- The short answer
- You do not choose a rung; you fall to it. Agreement first, contract rates second, tender-stage schedules third, and a reasonable price with margin last. Most valuation fights are about whether a rate above the last rung applies.
- The clause numbers
- In AS 4000-1997, confirmed from a public amended copy: cl 36.1 Directing Variations, 36.2 Proposed Variations, 36.3 Variations for convenience of Contractor, 36.4 Pricing. The 2025 sub-numbering is reported by firm summaries, not read.
- Omissions
- Deductions carry profit but not overheads in the one AS 4000-1997 copy read (an amended tender copy). A circulating "10% of the net omission" rule could not be sourced at all. `[NEGATIVE FINDING]`
- Time-related cost sits inside the AS 4000 estimate
- The cl 36.2 response covers programme, the Date of Practical Completion and cost including time-related costs, in both amended copies read. Price the direct work only and you may have agreed a price that leaves the delay money out. Price both routes and you invite a double-recovery answer.
- No overhead formula
- No Australian decision endorsing Hudson, Emden or Eichleay was located; in delay claims, off-site overhead is proved as actual cost. Within a variation price, the reasonable-rates rung carries its own allowance.
- Approval is not a variation
- Kaloriziko: pricing a non-variation does not make it one, approval is at most an implied admission, and a payment "on account" does not bind. Only $133,175 of the $3.24 million reduction concerned a claimed variation.
- The Superintendent wears two hats
- Agent in a loose sense when directing, certifier when pricing: under AS 2124 cl 23 bound to act honestly and fairly, and when certifying honestly and impartially (Peninsula Balmain [2002] NSWCA 211 at [50], [79]). AS 4000:2025 did not settle the tension.
Under AS 4000 (and, as summarised, AS 4902) a directed variation is priced by falling down a fixed order: prior agreement, then rates or prices in the Contract, then rates in a priced bill or schedule even though it is not a Contract document, and only then reasonable rates that carry profit and overheads. That ladder is the whole of the valuation machinery. It prices a variation that exists. It does not make one: the New South Wales Court of Appeal credited a developer with an approved, priced "variation" because the work had been in scope all along.
This is the valuation spoke of variations in Australia. The four-rung ladder across other forms is on the jurisdiction-neutral valuation page.
Three things decide an Australian valuation: which rung the variation falls to, whether the price already carries its time-related cost, and whether the work was a variation at all. The standard forms answer the first. Your records answer the other two.
What this page could and could not read. Standards Australia text is paywalled, and no licensed copy of AS 4000:2025, AS 4000-1997, AS 4902-2000 or AS 2124-1992 was read. AS 4000-1997 cl 36 is quoted only from a public amended copy in a tender bundle, and says so; everything else on the forms comes from attributed firm summaries. Kaloriziko (which quotes that contract's amended AS 4902-based clauses), Peninsula Balmain, Mainteck and Chengcheng were read on AustLII.
AS 4000 cl 36.4: the pricing ladder, rung by rung
An amended AS 4000-1997 copy read for this page has the Superintendent price each Variation "as soon as possible" using an order of precedence. Two firm summaries set out the limbs in the same order: a CMGuide note (2011, on AS 4000) and Holding Redlich's design and construct series (November 2022, on AS 4902).
| Rung | What the Superintendent uses | Carries margin? | The fight |
|---|---|---|---|
| (a) | A price the Principal and Contractor agreed before the work | Whatever was agreed | Was there an agreement, and on what scope? |
| (b) | Applicable rates or prices in the Contract | Only what the rate carries | Is the rate "applicable" to the varied work? |
| (c) | Rates in a priced bill of quantities, schedule of rates or schedule of prices, even though not a Contract document, so far as reasonable | Only what the rate carries | Is it reasonable to use a tender-stage rate here? |
| (d) | Reasonable rates or prices, including a reasonable amount for profit and overheads | Yes, expressly | What is reasonable, and on whose records? |
Record: limbs (a)–(c) as they appear in an amended AS 4000-1997 copy in a public tender bundle (whose limb (d) has been deleted by amendment), and the full order as summarised by CMGuide (AS 4000) and Holding Redlich (AS 4902). The "fight" column is opinion.
The one AS 4902-based text read, the amended contract in Kaloriziko, put a schedule of rates ahead of Contract rates and fixed the last limb's margin as percentages stated in the Annexure. Read the executed cl 36.4.
Limb (a) makes agreement paramount. That is why the proposed-variation procedure matters: it is the Superintendent's route to an agreed price before the work starts. An agreed price is the top rung, and everything below it is argument.
Limb (c) is the trap. It reaches rates the Contractor handed over at tender for evaluation, even where they never became Contract documents. (Opinion.) Assume anything priced and handed over is reachable, and price tender schedules as if they will be used against you.
Limb (d) is the only rung that expressly guarantees margin. So the Contractor's usual objective is to show that limbs (b) and (c) do not fit the varied work, and the Principal's is to show that they do. (Inference, from the structure of the limbs.)
What the sub-numbering rests on
The 1997 sub-numbering is confirmed from a public tender bundle containing an amended copy of AS 4000-1997: cl 36.1 Directing Variations, 36.2 Proposed Variations, 36.3 Variations for convenience of Contractor, 36.4 Pricing. The amended AS 4902-based contract in Kaloriziko has the same structure. Some published summaries put pricing at 36.2; for the 1997 edition that is wrong.
(Inference.) For AS 4000:2025, only cl 36.1 (Directing Variations) is confirmed; the rest is inferred and nothing reports a renumbering. Cite "AS 4000:2025 cl 36" and check the sub-number against your copy of the standard before you plead it.
On limb (d) the summaries differ: CMGuide gives the last limb as carrying profit but not overheads; Holding Redlich gives profit and overheads. Two copies resolve the shape, if not the words. An amended AS 4000-1997 copy ends cl 36.4 with "any deductions shall include a reasonable amount for profit but not overheads" (its limb (d) was deleted by amendment), and the Kaloriziko contract states one percentage for additions and another for deductions. (Inference.) The clause is an additions rule followed by a deductions rule; CMGuide has run the two together. Neither copy is the standard.
Negative variations: profit, overheads and a 10% rule nobody could find
Two rules about deleted work circulate for AS 4000. They should be treated very differently.
Profit but not overheads on deductions. The corpus records the pricing clause as continuing, after limb (d), with a rule that deductions carry a reasonable amount for profit but not overheads. On an omission the Principal recovers the Contractor's profit on the deleted work; the Contractor keeps the overhead recovery. The one AS 4000-1997 copy read (an amended tender copy) contains exactly that sentence; the unamended standard was not read.
"10% of the net omission." The research corpus describes a deduction of 10% of the difference where omissions exceed additions, and places it in cl 36.2. Four searches on 26 September 2026 located no source for an AS 4000 or AS 2124 net-omission percentage, and none appears in cl 36 of the amended AS 4000-1997 copy read. In that copy cl 36.2 is the proposed-variation procedure, not a pricing rule, and the principal had added its own omissions clause (cl 36.5), which is where rules like this come from. (Opinion.) Do not plead, deduct or concede a 10% figure on the strength of the standard form. If your executed contract contains one, it is a special condition.
A comparison, clearly labelled: AIA A201–2017 §7.3.8 credits deleted work at net cost, so a US contractor keeps overhead and profit on it; CCDC 2 – 2020 reaches a similar result through its fee. If the AS 4000 deductions rule reads as reported, it runs the other way on profit. Nothing in this paragraph is authority for an Australian proposition.
The research corpus also reports that AS 4000:2025 cl 36.1 expressly allows work to be omitted whether or not others perform it. That goes to whether the omission is a valid variation at all, and is treated on the deemed variations spoke.
AS 4000 cl 36.2 and time-related costs: valuation or prolongation?
On AS 4000, when the Superintendent gives notice of a proposed variation, the Contractor answers with an estimate. Turtons (July 2018, on AS 4000-1997) summarises that estimate as covering the effect on the construction programme, the effect on the Date of Practical Completion, and the cost of the variation, in its words "including all time-related costs". Two independently amended copies agree in substance: the AS 4000-1997 tender copy asks for a quote for the cost "including all warranties and time-related costs, if any", and the AS 4902-based contract in Kaloriziko for a breakdown "including all warranties and delay costs, if any". The unamended wording, and the 2025 wording, were not read.
That matters because most forms keep time-related cost out of the variation price. JCT sends it to loss and expense, CCDC to its delay and claims clauses. NEC4 puts time and cost into one quotation. On the copies read, AS 4000's proposed-variation response sits with NEC4: the time-related consequence of a proposed variation is inside the price the Contractor is asked for. (Comparison; see the neutral valuation page.)
(The table is opinion, built on the summaries above.) The under-recovery trap is an inference from the drafting, not a holding. No Australian decision was located holding that an agreed AS 4000 variation price settles the delay costs of that variation. The one appellate decision found on the question runs the other way on a bespoke contract: Chengcheng (Aust) Enterprise Melbourne Pty Ltd v Mansfield Corporation Pty Ltd held that agreeing and paying a variation did not exclude a separate delay costs claim, even though that contract's variation valuation itself included time-related costs ([78]). That result turned on that contract's variation and delay costs clauses, which is the point. The answer is in the words of your contract, not in a general rule.
The double-recovery point is not only a lawyer's argument. The NSW Government's construction procurement guide on prolongation claims tells its assessors that variation payments usually already include a proportion for off-site overheads, and not to count them twice. Offer that reconciliation before it is asked for.
The template page gives wording for both halves: a proposed-variation response that names the time-related cost it includes, and a reservation for any delay cost it does not. See the variation notice and claim templates. Where the delay money travels separately, it is proved as in prolongation and delay costs in Australia.
No Hudson, Emden or Eichleay: delay overhead is proved as actual cost
Limb (d) promises a reasonable amount for overheads. It does not say how to prove it, and Australian law offers no formula to fall back on.
No Australian decision adopting or rejecting the Hudson, Emden or Eichleay formulae was located: not in the corpus's survey, and not in two further searches run for this page on 26 September 2026. (Comparison.) On this site's research, England, Canada and the United States each have decisions engaging with the formulae; Australia has none located. (Opinion.) In a delay claim, treat off-site overhead as actual cost and actual under-recovery, proved from the accounts. A percentage lifted from a formula will be met with "where is that in your ledgers?". Within a variation price, limb (d) carries its own allowance for overheads; the argument there is what is reasonable.
The same discipline applies when a contractor gives up on itemising. Mainteck Services Pty Ltd v Stein Heurtey SA rejected the submission that proving a causal link between some breaches and the disruption entitled the claimant to the whole claim or an apportionment: "That is not the law" ([182]). "In a global claim, a significant cause of loss not attributable to the defendant is fatal" ([205]). A variation account that bundles unpriced variations with disruption and delay into one "total cost" figure takes that risk. See global claims and total cost in Australia.
AS 2124 cl 40.3 and cl 40.5: what changes on the older form
AS 2124-1992 remains in wide use. Its variations clause is cl 40, and on valuation the differences that matter are where margin goes, not the ladder itself.
| Point | AS 2124-1992 | AS 4000 |
|---|---|---|
| Pricing request | cl 40.3, Pricing the Variation: a detailed quotation supported by measurements or other evidence of cost | cl 36.2 proposed-variation response, including time-related cost (two amended copies) |
| Valuation clause | cl 40.5, Valuation. Its limbs were not reported by any source read here | cl 36.4 pricing ladder (numbering above) |
| Latent conditions | The Contractor claims the extra cost incurred (cl 12.3) | A deemed variation (cl 25.3 in AS 4000-1997, public amended copy; 2025 [EDITION ALERT]), priced down the ladder |
| Change in legislation | Gives rise to a variation (cl 14.1) | An adjustment for the difference in cost incurred (cl 11.2), not a variation (1997; 2025 not verified) |
| Superintendent's obligations | cl 23 | cl 20 (2025) |
Record: clause numbers and headings as summarised by Turtons (October 2018) and a state government AS 2124 special-conditions template relied on in the corpus. minor: one guide calls cl 40.3 a "detailed quotation", the template "Pricing the Variation"; they describe the same provision.
(Inference.) Because deemed variations and variations are priced down a ladder whose last rung carries margin, and cost-incurred adjustments are not, the two forms allocate margin in opposite directions on latent conditions and on change in law. Identify the form before advising on either. AS 2124 also carries a general prescribed-notice provision at cl 46.1. Its period is reported as 42 days in two independent sources, but sources disagree on what starts it : check your contract's cl 46.1 and special conditions. It is treated on the templates page and the written instruction spoke.
The Superintendent prices as well as directs
Under AS 4000 the same person directs the variation and then values it. When the Superintendent directs, it acts for the Principal. When it prices, it performs a certifying function between the parties.
Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd is the anchor. The contract (AS 2124-1992 cl 23) required the Superintendent to act "honestly and fairly". Hodgson JA held that the Superintendent is the owner's agent "only in a very loose sense", and that when certifying it "is not acting as the owner's agent, in the strict legal sense" ([50]); it must act "honestly and impartially", including in deciding whether to extend time without a claim ([79]). The case was about time, not valuation; that the same duty governs pricing is (Inference) from the certifying character of the task, and it is the reading the commentary adopts.
AS 4000:2025 did not resolve the tension. Carter Newell (August 2025) notes that AS 4000:2025 sets the Superintendent's general obligations at cl 20, but that the distinction between the Superintendent as the Principal's agent and as independent certifier or valuer "could be better reflected". (Opinion.) With cl 36.1 now reported to make the Superintendent the only gateway to an effective variation, and the Superintendent the valuer under the pricing clause, the duality matters more under the 2025 edition, not less. For a contractor challenging a valuation, a price shaped by the Principal's budget rather than by the ladder is the strongest structural argument available.
Kaloriziko (2025): approval is not a variation
This is the case that changes how a variation register should be read, and it is widely misreported.
Kaloriziko Pty Ltd as trustee for Ryde Combined Unit Trust v Calibre Construction Group Pty Ltd (No 2) was an appeal from Stevenson J ([2025] NSWSC 593). Adamson JA gave the principal judgment, and Mitchelmore and Kirk JJA agreed. The contract was a $31 million design and construct contract for apartments in Ryde, on general conditions in the AS 4902-2000 format, as amended. It was not AS 4000. Every clause number below is that contract's.
The rest of the reduction was $210,000 in liquidated damages (28 days at $7,500) and $2.9 million for the undervalue of properties transferred under a deed of settlement that released a party with co-ordinate liability. That is a contribution point, not a variations point. A statement that the builder's variations were cut by $3.24 million is wrong.
Items the developer approved, priced and paid
Five items (V1, V7, V11, V13 and V21, $569,778 paid) were held not to be variations: the work was within the scope. The developer's approval and payment did not displace cl 37.2, under which, as the Court quotes it, "[p]ayment other than final payment shall be payment on account only". The trial judge had held otherwise, and erred. But each item was an "excluded item" under the Formal Instrument of Agreement: work to be done but paid for separately. So the builder kept the money and owed no credit.
The item the developer approved but never paid
V44, consultancy fees, was approved but not paid. The fees were within the scope and not excluded, and pre-contract discussions were irrelevant because of an entire contract clause. The Court held that the approval did not operate as a direction under cl 36.1, and could not price a variation under cl 36.4. In the Court's words:
The pricing of a non-variation does not convert it to a variation.
The judgment's headnote records the approval as no more than an implied admission, capable of being displaced by the true contractual position. The developer was credited $133,175. And the Court put the pricing machinery in its place: "When cl 36 is complied with (that is, that there is a variation which is priced), the builder has a right to payment in addition to the original contract sum". The ladder presupposes the variation.
The Court also held that the date for practical completion had not been validly varied, because no written instrument executed by both parties existed, as cl 5(b) of the Formal Instrument required, and neither an oral agreement nor conduct was proved. That is a finding on the evidence, not a holding that a written-variation clause excludes oral variation in Australia. The written-direction question is on the written instruction spoke.
What it means for a contractor's variation register
How a register of approved variations fails at final account
- "Approved" is recorded as if it were a legal status. It is evidence, and on Kaloriziko weak evidence: an implied admission the true contract can displace.
- No scope reference on the line. The line says what was done and what was approved. It does not say which scope document shows the work was outside the contract, which is the only thing that made it a variation.
- Direction and approval run together. A price approved in a meeting, or a claim approved in a payment certificate, is not a written direction under the variations clause.
- Paid means closed. Where interim payments are on account only, payment settles nothing until the final certificate.
- Separately payable items filed as variations. Kaloriziko's builder kept $569,778 only because the items were excluded items under the Formal Instrument, not because they were approved variations. Classify each line by its true basis: variation, deemed variation, provisional sum, excluded item, or claim.
(Opinion.) For a principal the case cuts both ways. Approval did not bind this developer, but it was still an admission it had to displace, and it displaced it because an entire contract clause shut out the pre-contract history. An approval given casually, for cash-flow or relationship reasons, is evidence against you at final account.
The drafting responses
(Opinion, offered as drafting practice rather than authority.)
- Contractors: provide that a variation price agreed or determined under the pricing clause is final and binding once issued, and carve variation valuations out of the on-account language in the payment clause. And ask that every approval name the written direction it rests on.
- Principals: provide expressly that approving or paying a price is not an admission that the work is a variation, keep the on-account language, and keep an entire agreement clause that does real work.
- Both: a register line should carry the scope reference, the direction reference, the pricing limb used and whether time-related cost is in the price. Those four fields are what Kaloriziko tested.
Where Storia fits
Every rung of the ladder rests on records: the rate that applies, the quantities, the time-related cost in the price, and above all the trail showing the work was outside the scope before anyone priced it. Kaloriziko is what happens when the approval survives and that trail does not. Storia turns drawings, RFIs, schedules, correspondence and field reports into one source-linked project record, so each line of a variation register traces back to the scope document, the written direction and the pricing basis it came from. Because the record is built as the work happens, the valuation can be agreed in coordination, or taken from records to a claim-ready case in days.
The strongest case against this page's framing
A careful opponent would say that Kaloriziko is a narrow decision on an amended AS 4902-based contract with an entire contract clause and an express on-account payment clause, and that the page makes too much of it. That is partly right. The holding is tied to those clauses, and a standard AS 4000 contract has to be read on its own words. But the sentence Kaloriziko turned on, "Payment other than Final Payment shall be payment on account only", appears in cl 37.2 of both amended copies read, AS 4000-1997 and AS 4902-2000-based, so it is very likely the 1997 standard's own text. The 2025 wording was not read. And the core reasoning is not clause-specific. A pricing mechanism that prices "a variation" assumes one. An approval is evidence, not a contract. Neither point depends on AS 4902.
The same opponent would say the time-related-cost trap is overstated. It rests on amended copies and a firm summary, not the licensed clause, no Australian case applies it, and the one appellate decision found (on a bespoke contract) let a delay costs claim run alongside an agreed variation. Also fair. (Opinion.) The answer is that the cost of the discipline is one sentence on an estimate, and the cost of being wrong is the delay money on every priced variation. Where the law is unsettled, write down what the price includes.
The ladder's order is consistent across every source read. The 1997 decimal is confirmed; the 2025 decimal is reported.
What to do about it
(Opinion, offered as working practice rather than as authority.)
- Find the rung before you argue the price. Is there a prior agreement? A rate in the Contract? A tender schedule that reaches? Only then argue what is reasonable.
- Price tender schedules as if they will be used. Limb (c) reaches them even if they never became Contract documents.
- Answer every proposed-variation notice with a stated scope of price: direct cost, time-related cost, and what is reserved. Use the template.
- Reconcile before you are asked. Show that the preliminaries and overhead in the variation account are not in the delay claim.
- Prove delay overhead from the accounts. No formula located will carry it in Australia.
- Do not concede, deduct or claim a 10% net-omission figure unless it is in your executed contract.
- Keep the scope trail on every register line. Approval is not a variation, and payment on account is not settlement.
- Read the executed contract. Pricing clauses are commonly amended; the Kaloriziko contract's limbs differed from the standard. The form tells you what was probably negotiated away, not what governs.
In Victoria, the limits on adjudicating disputed variations (ss 10A–10B of the security of payment Act) were repealed from 15 April 2026, subject to the transitional s 54; see adjudicating the variation account in Victoria. For the whole Australian picture, return to variations in Australia.
Authorities
- Kaloriziko Pty Ltd as trustee for Ryde Combined Unit Trust v Calibre Construction Group Pty Ltd (No 2) [2025] NSWCA 259 (5 December 2025), Adamson JA (Mitchelmore and Kirk JJA agreeing); on appeal from [2025] NSWSC 593On amended AS 4902-2000 conditions: work within the scope was not a variation merely because the developer approved and priced it; "The pricing of a non-variation does not convert it to a variation." Approval was no more than an implied admission displaceable by the true contractual position, and payment other than final payment was on account only. Credit of $133,175 for V0044 (consultancy fees) to the developer.The other $3.11m of the $3,243,175 reduction was liquidated damages ($210,000) and a $2.9m co-ordinate-liability deduction arising from a deed of settlement, neither of them a variations point. Five further items ($569,778, paid) were held not to be variations but were separately payable "excluded items", so the builder kept that money.AustLII →
- Calibre Construction Group Pty Ltd v Kaloriziko Pty Ltd atf Ryde Combined Unit Trust (No 2) [2025] NSWSC 593 (19 June 2025), Stevenson J; correcting judgment (No 3) [2025] NSWSC 646The trial decision reversed on the approval point in Kaloriziko [2025] NSWCA 259. The Court of Appeal held the primary judge erred in treating approval and payment as displacing the contract's on-account payment clause. The first-instance reasons were not read; described here only as the Court of Appeal describes them.Find on AustLII →
- Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211 (3 July 2002), New South Wales Court of Appeal (Hodgson JA; Mason P and Stein JA agreeing)The Superintendent is the owner's agent "only in a very loose sense", and when certifying is not acting as the owner's agent in the strict legal sense ([50]). It must act honestly and impartially, including in deciding whether to extend time without a claim, a power exercisable in the interests of both parties ([79]).Read on AustLII, 26 September 2026. The contract was AS 2124-1992; cl 23 required the Superintendent to act "honestly and fairly".AustLII →
- Mainteck Services Pty Ltd v Stein Heurtey SA [2014] NSWCA 184 (6 June 2014), New South Wales Court of Appeal (Leeming JA; Ward JA agreeing; Emmett JA concurring)Establishing a causal connection between some breaches and the disruption does not entitle the claimant to the whole claim or an apportionment: "That is not the law" ([182]). "In a global claim, a significant cause of loss not attributable to the defendant is fatal" ([205]).Read on AustLII, 26 September 2026 ([182], [205]). "No special principles for building cases" is from Clayton Utz and Norton Rose Fulbright.AustLII →
- Chengcheng (Aust) Enterprise Melbourne Pty Ltd v Mansfield Corporation Pty Ltd [2018] NSWCA 244 (26 October 2018), New South Wales Court of Appeal (Ward JA; Macfarlan JA agreeing; Sackville AJA agreeing in the orders)On a bespoke "Design and Construct Contract – Lump Sum" (a Melbourne restaurant fit-out, not an AS form), agreeing and paying the Variations did not exclude liquidated Delay Losses under cl 10.6. There was "no commercial absurdity" in recovering both the cl 10.4.1 valuation, which included time-related costs, and a liquidated sum for delay ([72], [75], [78]).Read on AustLII, 26 September 2026.AustLII →
- AS 4000-1997 General Conditions of Contract Standards Australia, AS 4000-1997, cl 36 (Variations)cl 36.1 Directing Variations, cl 36.2 Proposed Variations (the Contractor's response includes time-related costs), cl 36.3 Variations for convenience of Contractor, cl 36.4 Pricing (an order of precedence; deductions carry profit but not overheads in the copy read). cl 37.2: payment other than Final Payment is on account only.Paywalled. Sub-clause numbers and headings confirmed from an amended copy in a public tender bundle; operative wording is quoted only where attributed to that copy.
- AS 4000:2025 General Conditions of Contract Standards Australia, AS 4000:2025, cl 20 and cl 36cl 36.1 is reported to make a variation effective only where the Superintendent directs it in writing before the Date of Practical Completion; cl 20 carries the Superintendent's general obligations.`` Paywalled. The cl 36 sub-numbering after 36.1 is reported by firm summaries, not read.
- AS 2124-1992 General Conditions of Contract Standards Australia, AS 2124-1992, cl 40cl 40.3 (Pricing the Variation, a detailed quotation supported by measurements or other evidence of cost) and cl 40.5 (Valuation). Latent conditions give the extra cost incurred (cl 12.3); legislative change gives a variation (cl 14.1).Headings from a state government special-conditions template and one practitioner guide. The limbs of cl 40.5 were not reported by any source read for this page.
About this material Library content is general information about construction claim practice, not legal advice. Entitlement, deadlines and procedure are governed by your own contract and by the law of the place the work is performed. Reviewed September 26, 2026 · Report a correction
In this article
- AS 4000 cl 36.4: the pricing ladder, rung by rung
- Negative variations: profit, overheads and a 10% rule nobody could find
- AS 4000 cl 36.2 and time-related costs: valuation or prolongation?
- No Hudson, Emden or Eichleay: delay overhead is proved as actual cost
- AS 2124 cl 40.3 and cl 40.5: what changes on the older form
- The Superintendent prices as well as directs
- Kaloriziko (2025): approval is not a variation
- Where Storia fits
- The strongest case against this page's framing
- What to do about it