Skip to main content

Australia

Reading

What applies here

Filter
ArticleSectionPlaceReviewed
Extension of timeMoving the completion date. The four elements a time claim must establish, the five defences that beat sound ones, and where each element is taken further.Construction / ClaimsOctober 6, 2026
Concurrent delayFive competing definitions and nine different answers on one fact pattern. Not settled law in any jurisdiction surveyed.Construction / ClaimsOctober 6, 2026
Notice and time barsThe element that defeats more sound claims than the other three combined. Three incompatible philosophies, and the statutory overrides now cutting across them.Construction / ClaimsSeptember 27, 2026
Delay analysis methods comparedSix delay analysis methods compared: what each needs, what it costs and how it is attacked, plus a chooser driven by timing, records and the contract.Construction / ClaimsOctober 6, 2026
Prolongation and delay costsThe money gateway. Compensation runs to the period the effect was felt, not to the weeks at the end of the job.Construction / ClaimsAugust 7, 2026
Records and evidenceWhich records support which analysis method, and what tribunals actually punish.Construction / ClaimsOctober 6, 2026
Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2Six letters: the AS 4000 delay notice and EOT claim, the FIDIC Notice of Claim and fully detailed Claim, and the CCDC time and money notices. Plus when each clock starts.Construction / ClaimsOctober 6, 2026
How to write an EOT claimEight steps from reading the contract to submitting the claim, a claim document outline you can copy, and the reasons EOT claims most often fail.Construction / ClaimsOctober 6, 2026
EOT claim readiness checklistEight groups to tick off before and after you submit an extension of time claim: contract, notice, records, causation, concurrency and float, quantum, the document, and follow-up.Construction / ClaimsOctober 6, 2026
Extension of time in AustraliaAustralia rejected Gaymark and enforces time bars, but two states now let a tribunal strike an unfair one out. Security of payment runs state by state.Construction / ClaimsAustraliaSeptember 26, 2026
Prevention and time at large in AustraliaTime at large has been declined repeatedly since Gaymark. The orthodoxy is that a contractor who fails to claim an extension keeps the completion date.Construction / ClaimsAustraliaSeptember 1, 2026
Concurrent delay in AustraliaAS 4000-1997 apportions overlapping delay and AS 2124-1992 denies it. The form decides the answer, and 84% of forms are amended.Construction / ClaimsAustraliaSeptember 1, 2026
Notice and time bars in AustraliaTime bars are enforced, with a new exception: Western Australia since 2022 and Victoria since 2025 can strike out a notice provision that is unfair.Construction / ClaimsAustraliaSeptember 26, 2026
Liquidated damages and penalties in AustraliaAndrews means a stipulation can be struck without any breach at all, and Paciocco puts Australia further from England than before Cavendish.Construction / ClaimsAustraliaSeptember 1, 2026
Prolongation and delay costs in AustraliaNo formula jurisprudence. Australian courts want actual cost proved contemporaneously, which is what most prolongation claims cannot produce.Construction / ClaimsAustraliaSeptember 1, 2026
Global claims and total cost in AustraliaWhat a global claim has to plead in Australia, why Cessnock is not the delay authority it is cited as, and where the total-cost route still fails.Construction / ClaimsAustraliaSeptember 27, 2026
Acceleration in AustraliaThere is no constructive acceleration doctrine. The claim is breach of the Superintendent's duty, and pleading the American doctrine loses it.Construction / ClaimsAustraliaSeptember 1, 2026
Delay analysis methods in AustraliaFour decisions, four positions, thirteen years. Alstom, White Constructions, V601 and Santos v Fluor disagree on what a method has to be.Construction / ClaimsAustraliaSeptember 1, 2026
Records and expert evidence in AustraliaConcurrent evidence, the Harmonised Expert Witness Code, and why White Constructions turned on records rather than on methodology.Construction / ClaimsAustraliaSeptember 1, 2026
Limitation and long-stops in AustraliaSix years almost everywhere, three in the Northern Territory, and a ten-year building long-stop in Victoria that substitutes rather than sits alongside.Construction / ClaimsAustraliaSeptember 1, 2026
Security of payment in AustraliaEight regimes, two models, and the question that decides a delay claim: whether an extension of time is adjudicable at all in that state.Construction / ClaimsAustraliaSeptember 26, 2026
VariationsScope and price. The five elements a variation claim must establish, why agreeing a value may not pay for the time it cost, and where each element is taken further.Construction / ClaimsOctober 6, 2026
What counts as a variationThe scope question, and why the Privy Council held in 2026 that it turns on the contract terms rather than on how the parties behaved on site.Construction / ClaimsSeptember 26, 2026
Written instruction and waiverYou did the work and there is no written instruction. Five regimes, five answers, and on US public work the rule is one estoppel cannot cure.Construction / ClaimsSeptember 26, 2026
Constructive and deemed variationsThe claim for a variation nobody instructed, and why the doctrine does not exist outside the United States, only functional substitutes measured differently.Construction / ClaimsSeptember 26, 2026
Valuation and the pricing ladderContract rates, then adjusted rates, then a fair valuation, then daywork. You may not skip a rung, and NEC4 has no ladder at all.Construction / ClaimsSeptember 26, 2026
Change order releasesImpact claims die in signed change orders, not in tribunals. The reservation language that works, and two citations the commentary gets backwards.Construction / ClaimsOctober 6, 2026
Variation claims in Australia: AS 4000, AS 2124 and the 2026 changesWho directed the work, in writing and before when; why approving a 'variation' does not make one (Kaloriziko, 2025); the AS 4000 pricing ladder; and Victoria's 2026 security-of-payment changes.Construction / ClaimsAustraliaSeptember 26, 2026
Oral variations in Australia: why Rock Advertising never crossedA writing clause cannot stop the Principal and Contractor agreeing a variation orally. But under AS 4000 cl 36.1 an oral instruction is not a direction, so the claim must be proved as an agreement or estoppel with the Principal.Construction / ClaimsAustraliaSeptember 26, 2026
AS 4000 deemed variations and latent conditions in AustraliaAustralia has no constructive-change doctrine. What it has is contractual deeming: latent conditions priced as Variations under AS 4000, the 2025 edition's reported additions, and AS 2124's different measure.Construction / ClaimsAustraliaSeptember 26, 2026
AS 4000 variation pricing: how to value a variation in AustraliaAS 4000 cl 36.4 prices a variation by prior agreement, contract rates, a priced schedule, then reasonable rates. Kaloriziko (2025): pricing a non-variation does not make it a variation.Construction / ClaimsAustraliaSeptember 26, 2026
Variation notice templates for AS 4000 and AS 2124Five letters: request the Superintendent's written direction, notify a Variation, notify a latent condition, give the AS 2124 cl 46.1 notice, and submit the price. Plus which to send when, and the records behind each.Construction / ClaimsAustraliaOctober 6, 2026
Variations in Victoria: security of payment after 15 April 2026Victoria repealed the ss 10A–10B claimable-variation gateway on 15 April 2026 and added s 13A on unfair notice-based time bars: what changed for variation claims, and what is still open.Construction / ClaimsVictoriaSeptember 26, 2026
Variation claims in Victorian adjudication: ss 10A–10B gone, s 13A inSince 15 April 2026 a disputed Victorian variation can be adjudicated. What ss 10A–10B excluded, which claims s 54 keeps on the old rules, the new-reasons bar, and s 13A read from the Act.Construction / ClaimsVictoriaSeptember 26, 2026
Construction claims in Australia · Storia