Prevention and Time at Large in British Columbia
British Columbia supplies both Canadian prevention anchors and the strongest candidate for a Canadian judgment actually finding time at large, Hawl-Mac (1985). That proposition contradicts most national commentary, rests on a 41-year-old first-instance decision, and makes a defective or unadministered extension-of-time mechanism a materially stronger argument in BC.
At a glance
- British Columbia, Canada, common law
- Construction claims, extension of time and delay
- Case law secondary only, no paragraph pinpoints; Arbitration Act from the Bill 7 (2020) third-reading text rather than the consolidation
Key facts
- 01
Can time be at large in BC?
Yes, on the strongest available candidate, Hawl-Mac (1985), 10 CLR 177 but it is first instance and unverified against the primary text
- 02
The national picture
The leading Canadian commentary treats time at large as under-considered by Canadian courts, not as never found. Both positions are recorded, and they are compatible
- 03
The mechanism
Failure to determine a new completion date within a reasonable time of the request, before the original completion date passed, meant the owner could not rely on that date, and liquidated damages failed
- 04
Prevention anchors
Perini Pacific, (1966), 57 DLR (2d) 307 (BCCA): the prevention holding is the Court of Appeal's; the liquidated damages counterclaim was not in issue on the further appeal to the Supreme Court of Canada, and N.B.C. Mechanical (1999 BCCA 775), both British Columbia cases doing national work
- 05
Extensions of time
Permissive, not mandatory, and a contractor need not seek one in order to claim delay damages (Foundation Co, 1997)
- 06
No damage for delay
No BC decision construes such a clause after Tercon (2010). The BC line is pre-Tercon and construction-based
- 07
Relief from forfeiture
No BC decision applies Law and Equity Act s 24 to a construction notice provision or time bar. Open and untested
- 08
Currency
The argument is built from 1966, 1985 and 1997. No BC judgment between 2015 and 2026 is squarely a large-project delay decision
British Columbia is where the Canadian prevention principle came from, and it is the only province with a serious candidate for a judgment that actually put time at large. That candidate is Hawl-Mac. It is from 1985, it is first instance, and most national commentary writes as though it does not exist.
This page carries a proposition the rest of the Canadian literature has largely passed over. The leading Canadian commentary treats time at large as under-considered by Canadian courts (first mentioned here in a 1966 British Columbia Court of Appeal decision and not thoroughly examined since), which is not a statement that no Canadian court has found it. A British Columbia decision that two independent indexes place at (1985), 10 CLR 177 is the counter-example on the result. Whether the judgment used the language of time at large depends on words nobody in this corpus has read. That is said in the sentence wherever the point arises below, and it is not softened anywhere else.
The evidence rule for this page is the strict one. No BC judgment was read in original text. CanLII and bccourts.ca blocked automated retrieval, so every case proposition here rests on two or more independent reputable secondary sources and carries no paragraph pinpoint. Statutory and contract-form material is flagged separately where its provenance is different. For the pan-Canadian doctrine this page does not repeat, see the Canadian prevention principle and time at large, for the rest of the province's delay law, the British Columbia extension-of-time hub.
Can time be at large in British Columbia?
Yes, on the strongest authority available anywhere in Canada, and that authority is a 1985 BC Supreme Court judgment. Hawl-Mac Construction Ltd v Campbell River (District), (1985), 10 CLR 177, 1985 CanLII 342 (BCSC)1 is reported as holding that a failure to grant an extension of time in time meant the owner could not rely on the original completion date and could not enforce liquidated damages. That is the operative consequence of time at large.
The leading Canadian commentary treats time at large as under-considered by Canadian courts: it records that the concept was first mentioned here in a 1966 British Columbia Court of Appeal decision and has not been thoroughly examined since, and that it has featured prominently in private arbitrations. That is not a statement that no Canadian court has found time at large, and it is not inconsistent with Hawl-Mac. Hawl-Mac is reported by two independent Canadian sources as a decision in which time was held to be at large and liquidated damages could not be enforced. It is a 1985 first-instance judgment and the primary text should be read before it is pleaded, but there is no contrary Canadian authority and no doctrinal conflict to reconcile. What is not determinable without the text is whether the judgment used the language of time at large or reached the same place by finding a breach of an express term.
| Position | Where it comes from | What it claims |
|---|---|---|
| Time at large is under-considered in Canada | A national legal-press piece on time at large | The concept was first mentioned here in a 1966 BCCA decision, has not been thoroughly examined since, and lives in private arbitration |
| BC has a finding of it | Two construction-press and firm sources | Hawl-Mac held a late extension decision defeated the completion date and the liquidated damages |
| The corpus position | Both, read together | The two are compatible. Hawl-Mac is the Canadian counter-example on the result, subject to verification of the primary text, and no Canadian authority holds the other way |
Layer: inferential, and comparative between commentators. Both rows rest on the secondary tier (no primary judgment text was read) so the third row is a reading of the sources, not a holding of any court.
What Hawl-Mac is reported to decide, and the reasons for caution
Three propositions, all directly on point, and all resting on secondaries. First, the owner or engineer must determine a new completion date within a reasonable time after the request for an extension was made. A BC decision on the actual operation of a contractual extension mechanism, which this corpus otherwise lacks anywhere in Canada. Second, failure to grant an extension in time sets time at large: the contractor is no longer required to complete by a specified date but within a reasonable period, and liquidated damages cannot then be enforced. On the facts, the engineer's failure to decide the extension request in time meant the owner could not rely on the original completion date. One BC source reports the contract as imposing a seven-day period on the engineer; the other accessible accounts describe only a reasonable-time or "prompt" duty, so the seven-day figure is single-sourced and should be confirmed against the judgment before it is pleaded as a day count. Third, and marked UNVERIFIED, a no-damage-for-delay clause was not enforced.
Now the reasons to be careful, which belong in any submission that relies on it. It is 41 years old. It is first instance, and no BC appellate court has adopted or applied it in the accessible record. Hawl-Mac is reported at (1985), 10 CLR 177, at 60 BCLR 57 and at (1984-85) 1 Const LJ 370, and is available on CanLII at 1985 CanLII 342 (BCSC). It is treated squarely as a time-at-large decision in the Canadian construction trade press and in the international literature, but it is rarely picked up in Canadian firm commentary on delay. NEGATIVE FINDING The trial judge could not be identified in any accessible source. The judgment is on CanLII at 1985 CanLII 342 and should be pulled before the quoted words are relied on.
Why the answer matters more in BC than the national commentary suggests
Because it changes what a contractor does about a broken extension-of-time mechanism. If Hawl-Mac is right, then in British Columbia an owner or certifier who lets an extension request sit unanswered past the completion date is not merely in breach of an administrative duty. It has forfeited the completion date and, with it, the liquidated damages. That is a materially stronger answer to a defective or unadministered mechanism than the national commentary offers.
It also explains a gap. NEGATIVE FINDING There is no BC authority on whether an extension of time may be granted retrospectively, after the completion date has passed. The nearest BC material is Hawl-Mac, which addresses the converse: an extension granted too late does not save the completion date but sets time at large instead. The inference (stated as an inference) is that BC has never had to decide the retrospective-extension question because Hawl-Mac resolves the practical problem in the contractor's favour by a different route.
The defensible way to plead it: Hawl-Mac is the strongest candidate for a Canadian finding of time at large, subject to verification of the primary text, and the national commentary asserting that no Canadian court has found time at large should be read against it.
Both national prevention anchors are British Columbia cases
The Canadian prevention principle is BC law twice over, and this is the part of the page that does the least new work. Perini Pacific Ltd v Greater Vancouver Sewerage & Drainage District, (1966), 57 DLR (2d) 307 (BCCA)2 is the Canadian statement of Dodd v Churton: an owner is not allowed to insist upon the penalty for delay if, by ordering extra, it has prevented the builder from completing by the specified time. ★ That holding is the Court of Appeal's. The owner's liquidated damages counterclaim was dismissed there and was not in issue on the further appeal, [1967] SCR 189, 60 DLR (2d) 385, where the Supreme Court decided a different question: enforcing a no-damage-for-delay clause against the contractor's own claim. Citing the prevention holding as "aff'd [1967] SCR 189" implies a Supreme Court endorsement that does not exist. N.B.C. Mechanical Inc v A H Lundberg Equipment Ltd, 1999 BCCA 7753 applies it: the owner's $200,000 liquidated damages counterclaim failed because the owner's own requests for extras had caused a significant part of the delay.
Both are developed at the Canada level rather than here, see the Canadian liquidated damages page but the fact that both are BC decisions is itself the point. An Ontario or Alberta contractor running a prevention defence is arguing on British Columbia and English authority, and should say so rather than be caught by it. On the refinement, plead the judgment accurately. The trial judge in N.B.C. Mechanical held that "whether or not NBC could have completed its work by the deadline were it not for the delays caused by Lundberg is irrelevant", and the Court of Appeal declined to interfere. But it declined on a standard of review: the attribution of responsibility for delay was "an assessment of the whole of the evidence", and the contractor's own admitted 80 per cent completion at the deadline was "only one factor to be considered". So the refinement is a trial finding affirmed on deference, not an appellate rule that concurrent contractor delay is categorically irrelevant. Plead it that way, and expect an owner to run the "only one factor" line back at you. See concurrent delay and apportionment in BC.
And then the province stops. NEGATIVE FINDING No BC decision after 2000 was located applying Perini Pacific to find prevention on construction facts. The prevention line appears after 2000 only in the CIMIC arbitral award, and before 2000 in Kei-Ron Holdings Ltd v Coquihala Motor Inn Ltd, [1996] BCJ No 1237 (BCSC)4 itself UNVERIFIED, a general application of the principle that no party may take advantage of the non-fulfilment of a condition whose performance it has hindered. Note the styling the corpus records: "Coquihala", not "Coquihalla". Search both.
| Authority | Citation | What it actually carries |
|---|---|---|
| Perini Pacific | (1966), 57 DLR (2d) 307 (BCCA): the SCC appeal, [1967] SCR 189, did not touch this point | Prevention by ordering extras, or owner-caused critical delay, defeats the liquidated damages or penalty |
| N.B.C. Mechanical | 1999 BCCA 775 | LD counterclaim defeated where the owner's own requests for extras caused a significant part of the delay. A trial finding upheld on deference, not an appellate restatement |
| Hawl-Mac | (1985), 10 CLR 177 (BCSC) | Prevention, or breach, by failing to operate the extension machinery in time |
| Foundation Co v UGG | (1997), 91 BCAC 254 (BCCA) | An extension is permissive. A contractor need not seek one to claim delay damages |
Layer: jurisdictional, these are British Columbia rules. Every row rests on the secondary tier under this cluster's evidence rule: two or more independent sources agree on citation and proposition, no primary judgment text was read, and no paragraph pinpoints are given.
An extension of time is permissive, not mandatory
This is the most under-known proposition in BC delay law, and it is appellate. Foundation Co of Canada Ltd v United Grain Growers Ltd, (1997), 91 BCAC 254, (1997), 33 CLR (2d) 159 (BCCA)5 establishes that an extension of time is permissive rather than mandatory, and, the part that matters most in practice. A contractor is not obliged to seek an extension of time in order to claim delay damages.
Take that slowly, because it disposes of a defence owners run constantly. The argument that a contractor who never applied for an extension has thereby given up its delay damages does not reflect BC law as reported. Entitlement to be paid for owner-caused delay and entitlement to relief from the completion date are separate questions, and losing or never running the second does not extinguish the first. For a claimant who has been advised that its failure to work the extension machinery is fatal, this is the case to read first. It is BCCA authority, it is from 1997, and (like everything else here) it has not been revisited.
The same judgment does two further things that a BC pleading should use together. The trial judge apportioned delay 75% to the owner and its engineer and 25% to the contractor, and the Court of Appeal dismissed the appeals against that allocation, which is why BC concurrency is a damages exercise rather than an entitlement one. And it barred the owner's own delay counterclaim because the owner had deliberately withheld notice of that claim until a strategically advantageous moment, notice in BC cuts both ways, and the first question in any BC delay defence is whether the owner complied with its own notice obligations. See notice and time bars in BC.
The owner's answer. The sweep-up clause, and the gap it leaves
An owner meets a prevention argument by pointing at the contract: the act complained of is a listed extension event, the machinery covers it, so time never went at large. That answer works only as far as the clause reaches, and on CCDC 2 – 2020, GC 6.5.1 and GC 6.5.3.46 the reach is narrower than practitioners assume. GC 6.5.1 covers delay by the Owner, the Consultant or anyone employed or engaged by them contrary to the provisions of the Contract Documents, a qualifier that excludes owner conduct which is merely attributable to the Owner without breaching anything. GC 6.5.3.4, "any cause beyond the Contractor's control", is expressly time-only unless the delay in fact results from Owner or Consultant action.
The consequence is that the CCDC sweep-up is narrower than the JCT and FIDIC equivalents, which leaves more room for an owner act to fall outside the machinery altogether, the classic Peak v McKinney gap, and the space in which a time-at-large argument lives. Read the supplementary conditions before running any of this: they almost universally amend GC 6.5, and the amended clause is the one that governs.
Then the two things BC has never decided, both searched. NEGATIVE FINDING There is no BC citation of Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd, [2007] EWHC 447 (TCC)7, of Adyard Abu Dhabi v SD Marine Services, [2011] EWHC 848 (Comm)8, or of North Midland Building Ltd v Cyden Homes Ltd, [2018] EWCA Civ 17449. So expect the owner to argue the Multiplex proposition, that a functioning extension clause defeats prevention and note in reply that no BC authority adopts it. Expect Adyard-style insistence on actual rather than theoretical prevention, and note the same. And on new BC projects drafted with a North Midland-style allocation of concurrent-delay risk to the contractor, note that BC has never considered whether such a clause is effective. On the corpus's assessment that is the largest open question in BC delay law as at 8 September 2026.
No damage for delay, and relief from forfeiture, two untested interfaces
Two doors an owner will try to close, and BC law on both is older than the tests that now govern them. Hawl-Mac is reported as a case in which a no-damage-for-delay clause was not enforced and the contractor recovered out-of-pocket expenses despite wording barring "delay-related losses arising from whatever cause", a proposition this corpus marks UNVERIFIED, because it rests on secondary description of a judgment nobody has read. The reported reasoning is a construction one: such clauses will not be enforced where they do not clearly prohibit the specific claim type.
NEGATIVE FINDING No BC decision construes a no-damage-for-delay clause after Tercon Contractors Ltd v British Columbia, 2010 SCC 410. BC's position is therefore a pre-Tercon, construction-based line Hawl-Mac and Litchfield Bulldozing Ltd v PCL Construction Ltd, (1985), 14 CLR 28711 and any account of how a BC court would apply the three-stage Tercon framework to such a clause is prediction, not authority. Say so in the submission rather than presenting a predicted outcome as settled law. It is worth adding that no Canadian jurisdiction prohibits such clauses by statute, so the whole question is one of construction and unconscionability rather than legislative override.
The second door is the time bar, and here the finding is flatter still. NEGATIVE FINDING No BC decision applies Law and Equity Act, RSBC 1996, c 253, s 2412 relief from forfeiture to a construction notice provision or time bar. The visible s 24 jurisprudence is insurance and residential tenancy. The argument is open and untested, which is neither a recommendation nor a warning off, but a statement of what a court would be being asked to do for the first time. Expect the counter-argument that a contractual notice period is a condition of entitlement rather than a forfeiture, and that s 24 therefore has nothing to operate on.
Where the doctrine now lives, and how to run it from 1966, 1985 and 1997
In arbitration, and that is why the case law stopped. CIMIC Morningstar Investments Ltd v Chandos Construction Ltd, 2026 BCCA 213 is a leave refusal, and must never be cited as an appellate statement of doctrine. What the corpus records, and no more, is this: the underlying arbitral award involved a finding that the owner's design changes and late approvals put time at large so that liquidated damages could not be enforced, the award was approximately CAD 6.47M. The owner argued the doctrine does not apply to CCDC 2. And leave to appeal was refused under Arbitration Act, SBC 2020, c 2, s 5914. The Court of Appeal held only that the arbitrator's application was not an extricable question of law. It said nothing about whether prevention or time at large is correct in law under CCDC 2. A BC-seated arbitral finding of time at large, left undisturbed, that is the accurate description, and the section number should be re-checked against the consolidated Act, because this corpus obtained the Arbitration Act text from the Bill 7 (2020) third-reading version.
Nor is there another forum in which this doctrine could be developing. There is no adjudication in British Columbia today, because the Construction Prompt Payment Act received Royal Assent on 27 November 2025 and is not in force as at 8 September 2026, and when it is proclaimed it will apply only to contracts entered into after commencement, so essentially every BC contract live today will never be subject to BC adjudication. Even then, the register records as unresolved whether a BC adjudicator could grant time: delay will be adjudicable in substance through the change-order and valuation heads: which expressly reach approved and proposed change orders, and so are wider than Ontario's, but declaratory time relief is uncertain. See arbitration, experts and forum in BC.
Which leaves the position to state plainly to any client, and to any practitioner arriving from Ontario, Alberta, England or the United States. A British Columbia prevention argument today is built from 1966, 1985 and 1997, one appellate decision affirmed by the Supreme Court of Canada sixty years ago, one first-instance judgment reported only in the Construction Law Reports, and one Court of Appeal decision now nearly thirty years old, supplemented by N.B.C. Mechanical from 1999. The province that gave Canada its prevention doctrine has added almost nothing to it since.
That silence is a searched finding, not a gap in the research. NEGATIVE FINDING No BC judgment between 2015 and 2026 is squarely a large-project extension-of-time or delay decision, and the only appellate delay activity in the window is the CIMIC leave refusal. The causes are traceable: arbitration capture, time at large "has featured prominently in private arbitrations", and BC's most significant finding of it in forty years sits in a confidential award, the near-unreviewability of an arbitrator's reading of a delay clause under s 59, a construction docket reaching judgment that is dominated by residential and lien practice, and BC firms now writing about Ontario cases, with national concurrency surveys of 2021 and 2025 citing no BC case at all. The doctrine is still being made in British Columbia. It is simply not being reported.
Sources and authorities
- 1Hawl-Mac Construction Ltd v Campbell River (District)(1985), 10 CLR 177, 1985 CanLII 342 (BCSC)
The strongest candidate for a Canadian judgment finding time at large. The owner or engineer must determine a new completion date within a reasonable time of the request; failure to do so before the original completion date had passed meant the owner could not rely on that date and liquidated damages could not be enforced. One BC source reports the contract as imposing a seven-day period on the engineer; other accessible accounts describe only a reasonable-time or "prompt" duty, so the day count is SINGLE-SOURCE and must not be pleaded as established. A no-damage-for-delay clause was also not enforced, the contractor recovering out-of-pocket expenses.
- 2Perini Pacific Ltd v Greater Vancouver Sewerage & Drainage District(1966), 57 DLR (2d) 307 (BCCA); SCC appeal [1967] SCR 189, 60 DLR (2d) 385, 1967 CanLII 104
The Canadian statement of the prevention principle. A building owner is not allowed to insist upon the penalty for delay if, by ordering extra, he has prevented the builder from completing the work by a specified time.
- 3N.B.C. Mechanical Inc v A H Lundberg Equipment Ltd1999 BCCA 775
The owner's liquidated damages counterclaim failed because the owner's own requests for extras caused a significant part of the delay, so the contractor was prevented from completing by the stipulated date. The trial judge held that whether the contractor could have completed on time but for the owner's delays was irrelevant; the Court of Appeal declined to interfere, treating attribution of responsibility for delay as an assessment of the whole of the evidence and the contractor's own incomplete progress as "only one factor to be considered".
- 4Kei-Ron Holdings Ltd v Coquihala Motor Inn Ltd[1996] BCJ No 1237 (BCSC)
A general application of the principle in Boon v R, [1934] 3 DLR 161 (SCC), that no party can take advantage of the non-fulfilment of a condition the performance of which has been hindered by himself.
- 5Foundation Co of Canada Ltd v United Grain Growers Ltd(1997), 91 BCAC 254, (1997), 33 CLR (2d) 159 (BCCA)
An extension of time is permissive rather than mandatory, and a contractor is not obliged to seek an extension of time in order to claim delay damages. Delay was apportioned by the trial judge, owner and engineer 75% and contractor 25%, with the owner's and engineer's appeals against that allocation dismissed, and the owner's own delay counterclaim was barred because it had deliberately withheld notice of that claim until a strategically advantageous moment.
- 6CCDC 2 – 2020 Stipulated Price ContractGC 6.5.1, GC 6.5.3.4
GC 6.5.1 covers delay by the Owner, the Consultant or anyone employed or engaged by them, but only where that delay is contrary to the provisions of the Contract Documents. GC 6.5.3.4, "any cause beyond the Contractor's control", is expressly time-only unless the delay in fact results from Owner or Consultant action, in which case it converts to a compensable claim.
- 7Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd[2007] EWHC 447 (TCC)
The English position that prevention does not set time at large where the contract provides for an extension of time in respect of the relevant events.
- 8Adyard Abu Dhabi v SD Marine Services[2011] EWHC 848 (Comm)
The English requirement of actual prevention, rather than a theoretical possibility of prevention.
- 9North Midland Building Ltd v Cyden Homes Ltd[2018] EWCA Civ 1744
The English authority on a contractual allocation of concurrent-delay risk to the contractor.
- 10Tercon Contractors Ltd v British Columbia2010 SCC 4
The three-stage framework governing any exclusion clause, including a no-damage-for-delay clause.
- 11Litchfield Bulldozing Ltd v PCL Construction Ltd(1985), 14 CLR 287
Part of the pre-Tercon British Columbia line on no-damage-for-delay clauses.
- 12Law and Equity ActRSBC 1996, c 253, s 24
The general relief-from-forfeiture power. No BC decision applying it to a construction notice provision or time bar was located.
- 13CIMIC Morningstar Investments Ltd v Chandos Construction Ltd2026 BCCA 2
Leave to appeal an arbitral award was refused. The arbitrator had read a ten-day written notice requirement in context, found the owner had actual knowledge, found the owner's design changes and late approvals materially contributed to the delay, applied the prevention principle to hold that time was at large so that liquidated damages could not be enforced, and awarded approximately CAD 6.47M. The owner had argued that the doctrine does not apply to CCDC 2.
- 14Arbitration ActSBC 2020, c 2, s 59
Appeals from an arbitral award lie only on a question of law with leave, the route by which leave was refused in CIMIC.
General information, not legal advice. Reviewed Sep 8, 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.