Ontario delay claim clocks
Ontario runs five independent clocks on a delay claim: contractual notice, adjudication, lien, holdback and limitation. Each has a different trigger, a different character in law and a different consequence for being missed, and none of them saves any of the others. Which of them run at all depends on the contract date.
At a glance
- Deadlines and procedure
- Ontario, Canada, common law
- CCDC 2 – 2020 · CCA 1 · OPSS.MUNI 100 · OPSS.PROV 100 · IO Project Agreement
Key facts
- 01
The organising point
Five clocks, five different characters in law. Notice decides entitlement, adjudication decides forum, lien decides security, holdback decides cash flow, limitation decides whether you can sue at all. Missing one does not excuse missing another, and satisfying one does not stop another running.
- 02
Ask the regime question first
Three date-keyed regimes run simultaneously. Contract before 1 July 2018: former Construction Lien Act, no prompt payment, no adjudication. 1 July 2018 – 31 December 2025: Construction Act, adjudication available but time not adjudicable. On or after 1 January 2026, the full 2026 regime.
- 03
The single most useful sentence
In August 2026 nearly every Ontario project with a mature delay claim sits in the middle row (contract signed between 1 July 2018 and 31 December 2025) so an extension of time is still not adjudicable on it.
- 04
Clock A, contractual notice
The only clock that decides entitlement. CCDC 2 – 2020 GC 6.5.4 gives 10 Working Days from the commencement of the delay, not from its effect. OPSS.MUNI 100 GC 3.06.01 runs backwards, 15 Days before the Contract Time expires. Conditions precedent, strictly enforced, and the owner need not prove prejudice.
- 05
Clock C, adjudication
90 days after the contract is completed, abandoned or terminated (s 13.5(3)), extendable by agreement. A statutory precondition to a statutory remedy, not a limitation period. Jurisdictional objections must be taken when first making submissions.
- 06
Clock D, lien and holdback
60 days to preserve, 90 to perfect, unchanged by the 2026 amendments. Bill 216's lien-expiry proposal did not survive. Annual holdback release is now the owner's obligation, and s 27.1 is repealed.
- 07
The 30-day tail
Adjudication runs 90 days post-completion. Lien preservation runs 60. A contractor whose lien has expired can still commence an adjudication for 30 more days, but starting an adjudication does not preserve a lien.
- 08
Clock E, limitation
Two years from discovery (Limitations Act, 2002 s 4), 15-year ultimate period (s 15), and in Ontario, unlike anywhere else in Canada, a business agreement may lawfully shorten or exclude it (s 22(5)–(6)).
Ontario runs five separate clocks on a construction delay claim, and they are not variations on one theme. Contractual notice, adjudication, lien, holdback and limitation each start on a different trigger, each has a different character in law, and each carries a different consequence for being missed. None of them saves any of the others. A preserved lien does not extend a notice period, an adjudication does not preserve a lien, and a valid notice does not stop the limitation clock.
That is the whole of the page in one paragraph, and the rest of it is the detail: which clock, which trigger, which day count, and what a court will do about a miss. But the detail is conditional on one prior question, so the page starts there: which regime is the contract on? Ontario has three, they run simultaneously, and they are keyed to the contract date rather than to the date of the delay. The oldest of the three is the former Construction Lien Act1, which still governs any Ontario contract entered before 1 July 2018 and supplies neither prompt payment nor adjudication.
A standing evidence warning applies to every number below. CanLII, the Supreme Court portal, ontariocourts.ca and Ontario e-Laws all blocked automated fetching when this corpus was built. No Canadian judgment and no Ontario statutory text was read directly from an official consolidated source. Statutory content came from enacting bill texts plus law-firm bulletins. Case content rests on bulletins. Where the corpus records two independent reputable secondaries agreeing, that is the highest confidence available here, and every day count on a limitation-critical step should be confirmed against the consolidated statute before it is diarised.
Which Ontario regime is the contract on?
Ask this before reading any deadline. Ontario runs three date-keyed regimes simultaneously, and the trigger is the date the contract was entered into, not the date the delay occurred or the date the claim is brought. The 2026 reform is prospective, and on the question that matters most to a delay claim (whether an extension of time can be adjudicated) it does not reach back.
| Contract date | Governing regime | What it means for a delay claim |
|---|---|---|
| Before 1 July 2018 | Former Construction Lien Act | No prompt payment and no adjudication. Old holdback and lien rules. Contractual notice and limitation are the only live clocks |
| 1 July 2018 – 31 December 2025 | Construction Act, Part I.1 prompt payment and Part II.1 adjudication | Adjudication is available on the pre-2026 closed list of adjudicable matters, but time is not adjudicable. The owner's s 27.1 notice of non-payment of holdback is still available |
| On or after 1 January 2026 | The full 2026 regime | EOT adjudicable as an ancillary head on non-P3 projects, 90-day post-completion adjudication window, mandatory annual holdback release, s 27.1 repealed, 7-day notice of termination |
Jurisdictional, and statutory. The three-regime structure rests on two independent secondary sources. No consolidated statutory text was read for this corpus. s 87.4 is the transition provision (amended by Bill 60 for project agreements) and s 88 gives the Minister transitional regulation-making power. Transitional jurisdiction is already being litigated.
In August 2026 nearly every Ontario project with a mature delay claim sits in the middle row. A claim ripe enough to be worth arguing about was almost certainly contracted before 1 January 2026, which means an extension of time is still not adjudicable on it. That is the single most useful sentence on this page, and it is the one most commonly got wrong in commentary written when the reform was announced.
Two further carve-outs narrow the new regime even where the contract date qualifies. Under O. Reg. 264/25 s 192: one firm cites the provision as s 19.1, while ODACC, the OAA and Cassels cite s 19, which is preferred. The extension-of-time head is available only where resolving it is "reasonably necessary" to a subsequent determination, so a pure EOT referral is still not available, and it does not apply to public-private-partnership project agreements with a special purpose entity at all. The largest Ontario projects, where delay claims run to eight figures, are precisely the ones the reform does not reach.
Clock A: contractual notice, and why it is the only one that decides entitlement
Contractual notice is the clock that decides whether there is a claim. Miss it and there is nothing left to adjudicate, lien or sue on. Ontario treats a notice-of-claim period as a condition precedent, strictly enforced, and the owner need not prove prejudice: Technicore Underground Inc v Toronto (City)3 2012 ONCA 597. The day counts differ sharply between the four contract families in live use in the province.
| Form | Clock | Deadline | Trigger |
|---|---|---|---|
| CCDC 2 – 2020 GC 6.5.4 | Time | 10 Working Days | Commencement of the delay, not its effect. One notice suffices for a continuing cause |
| CCDC 2 – 2020 GC 6.5.5 | Time | 10 Working Days after demand | The Consultant's failure to furnish instructions |
| CCDC 2 – 2020 GC 6.6.1 | Money | "Timely", no fixed period | Intention to claim a change in Contract Price. With the OAA/OGCA SC 6.6.1 the notice must also go to the Consultant |
| CCA 1 – 2021 subcontract | Time | 7 Working Days | Three fewer than the main contract |
| OPSS.MUNI 100 GC 3.06.01 | Time | 15 Days BEFORE the Contract Time expires | Runs backwards from the end date |
| OPSS.MUNI 100 GC 3.13.03 | Claim | Verbal, IMMEDIATELY | Becoming aware of a potential claim situation |
| OPSS.MUNI 100 GC 3.13.03 | Claim | 7 Days | Commencement of any part of the Work affected, written Notice of Intent to Claim |
| OPSS.MUNI 100 GC 3.13.03 | Claim | 30 Days, extendable to 90 | Completion of the work affected, the detailed claim |
| OPSS.PROV 100 GC 3.06 | Time | "As soon as the need becomes evident", no day count | Must be on MTO form PH-CC-756. A letter is not an application |
| OPSS.PROV 100 GC 3.14 | Money | 10 days / 10 Business Days | Cost-estimate submission. Unresolved change-order pricing |
| IO Project Agreement | All | Unverified, project-specific | Read the specific Project Agreement. Never assume from CCDC or from another IO project |
Form-default, and edition-specific. Clause numbers and headings are confirmed against publicly available sources. No CCDC, CCA, OPSS or IO operative text was read in original form for this corpus. Bespoke amendment is normal and the executed contract governs, read the supplementary conditions before the general conditions. The IO Project Agreement day counts are recorded as UNVERIFIED: the three-way event classification is verified, but the periods sit partly in the Articles and partly in the Schedules and were not surfaced.
Three structural traps sit inside that table. First, CCDC 2 – 20204 GC 6.5.4 runs from the commencement of the delay, not from its effect. A contractor waiting to see how bad it gets has already lost the ten Working Days. Second, OPSS.MUNI 1005 GC 3.06.01 runs backwards: the application to extend must be made at least 15 Days before the Contract Time expires, which is a structure no CCDC practitioner expects and which is easiest to miss on a job that is already visibly late. Third, OPSS.PROV 1006 GC 3.06 imposes no day count at all but does impose a mandatory prescribed form. A contractor that writes a well-drafted letter instead of form PH-CC-756 has not applied for anything.
On an Infrastructure Ontario Project Agreement7 there is no standard answer at all. The Delay Event, Compensation Event and Relief Event classification is verified, but the Article numbers that carry it are not fixed and differ between IO projects, so read them off the agreement in front of you. The notice periods are UNVERIFIED and project-specific. They sit partly in the Articles and partly in the Schedules and were not surfaced for this corpus. Infrastructure Ontario publishes redacted execution-version Project Agreements, so the operative periods can be read out of the actual document. Never assume them from CCDC or from another IO project.
The subcontract chain compounds the problem rather than easing it. CCA 1 – 20218 gives a subcontractor 7 Working Days, three fewer than the main contract gives the contractor, so a subcontractor waiting to be told what the contractor intends to do will be out of time before the contractor is.
Content matters as much as timing. In Ross-Clair v Canada (Attorney General)9 2016 ONCA 205 the Court of Appeal held that "failure to provide sufficient information within 30 days after completion is a failure to provide notice of the claim at all". An inadequate claim is not a late claim. It is a non-existent claim. The same strictness produced the outcome in Elite Construction Inc v Canada (Attorney General)10 2021 ONSC 562, where a CAD 4.1M delay claim was dismissed on summary judgment for failure to notify within ten working days and affirmed on appeal at 2021 ONCA 803.
One Ontario point cuts the other way, and it is worth knowing because it is not obvious: a period in a staged ADR clause is read as a minimum, not a cut-off: J.P. Thomson Architects Ltd v Greater Essex County District School Board11 2025 ONCA 378. Ontario splits its rule of construction between the two kinds of time limit, and the fuller treatment of that split (together with what the standard forms do across jurisdictions) is in notice and time bars in Ontario.
Clock B: staged ADR, which is a floor rather than a ceiling
Staged ADR is the one clock that is not a bar. Both Ontario ladders: the CCDC 2 – 2020 Part 8 sequence and the OPSS.MUNI 100 GC 3.13.04 to GC 3.14.02 sequence: set periods that must elapse or be attempted before the next step, and under J.P. Thomson, 2025 ONCA 378, a period expressed as "within thirty (30) days" in a staged mediation clause is a minimum, not a cut-off.
| Form | Step | Deadline |
|---|---|---|
| CCDC 2 – 2020 Part 8 | Notice of dispute after a decision | 15 Working Days |
| CCDC 2 – 2020 Part 8 | Response | 10 Working Days |
| CCDC 2 – 2020 Part 8 | Amicable settlement attempt | 10 days |
| CCDC 2 – 2020 Part 8 | Mediator requested if not named at signature | 10 days |
| OPSS.MUNI 100 GC 3.13.04–.05 | Negotiation, then mediation if unresolved | 30 Days following the opinion |
| OPSS.MUNI 100 GC 3.13.04–.05 | Mediator's review to complete | 90 Days following the opinion |
| OPSS.MUNI 100 GC 3.14.01–.02 | Notice of arbitration | 60 Days following the opinion, 120 Days if mediation was attempted |
| OPSS.MUNI 100 GC 3.14.01–.02 | Hearing to commence | 90 Days of appointment |
Form-default. CCDC 2 – 2020 is current as at August 2026, with no 2025 or 2026 update. OPSS.MUNI 100 is the November 2019 edition. Clause numbers are confirmed from secondary sources and no operative text was read. The executed contract governs, and public owners routinely replace these ladders wholesale.
One Ontario-specific feature deserves separate attention because it changes who is in the room. On a CCDC 2 supplemented by the OAA/OGCA Agreed-to Recommended Supplementary Conditions12, the Consultant may join the arbitration as a full party within 10 days of receipt, on 5 days' notice (SC 8.3.9–8.3.13). A two-party delay arbitration can therefore become tripartite at the Consultant's election, which affects pleading, privilege and settlement strategy from the outset. Note also that the same OAA/OGCA package contains no supplementary condition amending GC 6.5 at all: unusually for Canadian supplementaries, the Ontario industry-agreed package leaves the delay machinery alone.
The staged ladder interacts with limitation as well as with entitlement, and the interaction runs in the claimant's favour: a mandatory ADR step can postpone the start of the basic limitation period. That is Clock E's problem and is dealt with there.
Clock C: adjudication, a statutory precondition rather than a limitation period
Adjudication decides forum, not entitlement. Under the Construction Act13 a notice of adjudication must be given within 90 days after the contract is completed, abandoned or terminated (s 13.5(3)), and the parties may agree to extend that window. Miss it and the claim survives. It simply has to be litigated or arbitrated instead. The character of the clock is a statutory precondition to a statutory remedy, not a limitation period.
| Clock | Deadline | Note |
|---|---|---|
| Notice of adjudication, contract | 90 days after the contract is completed, abandoned or terminated (s 13.5(3)) | The parties may agree to extend |
| Notice of adjudication, subcontract | 90 days from the earliest of contract completion, abandonment or termination, certification or declaration of subcontract completion, and the date the subcontractor last supplied (s 13.5(3.1)) | Three possible triggers, and the earliest governs |
| Jurisdictional objection | When first making submissions, or as soon as the matter is raised (s 13.12.1) | Object now or lose it |
| Determination | 30 days statutory | Only 61% of determinations met it in FY2025 |
| Slip rule correction | 5 days (s 13.17.1) | Typographical, calculation or similar errors, or an oversight, without a hearing |
| Payment of the determined amount | 15 days from communication (s 13.19(2)) | Amended up from 10 by 2024, c. 20, Sched. 4, s. 23 (1). The 10 days in wide circulation is the pre-2026 figure |
| Leave to seek judicial review | 35 days from communication (s 13.18(2)), leave of the Divisional Court, six operative grounds at s 13.18(5) | Amended up from 30 by 2024, c. 20, Sched. 4, s. 22 (1). Diarise 30 as prudence, a missed leave deadline is fatal |
Jurisdictional, and statutory. The ss 13.18 and 13.19 day counts were read on 10 September 2026 in the consolidated Construction Act on Ontario e-Laws and corroborated against the Royal Assent print of Bill 216, Schedule 4. The remaining section numbers and day counts on this page come from enacting bill texts and firm bulletins.
Note the correction that most commonly needs making about sections 13.18 and 13.19 of the Construction Act14: s 13.18 is the judicial review provision (leave of the Divisional Court, closed grounds, applications that may be dismissed without reasons) and s 13.19 is "Amounts payable". Commentary that has them the other way round is wrong, and on this particular pair being wrong is expensive.
The jurisdictional-objection rule at s 13.12.1 is the trap a first-time referral respondent falls into. The objection must be taken when first making submissions, so a respondent that argues the merits first and the adjudicator's jurisdiction second has generally lost the point. And complexity is not itself a jurisdictional answer: Sayers Foods Ltd v Gay Company Ltd15, 2026 ONSC 918 (Div Ct), holds at para 80 that "complexity of a dispute does not oust an Adjudicator's jurisdiction to decide that dispute if it is necessary to do so to rule on a 'matter' properly the subject of an adjudication".
Two negative findings belong here because they set the expectation a reader should have. First, before Sayers Foods no Ontario judicial review had addressed delay or extension of time at all: structurally, because time was not adjudicable before 1 January 2026. Ontario's adjudicated-EOT case law is one case deep. Second, ODACC does not track delay, EOT or change-order disputes as a category, so no Ontario dataset on adjudicated delay claims exists, and none can until the FY2026 report. Anyone quoting statistics on adjudicated delay outcomes in Ontario is quoting something that has not been measured. The scheme itself is set out at prompt payment and adjudication in Ontario.
One further question is expressly open: no Ontario authority decides whether an arbitration clause ousts statutory adjudication. The scheme implies it cannot be contracted out of. A party "may" refer, and s 4 bars waiver of the Act's provisions, but it has not been decided, and it affects every Infrastructure Ontario and AFP project, all of which contain bespoke arbitration regimes.
Clock D: liens and holdback, which decide security and cash flow
Lien and holdback decide security and cash flow, not entitlement. Lien preservation is 60 days and perfection is 90 days, and the 2026 amendments did not change either: Bill 216's lien-expiry proposal did not survive, so 2024–25 commentary describing a new Ontario lien regime is describing a dropped proposal. Missing the lien clock costs the security, not the claim: a contractor whose lien has expired retains the contract claim and can still sue.
| Clock | Deadline | Note |
|---|---|---|
| Lien preservation | 60 days | Unchanged by the 2026 amendments |
| Lien perfection | 90 days | Unchanged |
| Notice of termination | 7 days from termination, published in the prescribed form | The publication date is deemed the date of termination, and it sets the lien clock |
| Notice of Annual Release of Holdback (Form 6) | 14 days after each contract anniversary | The owner's obligation, on contracts running over one year |
| Payment of annual holdback | Not less than 60 and not later than 74 days after publication | A fixed 14-day window opening on day 60 |
| Cascade to subcontractors | 14 days of receipt | The contractor's obligation once paid |
| Proper invoice deeming | 7 days for the owner to give written notice of a deficiency | Silence makes the invoice proper, and starts the 28-day payment clock |
Jurisdictional, and statutory. No consolidated statutory text was read for this corpus. The day counts rest on enacting bill texts and two independent secondary sources. The regime applies according to the contract date, so mandatory annual holdback release, the 7-day notice of termination and the repeal of s 27.1 reach only contracts entered on or after 1 January 2026, and P3 project agreements entered with a special purpose entity before 1 January 2026 are exempt from mandatory annual holdback release under s 87.4 as amended by Bill 60.
Section 27.1 is repealed. The owner's notice of non-payment of holdback (the mechanism an owner previously used to hold money against an asserted delay claim) is gone from 1 January 2026, and is still available only on contracts in the middle regime. Combined with prompt payment and with mandatory annual release, Ontario has systematically stripped owners of money as leverage against a delay claim. An owner that wants to withhold against delay now needs an express contractual delay-damages and set-off mechanism and has to prove it inside a 30-day adjudication.
Adjudication runs 90 days post-completion. Lien preservation runs 60. A contractor whose lien has expired can still commence an adjudication for 30 more days, but starting an adjudication does not preserve a lien.
That 30-day tail is the most useful arithmetic on this page, and it works in only one direction. It is a second chance at a forum, not a second chance at security. The practical rule is to preserve on the 60-day clock and adjudicate in parallel or in the tail, never to treat the adjudication window as covering the lien window.
One negative finding constrains what can be claimed here: there is no post-2018 Ontario appellate authority on the lienability of delay or prolongation costs. Whether, and to what extent, extended site overhead and prolongation costs are lienable in Ontario is unresolved at appellate level, and a practitioner asserting a lien amount that consists largely of delay costs is arguing an open point. The lien and holdback machinery in full is at liens, holdback and security in Ontario.
Clock E: limitation, which decides whether you can sue at all
Limitation is the clock that ends the claim rather than a remedy for it. The basic period is two years from discovery under section 4 of the Limitations Act, 200216, with the four-limb discoverability test at s 5: including the fourth limb, that "a proceeding would be an appropriate means" to seek to remedy the loss, and a 15-year ultimate period at s 15. What makes Ontario different from the rest of Canada is s 22(5)–(6)17.
| Clock | Position |
|---|---|
| Basic limitation period | 2 years from discovery: Limitations Act, 2002 s 4 |
| Discovery | The four-limb s 5 test, including "a proceeding would be an appropriate means" |
| Ultimate limitation period | 15 years, s 15 |
| Contractual variation | Permitted in a "business agreement": extend, SHORTEN, suspend or exclude (s 22(5)–(6)) |
Jurisdictional, and statutory. No consolidated statutory text was read for this corpus. The s 22 business-agreement power is Ontario's alone: Alberta, Saskatchewan and Manitoba permit extension only, and Quebec's art 2884 C.c.Q. permits no conventional prescription period at all, neither longer nor shorter. Do not extend the Ontario position to any other province.
Read the supplementary conditions for a limitation clause before you read anything else. In Ontario a commercial construction contract can lawfully cut the two-year period down, and s 22(5)–(6) of the Limitations Act, 2002 is why. That is not available in Alberta, Saskatchewan or Manitoba, where only extension is permitted, and it is flatly prohibited in Quebec. An English or Australian practitioner arriving on an Ontario job should treat the limitation period as a negotiated term until the contract says otherwise.
A shortened period is not, however, easy to draft. Under Ontario (Transportation) v J & P Leveque Bros Haulage Ltd18 2025 ONCA 573 a contractual limitation clause must clearly describe a limitation period, identify its scope, and expressly exclude the statutory periods. On a Highway 60 rehabilitation contract the Court of Appeal reversed the motion judge and held that MTO's own clause failed that test, so the s 4 period governed and the action was not barred. If the province's standard form cannot get this right, an owner's bespoke supplementary conditions probably cannot either, and the clause is worth attacking.
On when the clock starts, accrual on an Ontario construction payment claim is invoice-and-default discoverability: 1838120 Ontario Inc v Township of East Zorra-Tavistock19 2021 ONSC 3341: an invoice issued within a reasonable time, a reasonable payment period elapsed, and payment default. Negotiations do not toll. A contractor that spends eighteen months in commercial discussion with an owner has spent eighteen months of a two-year period, unless something else has postponed the start.
Something else sometimes does. Where the contract makes a dispute-resolution step mandatory, that step bears on the s 5(1)(a)(iv) question whether a proceeding would be an appropriate means, PQ Licensing S.A. v LPQ Central Canada Inc20 2018 ONCA 331, so a mandatory staged ADR clause of the kind at Clock B can postpone the start of the basic period. That is a real argument, not a hopeful one, but it depends on the clause being mandatory rather than permissive.
Two things are unresolved and should be treated as such. There is no bright-line Ontario accrual rule for delay claims (not the delaying event, not substantial performance, not the final certificate) so accrual is argued case by case on the s 5 test. And it is undecided whether a contractual limitation clause valid under s 22 can cut down or extend the 90-day adjudication window: logically s 13.5(3) is a precondition rather than a limitation period, but the express statutory power to extend that window by agreement invites the argument. The fuller analysis is at limitation periods and claim accrual in Ontario.
What each clock actually decides, and how to run all five
Each clock answers a different question, and the answers do not substitute for one another. Set against each other they produce a short operating rule: notice decides entitlement, adjudication decides forum, lien decides security, holdback decides cash flow (and it is now the owner's obligation) and limitation decides whether you can sue at all.
| Clock | What it decides | What a miss costs | Character in law |
|---|---|---|---|
| A, contractual notice | Entitlement | The claim itself. There is nothing left to bring | Condition precedent, strictly enforced. The owner need not prove prejudice |
| B, staged ADR | Sequence | Usually nothing. The periods are minimums, not cut-offs | A procedural floor, and a mandatory step can postpone limitation |
| C, adjudication | Forum | The interim remedy. You litigate or arbitrate instead | A statutory precondition to a statutory remedy, not a limitation period |
| D, lien and holdback | Security and cash flow | The security. The contract claim survives | Statutory conditions of the lien remedy, not limitation periods |
| E, limitation | Whether you can sue at all | Everything | A true limitation period, and in Ontario it may have been shortened by contract |
Inferential. The characterisations are drawn from the authorities and the statutory scheme recorded in this corpus, not from any single judgment stating them in this form. Every underlying citation and section number rests on secondary sources.
Two points of context close the picture. The pan-Canadian doctrine these clocks sit on top of (concurrency, the prevention principle, the penalty rule, delay analysis and expert evidence) is not Ontario-particular and is set out in the Canadian extension-of-time hub. The Ontario material that sits above these clocks, including the four contract families and the three-regime transition, is at the Ontario extension-of-time hub. And Quebec is carved out of all of it: it is a civil-law jurisdiction, prescription runs three years from fin des travaux, and art 2884 C.c.Q. forbids any conventional period, in either direction. Nothing on this page should be carried across that border.
Sources and authorities
- *Verification, unless noted
No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
- 1Construction Lien Act (Ontario), the pre-1 July 2018 regimeConstruction Lien Act, RSO 1990, c C.30 (Ontario), as it read before 1 July 2018
The regime that continues to govern Ontario contracts entered before 1 July 2018: lien and holdback rules in their former form, and neither prompt payment nor adjudication.
- 2O. Reg. 264/25 s 19, the ancillary extension-of-time headO. Reg. 264/25 (Ontario), s 19
Adds "a request for an extension of time to complete the work prescribed by the contract" to the adjudicable matters, but only where resolving it is reasonably necessary to a subsequent determination, so a pure EOT referral remains unavailable. It does not apply to public-private- partnership project agreements with a special purpose entity, and it does not apply to contracts entered before 1 January 2026. One firm cites the provision as s 19.1. ODACC, the OAA and Cassels cite s 19, which is preferred.
- 3Technicore Underground Inc v Toronto (City)2012 ONCA 597, Court of Appeal for Ontario
Contractual notice provisions are strictly enforced and the owner need not prove prejudice from the failure to give notice. The Ontario anchor for treating a notice-of-claim period as a condition precedent.
- 4CCDC 2 – 2020, Stipulated Price Contract: GC 6.5, GC 6.6 and Part 8CCDC 2 – 2020 (Canadian Construction Documents Committee)
GC 6.5.4 requires written notice of a claim for extension of Contract Time within 10 Working Days of the commencement of the delay, with one notice sufficient for a continuing cause, GC 6.5.5 gives 10 Working Days after demand where the Consultant fails to furnish instructions, GC 6.6.1 requires timely notice of an intention to claim a change in Contract Price and fixes no period. Part 8 supplies the staged dispute ladder: 15 Working Days to give notice of dispute, 10 Working Days to respond, 10 days for amicable settlement.
- 5OPSS.MUNI 100, General Conditions of Contract (November 2019)OPSS.MUNI 100, General Conditions of Contract, November 2019 edition
The Ontario municipal standard form. GC 3.06.01 requires an application to extend the Contract Time at least 15 Days prior to its expiration. GC 3.13.03 requires verbal notice immediately on becoming aware of a potential claim situation, a written Notice of Intent to Claim within 7 Days of the commencement of any part of the Work affected, and a detailed claim no later than 30 Days after completion of the work affected, extendable to 90 Days. GC 3.13.04–.05 and GC 3.14.01–.02 supply the staged mediation and arbitration ladder.
- 6OPSS.PROV 100, MTO General Conditions of Contract (April 2023)OPSS.PROV 100, General Conditions of Contract, April 2023 edition (Ontario Ministry of Transportation)
The Ontario provincial highways standard form. GC 3.06 requires an application for an extension of Contract Time to be made in writing on MTO form PH-CC-756, Compensation Request, as soon as the need for the extension becomes evident, no fixed day count and a mandatory prescribed form. GC 3.14 sets 10 days after cost-estimate submission for a Compensation Request and 10 Business Days for unresolved change-order pricing. A July 2025 draft edition is out for consultation.
- 7Infrastructure Ontario / AFP Project AgreementRedacted execution-version agreements published by Infrastructure Ontario. Article numbering varies by project
Splits time relief three ways by event classification: a Delay Event gives time only, a Compensation Event gives time and money, a Relief Event gives neither, only relief from performance and from default remedies. Each carries an express mitigation obligation. The notice periods are project-specific, sit partly in the Articles and partly in the Schedules, and were not surfaced in this research pass.
- 8CCA 1 – 2021, Stipulated Price SubcontractCCA 1 – 2021 (Canadian Construction Association)
The standard subcontract to CCDC 2, requiring notice of a claim for extension of subcontract time within 7 Working Days, three fewer than the 10 Working Days in the main contract.
- 9Ross-Clair v Canada (Attorney General)2016 ONCA 205, Court of Appeal for Ontario
"Failure to provide sufficient information within 30 days after completion is a failure to provide notice of the claim at all." Content is a condition of the notice, not merely its timing: an inadequate claim is not a late claim, it is a non-existent one.
- 10Elite Construction Inc v Canada (Attorney General)2021 ONSC 562, Ontario Superior Court of Justice, aff'd 2021 ONCA 803
A CAD 4.1M delay claim dismissed on summary judgment for failure to notify within 10 working days, and affirmed on appeal at 2021 ONCA 803. The Court of Appeal dismissed the appeal on the availability of summary judgment and on the absence of any waiver of the strict contractual notice requirements.
- 11J.P. Thomson Architects Ltd v Greater Essex County District School Board2025 ONCA 378, Court of Appeal for Ontario
A period expressed as "within thirty (30) days" in a staged mediation clause is a minimum, not a cut-off. Ontario reads a period in a staged ADR clause differently from a notice-of-claim period.
- 12OAA/OGCA Agreed-to Recommended Supplementary Conditions for CCDC 2 – 2020OAA/OGCA Agreed-to Recommended Supplementary Conditions to CCDC 2 – 2020 (Ontario Association of Architects and Ontario General Contractors Association)
The Ontario industry-agreed supplementary package. It contains no supplementary condition amending GC 6.5, so the delay machinery is left alone. SC 6.6.1 requires the notice of intention to claim a change in Contract Price also to go to the Consultant. SC 8.3.9–8.3.13 permit the Consultant to join an arbitration as a full party within 10 days of receipt, on 5 days' notice.
- 13Construction Act (Ontario), Part I.1 prompt payment and Part II.1 adjudicationConstruction Act, RSO 1990, c C.30 (Ontario), as amended
The comprehensive Ontario scheme governing liens, holdback, prompt payment and adjudication. Part I.1 and Part II.1 commenced 1 October 2019 for contracts entered on or after 1 July 2018. The 2026 amendments introduced mandatory annual holdback release, the 7-day notice of termination, the 90-day post-completion adjudication window and the repeal of s 27.1.
- 14Construction Act (Ontario) ss 13.18 and 13.19: leave to seek judicial review, and amounts payableConstruction Act, RSO 1990, c C.30 (Ontario), ss 13.18, 13.19
s 13.18 is the judicial review provision: leave of the Divisional Court, 35 days from communication of the determination (s 13.18(2)), with a closed list of six operative grounds at s 13.18(5). s 13.19 is "Amounts payable", payment of the determined amount within 15 days (s 13.19(2)). Both periods were amended up from 30 and 10 by 2024, c. 20, Sched. 4, ss 22 (1) and 23 (1).
- 15Sayers Foods Ltd v Gay Company Ltd2026 ONSC 918 (Divisional Court)
"Complexity of a dispute does not oust an Adjudicator's jurisdiction to decide that dispute if it is necessary to do so to rule on a 'matter' properly the subject of an adjudication" (para 80). The first Canadian delay dispute fought through adjudication and surviving judicial review, displacing the earlier Pasqualino line on the complexity point.
- 16Limitations Act, 2002 (Ontario): ss 4, 5 and 15Limitations Act, 2002, SO 2002, c 24, Sch B, ss 4, 5, 15
s 4 sets the basic limitation period at two years from the day the claim was discovered. s 5 supplies the four-limb discoverability test, including the requirement that a proceeding would be an appropriate means to seek to remedy the loss. s 15 sets a 15-year ultimate limitation period running from the act or omission.
- 17Limitations Act, 2002 (Ontario) s 22(5)–(6), variation by business agreementLimitations Act, 2002, SO 2002, c 24, Sch B, s 22(5)–(6)
In a business agreement the basic and ultimate limitation periods may be varied by contract: extended, shortened, suspended or excluded outright. Ontario is the only Canadian jurisdiction where commercial parties may lawfully shorten or exclude a limitation period. Alberta, Saskatchewan and Manitoba permit extension only, and Quebec's art 2884 C.c.Q. permits no conventional period at all.
- 18Ontario (Transportation) v J & P Leveque Bros Haulage Ltd2025 ONCA 573, Court of Appeal for Ontario
A contractual limitation clause must clearly describe a limitation period, identify its scope, and expressly exclude the statutory periods. On a Highway 60 rehabilitation contract the Court of Appeal reversed the motion judge and held MTO's own clause failed that test, so the s 4 period governed and the action was not barred.
- 191838120 Ontario Inc v Township of East Zorra-Tavistock2021 ONSC 3341, Ontario Superior Court of Justice
Accrual on a construction payment claim is invoice-and-default discoverability: an invoice issued within a reasonable time, a reasonable payment period elapsed, and payment default. Negotiations do not toll the limitation period.
- 20PQ Licensing S.A. v LPQ Central Canada Inc2018 ONCA 331, Court of Appeal for Ontario
Where the contract makes a dispute-resolution step mandatory, that step bears on whether a proceeding would be an appropriate means to remedy the loss under s 5(1)(a)(iv) of the Limitations Act, 2002, so a mandatory staged ADR clause can postpone the start of the limitation period.
General information, not legal advice. Reviewed Sep 10, 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.