Extension of time in Canada

Canadian delay and extension-of-time law is almost entirely common law and contract. No province or territory has a statute addressing construction delay as such. On procedure Canada is close to England and strict, on remedy it is closer to the United States, because Canadian courts apportion concurrent delay rather than granting full relief.

Reviewed Sep 10, 202617 min read25 sources
Same topic inCAQCONBCABUSAUE&W

At a glance

Canada
Jurisdiction
Canada, common-law provinces and territories
Scope
Excludes Quebec, which is civil law and separately addressed
Principal form
CCDC 2 – 2020, GC 6.5
Evidence basis
Secondary sources, no judgment or consolidated statute read in original text
§ 00

Key facts

  1. 01

    Where the entitlement comes from

    The contract, and nothing else. No Canadian province or territory has a statute addressing construction delay claims, no statutory extension entitlement, no statutory concurrency rule, no statutory delay-analysis standard.

  2. 02

    The standard form

    CCDC 2 – 2020 remains current, there is no 2025 or 2026 update. GC 6.5.4 requires written notice within 10 Working Days of the commencement of the delay not of its effect.

  3. 03

    Read the supplementary conditions first

    Supplementary conditions usually amend GC 6.5, but the OAA/OGCA package for Ontario contains no such amendment, and whether the ACA SC CCDC2-2020 package for Alberta amends GC 6.5 is unverified. Read the executed contract.

  4. 04

    Where the claim dies

    Notice, more often than anywhere else in the common-law world. Elite Construction lost CAD 4.1 million on summary judgment for a missed 10-working-day notice, and the owner did not have to prove prejudice.

  5. 05

    Concurrent delay

    Canada apportions. Do not import the English full-EOT rule. Schindler requires the postponement to be broken into its component parts to apportion time, responsibility and cost.

  6. 06

    Liquidated damages

    Canada has not adopted Cavendish. The genuine-pre-estimate test survives with an unconscionability overlay. A UK drafter's "legitimate interest" justification has no purchase here.

  7. 07

    No-damage-for-delay clauses

    No statutory prohibition anywhere in Canada federal, provincial or territorial. Unlike the United States, the only route of attack is the Tercon exclusion-clause framework.

  8. 08

    Check the province before anything else

    Limitation variation, lien periods, trust status and adjudication scope all change at the border. Ontario alone lets commercial parties shorten or exclude a limitation period.

There is no Canadian law of extension of time. There is a Canadian body of contract law applied to extension-of-time clauses, and the clause is almost always GC 6.5 of CCDC 2 – 2020 as amended by supplementary conditions the owner wrote. Everything a claimant is entitled to comes from that clause, everything a claimant loses, it loses on notice, on proof of the critical path, or at a provincial border it did not know it had crossed.

That is the structural fact that distinguishes Canada from both the United States, where state statutes prohibit no-damage-for-delay clauses, and Quebec, where a Civil Code governs the contract of enterprise. No Canadian province or territory has a statute addressing construction delay claims as such. There is no statutory extension entitlement, no statutory concurrency rule, no statutory delay-analysis standard, and no statutory prohibition on no-damage-for-delay clauses anywhere in the country.

For a practitioner arriving from England, Australia or the United States, the two things to recalibrate first are these. On procedure Canada is close to England, and strict: notice provisions are conditions precedent, and the owner does not have to prove prejudice. On remedy Canada is closer to the United States, because Canadian courts apportion where multiple parties contribute overlapping delay, which orthodox English law does not do. The corpus records that second proposition as an inference from the pattern of the authorities, not as something any Canadian court has stated in those terms.

A standing warning on the evidence base for this page and the cluster beneath it: CanLII, the Supreme Court portal, ontariocourts.ca and Ontario e-Laws all blocked automated retrieval during the research pass. No Canadian judgment and no consolidated provincial statutory text was read in original form. Case content rests on law-firm bulletins, statutory content came from enacting bill texts plus bulletins. Every citation, section number and day count below should be checked against the judgment or the consolidated statute before it is pleaded or relied on for a limitation-critical step.

§ 01

Quebec is carved out of everything below

Almost nothing on this page governs Quebec, and a common-law precedent imported into a Quebec file will be wrong in ways that are not obvious. Quebec is a civil-law jurisdiction with its own Code civil du Québec, its own contract form (CCDC 2CcQ – 2024), its own public-works regime and its own payment legislation.

Specifically: there is no statutory completion date and no statutory extension mechanism in the contrat d'entreprise chapter, "time at large" does not exist. Where a term is indeterminate art 1512 C.c.Q. requires the court to fix it, which is the opposite consequence, there is no Quebec doctrine of concurrent delay, only apportionment of fault. There is no named doctrine of constructive acceleration, and there is no penalty-versus-liquidated-damages characterisation at all, because a clause pénale is valid and enforceable without proof of quantum and is merely reducible. Prescription is three years and does not begin until fin des travaux, and under art 2884 C.c.Q. the parties may not agree any conventional period, neither longer nor shorter.

Start instead at extension of time in Quebec, and use the Quebec versus common-law Canada comparison before adapting any precedent across the border.

§ 02

Where the entitlement comes from: CCDC 2 – 2020 and the current form landscape

The extension entitlement is contractual. On private and institutional work the form is almost always CCDC 2 – 2020, the Stipulated Price Contract1, and the delay machinery is GC 6.5. The structure repays reading closely, because it splits time relief from money relief along a line that decides the value of most claims:

ProvisionWhat it coversTimeMoney
GC 6.5.1Delay caused by the Owner, the Consultant or anyone employed by them, or by an act or omission contrary to the Contract DocumentsYesYes, reasonable costs
GC 6.5.2A stop work order by a court or public authority, not due to an act or fault of the ContractorYesYes, reasonable costs
GC 6.5.3Labour disputes, fire, unusual delay by common carriers, abnormally adverse weather, and causes beyond the Contractor's controlYesNo
GC 6.5.4The notice condition, 10 Working Days from the commencement of the delay––
GC 6.5.5The Consultant's failure to furnish instructions. A waiting period: no request for an extension until 10 Working Days after demand––
GC 6.6.1The separate notice of intention to claim a change in the Contract Price, "timely", no fixed period––
GC 10.1.2Adjustment for changes in taxes and duties after bid closingNoYes

Layer: form-default. This is the published CCDC 2 – 2020 text as reported in secondary sources the form itself was not read in original. It is displaced by the supplementary conditions of the executed contract, which usually amend GC 6.5. Though the Ontario OAA/OGCA package verifiably does not, and the position of the Alberta ACA package is unverified. Read the executed contract.

Three points about the wider form landscape as at August 2026. CCDC 2 – 2020 remains current there is no 2025 or 2026 update, and a Quebec-adapted CCDC 2CcQ – 2024 is separately current. CCDC 5A, 5B, 17 and 30 were reissued on 30 June 2025, and the reissue matters to delay in three ways: Contract Time was redefined to run to Ready-for-Takeover, which changes what an extension actually extends, the schedule was split into an Owner-prepared Project Schedule and a CM-prepared Construction Schedule, creating an Owner-owned baseline against which Owner-caused delay can be measured. And CCDC 5B expanded "delays beyond the Construction Manager's control" to include any subcontractor's default, insolvency, abandonment or termination. The design-build suite was refreshed in spring 2026 (CCDC 14, 15, 32 (Progressive Design-Build) and 33) but whether CCDC 32 and 33 alter the delay machinery is unverified in this corpus.

GC 6.5.3 is where most non-owner-caused delay is argued, and it is worth knowing that the Canadian law of supervening events sitting behind it comes from outside construction. Atlantic Paper Stock Ltd v St Anne-Nackawic Pulp & Paper Co2 1975 CanLII 170 (SCC) supplies the definition. "a supervening, sometimes supernatural, event, beyond control of either party", together with the ejusdem generis reading of a listed catch-all and the rule that a party cannot rely on a misfortune it authored. And Naylor Group Inc v Ellis-Don Construction Ltd3 2001 SCC 58 at paras 52–60 holds that an event already in existence at tender is not supervening at all, which disposes of a surprising number of arguments about conditions the contractor could have priced.

And one correction worth carrying, because the opposite is widely repeated. CCDC 2 is not free of an escalation mechanism. It has no general materials-price escalation clause, but GC 10.1.2 adjusts the Contract Price for changes in taxes and duties after bid closing. The practical consequence in a tariff environment is that tariffs are a money event, not a time event, and there is no CCDC or Canadian Construction Association guidance or model supplementary condition on tariffs or escalation at all.

§ 03

Read the supplementary conditions before the general conditions

Supplementary conditions usually amend GC 6.5, and on a public project they are where the owner has moved the risk, but that is a working expectation rather than a verified rule, and the one industry package the corpus can speak to squarely goes the other way. The OAA/OGCA Agreed-to Recommended Supplementary Conditions for CCDC 2 – 2020 (the Ontario industry-agreed package) contain no supplementary condition amending GC 6.5. They do amend the money notice, requiring it to go to the Consultant as well, and they let the Consultant join a subsequent arbitration as a full party.

The equivalent Alberta question has no answer. It is UNVERIFIED whether the Alberta Construction Association's ACA SC CCDC2-2020 package amends GC 6.5 at all, the corpus records that as the top Alberta gap. And no Consulting Engineers of Alberta recommended supplementary conditions to CCDC 2 and no City of Edmonton general conditions were located in any publicly indexed form. So on an Alberta project the 10 Working Days in GC 6.5.4 cannot be assumed either to survive or to have been amended: the executed contract has to be read.

Public boards, transit agencies and ministries publish their own packages and those are a different matter entirely. On Ontario public work the applicable form may not be CCDC at all: OPSS.MUNI 100 runs a notice clock that expires 15 days before the Contract Time ends rather than a period after an event, and OPSS.PROV 100 requires the application to be made on a prescribed MTO form, so a letter is not an application. Those are set out in the Ontario notice and time bars page.

§ 04

Where a Canadian delay claim actually dies

Ranked by what the judgments show rather than by any frequency dataset, because no Canadian dataset on delay claims exists.

What saves a late notice, where anything does, is waiver by conduct Colautti Construction Ltd v Ottawa (City)10 1984 CanLII 1969 (ONCA), where the owner had repeatedly paid for unauthorised extras. Or the good-faith line running from Bhasin through Callow to Wastech. What does not save it is site friction: Northland Kaska Corp v R11 2001 BCSC 929 held that "the grumblings of a contractor are not sufficient to constitute notice". The Canadian notice and time bars page develops each of these.

§ 05

Concurrency, prevention and liquidated damages. The three doctrines a foreign practitioner gets wrong

Concurrency. Canada apportions. Do not import the English rule that a contractor concurrently delayed by an employer risk event gets a full extension. Schindler set the Canadian evidentiary standard and Walsh v TTC applied a functional test, but no Canadian appellate decision squarely on concurrent delay was located for 2024–2026, so the doctrine sits on first-instance authority. The Canadian concurrency page sets out how far the apportionment proposition can actually be pushed, and what it rests on.

Prevention. The anchor is Perini Pacific Ltd v Greater Vancouver Sewerage & Drainage District12, (1966), 57 DLR (2d) 307 (BCCA): "A building owner is not allowed to insist upon the penalty for delay if, by ordering extra, he has prevented the builder from completing the work by a specified time." Note two things. That holding is the Court of Appeal's. The liquidated damages counterclaim was not in issue before the Supreme Court, which on the further appeal enforced a broad no-damage-for-delay clause against the contractor's own delay claim. Prevention beat the owner's liquidated damages; the exculpatory clause beat the contractor's delay costs. Same case, opposite parties' claims. And CIMIC Morningstar Investments Ltd v Chandos Construction Ltd13 2026 BCCA 2 is a leave decision on an arbitral award: it confirms deference, it does not restate the principle, and the underlying award is not public. It should not be cited as an appellate statement of Canadian prevention doctrine.

Liquidated damages. ★ Canada has not adopted Cavendish Square v Makdessi. The genuine-pre-estimate test survives, with an unconscionability overlay layered on top of it. A UK drafter's "legitimate interest" justification for a high LD rate has no purchase in Canada, and no Ontario decision adopts Cavendish. Separately, Chandos Construction Ltd v Deloitte Restructuring Inc14 2020 SCC 25 makes a forfeiture clause triggered by insolvency void on anti-deprivation grounds regardless of whether the sum is a genuine pre-estimate. A second, independent way for a delay-damages mechanism to fail. And where an owner tries to exclude delay damages altogether, Tercon Contractors Ltd v British Columbia (Transportation and Highways)15 2010 SCC 4 supplies the only framework of attack, because no Canadian jurisdiction prohibits no-damage-for-delay clauses by statute.

§ 06

Proving the claim, and what it is worth

Two corrections govern the quantum side of a Canadian delay claim, and both are widely reproduced wrongly.

Shore & Horwitz Construction Co Ltd v Franki of Canada Ltd16 [1964] SCR 589 is Supreme Court authority for recovering unabsorbed head-office overhead at a rate per unit of time. But the Court worked from actual audited cost, taking monthly overhead multiplied by months of delay and assessing head-office overhead at 4.99% of other costs. The circulated "Shore & Horwitz formula", overhead and profit multiplied by delay days and divided by contract duration: is a practitioner gloss, not the Court's holding, and citing it as such invites a correction from the bench. Separately, Ellis-Don Ltd v Parking Authority of Toronto (1978), 28 BLR 98 is an unabsorbed head-office overhead case, not the leading Canadian disruption or loss-of-productivity authority: it contains no measured mile, no productivity finding and no general statement about disruption.

On method, the honest position is that Canada has very little. No Canadian judgment cites the SCL Delay and Disruption Protocol. Exactly one (Walsh v TTC) cites AACE RP 29R-03. No Canadian judgment applies the Eichleay formula, uses the phrase "global claim", or supplies a measured-mile or modified-total-cost authority. Canada has no national delay-analysis standard, and no court has accepted or rejected a named methodology as a matter of law. What a Canadian court does want is the Schindler decomposition, contemporaneous records, and an expert who survives White Burgess Langille Inman v Abbott and Haliburton Co17 2015 SCC 23, where independence is a threshold admissibility question rather than a matter of weight. On acceleration, Golden Hill Ventures Ltd v Kemess Mines Inc18 2002 BCSC 1460 is widely circulated as the leading authority but should not be relied on as such: it is a trial judgment principally on tender disclosure and differing site conditions, and no source attributes an acceleration quantum or loss-of-productivity holding to it. Morrison-Knudsen Co v British Columbia Hydro & Power Authority19 is the safer anchor for the concept, though only for the bare definition ("speeding up the work"), not for a settled multi-element test, which remains unsupported by any verified primary source. See prolongation and delay costs for the full acceleration discussion.

The prolongation and delay costs page sets out the heads and their proof, and the neutral delay analysis methods page covers the methodologies themselves.

§ 07

Check the province before anything else

Four things change at a provincial border, and the first of them decides whether a claim exists at all.

PointWhat is uniform across common-law CanadaWhat changes at the border
DoctrineConcurrency by apportionment. The prevention principle from Perini Pacific. The two-limb LD and penalty test with no Cavendish, Chandos anti-deprivation. Sattva and Ledcor on interpretation. The Bhasin, Callow and Wastech good-faith lineNothing, these are common-law propositions applied nationally
LimitationNothingOntario alone permits commercial parties to extend, shorten, suspend or wholly exclude a limitation period in a business agreement. Alberta, Saskatchewan and Manitoba permit extension only. British Columbia's statute is silent. Quebec permits nothing either way
LiensNothingPreservation and perfection periods differ, and so does whether the lien secures the delay claim at all. Ontario partly, on a price-versus-damages line. Alberta partly, on a directly-related-to-the-liened-work line that is in conflict with no appellate resolution. Quebec effectively not, because delay damages add no plus-value
AdjudicationNothingOntario alone makes an extension of time adjudicable, and only on non-P3 contracts dated on or after 1 January 2026. Alberta is two regimes: the widest consent catch-all in Canada with no cap on private and municipal work under the PPCLA, and delay excluded from adjudication by name on provincial Crown public works under Public Works Act s 14.3(2). The Northwest Territories has prompt payment and no adjudication mechanism at all
TrustsNothingTrust status decides whether a delay-damages set-off exposes the party making it to personal liability for breach of trust. Verified for Ontario, Alberta, British Columbia and New Brunswick. In Alberta the lien fund is not the trust: PPCLA s 22 bites only on payments received after a Certificate of Substantial Performance, so a project abandoned before certification has no trust at all. British Columbia does have a statutory trust (Builders Lien Act ss 10-14, with a second trust at s 5(2) over the holdback account) reaching money received, one tier only, and actionable for a hard one year under s 14

Layer: jurisdictional. The uniform column rests on Supreme Court and appellate authority, the variable column rests on provincial statutes, of which only British Columbia's Builders Lien Act was read in original text, from the BC Laws consolidation. Limitation and lien figures for every other jurisdiction must be checked against the statute before any limitation-critical step.

★ Alberta is the province that most repays reading the row rather than the headline, because it now runs two regimes and they point opposite ways. On private and municipal work the Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 gives the widest consent catch-all in Canada, allows referral up to 30 days after final payment under s 33.4, permits adjudication to run concurrently with litigation. Both since 1 April 2025, under Bill 30 (2024), and imposes no cap. On provincial Crown public works none of that is available: PPCLA s 1.1 excludes public works as defined in the Public Works Act, and agreements with the provincial Crown or a Crown agent, from the PPCLA entirely, and under Public Works Act, RSA 2000, c P-46, s 14.3(2)20, added by Bill 30 (2024) for contracts entered into on or after 1 April 2025, ★ delay is not adjudicable at all: schedule changes, completion and milestone dates, relief events, designated changes in law, remedial actions and force majeure are excluded by name. A cap applies to Public Works Act adjudication and only there, and the figure is CONFLICT between the $200,000 gloss on the Court of Justice Act (Alberta) s 9(1)(i) cross-reference and the $100,000 Alberta Court of Justice civil limit in force since 1 August 2023.

★ The Alberta trust proposition is the one most often stated wrongly. The lien fund is not the trust. PPCLA s 22 creates the trust, and in ATB Financial v DLM Oilfield Enterprises Ltd21, 2020 ABQB 562, decided under the Builders' Lien Act, RSA 2000, c B-7, before the Act was renamed on 29 August 2022 there was no Certificate of Substantial Performance and therefore no trust at all. So a delayed Alberta project terminated or abandoned before certification has no trust, and the major and minor lien funds are something else: owner-held security, each split into Part A, the 10% statutory holdback, and Part B, the amount payable.

Two consequences of that variation are worth stating outright. The first is that a limitation clause in an owner's supplementary conditions is a live risk in Ontario and a nullity in Quebec, but even in Ontario the drafting has to be right, because Ontario (Transportation) v J & P Leveque Bros Haulage Ltd22 2025 ONCA 573 reversed a finding that a ministry contract had validly substituted its own period, on the ground that the clause failed to describe the period clearly, identify its scope and expressly exclude the statutory periods. The second is that the entire Canadian body of adjudication-review law is Ontarian: no reported judicial review of an adjudicator's determination exists in Alberta, Saskatchewan, Manitoba or federally. It consists of Ledore Investments Ltd v Dixin Construction Ltd23 2024 ONSC 598 (Div Ct): a procedural fairness case, not a jurisdictional-error case, in which the adjudicator decided a dispositive issue neither party had raised, and in which the underlying dispute was a delay set-off, and Sayers Foods Ltd v Gay Company Ltd24 2026 ONSC 918 (Div Ct), holding at para 80 that "complexity of a dispute does not oust an Adjudicator's jurisdiction to decide that dispute if it is necessary to do so to rule on a 'matter' properly the subject of an adjudication". Since delay only became adjudicable under the Ontario Construction Act25 on 1 January 2026, Ontario's adjudicated-EOT case law is one case deep. And the Northwest Territories has prompt payment with no adjudication mechanism at all.

The provincial comparison sets out each row with its verification status, including which provinces the corpus could find no source for at all. Three provinces now have enough distinctive machinery to need their own clusters. Ontario, five independent clocks, three date-keyed statutory regimes and an adjudicable extension of time, begins at extension of time in Ontario. ★ Alberta: two Acts rather than one, a lien regime with a wellsite variant, a trust that only starts at substantial performance, a but-for concurrency outlier and a cap on expert evidence begins at extension of time in Alberta. Quebec is civil law and is carved out of everything on this page, it begins at extension of time in Quebec.

§ 08

Six things to unlearn before running a Canadian delay claim

  1. Do not import the English full-EOT rule for concurrency. Canadian courts apportion.
  2. Do not cite Cavendish. It is not Canadian law, and no Ontario decision adopts it.
  3. Do not cite the "Shore & Horwitz formula" as the Supreme Court's holding. The Court used actual audited cost.
  4. Do not treat Ellis-Don v Parking Authority as a disruption case. It is an overhead-formula case with no measured mile.
  5. Do not cite CIMIC 2026 BCCA 2 as an appellate statement of the prevention principle. It is a leave decision, and the underlying award is not public.
  6. Do not assume the province. Limitation variation, lien periods, trust status and adjudication scope all change at the border, and Quebec changes everything.

One further point that is open rather than settled, and worth knowing because it is an available argument: whether a provincial public-health order is a "stop work order" under CCDC 2 GC 6.5.2 has never been decided in Canada. It matters, because GC 6.5.2 carries money as well as time while GC 6.5.3 carries time only. On the same theme, no Canadian judgment holds COVID-19 to be force majeure under a construction contract, 2020–2026, no Canadian authority construes "abnormally adverse weather conditions" in GC 6.5.3.3 or endorses a method of proving it, and there is no Canadian authority on the GC 6.5.3.1 lock-out carve-in or on what counts as a "recognized contractors' association". Each of those is a gap a well-drafted claim can occupy and a gap an opposing party can occupy just as easily.

Notes

Sources and authorities

25 cited
  1. *
    Verification, unless noted

    No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.

  2. 1
    CCDC 2 – 2020, Stipulated Price ContractCanadian Construction Documents Committee, 2020 edition

    GC 6.5 is the delay and extension machinery, 6.5.1 owner and consultant delay, 6.5.2 stop work orders, 6.5.3 other causes including abnormally adverse weather, 6.5.4 the 10-Working-Day notice, 6.5.5 the consultant's failure to furnish instructions. GC 6.6.1 is the separate money notice. GC 10.1.2 adjusts the price for changes in taxes and duties after bid closing, there is no general materials-price escalation clause.

    CCDC

  3. 2
    Atlantic Paper Stock Ltd v St Anne-Nackawic Pulp & Paper Co1975 CanLII 170 (SCC), [1976] 1 SCR 580

    The Canadian force majeure root, a supervening, sometimes supernatural, event beyond the control of either party. Establishes the ejusdem generis reading of a listed catch-all and the author-of-its-own-misfortune bar.

    Find on CanLII

  4. 3
    Naylor Group Inc v Ellis-Don Construction Ltd2001 SCC 58, paras 52–60

    An event already in existence at tender is not supervening, and cannot found a force majeure or unforeseeability argument.

    Find on CanLII

  5. 4
    Elite Construction Inc v Canada (Attorney General)2021 ONSC 562, affirmed on appeal

    A CAD 4.1 million claim dismissed on summary judgment for failure to give notice within 10 working days.

    Find on CanLII

  6. 5
    Technicore Underground Inc v Toronto (City)2012 ONCA 597, Court of Appeal for Ontario

    Strict compliance with a contractual notice provision is required, and the owner need not prove prejudice from the failure to notify.

    Find on CanLII

  7. 6
    Corpex (1977) Inc v The Queen in right of Canada1982 CanLII 213 (SCC)

    A notice provision can bar a claim even without express "failing which" language.

    Find on CanLII

  8. 7
    Ross-Clair v Canada (Attorney General)2016 ONCA 205, Court of Appeal for Ontario

    Failure to provide sufficient information within 30 days after completion is a failure to provide notice of the claim at all. An inadequate claim is not a late claim. It is a non-existent claim.

    Find on CanLII

  9. 8
    Schindler Elevator Corp v Walsh Construction Company of Canada2021 ONSC 283, Ontario Superior Court of Justice

    The leading Canadian concurrency authority, and the source of the Canadian critical-path evidentiary standard. The postponement must be broken into its component parts to apportion the time, responsibility and costs.

    Find on CanLII

  10. 9
    Walsh Construction v Toronto Transit Commission et al2024 ONSC 2782, Ontario Superior Court of Justice

    Functional concurrency, delay-expert credibility and the critique-only trap. A 161-day trial producing a binary 1,047-versus-411-day outcome, and an award of acceleration costs.

    Find on CanLII

  11. 10
    Colautti Construction Ltd v Ottawa (City)1984 CanLII 1969 (ONCA)

    Waiver by conduct, where the owner had repeatedly paid for unauthorised extras. The principal route by which a Canadian claimant escapes a missed notice.

    Find on CanLII

  12. 11
    Northland Kaska Corp v R2001 BCSC 929, Supreme Court of British Columbia

    "The grumblings of a contractor are not sufficient to constitute notice." Complaint, correspondence and site friction are not a contractual notice.

    Find on CanLII

  13. 12
    Perini Pacific Ltd v Greater Vancouver Sewerage & Drainage District(1966), 57 DLR (2d) 307 (BCCA); SCC appeal [1967] SCR 189, 60 DLR (2d) 385, 1967 CanLII 104

    The Canadian prevention anchor. A building owner is not allowed to insist upon the penalty for delay if, by ordering extra work, he has prevented the builder from completing by the specified time.

    Find on CanLII

  14. 13
    CIMIC Morningstar Investments Ltd v Chandos Construction Ltd2026 BCCA 2, Court of Appeal for British Columbia

    Leave to appeal an arbitral award refused. It confirms appellate deference to arbitral awards. It does not restate delay doctrine, and the underlying award is not public.

    Find on CanLII

  15. 14
    Chandos Construction Ltd v Deloitte Restructuring Inc2020 SCC 25, Supreme Court of Canada

    Anti-deprivation. A forfeiture clause triggered by insolvency is void regardless of whether the sum is a genuine pre-estimate, so a delay mechanism can fail on a ground entirely separate from the penalty rule.

    Find on CanLII

  16. 15
    Tercon Contractors Ltd v British Columbia (Transportation and Highways)2010 SCC 4, Supreme Court of Canada

    The three-stage framework governing any exclusion clause, construction, unconscionability at formation, and overriding public policy. It is the only route of attack on a no-damage-for-delay clause in Canada.

    Find on CanLII

  17. 16
    Shore & Horwitz Construction Co Ltd v Franki of Canada Ltd[1964] SCR 589, Supreme Court of Canada

    Supreme Court authority for recovery of unabsorbed head-office overhead at a rate per unit of time, computed from actual audited cost, with head-office overhead assessed at 4.99% of other costs.

    Find on CanLII

  18. 17
    White Burgess Langille Inman v Abbott and Haliburton Co2015 SCC 23, Supreme Court of Canada

    Expert independence and impartiality are a threshold admissibility question, not merely a matter of weight, which is where a delay expert is attacked first.

    Find on CanLII

  19. 18
    Golden Hill Ventures Ltd v Kemess Mines Inc2002 BCSC 1460, Supreme Court of British Columbia

    A trial judgment principally on tender disclosure and differing site conditions, not the leading Canadian acceleration authority as often circulated. Its digest classification carries no acceleration topic, and the characterisation traces to a single non-Canadian secondary source. Its section on time for completion is cited in secondary literature for acceleration of parts of the work, but that holding is unverified against the primary text.

    Find on CanLII

  20. 19
    Morrison-Knudsen Co v British Columbia Hydro & Power AuthorityNo citation obtained. Print no citation and no court

    Defines acceleration as "speeding up the work" or "increasing the rate of performance". Useful for the definition, not for a settled multi-element Canadian test. Two competing four-part formulations of a constructive-acceleration test circulate in secondary literature, attributed respectively to this case and to W A Stephenson. Both are single-source, neither carries a pinpoint, and a submission asserting that "the Canadian courts require the following elements" is currently unsupportable from any verified source. Not to be confused with the unrelated Morrison-Knudsen International Co v Commonwealth of Australia, (1972) 46 ALJR 265 (HCA).

  21. 20
    Public Works Act (Alberta)Public Works Act, RSA 2000, c P-46, s 14.3(2), as amended by Bill 30 (2024), the Service Alberta Statutes Amendment Act, 2024, applying to contracts entered into on or after 1 April 2025

    The separate prompt-payment and adjudication regime for Alberta provincial Crown public works, which the Prompt Payment and Construction Lien Act does not reach because PPCLA s 1.1 excludes public works and agreements with the provincial Crown or a Crown agent. Section 14.3(2) excludes from adjudication changes or delays to a construction schedule, completion and milestone dates, and disputes over the interpretation of relief events, designated changes in law, remedial actions and force majeure events. Every category in which an extension-of-time claim lives, excluded by name. A monetary cap applies to Public Works Act adjudication only, cross-referenced to the Court of Justice Act (Alberta) s 9(1)(i). The corpus records a CONFLICT between the $200,000 commentary gloss and the $100,000 Alberta Court of Justice civil limit in force since 1 August 2023, and neither figure should be printed without reading s 9(1)(i).

    Find on CanLII

  22. 21
    ATB Financial v DLM Oilfield Enterprises Ltd2020 ABQB 562, Court of Queen's Bench of Alberta, decided under the Builders' Lien Act, RSA 2000, c B-7, before the Act was renamed on 29 August 2022

    No Certificate of Substantial Performance had been issued, so no statutory trust existed over a payment made by the owner to the contractor after the contractor's receiver was appointed, and the unpaid subcontractors' unjust-enrichment argument failed because the owner-contractor contract precluded restitution. The trust provision now numbered PPCLA s 22 therefore bites only on payments received after certification, and the major and minor lien funds are separate owner-held security rather than trust property.

    Find on CanLII

  23. 22
    Ontario (Transportation) v J & P Leveque Bros Haulage Ltd2025 ONCA 573, Court of Appeal for Ontario

    A contractual limitation clause must clearly describe the period, identify its scope and expressly exclude the statutory periods. A clause that does not do all three does not displace the statute.

    Find on CanLII

  24. 23
    Ledore Investments Ltd v Dixin Construction Ltd2024 ONSC 598 (Divisional Court)

    The first successful judicial review of an adjudication determination in Canada, decided on procedural fairness, the adjudicator determined a dispositive issue neither party had raised. The underlying dispute was a delay set-off.

    Find on CanLII

  25. 24
    Sayers Foods Ltd v Gay Company Ltd2026 ONSC 918 (Divisional Court)

    "Complexity of a dispute does not oust an Adjudicator's jurisdiction to decide that dispute if it is necessary to do so to rule on a 'matter' properly the subject of an adjudication" (para 80). The first Canadian delay dispute fought through adjudication and surviving judicial review.

    Find on CanLII

  26. 25
    Construction Act (Ontario)RSO 1990, c C.30, as amended with effect from 1 January 2026

    Ontario's prompt-payment, adjudication, lien, holdback and trust scheme. Since 1 January 2026 an extension of time is adjudicable as an ancillary head, on non-P3 contracts entered into on or after that date.

    Find on CanLII

General information, not legal advice. Reviewed Sep 10, 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…