Aller au contenu principal

Confidentialité

À propos des témoins

Les témoins essentiels font fonctionner ce site. Les témoins d’analyse facultatifs nous aident à comprendre ce qui fonctionne, activés seulement si vous acceptez.

LIBRARY
AustralieExtension of timeJurisdiction article

Liquidated damages and penalties in Australia

Australia runs its own penalties doctrine, wider than England's at the gateway and narrower nowhere. Andrews v ANZ [2012] HCA 30 lets a stipulation be struck even without breach. Paciocco [2016] HCA 28 sets an "out of all proportion" ceiling. No construction LD clause has yet fallen on the no-breach ground.

Reviewed 1 sept. 202612 min read10 sources

Disponible en anglais seulement Cet article n'a pas encore été traduit. Les délais, le droit à réclamation et la procédure décrits ici touchent au droit, et une traduction automatique constituerait un risque de crédibilité plutôt qu'une commodité : l'original anglais est donc servi intégralement jusqu'à ce qu'une traduction révisée existe.

At a glance

Australie
Class
Doctrine
Jurisdiction
Australia. National, High Court authority
Contract forms
AS 4000:2025, AS 2124-1992, GC21
Last reviewed
1 September 2026
§ 00

Key facts

  1. 01

    The short answer

    A delay LD clause is a penalty in Australia if the stipulated detriment is "out of all proportion" to the legitimate interests it protects. And, unlike England, it can be a penalty even where there is no breach of contract at all.

  2. 02

    The gateway

    Andrews v Australia and New Zealand Banking Group Ltd [2012] HCA 30 restored the equitable penalty doctrine. Breach is sufficient but not necessary to trigger it. A collateral stipulation securing performance is enough.

  3. 03

    The ceiling

    Paciocco v Australia and New Zealand Banking Group Ltd [2016] HCA 28 asks whether the detriment is out of all proportion to the legitimate interests protected. Interests that go beyond Hadley v Baxendale remoteness and need not have been foreseeable to the other side.

  4. 04

    What changed and what did not

    Australia kept the gateway England abandoned, then adopted England's ceiling. Genuine pre-estimate of loss is now a safe harbour, not the test.

  5. 05

    The honest limit

    `[NEGATIVE FINDING]` No Australian construction decision located for this corpus has actually struck a delay LD clause on the Andrews no-breach ground. The risk is doctrinal and live, not a demonstrated outcome.

  6. 06

    The construction record so far

    Every reported construction LD challenge in this corpus has failed. Grocon, Growthbuilt and Leighton all upheld the clause, and the onus sits on the party alleging the penalty.

  7. 07

    The relief

    An unenforceable clause is void only to the extent of the excess over provable loss, not wholly void. The protected party keeps its proved loss.

  8. 08

    The drafting trap

    The standard English fix for a penalty risk. Restructure the trigger so it is not a breach. makes the position worse in Australia, because removing breach does not remove the stipulation from the Andrews gateway at all.

An English or North American practitioner arrives on an Australian job assuming the penalty question is about breach: was the contract broken, and if so, is the stipulated sum a proportionate response? In Australia that assumption is wrong at the first step. A stipulation can be struck down as a penalty even where there is no breach of contract at all. A gateway England deliberately closed and Australia deliberately reopened.

That single divergence is the reason Australian penalties law cannot be read off an English or North American textbook. It is High Court authority and it does not vary by state, contract form, or industry. It applies to a delay liquidated damages clause in an AS 4000 subcontract exactly as it applies to a bank fee. The doctrine has two stages: a gateway that decides whether the penalty rule is engaged at all, and a ceiling that decides whether the stipulated sum survives. Australia's gateway is wider than England's. Its ceiling is, after a decade of apparent convergence, close to identical.

The practical stakes are ordinary drafting decisions, not exotic ones: what triggers the LD clause, how the rate was calculated, whether the clause says it is the exhaustive remedy, and whether the extension-of-time mechanism sitting next to it is actually being used. Get those four things right and the Australian authorities so far are on the drafter's side. Get the trigger wrong. Particularly by copying an English drafting fix that assumes breach is a precondition, and the clause is exposed to a doctrine England no longer runs at all.

§ 01

Stage one: the Andrews gateway does not require a breach

Andrews v Australia and New Zealand Banking Group Ltd1 [2012] HCA 30 restored the older equitable penalty doctrine that England's Supreme Court later abandoned in Cavendish Square Holding BV v Talal El Makdessi. The Australian gateway asks, as a matter of substance and not form, whether the stipulation is:

  1. collateral or accessory to a primary stipulation operating in favour of the other party
  2. triggered by the failure of that primary stipulation. Breach is sufficient but not necessary, and
  3. such as to impose an additional detriment on the first party, for the benefit of the second, in the nature of security for, and in terrorem of, performance of the primary stipulation.

There is a drafter's escape route built into the gateway itself. The doctrine does not apply where the payment is not a collateral detriment at all, but the agreed price of an additional right, accommodation or alternative performance conferred on the payer. The conditional-benefit analysis. A payment structured as the cost of an option the payer is free to take up sits outside the doctrine altogether. A payment structured as the cost of the payer's default does not.

England, since Cavendish (2015)

Breach is the price of admission

The penalty rule only engages once there has been a breach of contract. Structure the trigger as something other than a breach. A milestone, a service-level abatement, and the doctrine has no purchase on the clause at all, whatever the proportionality of the sum.

Australia, under Andrews

Breach is one route in, not the only one

The equitable doctrine is engaged by the collateral, accessory, security-for- performance character of the stipulation. A non-breach trigger does not exit the doctrine. It simply means the analysis proceeds without a breach on the facts.

§ 02

Stage two: the Ringrow/Paciocco proportionality ceiling

Once the gateway is engaged, the question becomes proportionality. Paciocco v Australia and New Zealand Banking Group Ltd2 [2016] HCA 28, building on Ringrow Pty Ltd v BP Australia Pty Ltd3, asks. Judged objectively and ex ante, at the time of contracting. Whether the stipulated detriment is "out of all proportion" to the legitimate interests the provision exists to protect: "extravagant, exorbitant or unconscionable", or showing "a degree of disproportion sufficient to point to oppressiveness".

The width of "legitimate interests" is the part of Paciocco most likely to surprise a foreign drafter. Interests are not confined to damages recoverable for breach. They extend beyond Hadley v Baxendale remoteness, are not limited by common-law causation, need not have been foreseeable to the counterparty, may be non-monetary, and may embrace the protected party's enterprise-level financial position (Kiefel J at [29] and [65], Gageler J at [161]–[162], and Keane J at [271]–[273]). The benchmark is the greatest loss that could conceivably be proved to follow. Not the loss actually suffered, and not the loss most likely to be suffered. Mere disproportion is not enough, and the onus of proving the penalty sits on the party alleging it.

§ 03

Paciocco moved the ceiling, not the gateway: the point most commentary gets wrong

Paciocco is widely described as realigning Australia with England. That description conflates two different axes, and getting them backwards is the most common mistake a foreign-trained practitioner makes on an Australian file.

AxisWhere Australia sits
Does the doctrine require a breach?No. Andrews is unchanged, and Australia is further from England than it was before Paciocco, Gageler J at [121] said the UK Supreme Court was "wrong" to make breach a precondition
What is the proportionality standard once the doctrine is engaged?Closer to England. Keane J at [255] adopted Lord Hodge's Cavendish formulation for the proportionality inquiry itself

The safe formulation is: Australia kept the gateway England abandoned, and then adopted England's ceiling. Genuine pre-estimate of loss survives, but only as a safe harbour: a clause that is a genuine pre-estimate will not be struck. Not as the operative test for whether a clause is a penalty at all.

§ 04

Stage three: relief is severance, not voidness

Where a stipulation fails the ceiling, the consequence in Australia is narrower than in England. The clause is unenforceable only to the extent of the excess over the loss actually provable. It is not wholly void, and the protected party may still recover its proved loss. A penalty finding in Australia does not hand the paying party a windfall. It puts the protected party to proof of what it actually lost.

That has a consequence a drafter should plan around rather than only litigate around. Because the fallback is severance and proof of actual loss rather than outright loss of the remedy, a principal facing a penalty challenge is rarely staring at zero recovery. It is staring at the cost and delay of proving up its loss the ordinary way, with the certainty and the cash-flow advantage of the liquidated sum gone. That is a real loss even when the clause is only partly cut down, and it is the reason the drafting checklist below is worth following even on a clause a principal expects would ultimately survive a challenge.

§ 05

The construction cases: every reported delay LD challenge in this corpus has lost

The doctrine is High Court law, but it is tested in construction disputes against ordinary delay liquidated damages clauses, and the reported record so far runs one way.

DecisionOutcome
Grocon Constructors (Qld) Pty Ltd v Juniper Developer No 2 Pty Ltd4 [2015] QSC 102, [2015] QCA 291LD clause upheld. The "single obligation" attack fails where the trigger is delay to Practical Completion. Contemporaneous documentation of the rate calculation is what won it
Growthbuilt Pty Ltd v Modern Touch Marble &amp. Granite Pty Ltd5 [2021] NSWSC 290A$3,500 per day on a A$60,000 subcontract, upheld. At [104]–[109]: the onus is on the challenger, and legitimate interests include lost revenue and lost opportunity at [105]. The defendant ran both the penalty attack and the prevention attack, and lost both
State of Tasmania v Leighton Contractors Pty Ltd6 [2005] TASSC 133A$8,000 per day upheld. Loss of public utility is a legitimate interest for a public principal
Multiplex Constructions Pty Ltd v Abgarus Pty Ltd7 (1992) 33 NSWLR 504Holding and finance costs on the development are legitimate interests
Carbone v Fowler Homes Pty Ltd8 [2024] NSWCA 192The nominal-rate problem: a rate set so low it cannot be a genuine pre-estimate raises the question whether LDs are the exhaustive remedy
J-Corp Pty Ltd v Mladenis9 [2009] WASCA 157 and Baese Pty Ltd v RA Bracken Building Pty Ltd10 (1990) 6 BCL 137The line on whether an LD clause excludes a claim for general damages

Layer: jurisdictional. Australian case law is the least-verified block in this corpus. AustLII, NSW Caselaw, Jade and hcourt.gov.au returned 403 during research. Every citation above should be checked against a primary source before it is relied on in submissions.

§ 06

What a construction LD clause must do to survive

Two further points sit outside the checklist because they are not yet settled by authority. Grocon had a tiered LD structure, and tiering and capping by severity [INFERENCE] is a plausible way to answer the single-obligation attack, though no decision tests it directly. And where the counterparty is a consumer or small business, UNVERIFIED the unfair contract terms regime should be checked separately. A clause can survive the penalties doctrine and still be void as an unfair term.

§ 07

"No breach" triggers: a live drafting risk, and an English reflex that backfires

Because Andrews removes the breach requirement, a stipulation triggered by a non-breach event: a milestone that is not itself a contractual obligation, or a service-level abatement regime. Is within the Australian doctrine even though the identical drafting would sit outside the English one entirely.

That produces a trap for anyone trained on English precedent. The standard English response to a penalty risk is to restructure the trigger so that it is not a breach. That takes the clause outside Cavendish altogether. In Australia it does not. Removing breach from the trigger does not remove the stipulation from the Andrews gateway, and it may forfeit the one argument that would otherwise have helped: that the sum is a genuine pre-estimate of loss flowing from a breach. The drafting response that works in London can leave a clause worse off in Sydney.

★ NEGATIVE FINDING No Australian construction decision has yet struck down a delay stipulation on the Andrews no-breach ground. This is the honest limit of the doctrine as applied so far: commentary identifies the risk, and abatement regimes are the named example, but it has not crystallised into a reported construction outcome. The risk is doctrinal and live, not a demonstrated result. And a clause should be drafted defensively against it precisely because no court has yet had to decide the point.

The drafting answer is the conditional-benefit structure, not the no-breach structure. Make the payment the price of an additional right or accommodation conferred on the payer, rather than a collateral detriment securing the payer's performance. That is the escape route the gateway itself provides, and it does not depend on removing breach from the trigger.

§ 08

How Australia compares: three common-law systems, three different answers

Australia's severance-based relief is a genuine point of difference from both its common-law neighbours, and the comparison is worth stating because it decides what "unenforceable" actually means to a client.

AustraliaCanadaUnited States
Breach required?No (Andrews)YesYes
TestAndrews gateway + "out of all proportion" to legitimate interestsTwo-limb genuine pre-estimate + unconscionability, Cavendish not adoptedRestatement §356. Single-look or second-look by state. Cavendish not adopted
Genuine pre-estimateA safe harbour, not the testStill the testStill the test
Relief on a successful challengeSeverance of the excess: proved loss remains recoverableClause unenforceable in its entiretyWhole or nothing. Never judicially reduced

Australia, Canada and the United States have all declined Cavendish, and each for a different reason. Canada runs a two-limb genuine-pre-estimate test with an unconscionability overlay. The United States is anchored in a Restatement provision that does not move because England moved. Australia went the other way entirely: it restored an equitable doctrine England had discarded, then borrowed England's proportionality language for the ceiling it applies once that doctrine is engaged. The result on relief is a third pattern again. Where Australia severs the excess and lets the rest stand, an American court enforces the clause whole or throws it out whole, with no judicial reduction available either way.

For an owner or contractor pricing risk on an Australian job, that last row is the practical takeaway. A penalty finding in Australia is not the windfall it would be if the whole clause fell away. The protected party keeps its proved loss, and the practical exposure for the paying party is the gap between the struck rate and what could actually be proved, not the whole liquidated sum.

None of this changes the primary conclusion for anyone drafting or reviewing a delay LD clause today. The construction cases so far. Grocon, Growthbuilt, Leighton, Abgarus. All went the protected party's way, and the onus sits with the challenger throughout. The doctrinal risk sits at the gateway, not in the reported outcomes: it is the clause built around a non-breach trigger, with no documented rate derivation and no operating extension-of-time mechanism, that would be the first to test the Andrews ground a construction court has not yet had to decide.

Notes

Sources and authorities

10 cited
  1. *
    Verification, unless noted

    UNVERIFIED Australian case law is the least-verified block in this corpus. Verify against a primary source before pleading.

  2. 1
    Andrews v Australia and New Zealand Banking Group Ltd[2012] HCA 30, High Court of Australia

    Restored the equitable penalty doctrine. A stipulation is a penalty, as a matter of substance and not form, where it is collateral or accessory to a primary stipulation in favour of the other party, triggered by the failure of that primary stipulation, and imposes an additional detriment in the nature of security for and in terrorem of performance, and breach of the primary stipulation is sufficient but not necessary to engage the doctrine.

    Chercher sur AustLII

  3. 2
    Paciocco v Australia and New Zealand Banking Group Ltd[2016] HCA 28, High Court of Australia

    Set the proportionality ceiling: whether the stipulated detriment is out of all proportion to the legitimate interests the provision exists to protect, judged objectively and ex ante at the time of contracting. Those interests extend beyond Hadley v Baxendale remoteness, are not limited by common-law causation, need not have been foreseeable, may be non-monetary, and may embrace the protected party's enterprise-level financial position (Kiefel J at [29] and [65], Gageler J at [161]–[162], and Keane J at [271]–[273]). Keane J at [255] adopted Lord Hodge's Cavendish formulation for the proportionality standard itself, while Gageler J at [121] said the UK Supreme Court was wrong to require a breach.

    Chercher sur AustLII

  4. 3
    Ringrow Pty Ltd v BP Australia Pty LtdHigh Court of Australia. Neutral citation not confirmed in this corpus

    Named in the source material, together with Paciocco, as the origin of the "out of all proportion" proportionality standard applied at Stage 2 of the Australian penalties test.

  5. 4
    Grocon Constructors (Qld) Pty Ltd v Juniper Developer No 2 Pty Ltd[2015] QSC 102, [2015] QCA 291

    LD clause upheld. The "single obligation" attack fails where the trigger is delay to Practical Completion by the Date for Practical Completion. Contemporaneous documentation of how the rate was calculated was decisive.

    Chercher sur AustLII

  6. 5
    Growthbuilt Pty Ltd v Modern Touch Marble & Granite Pty Ltd[2021] NSWSC 290

    A$3,500 per day on a A$60,000 subcontract upheld. At [104]–[109]: the onus is on the party challenging the clause, and legitimate interests at [105] include lost revenue and lost opportunity, not only out-of-pocket loss. The defendant ran both the penalty attack and the prevention attack and lost both.

    Chercher sur AustLII

  7. 6
    State of Tasmania v Leighton Contractors Pty Ltd[2005] TASSC 133

    A$8,000 per day upheld. Loss of public utility is a legitimate interest a public principal may protect by an LD rate.

  8. 7
    Multiplex Constructions Pty Ltd v Abgarus Pty Ltd(1992) 33 NSWLR 504

    Holding and finance costs on the development are legitimate interests capable of supporting a liquidated damages rate.

  9. 8
    Carbone v Fowler Homes Pty Ltd[2024] NSWCA 192

    Raises the nominal-rate problem. An LD rate set so low it cannot be a genuine pre-estimate of loss puts in issue whether the LD clause is the exhaustive remedy for the delay it covers.

    Chercher sur AustLII

  10. 9
    J-Corp Pty Ltd v Mladenis[2009] WASCA 157

    Part of the Australian line on whether an LD clause operates as the exhaustive remedy for delay or leaves general damages available on top.

  11. 10
    Baese Pty Ltd v RA Bracken Building Pty Ltd(1990) 6 BCL 137

    Part of the same Australian line, with J-Corp Pty Ltd v Mladenis, on whether an LD clause excludes a claim for general damages.

    Chercher sur AustLII

General information, not legal advice. Reviewed 1 sept. 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou…

Each issue links to the full articles in the Storia Library.

Clause pénale et pénalités en Australie · Storia