Skip to main content

Privacy

A note about cookies

Essential cookies keep this site running. Optional analytics help us understand what's working, only enabled if you accept.

LIBRARY
OntarioExtension of timeJurisdiction article

Prompt payment and adjudication in Ontario

Since 1 January 2026 Ontario is the only Canadian jurisdiction where an extension of time can be adjudicated. And only as an ancillary head, only where reasonably necessary to a money determination, not on P3 projects, and not on contracts signed before that date. In August 2026 that excludes almost every mature Ontario delay claim.

Reviewed Sep 10, 202625 min read26 sources
Same topic inONBCAB

At a glance

Ontario
Class
Statutory interim dispute resolution
Jurisdiction
Ontario, Canada, common law
Scope
Construction Act Parts I.1 and II.1
§ 00

Key facts

  1. 01

    The short answer

    An extension of time became adjudicable in Ontario on 1 January 2026 and is adjudicable nowhere else in Canada. It is an ancillary head only, available where resolving it is "reasonably necessary" to a subsequent determination, and it is not available on public-private-partnership projects.

  2. 02

    Check the contract date first

    Ontario runs three date-keyed regimes: pre-1 July 2018 (former Construction Lien Act, no adjudication at all), 1 July 2018 to 31 December 2025 (adjudication, but time not adjudicable), and on or after 1 January 2026 (the full reform). In August 2026 nearly every project with a mature delay claim sits in the middle row.

  3. 03

    The three new heads

    O. Reg. 264/25 s 19 one firm says s 19.1, a minor conflict, adds the scope of work, a request for a change in the contract price, and "a request for an extension of time to complete the work prescribed by the contract".

  4. 04

    The window that decides the forum

    90 days after the contract is completed, abandoned or terminated (s 13.5(3)), a separate earliest-of trigger for subcontracts (s 13.5(3.1)), extendable by agreement. Delay claims crystallise at completion, so this is the new date to diarise.

  5. 05

    The clocks after referral

    Determination in 30 days only 61% met it in FY2025, a 5-day slip rule (s 13.17.1), payment in 15 days (s 13.19(2)), and leave to seek judicial review in 35 days (s 13.18(2)). The 30 and 10 still in wide circulation are the pre-2026 figures.

  6. 06

    Get the two sections the right way round

    s 13.18 is judicial review, with leave of the Divisional Court and a closed list of grounds at 13.18(5). s 13.19 is "Amounts payable". The inversion is a common and corpus-flagged error.

  7. 07

    The case law is one case deep

    Ledore Investments v Dixin Construction is a procedural fairness case whose underlying dispute was a delay set-off. In Sayers Foods v Gay Company the Divisional Court held that complexity does not oust an adjudicator's jurisdiction to decide a dispute "if it is necessary to do so to rule on a matter properly the subject of an adjudication" (para 80).

  8. 08

    The money leverage is gone

    s 27.1 is repealed, annual holdback release is mandatory, and an invoice is deemed proper unless the owner objects within 7 days. An owner holding money against a delay claim now needs an express contractual set-off mechanism and must prove it in 30 days.

Since 1 January 2026 an extension of time is adjudicable in Ontario, and nowhere else in Canada. O. Reg. 264/25 s 19 makes "a request for an extension of time to complete the work" an adjudicable matter where resolving it is reasonably necessary to a subsequent determination. But not on P3 projects, and not on contracts predating 1 January 2026.

That second qualification is the one that decides whether the first matters to you. In August 2026 nearly every Ontario project carrying a mature delay claim sits on a contract signed between 1 July 2018 and 31 December 2025, inside the middle of Ontario's three date-keyed regimes, where adjudication exists but time is not on the list of things that can be adjudicated. The reform is prospective, and on real delay claims it will not bite for another one to three years. So the regime table comes first, before any of the machinery.

One evidential warning governs everything below. No Ontario statutory text was read from the consolidated statute and no Ontario judgment was read in original form for this article. CanLII, the Supreme Court portal, ontariocourts.ca and Ontario e-Laws were all inaccessible to the research behind it. Statutory content comes from enacting bill texts and firm bulletins, case content rests on firm bulletins. Every section number and every neutral citation here should be checked against the consolidated statute or the judgment before it is pleaded, and the two places where the sources positively conflict are marked in the text.

For the wider Ontario picture see the Ontario extension-of-time hub, for the pan-Canadian backdrop, the Canadian extension-of-time hub.

§ 01

Which of Ontario's three regimes is your contract on?

Ontario runs three delay-and-payment regimes simultaneously, keyed to the contract date, and the answer changes whether adjudication exists at all and whether time can be referred to it. Ask this before the merits. A contract signed on 20 December 2025 and a contract signed on 20 January 2026 are on different statutes for these purposes, and nothing about the project distinguishes them.

Contract or procurement dateGoverning regime
Before 1 July 2018Former Construction Lien Act. No prompt payment, no adjudication, old holdback and lien rules
1 July 2018 – 31 December 2025Construction Act with Part I.1 prompt payment and Part II.1 adjudication, the pre-2026 closed list of adjudicable matters (time is NOT adjudicable) and the owner's s 27.1 notice of non-payment of holdback still available
On or after 1 January 2026The full 2026 regime: s 13.5 open scope, EOT adjudicable on non-P3 work, 90-day post-completion window, mandatory annual holdback release, s 27.1 repealed, 7-day notice of termination

Layer, jurisdictional, and the authority is statute rather than case law. The rows rest on secondary sources: no consolidated Ontario statutory text was read for this corpus, so treat the section references as directional and check the transition provision itself.

The transition machinery is section 87.4 of the Construction Act1, introduced by Bill 216, the Building Ontario For You Act (Budget Measures), 2024, Schedule 42 and subsequently amended by Bill 60, the Fighting Delays, Building Faster Act, 2025, Schedule 23 specifically for project agreements. Section 88 confers Ministerial transitional regulation-making power, which means the boundary can move by regulation without a further bill. Bill 216 was the substantive overhaul, it followed Duncan Glaholt's 2024 independent review and rewrote or introduced more than thirty provisions, including ss 13.5, 13.12.1, 13.17.1, 13.18, 13.19, 26 to 27.1 and 87.4, but its commencement was by proclamation, so Bill 216 by itself commenced nothing. Bill 60 was corrective: it re-wrote s 26, replaced s 31(6) to (8) with the 7-day notice of termination, added a definition of "Minister", and touched ss 13.2, 13.4, 87.4 and 88. Bill 60 does not affect any of the adjudication amendments.

Two things about Bill 216 are commonly misreported. First, its original proposal to re-tie lien expiry to the annual holdback release notice did not survive. Lien preservation, perfection and expiry timing are unchanged at 60 and 90 days, and 2024–25 commentary describing a new Ontario lien regime is describing a dropped proposal. Second, the operative instruments are the four regulations that came into force on 1 January 2026, O. Reg. 264/25 Adjudications Under Part II.1, 265/25 Procedures for Actions Under Part VIII, 266/25 General and 267/25 Forms not the bill. O. Regs 302/18 and 304/18 were also amended. The reported filing date of 27 November 2025 is unverified.

Transitional jurisdiction is already being litigated. In Caledon (Town) v 2220742 Ont. Ltd. o/a Bronte Construction4 2024 ONSC 4555 the Divisional Court considered jurisdiction under the transitional provisions and upheld it. That is the practical warning: the date question is not a formality that the other side will concede, and it is litigable in its own right. The deadline architecture that follows from the answer is set out in the Ontario delay claim clocks.

§ 02

What actually became adjudicable on 1 January 2026

Three matters were added to the adjudicable list on 1 January 2026, and time is one of them. O. Reg. 264/25, Adjudications Under Part II.15 s 19 prescribes the scope of work to be performed under a contract, a request for a change in the contract price. And (the headline) "a request for an extension of time to complete the work prescribed by the contract". Each is adjudicable only where resolving it is "reasonably necessary" to make a subsequent determination.

Two qualifications on the citation itself. The section number carries a [CONFLICT, minor]: one firm refers to s 19.1 while ODACC, the Ontario Association of Architects and Cassels refer to s 19, and the corpus behind this article prefers s 19. And the whole content of the regulation rests on firm bulletins, the regulation itself was not read.

The enabling change on the statutory side is that section 13.5 of the Construction Act6 no longer contains a list at all. As amended it reads: "Subject to subsection (3), a party to a contract may refer a dispute with the other party to the contract respecting any prescribed matter or any matter agreed to by the parties to adjudication." Scope now lives in the regulation, which is why the regulation, not the Act, is where an Ontario practitioner looks to see whether a delay dispute is referable.

Three conditions decide cases, and they are worth separating.

"Reasonably necessary" is a jurisdictional gate, not a preamble. A pure extension-of-time referral is still not available in Ontario. EOT is an ancillary head, so the referral has to be drafted with the time question instrumental to a money determination, the value of a disputed change, the amount payable under a disputed invoice, the amount wrongly withheld. Or it will be attacked as outside the prescribed matters. Attacked, and possibly successfully: the third ground in the closed judicial review list is that the determination was of a matter that may not be the subject of adjudication.

The objection has to be taken in the adjudication. Under section 13.12.17 a party may object that the adjudicator lacks jurisdiction, or has exceeded it, with the timing tied to when that party first makes submissions or as soon as the matter is raised. A jurisdictional objection not raised before the adjudicator cannot ground judicial review unless the failure was justified. Object now or lose it, and note the mirror-image consequence for a referring party, which is that a respondent who says nothing at first submissions has largely conceded the gate.

And the largest projects get nothing. The three new heads are not available for adjudication on public-private-partnership projects, reported at s 19(1)6, but UNVERIFIED on the mechanism: the exact provision effecting the P3 / special-purpose-entity exclusion could not be read for this corpus, and one firm notes that certain P3 exemptions depend on the project agreement falling within types prescribed by regulation, with no such prescribing regulation issued as at the date of that bulletin. A related but distinct carve-out sits in the transition provision: project agreements entered with a special purpose entity under an AFP or P3 arrangement before 1 January 2026 are exempt from mandatory annual holdback release.

The very largest Ontario projects. The ones where extension-of-time claims are worth eight figures, are the ones where the new EOT-adjudication head does not apply. The first question in an Ontario delay file is therefore not "when did the delay start" but "is this an IO or AFP project agreement with a special purpose entity".

If the answer is yes, the reform gives you nothing on time and you are back inside the Infrastructure Ontario Project Agreement8 architecture, where a Delay Event gives time only, a Compensation Event gives time and money, and a Relief Event gives neither, only relief from performance and from default remedies. There is no CCDC analogue to a Relief Event, and an EOT claim on an IO project is won or lost at the classification step rather than in the delay analysis. The notice periods in those articles are project-specific, sit partly in the Articles and partly in the Schedules, and were not surfaced for this corpus, read the specific project agreement and never assume a period from CCDC or from another IO job.

One negative belongs here rather than in a footnote, because practitioners arriving from another province look for an equivalent and there is none. No Canadian equivalent of Ontario's O. Reg. 264/25 s 19 ancillary EOT head exists anywhere else. In Saskatchewan, Manitoba, the federal regime and Quebec, a delay or EOT question reaches an adjudicator only by being embedded in a change-order valuation or a payment dispute, or by consent. The Northwest Territories has prompt payment and no adjudication mechanism at all.

Alberta has to be split in two, and the second half is the one Ontario practitioners get wrong. Under the Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 and the Public Works Act, RSA 2000, c P-469, Alberta runs two regimes. On private and municipal work the PPCLA has the widest consent catch-all in Canada, "any other matter in relation to the contract or subcontract that the parties to the dispute agree to, regardless of whether or not a proper invoice was issued" allows referral up to 30 days after final payment under s 33.4, permits adjudication to run concurrently with litigation, both since 1 April 2025 under Bill 30 (2024), and imposes no cap. On provincial Crown public works none of that is available: PPCLA s 1.1 excludes public works as defined in the Public Works Act, and agreements with the provincial Crown or a Crown agent, from the PPCLA entirely, and Public Works Act s 14.3(2), also Bill 30 (2024), contracts from 1 April 2025: makes delay not adjudicable at all, excluding schedule changes, completion and milestone dates, relief events, designated changes in law, remedial actions and force majeure by name. A cap applies to Public Works Act adjudication only, and its figure is CONFLICT between $200,000 and the $100,000 Alberta Court of Justice civil limit in force since 1 August 2023. Describing Alberta simply as a consent-only jurisdiction is now wrong in both directions.

§ 03

How an Ontario EOT adjudication actually runs

An Ontario adjudication is fast, front-loaded and unforgiving on dates. The notice of adjudication must be given within 90 days of completion, abandonment or termination, a jurisdictional objection must be taken at first submissions, the adjudicator has 30 days to determine. The losing party has 15 days to pay, and an applicant for judicial review has 35 days to move for leave. Every one of those except the objection is a hard date.

The window is the change that matters most to a delay practice. Section 13.5(3) of the Construction Act makes adjudication of a contract dispute unavailable where the notice of adjudication is given more than 90 days after the date on which the contract is completed, abandoned or terminated. For a subcontract, s 13.5(3.1) runs the 90 days from the earliest of contract completion, abandonment or termination, certification or declaration of subcontract completion, and the date the subcontractor last supplied services or materials which for a subcontractor pushed off site early can be a long way before anyone considers the project finished. The parties may agree to extend either period.

That is a genuine reversal. Delay and EOT disputes almost always crystallise at or after completion, which is precisely the point at which adjudication used to become unavailable. The gate is now open for 90 days after completion, and then it shuts hard. Note also the 30-day tail against the lien clock: lien preservation is 60 days and the adjudication window is 90, so a contractor whose lien has already expired can still commence an adjudication for another 30 days. The two are independent starting an adjudication does not preserve a lien, and a determination lacks the property security a lien carries. Preserve on the 60-day clock and adjudicate in parallel or in the tail. The interaction is worked through in liens, holdback and security in Ontario.

A further new provision, s 13.5(3.2), enables regulations permitting cross-contract or multi-party adjudication between parties to different contracts on the same improvement. A delay chain, owner to general contractor to subcontractor, is the paradigm case for that power, and it is the enabling hook to watch.

One open point is worth flagging because it is available as an argument in either direction. Whether a contractual limitation clause valid under section 22 of the Limitations Act, 200210 and Ontario is the only Canadian jurisdiction where a commercial party may lawfully shorten or exclude a limitation period, can cut down or extend the 90-day adjudication window is undecided. Logically s 13.5(3) is a statutory precondition to a statutory remedy rather than a limitation period, which would put it outside s 22, but the express power to extend the window by agreement invites the contrary argument. The distinction is developed in the Ontario limitation periods note.

Once the referral is in, the clocks run as follows.

StepPeriodProvision and note
Notice of adjudication, contract90 days after completion, abandonment or terminations 13.5(3), extendable by agreement
Notice of adjudication, subcontract90 days from the earliest of the three triggerss 13.5(3.1)
Objection to jurisdictionAt first submissions, or as soon as the matter is raiseds 13.12.1, object now or lose it
Determination30 daysOnly 61% (87 of 143) met it in FY2025
Correction of a slip5 dayss 13.17.1, typographical, calculation or similar errors, or an oversight, without a hearing
Payment of the determined amount15 days from communications 13.19(2), amended up from 10 by 2024, c. 20, Sched. 4, s. 23 (1)
Motion for leave to seek judicial review35 days from communications 13.18(2), amended up from 30 by 2024, c. 20, Sched. 4, s. 22 (1). Diarise 30 as prudence, a missed leave deadline is fatal

Layer, jurisdictional, and the authority is statute. The two day counts in the last two rows were read on 10 September 2026 in the consolidated Construction Act on Ontario e-Laws; the 61% figure is from the ODACC annual report and not from the statute.

Get the two section numbers the right way round, because the inversion is common and it is a corpus-flagged error. Section 13.1811 is Setting aside on judicial review: "An application for judicial review of a determination of an adjudicator may only be made with leave of the Divisional Court", the leave motion filed no later than 35 days after the determination is communicated (s 13.18(2)), on a closed list of six operative grounds at s 13.18(5), numbered 1 and 3 to 7: legal incapacity, the determination being of a matter that may not be the subject of adjudication or entirely unrelated to the subject of the adjudication, the adjudication having been conducted by someone other than the appointed adjudicator, the procedures not according with those prescribed and the failure having prejudiced the applicant's right to a fair adjudication, a reasonable apprehension of bias, and fraud. Paragraph 2, the ground that the contract was invalid or had ceased to exist, was repealed by 2024, c. 20, Sched. 4, s. 22 (2), so an owner can no longer attack a determination on that footing. A motion for leave "may be dismissed without reasons". Section 13.1912 is Amounts payable, payment no later than 15 days after communication (s 13.19(2)), subject to any Part IV holdback requirement, with interest at the prejudgment rate or the higher contract rate. 13.18 is judicial review, 13.19 is amounts payable.

Both day counts are settled, and they are not the numbers most sources still print. s 13.18(2) gives 35 days from communication of the determination to file a motion for leave, and s 13.19(2) gives 15 days to pay. Both were amended up from 30 and 10 by 2024, c. 20, Sched. 4, ss 22 (1) and 23 (1), and both carry that amendment credit on the consolidated text, which was read for this page on 10 September 2026. The 30 and 10 still in circulation are the pre-2026 figures, so check the date of anything that gives them. Diarise 30 and 10 anyway, as prudence rather than as doubt: the five days gained are worth nothing, the five days lost are unrecoverable, and the date on which a determination was communicated can itself be argued about.

What the FY2025 data says about the pace is worth having in front of you when deciding whether to refer a delay question at all.

324Adjudications commenced in FY2025, up from 269 in FY2023
61%Of determinations meeting the 30-day statutory deadline, 87 of 143
$634,561Average amount claimed, median $212,812
13%Of the amount claimed that was determined payable across the year

Those figures are from the ODACC 2025 Annual Report13 for the fiscal year 1 August 2024 to 31 July 2025: 324 adjudications commenced, 143 determinations and 116 matters terminated before determination, $205,597,884.82 claimed in total against $26,610,365.85 determined payable. Two operational points follow. The 30-day determination period is aspirational in practice, nearly four determinations in ten were late in FY2025. So a party planning a cash-flow sequence around it should build slack. And the amounts are mid-market: the average claim has risen from $90,828 in 2020 to $277,168 in 2022 to $634,561 in FY2025, and the transportation and infrastructure sector accounted for 36 adjudications and $8.26 million with the highest median at $149,449. Private adjudicators are now permitted alongside the ODACC roster, which may change the throughput picture from FY2026.

And there is no delay dataset, in Ontario or anywhere in Canada. ODACC does not track delay, extension-of-time or change-order disputes as a category, change orders are folded into "payment under a contract", which accounted for 72 of the FY2025 determinations. There is no line item for time at all. No Ontario dataset on adjudicated delay claims exists, and none can until the FY2026 report, which will be the first period in which an extension of time was adjudicable.

§ 04

The review case law. And it is the whole Canadian body

Ontario's judicial review jurisprudence on adjudication is the entire Canadian body of law on the subject. No reported judicial review of an adjudicator's determination exists in Alberta, Saskatchewan, Manitoba or federally, Alberta prescribes a 30-day window and no decided case has surfaced. Two Ontario decisions carry the delay content, and one of them is the only adjudicated-EOT authority in the country.

Ledore Investments Ltd v Dixin Construction Ltd14 2024 ONSC 598 is the first successful judicial review of a determination in Canada. It is a procedural fairness case, not a jurisdictional-error case, and it is regularly miscited as the latter. The adjudicator decided the matter on a dispositive issue that neither party had raised, judicial review was granted for breach of procedural fairness and the matter remitted. The underlying dispute was a delay set-off, steel supplied roughly five months late, termination, and payment refused. It is the limit on adjudication's rough justice: speed does not licence deciding a case on a ground the parties never argued.

Sayers Foods Ltd v Gay Company Ltd15 2026 ONSC 918 is the first Ontario delay adjudication to survive judicial review, and the sentence an owner needs to hear is at para 80: "Complexity of a dispute does not oust an Adjudicator's jurisdiction to decide that dispute if it is necessary to do so to rule on a 'matter' properly the subject of an adjudication." A family grocery store had engaged the contractor under a CCDC 2 contract to rebuild after a fire, said the contractor missed a March 2023 completion date, claimed roughly $900,000 in delay damages and later asserted a delay credit exceeding $1.2 million as a set-off against payment. The contractor commenced two adjudications totalling about $851,000. On review the Divisional Court held that the adjudicator may decide all issues necessary to resolve the single matter before them, including complex delay arguments, that the owner's set-off failed on the contract rather than on jurisdiction, because the contract contained no binding completion date, no delay-damages mechanism and no contractual set-off right, so the delay claim could not defeat the payment entitlement. And that the standard of review is reasonableness for the adjudicator's factual and contractual findings, correctness for procedural fairness (para 9), with judicial review "not a re-hearing de novo before this court on the record below, but rather a review of the decision in light of the record below" (para 33). Jurisdictional error, procedural unfairness, irreparable harm, fraud and reasonable apprehension of bias were all argued and all rejected. Sayers Foods displaces Pasqualino (2022) on the complexity point. Both decisions were read in original text on CanLII on 10 September 2026, and both are Divisional Court: Sayers Foods, 2026 ONSC 918 (court file 238/24 JR), and Pasqualino, 2022 ONSC 5632 (court file DC-22-00000004-00, also reported at 35 CLR (5th) 453).

The rest of the line supplies the procedural architecture rather than delay content.

CaseCitationWhat it decides
SOTA Dental Studio Inc v Andrid Group Ltd162022 ONSC 2254 (Div Ct)Pay or get a stay. An applicant who neither paid the determination nor obtained a stay had its application dismissed without the court reaching the merits
Pasqualino v MGW-Homes Design Inc172022 ONSC 5632 (Div Ct), 35 CLR (5th) 453. Read in original text, 10 September 2026Jurisdictional arguments must be raised during the adjudication, adjudication is available beyond the active construction phase
Okkin Construction Inc v Apostolopoulos182022 ONSC 6367The Superior Court has no jurisdiction over adjudication disputes. The only recourse is Divisional Court judicial review
Anatolia Tile & Stone Inc v Flow-Rite Inc192023 ONSC 1291 (Div Ct)The leave test, good reason to doubt reasonableness or procedural unfairness probably affecting the outcome, and either irreparable harm or an issue of transcendent importance
Arad Incorporated v Rejali et al202023 ONSC 3949 (Ont SCJ, not Div Ct)A determination alone will not reduce or return lien security. "there has to be something more". The determination is interim, not final
Blackstone Paving and Construction Ltd v Barrie (City of)212024 ONSC 4556 (Div Ct)Notice-of-non-payment compliance and procedural fairness, dismissed

Layer, jurisdictional. Every decision listed is first instance or Divisional Court, there is no appellate authority on Ontario adjudication in this material. No Canadian judgment was read in original form for this corpus and the holdings rest on secondary sources.

Stacked together, those cases make review far narrower than "correctness on jurisdiction, reasonableness on the merits" suggests. An applicant faces, in order: the closed s 13.18(5) list, then leave, on the Anatolia two-part test and the SOTA precondition of payment or a stay, then the standard, reasonableness for factual and contractual findings and fairness for process, with fairness itself running through the conjunctive s 13.18(5)5 test that requires both a procedural failure and prejudice. And finally the near-total displacement of jurisdiction as a ground by s 13.12.1. An owner that loses a delay set-off in an adjudication has almost no route back, notwithstanding that the determination is legally interim (Arad).

Ontario's adjudicated-EOT case law is, as at August 2026, one case deep. Before Sayers Foods no Ontario judicial review had addressed delay or extension of time at all, and the reason is structural rather than accidental: pre-2026 s 13.5(1) contained a closed list that did not include time, so a delay dispute could only reach an adjudicator dressed as something else.

One collateral risk belongs with the forum question. A delay claim tried inside a lien action rather than an ordinary action carries appeal-route risk that the ordinary action does not, on the s 110 Courts of Justice Act uncertainty left by Castle Homes Design Inc v McKenzie22 2026 ONCA 98. That is a reason to think about the procedural vehicle at the outset rather than after a determination has been handed down.

§ 05

How prompt payment changed the leverage on a delay claim

The 2026 package systematically removed the money an Ontario owner used to hold against a delay claim. An invoice is now deemed proper unless the owner objects within 7 days, the 28-day payment clock runs from the proper invoice, annual holdback release is mandatory. And s 27.1. The owner's notice of non-payment of holdback is repealed. An owner that wants to withhold against delay now needs an express contractual mechanism and must prove it, fast.

Take the deeming rule first. Section 6.1 of the Construction Act23 deems an invoice to be a proper invoice unless the owner gives written notice of the deficiency within 7 days of receipt. Because the 28-day prompt-payment clock runs from the proper invoice, the deeming rule converts owner silence into a running clock: an owner that says nothing for a week has started a 28-day obligation it may not have intended to start. For a contractor with a live delay claim that is a scheduling tool it forces the owner to articulate its objection in writing, early, and in terms it will have to live with.

Then the holdback. Sections 26 to 27.124 now require the owner, on a contract running more than one year, to publish a Notice of Annual Release of Holdback in Form 6 within 14 days of each contract anniversary, and to pay the released holdback not less than 60 and not later than 74 days after publication a fixed 14-day payment window that opens on day 60. There is a 14-day cascade to subcontractors on receipt. And the owner's escape hatch is gone: s 27.1, the notice of non-payment of holdback, is repealed, so the statutory power to refuse release for incomplete or deficient work no longer exists.

For an owner that historically ran delay damages as a set-off against holdback, the practical consequence is precise. Holdback used to be the money that sat there while the parties argued about whether the contractor was late. The owner could decline to release it by giving a statutory notice, and the burden of doing something about that fell on the contractor. Now the release is mandatory and calendar-driven, the contractor's invoices are self-proving after seven days, and if the owner wants to keep the money it must rely on a contractual delay-damages and set-off mechanism which, on Sayers Foods, it will have to substantiate inside a 30-day adjudication rather than by simply holding the cash and waiting.

None of this touches the contractual notice clock, and that is the trap for a contractor who reads the reform as a general loosening. CCDC 2 – 2020 GC 6.5.425 still requires Notice in Writing of the cause of delay to the Consultant not later than 10 Working Days after the commencement of the delay, not of its effect, with one notice sufficing for a continuing cause, and Ontario courts treat that as a condition precedent without requiring the owner to prove prejudice. A statutory adjudication does not revive an entitlement that a missed contractual notice has already extinguished. The condition-precedent question across the standard forms generally is set out in the neutral treatment of notice and time bars.

§ 06

The open question on every IO and AFP project, can an arbitration clause oust adjudication?

Whether an arbitration clause ousts statutory adjudication has not been decided in Ontario. The scheme strongly implies that it cannot be contracted out of, a party "may refer" a dispute to adjudication, and section 4 of the Construction Act26 bars waiver of the Act's provisions, but no Ontario court has said so. The question is expressly open, and it is not academic: IO and AFP project agreements all contain bespoke arbitration regimes.

The interaction with the P3 carve-out is what makes it live. On a P3 project entered before 1 January 2026 the position is straightforward in the sense that nothing helps the contract predates the reform and the new heads would not apply to it anyway. On a P3 project entered after that date the EOT head still does not apply, but adjudication of a payment dispute is not carved out. And it is there, on a payment dispute between a special purpose entity and its contractor under an agreement with a multi-tier arbitration clause, that the ouster question will eventually be argued.

There is a second reason it will take time to answer. Ontario's largest delay disputes generate no citable law. IO and Metrolinx project agreements resolve confidentially, and no public judgment or published award on Ontario Line delay exists. The disputes most likely to produce an answer on arbitration versus adjudication are the disputes least likely to be reported. Until one surfaces, a practitioner on an IO or AFP job should plan on the arbitration route, treat any adjudication as an argument to be made rather than a right to be exercised, and, on the classification question that actually decides these claims: go back to Articles 31, 32 and 33 of the project agreement.

Notes

Sources and authorities

26 cited
  1. *
    Verification, unless noted

    No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.

  2. 1
    Construction Act ss 87.4 and 88, transitionConstruction Act (Ontario), s 87.4 (new, Bill 216, Sch 4, amended by Bill 60, Sch 2) and s 88

    s 87.4 is the transition provision keying the 2026 regime to contract and procurement dates, amended by Bill 60 specifically for project agreements, s 88 confers Ministerial transitional regulation-making power. Project agreements entered with a special purpose entity under an AFP or P3 arrangement before 1 January 2026 are exempt from mandatory annual holdback release.

    Find on CanLII

  3. 2
    Bill 216, Building Ontario For You Act (Budget Measures), 2024, Schedule 4Bill 216 (Ontario), Sch 4, commencement by proclamation

    The substantive overhaul of the Construction Act, following Duncan Glaholt's 2024 independent review. It amended ss 1, 6, 6.1, 6.3, 7, 8, 10, 13.1, 13.3, 13.5, 13.7 to 13.10, 13.12, 13.14, 13.17, 13.18, 13.19, 14, 22, 26 to 27.1, 31, 34, 39, 50 and 88, and introduced ss 13.12.1, 13.17.1 and 87.4. Bill 216 by itself commenced nothing. The operative date came by proclamation with the four regulations. Its original proposal to re-tie lien expiry to the annual holdback release notice did not survive, lien preservation, perfection and expiry timing are unchanged.

    ola.org

  4. 3
    Bill 60, Fighting Delays, Building Faster Act, 2025, Schedule 2Bill 60 (Ontario), Sch 2, SO 2025, c 14

    A corrective bill. It re-wrote s 26, replaced s 31(6) to (8) with a requirement to publish notice of termination within 7 days, the publication date becoming the operative date for lien expiry, added a definition of "Minister", and amended ss 13.2, 13.4, 87.4 and 88. Bill 60 does not affect any of the adjudication amendments.

    ola.org

  5. 4
    Caledon (Town) v 2220742 Ont. Ltd. o/a Bronte Construction2024 ONSC 4555, Divisional Court of Ontario

    Jurisdiction under the transitional provisions was challenged and upheld. The transition machinery is already being litigated, which is what makes the contract-date question the first question in an Ontario adjudication file.

    Find on CanLII

  6. 5
    O. Reg. 264/25, Adjudications Under Part II.1O. Reg. 264/25 (Ontario), s 19, in force 1 January 2026

    Prescribes three matters in addition to the existing heads, adjudicable only where their resolution is reasonably necessary to make a subsequent determination: the scope of work to be performed under a contract, a request for a change in the contract price. And "a request for an extension of time to complete the work prescribed by the contract". The three new heads are reported as unavailable on public-private-partnership projects, the exclusion being keyed to a project agreement with a special purpose entity.

    Find on CanLII

  7. 6
    Construction Act s 13.5, matters that may be adjudicated, and the 90-day windowConstruction Act (Ontario), s 13.5, including ss 13.5(3), 13.5(3.1) and 13.5(3.2)

    As amended by Bill 216, Sch 4, s 13.5 no longer carries a closed list: "Subject to subsection (3), a party to a contract may refer a dispute with the other party to the contract respecting any prescribed matter or any matter agreed to by the parties to adjudication." s 13.5(3) bars adjudication of a contract dispute where the notice is given more than 90 days after the contract is completed, abandoned or terminated, s 13.5(3.1) supplies an earliest-of trigger for subcontracts, the parties may agree to extend. s 13.5(3.2) enables regulations permitting cross-contract adjudication between parties to different contracts on the same improvement.

    Find on CanLII

  8. 7
    Construction Act s 13.12.1, objection to jurisdictionConstruction Act (Ontario), s 13.12.1, introduced by Bill 216, Sch 4

    A party may object that the adjudicator lacks jurisdiction, or has exceeded it, with the timing tied to when the party first makes submissions or as soon as the matter is raised. A jurisdictional objection not taken before the adjudicator cannot ground judicial review unless the failure to take it was justified.

    Find on CanLII

  9. 8
    Infrastructure Ontario / AFP Project AgreementRedacted execution-version agreements published by Infrastructure Ontario. Article numbering varies by project

    An IO Project Agreement splits time and money three ways. A Delay Event, gives time only. An extension of the Scheduled Substantial Completion Date. A Compensation Event gives time and money. A Relief Event gives neither, only relief from performance and from default remedies. An express mitigation obligation appears in all three articles. The notice periods are project-specific, sit partly in the Articles and partly in the Schedules, and were not surfaced for this corpus, read the specific project agreement.

    Infrastructure Ontario

  10. 9
    Alberta's two adjudication regimes. PPCLA and the Public Works ActPrompt Payment and Construction Lien Act, RSA 2000, c P-26.4 (Alberta), ss 1.1 and 33.4, and the Prompt Payment and Adjudication Regulation, s 19. Public Works Act, RSA 2000, c P-46, s 14.3(2). Both as amended by Bill 30 (2024), the Service Alberta Statutes Amendment Act, 2024, in force 1 April 2025

    On private and municipal work the PPCLA carries the widest consent catch-all in Canada, allows referral up to thirty days after final payment under s 33.4, permits adjudication concurrently with litigation, and imposes no monetary cap. On provincial Crown public works none of that applies: PPCLA s 1.1 excludes public works as defined in the Public Works Act, and agreements with the provincial Crown or a Crown agent, from the PPCLA entirely, and Public Works Act s 14.3(2) excludes from adjudication changes or delays to a construction schedule, completion and milestone dates, and disputes over the interpretation of relief events, designated changes in law, remedial actions and force majeure events, so delay is not adjudicable at all on an Alberta provincial public work. A monetary cap applies to Public Works Act adjudication only, the corpus records a CONFLICT on the figure between $200,000 and the $100,000 Alberta Court of Justice civil limit in force since 1 August 2023.

    Find on CanLII

  11. 10
    Limitations Act, 2002 s 22, variation by business agreementLimitations Act, 2002 (Ontario), s 22(5) to (6)

    In a business agreement the parties may extend, shorten, suspend or exclude the statutory limitation periods. Ontario is the only Canadian jurisdiction permitting a commercial party to shorten or exclude a limitation period, Alberta, Saskatchewan and Manitoba permit extension only.

    Find on CanLII

  12. 11
    Construction Act s 13.18, setting aside on judicial reviewConstruction Act (Ontario), s 13.18, including s 13.18(5)

    "An application for judicial review of a determination of an adjudicator may only be made with leave of the Divisional Court." The leave motion must be filed no later than 35 days after the determination is communicated (s 13.18(2), as amended by 2024, c. 20, Sched. 4, s. 22 (1)), and "a motion for leave … may be dismissed without reasons". s 13.18(5) contains a closed list of six operative grounds, numbered 1 and 3 to 7: legal incapacity. The determination was of a matter that may not be the subject of adjudication or of a matter entirely unrelated to the subject of the adjudication, the adjudication was conducted by someone other than the appointed adjudicator, the procedures did not accord with those prescribed and the failure prejudiced the applicant's right to a fair adjudication, reasonable apprehension of bias, and fraud. Paragraph 2, the ground that the contract was invalid or had ceased to exist, was repealed by 2024, c. 20, Sched. 4, s. 22 (2).

    Find on CanLII

  13. 12
    Construction Act s 13.19, amounts payableConstruction Act (Ontario), s 13.19

    A party required under a determination to pay an amount "shall pay the amount no later than 15 days after the determination has been communicated to the parties to the adjudication" (s 13.19(2), as amended by 2024, c. 20, Sched. 4, s. 23 (1)), subject to any Part IV holdback requirement (s 13.19(1)), with interest from the due date at the prejudgment rate under s 127(2) of the Courts of Justice Act or the higher contractual rate (s 13.19(3)). s 13.19 is the amounts-payable section and is not the judicial review section.

    Find on CanLII

  14. 13
    ODACC 2025 Annual Report (Year 6)Ontario Dispute Adjudication for Construction Contracts, fiscal year 1 August 2024 to 31 July 2025

    324 adjudications commenced, 143 determinations and 116 matters terminated before determination. Total claimed $205,597,884.82, average $634,561.37, median $212,811.77. Total determined payable $26,610,365.85, average $186,086.47, median $73,658.18. Only 61% of determinations, 87 of 143, met the 30-day statutory deadline. Subject matter was recorded as payment under a contract including change orders (72), valuation of services or materials (47), notices of non-payment (9), non-payment of holdback (6), other agreed matters (6) and payment of holdback (3). By sector: residential 50, commercial 40, transportation and infrastructure 36, public buildings 14, industrial 3. The average claim has risen from $90,828 in 2020 to $277,168 in 2022 to $634,561 in FY2025. Delay, extension of time and change orders are not tracked as categories.

    ODACC

  15. 14
    Ledore Investments Ltd v Dixin Construction Ltd2024 ONSC 598, Divisional Court of Ontario

    The first successful judicial review of an adjudicator's determination in Canada, and a procedural fairness case rather than a jurisdictional-error case. The adjudicator decided the matter on a dispositive issue that neither party had raised. Judicial review granted for breach of procedural fairness, and the matter remitted. The underlying dispute was a delay set-off, steel supplied roughly five months late, termination, and payment refused.

    Find on CanLII

  16. 15
    Sayers Foods Ltd v Gay Company Ltd2026 ONSC 918 (Div Ct), Ontario, court file 238/24 JR

    "Complexity of a dispute does not oust an Adjudicator's jurisdiction to decide that dispute if it is necessary to do so to rule on a 'matter' properly the subject of an adjudication" (para 80). The adjudicator may decide the issues necessary to resolve the single matter before them, including complex delay arguments, and a party cannot force a dispute out of adjudication by pleading that its delay defence is too complicated for a 30-day process. The owner's delay set-off failed on the contract rather than on jurisdiction. There was no binding completion date, no delay-damages mechanism and no contractual set-off right, so it could not defeat the payment entitlement. Reasonableness applies to the adjudicator's factual and contractual findings, correctness to procedural fairness, and judicial review is not a re-hearing de novo.

    Find on CanLII

  17. 16
    SOTA Dental Studio Inc v Andrid Group Ltd2022 ONSC 2254, Divisional Court of Ontario

    Pay or get a stay. A judicial review applicant who had neither paid the determination nor obtained a stay had its application dismissed without the court reaching the merits.

    Find on CanLII

  18. 17
    Pasqualino v MGW-Homes Design Inc2022 ONSC 5632 (Div Ct), 35 CLR (5th) 453, Ontario

    Jurisdictional arguments must be raised during the adjudication, and adjudication is available beyond the active construction phase. On the complexity question the decision is displaced by Sayers Foods.

    Find on CanLII

  19. 18
    Okkin Construction Inc v Apostolopoulos2022 ONSC 6367. The corpus records no court designation for this decision

    The Superior Court has no jurisdiction over adjudication disputes. The only recourse against a determination is judicial review in the Divisional Court.

    Find on CanLII

  20. 19
    Anatolia Tile & Stone Inc v Flow-Rite Inc2023 ONSC 1291, Divisional Court of Ontario

    The leave test. The applicant must show either good reason to doubt the determination is reasonable, or procedural unfairness that probably affected the outcome, and, in addition, either irreparable harm or an issue of transcendent importance. Adjudicators have jurisdiction to decide contract validity, reviewed on reasonableness.

    Find on CanLII

  21. 20
    Arad Incorporated v Rejali et al2023 ONSC 3949, Ontario Superior Court of Justice, not the Divisional Court

    A determination alone will not reduce or return lien security, "there has to be something more". The determination is interim, not final.

    Find on CanLII

  22. 21
    Blackstone Paving and Construction Ltd v Barrie (City of)2024 ONSC 4556, Divisional Court of Ontario

    Compliance with the notice-of-non-payment requirements and procedural fairness were argued, the application was dismissed.

    Find on CanLII

  23. 22
    Castle Homes Design Inc v McKenzie2026 ONCA 98, Court of Appeal for Ontario

    Recorded in this corpus for the uncertainty it leaves over the appeal route under s 110 of the Courts of Justice Act. A delay claim tried inside a lien action carries appeal-route risk that the same claim tried in an ordinary action does not.

    Find on CanLII

  24. 23
    Construction Act s 6.1, proper invoice, and the 28-day payment clockConstruction Act (Ontario), s 6.1, as amended by Bill 216, Sch 4

    An invoice is deemed to be a proper invoice unless the owner gives written notice of the deficiency within 7 days of receipt. The 28-day prompt-payment clock runs from the proper invoice, so owner silence converts into a running clock.

    Find on CanLII

  25. 24
    Construction Act ss 26 to 27.1, annual holdback release, and the repeal of s 27.1Construction Act (Ontario), ss 26 to 27.1, as amended and in part repealed by Bill 216, Sch 4 and Bill 60, Sch 2

    On contracts running more than one year the owner must publish a Notice of Annual Release of Holdback in the prescribed form within 14 days of each contract anniversary, and pay the released holdback not less than 60 and not later than 74 days after publication, with a 14-day cascade to subcontractors on receipt. s 27.1 (the owner's notice of non-payment of holdback) is repealed, so the statutory power to refuse release for incomplete or deficient work is gone.

    Find on CanLII

  26. 25
    CCDC 2 – 2020, GC 6.5 DelaysCCDC 2 – 2020, GC 6.5.4

    GC 6.5.4 requires Notice in Writing of the cause of delay to the Consultant not later than 10 Working Days after the commencement of the delay, not of its effect, and one notice suffices for a continuing cause. Nothing in the adjudication regime displaces it. CCDC 2 – 2020 remains the current stipulated price form.

    CCDC

  27. 26
    Construction Act (Ontario), Part I.1 prompt payment and Part II.1 adjudicationConstruction Act, RSO 1990, c C.30, as amended. Parts I.1 and II.1, and s 4

    The Act supplies a mandatory prompt-payment regime and an interim adjudication regime. A party "may refer" a dispute to adjudication, and s 4 bars waiver of the Act's provisions. The two features from which the scheme's non-contractibility is usually inferred. Adjudication is available beyond the active construction phase, and the Superior Court has no jurisdiction over adjudication disputes.

    Find on CanLII

General information, not legal advice. Reviewed Sep 10, 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…

Each issue links to the full articles in the Storia Library.

Ontario construction adjudication: prompt payment and EOT · Storia