- The short answer
- The Superintendent's unilateral power to extend time has displaced the prevention principle in most Australian disputes. The power must be exercised honestly and fairly, and a principal that declines to use it for delay of its own causing loses its liquidated damages entitlement. Producing a new completion date, not no date at all.
- The orthodox position
- A contractor that had an available EOT mechanism but failed to use it was not "prevented". Turner Corporation v Austotel (1994) 13 BCL 378 (NSWSC). The prevention principle does not rescue a contractor from its own procedural failure.
- Gaymark. The only finding
- Gaymark Investments v Walter Construction Group (1999) 16 BCL 449 (NTSC) is the only Australian decision ever to find time at large. It is a first-instance Northern Territory judgment, widely criticised, rejected in England, and distinguished rather than disapproved. Never expressly overruled, but confined to contracts with a time bar and no unilateral EOT power.
- SMK Cabinets. The correction
- SMK Cabinets [1984] VR 391 is widely mis-described as a time-at-large case. It disallowed liquidated damages prospectively from the act of prevention. It did not put time at large, and should not be cited for that proposition.
- Declined since
- Time at large has been declined repeatedly since Gaymark. Growthbuilt [2021] NSWSC 290, CMA Assets [2015] WASC 217, and Bensons [2021] VSCA 69, which held that "the touchstone must be the terms of the contract".
- The duty enforced at its sharpest
- V601 Developments v Probuild [2021] VSC 849 found the Superintendent had colluded with the principal, set aside the liquidated damages certificates, and awarded acceleration costs. The modern high-water mark for the honesty-and-fairness duty.
- The device that neutralises the duty
- Queensland TMR contracts provide, at clause 2.2(j), that absolute discretions need not be exercised for the contractor's benefit. A direct attack on the honest-and-fair architecture. The same device succeeded in Growthbuilt and CMA Assets and appears in amended AS forms. It is the single most consequential amendment to look for.
- The statutory overlay
- From 15 April 2026 in Victoria and since 1 August 2022 in Western Australia, an EOT time bar affecting a payment or security entitlement may be declared unfair and of no effect. In those two states the contractor can attack the bar directly rather than argue prevention.
Australia has the English prevention principle on the books and almost never needs it. A better mechanism does the same job: the Superintendent's unilateral power to extend time, which must be exercised honestly and fairly. Where a principal has that power and will not use it for delay of its own making, it loses its liquidated damages, and the result is a new completion date, not no completion date at all.
That reframing matters more than any single case on this page. In England the contractor argues prevention to destroy the completion date outright. In Australia the contractor argues that the Superintendent was obliged to extend. A narrower, more predictable and much easier remedy to win, and one that keeps a date alive rather than setting one at large. Time at large is correspondingly rare. Everything below rests on a single source note, and a verification caveat applies to nearly all of it: AustLII, NSW Caselaw, Jade and the High Court's own site all returned 403 during the research behind this page, so treat the Australian case law here as secondary-sourced and unverified pending primary-text confirmation. For the wider framework, start at extension of time in Australia.
The orthodox position: prevention does not rescue a procedural failure
The starting point is unhelpful to contractors who had a mechanism and did not use it. In Turner Corporation Ltd (Recvr & Mgr Apptd) v Austotel Pty Ltd (1994) 13 BCL 378 (NSWSC, Cole J), a contractor that had an available extension-of-time mechanism but failed to use it was not "prevented". The prevention principle does not exist to rescue a contractor from its own procedural failure. It answers a different question, whether the principal's conduct destroyed the mechanism, not whether the contractor bothered to operate it. That is the prevailing position across Australian jurisdictions, and it aligns with the later English position in Multiplex v Honeywell (No 2).
Gaymark: the only Australian finding, and how confined it is
Set against that orthodoxy is a single outlier. Gaymark Investments Pty Ltd v Walter Construction Group Ltd (1999) 16 BCL 449, [1999] NTSC (Bailey J) reached the contrary result: the contractor's failure to lodge EOT applications within a contractual time bar, for delays the principal caused, put time at large and defeated the liquidated damages claim entirely.
Its current standing is doubtful and effectively confined. Gaymark has been widely criticised, and was rejected in England by Jackson J in Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2) [2007] EWHC 447 (TCC) at [103]. But no Australian appellate court has expressly overruled it. It remains a first-instance Northern Territory decision that has been distinguished rather than disapproved, and it retains argumentative value in one specific configuration: a contract with a time bar and no unilateral EOT power. Because most Australian standard forms do have that power, the configuration is rare, which is precisely why Gaymark has never had to be overruled outright. It has simply had nothing to bite on.
The doctrine that actually governs: the unilateral power
Where Gaymark is the exception, the following line of authority is the rule. Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211, (2002) 18 BCL 322 held, on AS 2124, that the Superintendent's unilateral extension-of-time power must be exercised honestly and fairly, and that the Superintendent was required to grant an extension even though the contractor was out of time. 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491 follows the same line: the independent certifier owes a duty to act honestly and fairly in exercising EOT powers.
Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151 sharpens the point into a rule that decides money. On an amended AS 4303-1995 subcontract, the subcontractor completed 144 days late without timely EOT claims, and the head contractor sought to set off liquidated damages. The Court held that to claim liquidated damages, the head contractor was obliged to exercise its unilateral power to extend time for delays it had itself caused. It indicated an implied duty of good faith in exercising the discretion, but confined that duty to the prevention rationale, meaning it obliges extension only for delays the principal actually caused, not an at-large fairness obligation running in every direction.
A principal who declines to use the unilateral power for delays it caused loses the liquidated damages that power was meant to protect.
V601 Developments: the duty enforced at its sharpest
V601 Developments Pty Ltd v Probuild Constructions (Aust) Pty Ltd [2021] VSC 849 (Digby J) is the modern high-water mark. The Superintendent was found to have colluded with the principal. The liquidated damages certificates were set aside and the LD claim failed wholly. Acceleration costs were recovered, though the court expressly declined to treat the EOT refusal as a "direction". And the EOT clause was held to require retrospective delay analysis, a contractual limb that other Australian methodology cases lack.
V601 is the case to cite when the Superintendent has not been independent. It converts the Peninsula Balmain duty from a principle into an actual remedy: not just a statement that the discretion must be exercised honestly and fairly, but a court prepared to set aside certificates and defeat an LD claim wholly where it was not.
The device principals use to neuter the duty
The honest-and-fair architecture has an obvious point of attack, and principals have found it. Queensland TMR contracts provide, at clause 2.2(j), that absolute discretions need not be exercised for the contractor's benefit. That is a direct attack on the whole Australian EOT architecture, which rests on the unilateral power being exercised honestly and fairly. Remove the obligation to consider the contractor's interest at all, and the Peninsula Balmain duty has little left to bite on.
The same device succeeded in Growthbuilt [2021] NSWSC 290 and CMA Assets [2015] WASC 217, and it appears in amended AS forms more broadly. It is arguably the single most consequential amendment a principal can make to an Australian EOT regime, and it is the first thing to look for when reading an executed contract rather than the printed standard form.
Time at large: and a widely repeated mis-description
Only Gaymark has ever found time at large in Australia. It is a first-instance Northern Territory decision, criticised, distinguished rather than disapproved, and never expressly overruled.
One case is regularly cited alongside it and should not be. SMK Cabinets [1984] VR 391 is widely mis-described as a time-at-large case. It is not. It disallowed liquidated damages prospectively from the act of prevention. It did not set time at large, and it should not be cited for that proposition.
And the doctrine has been declined repeatedly since Gaymark: Growthbuilt at [80]. CMA Assets [2015] WASC 217, and Bensons [2021] VSCA 69. Holding that "the touchstone must be the terms of the contract".
The Australian answer to "is time at large?" is almost never, and the contract is where the argument is won or lost.
| England and Wales | Australia | |
|---|---|---|
| Status of the principle | A default rule of risk allocation, displaceable by clear express words | Present, but largely displaced in practice by the unilateral EOT power |
| The contractor's usual route | Argue prevention to destroy the completion date | Argue the Superintendent was obliged to extend. Producing a new date |
| Time at large | An established doctrinal outcome | Found only once, in Gaymark. Declined in Growthbuilt, CMA Assets, Bensons |
| The certifier's duty | Certification duties are contractual, not fiduciary | Must be exercised honestly and fairly, Peninsula Balmain, 620 Collins Street |
| A principal's own-caused delay | Prevention defeats the LD clause outright | The principal must extend for its own delay or lose LDs, Probuild v DDI Group |
Comparative. The Australian row states first-instance and intermediate appellate authority. Case law throughout this corpus is treated as secondary-sourced and unverified.
The interaction with AS 2124's concurrency bar
Under AS 2124-1992, clause 35.5, the contractor gets no extension of time to the extent delays are concurrent. But Probuild v DDI Group holds that a principal must exercise its unilateral power for delays it caused if it wants its liquidated damages.
Where the principal caused part of a concurrent delay period, those two rules pull in opposite directions. The form denies the EOT. Probuild obliges the extension. That interaction is under-litigated and is a genuine open question, best flagged to a client rather than resolved with false confidence. See concurrent delay in Australia.
The statutory layer now sits on top
From 15 April 2026 in Victoria and since 1 August 2022 in Western Australia, a notice-based time bar. Including an EOT time bar affecting a payment or security entitlement. May be declared unfair and of no effect where compliance "is not reasonably possible" or "would be unreasonably onerous".
This substantially reduces the need for a prevention argument in those two states, because the contractor can attack the bar directly rather than arguing that the principal's conduct destroyed the completion date. It does, by statute and with a structured test, roughly what Gaymark tried to do at common law. See notice and time bars in Australia.
This is the single most consequential amendment to look for. Read the executed contract before assuming Peninsula Balmain applies. 84% of Australian standard forms are amended in practice, and a clause like Queensland TMR's 2.2(j) can neutralise the whole honest-and-fair architecture.
The contractor's first argument in Australia is the discretion, not the doctrine. Certifier independence is the real battleground. A Superintendent acting as the principal's agent, rather than exercising an honest and independent judgment, is the target under Peninsula Balmain and V601.
AS 2124-1992 clause 35.5 denies an EOT for concurrent delay, but Probuild v DDI Group obliges the principal to extend for delay it caused. That tension is unresolved. Flag it rather than assume either rule wins outright.
Do not. It disallowed liquidated damages prospectively from the act of prevention. It is not a time-at-large case, however often it is described as one.
Since 15 April 2026 in Victoria and since 1 August 2022 in Western Australia, an EOT time bar affecting a payment or security entitlement can be attacked directly as unfair, without needing to run a prevention argument at all.
Three practical consequences
The reframing from prevention to unilateral power carries through into how a dispute is actually run.
First, the contractor's first argument is the discretion, not the doctrine. Ask what the Superintendent knew, when it knew it, and whether the power was considered at all. Not whether the principal's conduct was, in the abstract, an act of prevention.
Second, certifier independence becomes the battleground. Peninsula Balmain and 620 Collins Street are about the certifier's duty to act honestly and fairly. A Superintendent who acts as the principal's agent rather than as an independent decision-maker in exercising the power is the target, and V601 shows what a court will do once collusion is established.
Third, time at large is correspondingly rarer in Australia than the English case law would suggest. The unilateral power keeps a date alive in the great majority of disputes, which is exactly why Gaymark has stayed a first-instance outlier rather than becoming a live doctrine. There is almost always a power available to make the Gaymark configuration inapplicable.
What this means for how a claim is actually built
None of this removes the value of records. Probuild v DDI Group and V601 both turn on what the Superintendent knew and when, which means the contractor's case is built the same way a prevention case would be built in England: contemporaneous notices, programme updates, and correspondence showing the principal's own conduct caused the critical delay. The difference is what that evidence is used to prove. In England it proves that the completion date has been destroyed. In Australia it proves that a discretion was not exercised honestly, or was not exercised at all. A narrower proposition, but one a court is considerably more willing to find in the contractor's favour, because the consequence for the principal is a recalculated date rather than the loss of the entire liquidated damages regime.
That also explains why the Queensland TMR-style device is worth identifying early rather than late. Where clause 2.2(j)-style wording is present, the contractor's Probuild argument has nothing to attach to. There is no honest-and-fair obligation for the principal to have breached, because the contract says the discretion need not be exercised for the contractor's benefit at all. In that configuration the contractor is thrown back onto Gaymark's narrow ground: a time bar, and effectively no unilateral power worth the name. It is one of the few situations in which Gaymark becomes directly relevant again, rather than a historical curiosity.
The synthesis
The presence of a unilateral EOT power, honestly exercised, is what saves the principal's liquidated damages entitlement, and a principal who declines to use that power for its own delays loses them. That is the practical rule that does almost all of the work on an Australian project, and it is why the prevention principle proper, and time at large with it, comes up so rarely. A contractor arguing prevention in Australia is usually running the second-best argument. The first is that the Superintendent was obliged to extend.
Authorities
- Turner Corporation Ltd (Recvr & Mgr Apptd) v Austotel Pty Ltd (1994) 13 BCL 378, New South Wales Supreme Court (Cole J)A contractor that had an available extension-of-time mechanism but failed to use it was not "prevented". The prevention principle does not rescue a contractor from its own procedural failure. The prevailing position across Australian jurisdictions, aligning with the later English position in Multiplex v Honeywell (No 2).Australian case law is the least-verified block in this corpus. AustLII, NSW Caselaw, Jade and hcourt.gov.au all returned 403 during research. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- Gaymark Investments Pty Ltd v Walter Construction Group Ltd (1999) 16 BCL 449, [1999] NTSC, Northern Territory Supreme Court (Bailey J)The contractor's failure to lodge extension-of-time applications within a contractual time bar, for delays the principal caused, put time at large and defeated liquidated damages. The only Australian decision ever to find time at large. Widely criticised, distinguished rather than disapproved, and never expressly overruled. It retains argumentative value only where the contract has a time bar and no unilateral EOT power, a configuration most Australian standard forms avoid by including that power.Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2) [2007] EWHC 447 (TCC), Technology and Construction Court, England and WalesRejected Gaymark at [103]. Acts of prevention do not set time at large where the contract provides for extension of time in respect of those events, and a contractor's own failure to serve a condition-precedent notice does not put time at large.An English decision, cited here for its rejection of Gaymark. Not part of the Australian-case-law verification caveat.Find on Find Case Law →
- Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211, (2002) 18 BCL 322, New South Wales Court of AppealOn AS 2124. The Superintendent's unilateral extension-of-time power must be exercised honestly and fairly, and the Superintendent was required to grant an extension even though the contractor was out of time.Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491, Supreme Court of VictoriaThe independent certifier owes a duty to act honestly and fairly in exercising extension-of-time powers. The same line as Peninsula Balmain.Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151, New South Wales Court of AppealOn an amended AS 4303-1995 subcontract. The subcontractor completed 144 days late without timely EOT claims, and the head contractor sought to set off liquidated damages. Held: to claim liquidated damages, the head contractor was obliged to exercise its unilateral power to extend time for delays it had itself caused. The Court indicated an implied duty of good faith in exercising the discretion, but confined to the prevention rationale. It obliges extension only for delays the principal actually caused, not an at-large fairness obligation.Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- V601 Developments Pty Ltd v Probuild Constructions (Aust) Pty Ltd [2021] VSC 849, Supreme Court of Victoria (Digby J)The modern high-water mark. The Superintendent was found to have colluded with the principal. The liquidated damages certificates were set aside and the LD claim failed wholly. Acceleration costs were recovered, though the court expressly declined to treat the EOT refusal as a "direction". The EOT clause was held to require retrospective delay analysis. Converts the Peninsula Balmain duty from a principle into a remedy where the Superintendent has not been independent.Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- Growthbuilt [2021] NSWSC 290, New South Wales Supreme CourtDeclined to find time at large, at [80]. Also an instance in which a clause providing that an absolute discretion need not be exercised for the contractor's benefit succeeded in neutralising the honest-and-fair duty.Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- CMA Assets [2015] WASC 217, Supreme Court of Western AustraliaDeclined to find time at large. Also an instance in which a clause providing that an absolute discretion need not be exercised for the contractor's benefit succeeded in neutralising the honest-and-fair duty.Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- Bensons [2021] VSCA 69, Victorian Court of AppealDeclined to find time at large: "the touchstone must be the terms of the contract".Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. Verify before pleading.Find on AustLII →
- SMK Cabinets [1984] VR 391, Supreme Court of VictoriaDisallowed liquidated damages prospectively from the act of prevention. It did not set time at large. The decision is widely mis-described as a time-at-large case and should not be cited for that proposition.Australian case law is the least-verified block in this corpus. Citation, court and holding rest on secondary sources. This correction is flagged in the source corpus as a live mis-description to guard against.
- AS 2124-1992, clause 35.5 Standards Australia, AS 2124-1992 General Conditions of Contract, cl 35.5The contractor gets no extension of time to the extent that delays are concurrent.Attributed to AS 2124-1992 only. AS 4000-1997's concurrency treatment at clause 34.4 is a separate provision and is not addressed on this page.
- Building and Construction Industry Security of Payment Act 2002 (Vic), s 13A s 13A, in force from 15 April 2026A notice-based time bar. Including an EOT time bar affecting a payment or security entitlement. May be declared unfair and of no effect where compliance is not reasonably possible or would be unreasonably onerous.Prospective at the time of writing. Not yet tested by case law.
- Building and Construction Industry (Security of Payment) Act 2021 (WA), s 16 s 16, in force since 1 August 2022A notice-based time bar. Including an EOT time bar affecting a payment or security entitlement. May be declared unfair and of no effect where compliance is not reasonably possible or would be unreasonably onerous.No case law applying s 16 to an EOT time bar specifically was identified in this corpus.
About this material Library content is general information about construction claim practice, not legal advice. Entitlement, deadlines and procedure are governed by your own contract and by the law of the place the work is performed. Reviewed September 1, 2026 · Report a correction
In this article
- The orthodox position: prevention does not rescue a procedural failure
- Gaymark: the only Australian finding, and how confined it is
- The doctrine that actually governs: the unilateral power
- V601 Developments: the duty enforced at its sharpest
- The device principals use to neuter the duty
- Time at large: and a widely repeated mis-description
- The interaction with AS 2124's concurrency bar
- The statutory layer now sits on top
- Three practical consequences
- What this means for how a claim is actually built
- The synthesis