claim under FIDIC 2017. JCT says so expressly, DB 2024 clause 5.7 and SBC 2024 clause 5.10 both state that no allowance is made in the Valuation for the effect of the Change on regular progress or for loss and expense reimbursable elsewhere. Getting this wrong produces either double recovery or no recovery, and both lose.
NEC4 is the sole exception, and deliberately so: NEC4 ECC clause 63 assesses both the time and the cost effects of the compensation event in one quotation, and NEC4 ECC clause 66 makes implementation final. An NEC4 contractor that submits a quotation pricing only the direct work has settled the time and disruption consequences of that compensation event. It is the most expensive routine error in the regime, and it is the same structural risk that runs through change order releases under every other form.
And the mirror-image trap. Clause 36.2 of AS 4000-1997 (Proposed Variations), in the public amended copy read, and the equivalent clause of the amended AS 4902-2000-based contract quoted in Kaloriziko, both require the Contractor, when responding to a proposed-variation notice, to address the effect on the programme and the cost, including time-related (or delay) costs. The 2025 text was not read, so check the 2025 clause before relying on the same wording. Time-related cost is expressly inside the pricing response. A contractor that carries JCT habits onto an AS 4000 job (pricing the direct work and reserving the delay costs for a separate claim) has, on the face of the clause, omitted the very thing it was asked to include. The habit that protects you on one form under-recovers on the other.
The same collapse happens wherever a quotation procedure is used rather than the default rules. JCT SBC 2024's Schedule 2 Variation Quotation, triggered by clause 5.3, and JCT DB 2024's Schedule 2 Supplemental Provision 2 "Valuation of Changes – Contractor's estimates" both require direct loss and expense and the effect on time to be priced inside the quotation, and acceptance is a final and inclusive settlement of those heads for that Change. Both are optional and apply only if stated in the Contract Particulars. Note also that JCT DB has no "Schedule 2 Quotation". That is an SBC instrument, and the DB analogue is Supplemental Provision 2.
Two practical disciplines follow, and they are the difference between a variation account that survives and one that gets halved.
Reconcile the overlap on the face of the claim. Where both a variation account and a prolongation claim are run, the standard employer answer is that a preliminaries uplift has been recovered twice for the same period. It is usually a good point. Identify the impact window, price the prolongation at the resource levels prevailing then rather than at the tail of the job, SCL Delay and Disruption Protocol8, 2nd Edition (February 2017), Core Principles 20 and 22, restrict the variation-account preliminaries to resources deployed for the varied work, and say so in the valuation. A claim that shows it has stripped out the overlap is far harder to attack than one that has to be reverse-engineered. The mechanics of the separate claim are set out in prolongation and delay costs.
Fix the design-and-build preliminaries problem at tender, because it cannot be fixed later. JCT DB 2024 has no bills of quantities. Preliminaries recovery on a Change therefore depends entirely on whether the Contract Sum Analysis discloses preliminaries in a form capable of pro rata adjustment. On a great many projects it does not. The CSA is a handful of elemental lines agreed at tender for payment purposes, not a pricing document. Where that is so the contractor is thrown back on fair valuation and must prove the preliminaries content from first principles, on every single Change, for the life of the job. It is a recurring and entirely avoidable source of under-recovery, and the only fix is to negotiate a Contract Sum Analysis with a preliminaries breakdown capable of adjustment before the contract is signed.
Sources and authorities
- 1Weldon Plant Ltd v The Commission for the New Towns[2000] BLR 496, [2000] EWHC Technology 76, [2001] 1 All ER (Comm) 264, Technology and Construction Court
ICE clause 52(1) is three sequential valuation rules, not a menu, and a fair valuation must include profit, "an employer must pay profit in valuations made under any rule", with site and time-related overheads proved as incurred and head office overhead entering as a percentage from the contractor's accounts.
- 2Northern Ireland Housing Executive v Healthy Buildings (Ireland) Ltd[2017] NIQB 43, High Court of Northern Ireland, Queen's Bench Division
Where NEC compensation-event quotations were never agreed contemporaneously, the court permitted retrospective assessment on actual cost records, invoking the mutual trust and co-operation obligation.
- 3Henry Boot Construction Ltd v Alstom Combined Cycles Ltd[2000] EWCA Civ 99, [2000] BLR 247 (CA), Court of Appeal, affirming [1999] BLR 123 (TCC)
Contract rates are sacrosanct, immutable and not subject to correction merely because a party is dissatisfied with them. A mistaken rate must still be used to value the variation, and the rule binds an under-priced contractor exactly as it binds an over-charged employer.
- 4Van Oord UK Ltd v Dragados UK Ltd[2021] CSIH 50, Inner House, Court of Session
A compensation event which is itself a breach of contract does not reduce total Defined Cost, and the mutual trust and co-operation obligation prevents a party enforcing terms arising from its own breach, so an employer cannot omit work and then rely on the reduced volume to drive the rate down.
- 5Eichleay Corp.ASBCA No. 5183, 60-2 BCA ¶ 2688, aff'd on reconsideration 61-1 BCA ¶ 2894 (1960), Armed Services Board of Contract Appeals
Source of the formula by which unabsorbed home office overhead is recovered on a US federal contract, available only on government-caused standby and on strict prerequisites.
- 6RICS Definition of Prime Cost of Daywork carried out under a Building Contract
The computation basis to which JCT DB 2024 clause 5.5 and JCT SBC 2024 clause 5.7 refer for daywork, before the percentage additions stated in the Contract Documents.
- 7Vim Engineering Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd[2021] SGHC 63, High Court of Singapore · on appeal [2023] SGHC(A) 2
At first instance, project manager signatures on site records "merely acknowledged work completion, not payment acceptance": a signature proves attendance, not entitlement and not agreement to the valuation basis.
- 8Society of Construction Law Delay and Disruption Protocol, 2nd EditionFebruary 2017
Core Principles 20 and 22 direct that the compensable effect is priced by reference to the period in which it was felt, which is what allows a variation account and a prolongation claim to be reconciled rather than double-counted.
General information, not legal advice. Reviewed Sep 26, 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.