Skip to main content

Privacy

A note about cookies

Essential cookies keep this site running. Optional analytics help us understand what's working, only enabled if you accept.

LIBRARY
United StatesExtension of timeJurisdiction article

No-Damage-for-Delay Clauses: Enforceable in Texas, Void in Ohio

A no-damage-for-delay (NDFD) clause limits a contractor's delay remedy to a time extension only. US enforceability is not uniform: it turns on state law, judicially created exceptions, and, in a minority of states, statutory override that can void the clause outright.

Reviewed Sep 1, 20268 min read22 sources

At a glance

United States
Jurisdiction
United States, state and federal
Governing regimes
State common law and statute · FAR (contrast only)
Evidence basis
Eight states verified from statutory text · eight reported by secondary sources only · case law secondary
§ 00

Key facts

  1. 01

    Default position

    Presumptively enforceable at common law in most states, subject to exceptions.

  2. 02

    Federal contracting

    Not a feature of standard FAR contracting: a CO cannot waive FAR 52.242-14 / 52.243-4 remedies.

  3. 03

    Strongest common-law exception

    Bad faith / active interference: includes refusal to issue warranted time extensions.

  4. 04

    Broadest statutory ban

    Ohio Rev. Code § 4113.62(C): public and private, no unreasonableness qualifier.

  5. 05

    States reaching private contracts

    Ohio, Washington, Kentucky: the exception to the public-works-only pattern.

  6. 06

    Verified statute states

    California, Ohio, Washington, Virginia, Oregon, Minnesota, Missouri, Kentucky (8).

  7. 07

    Secondary-source-only states

    Colorado, Louisiana, North Carolina, Kansas, Nevada, New Jersey, Arizona, Indiana (8), unverified.

  8. 08

    2024–2026 legislative activity

    No new NDFD statute enacted. Energy went to retainage caps (NY SB 5655, CA SB 61).

No-damage-for-delay is the single largest axis of intra-US variation in delay law. The identical clause, in the identical form contract, can be fully enforceable on a project in Houston and void as a matter of public policy on a project in Cleveland. An article, or a claim strategy, that does not name the state has not scoped itself.

§ 01

The general position

NDFD clauses are presumptively enforceable at common law in most US jurisdictions, subject to a set of judicially created exceptions and, in a minority of states, to statutory override. There is no federal common law of NDFD for private work and no uniform national rule: enforceability is decided state by state, and within a state it can turn on whether the project is public or private.

NDFD is not a feature of standard federal construction contracting. FAR 52.242-14 (Suspension of Work) and FAR 52.243-4 (Changes) supply remedies that a Contracting Officer cannot waive by contract drafting. There is no federal analogue to a state NDFD clause sitting inside the standard FAR delay machinery. [GAP, not in corpus: a district court has reportedly held NDFD clauses per se enforceable on federally funded works in California where federal contracting rules displace state law, but the corpus flags this as headline-only and unverified, so it is not asserted here as fact.]

§ 02

The common-law exceptions

Even where no statute applies, an NDFD clause is not absolute. US courts recognize a set of exceptions that let a contractor recover delay damages despite the clause:

  1. Bad faith, active interference, fraud or misrepresentation: the most widely adopted exception, and the one most often successfully invoked. Some jurisdictions extend it to gross negligence. Courts have found active interference in specific owner directives disrupting sequence, administrative mismanagement, an excessive volume of changes, denial of site access, failure to coordinate separate contractors, and refusal to issue warranted time extensions. See Port of Houston Authority v. Zachry Construction Corp.1 (Tex.). This is the same active-interference ground discussed as the NDFD escape hatch in the prevention-principle analysis, and is not re-derived here. See the related article on prevention and time at large.
  2. Delay not contemplated by the parties: an NDFD clause covers only delay that is reasonably foreseeable, arises from the contractor's work during performance, or is mentioned in the contract: Corinno Civetta Constr. Corp. v. City of New York, 67 N.Y.2d 297 (1986)2, the leading US authority. Many jurisdictions reject this exception outright.
  3. Delay so unreasonable in length or duration that it amounts to abandonment of the contract.
  4. Fundamental breach or failure of a condition precedent to performance. Rarely applied.
  5. The clause does not by its terms cover the delay: strict construction against the drafter.
  6. Third-party beneficiary limits: a clause protecting the owner does not automatically protect a construction manager, design professional, or upstream contractor not named in it.
  7. Waiver or estoppel arising from owner conduct, approvals, or representations.
The contractor's own failure to give contractual notice of delay is a complete answer in most jurisdictions, and is expressly preserved by every state anti-NDFD statute surveyed below.
§ 03

The statute survey

Roughly half the states have gone further than the common-law exceptions and enacted a statute voiding or limiting NDFD clauses outright, typically for public work. The corpus draws a hard evidentiary line between statutes verified against statutory text and statutes reported only by secondary sources. That line is preserved below rather than flattened into one undifferentiated list.

Do not read "public work only" as the rule across the board. Ohio, Washington and Kentucky are explicit exceptions that reach private contracts too.

Verified from statutory text

StateCitationScopeEffect
CaliforniaCal. Pub. Contract Code § 71023Public agency contracts and subcontracts thereunderVoid where delay is unreasonable and not within the parties' contemplation. Agencies cannot require waiver of the section. Preserves notice, arbitration/settlement and liquidated damages
OhioOhio Rev. Code § 4113.62(C)(1)–(2)4Public and private. Prime contracts and subcontractsVoid as against public policy where delay is a proximate result of the owner's act or failure to act, with no "unreasonableness" qualifier, the broadest ban in the US
WashingtonRCW 4.24.3605Public and private construction contractsVoid and unenforceable for unreasonable delay caused by the contractee. Preserves notice, arbitration/settlement and reasonable liquidated damages
VirginiaVa. Code § 2.2-4335(A)6Public construction contractsVoid for unreasonable delay caused by acts or omissions within the public body's control, (B) preserves the public body's own recovery, notice, LDs and dispute procedures. Leading case: Blake Constr. Co./Poole & Kent v. Upper Occoquan Sewage Auth., 587 S.E.2d 711 (Va. 2003)7
OregonORS 279C.3158Public improvement contractsVoid for unreasonable delay caused by the contracting agency. Preserves notice, arbitration/settlement and reasonable LDs
MinnesotaMinn. Stat. § 15.4119Public works contracts, state and political subdivisionsSubd. 2 voids waivers of costs, damages or equitable adjustment for entity-caused delay. Subd. 4 preserves notice, reasonable LDs and arbitration
MissouriMo. Rev. Stat. § 8.96210 (post-2022. Formerly § 34.058)Public works contracts, state, counties, cities and political subdivisions, excluding MoDOTVoid where delay is within the public entity's control. Preserves contractor-caused-delay limits, notice, reasonable LDs and arbitration
KentuckyKRS § 371.405(2)(d)11 (Kentucky Fairness in Construction Act)Public and privateVoid: a provision purporting to waive a contractor's right to costs, additional time, or damages for delay within the contracting entity's control. Notice and claim-preservation requirements are not barred by the KFCA. The statute kills the clause, not the time bar

Reported by secondary sources only: verify before citing

StateCitationReported effect
ColoradoColo. Rev. Stat. § 24-91-103.512Public contracts. Voids NDFD for delay caused by the public entity. Citation confirmed by two independent secondary sources. Statutory text not retrieved
LouisianaLa. R.S. 38:2216(H)13Public contracts. Voids NDFD. [UNVERIFIED]
North CarolinaN.C. Gen. Stat. § 143-134.314Public contracts. Unenforceable only where delay is caused solely by the owner or its agent, narrower than most
KansasKan. Stat. Ann. § 16-190715Public contracts. Void, unenforceable, against public policy. [UNVERIFIED]
NevadaNev. Rev. Stat. § 338.48516Public contracts. Unenforceable for unreasonable-length delay or delay from fraud, active interference or scope additions. Private contracts generally enforceable. [UNVERIFIED]
New JerseyN.J. Stat. Ann. § 2A:58B-317Public contracts. Unenforceable where the entity's negligence, bad faith, active interference or other tortious conduct caused the delay. [UNVERIFIED]
ArizonaA.R.S. § 41-261718State governmental contracts. Does not void NDFD outright. Requires a negotiation provision for unreasonable owner-caused delay not within contemplation. [UNVERIFIED]
IndianaNo citation located19Reported as prohibited for unforeseen conditions encountered during a project. [UNVERIFIED] No citation given by the source.

Correcting two circulating errors

Rhode Island has no located NDFD statute. No citation was found despite the search. A construction compendium for the state does not discuss NDFD clauses at all, and a widely circulated 50-state matrix lists Rhode Island among states with no case law on the subject. Rhode Island does have separate statutes on construction indemnity and anti-lien-waiver, but those are different subject matter entirely. Rhode Island appears in several circulating NDFD lists in error: treat any list that shows it as a statutory-ban state as wrong unless a citation is produced. The negative finding is itself the useful fact here.

Oregon is also miscategorized by at least one matrix. The same widely circulated matrix that mislists Rhode Island erroneously groups Oregon among "generally enforceable / no case law" states, but ORS 279C.315, cited in the table above, is on the books and belongs in the verified column, not the unenforceable-with-no-authority one.

§ 04

Three state decisions the corpus was missing

DecisionPoint
Scoccolo Construction v City of Renton, 158 Wn.2d 506 (Wash.)20A utility "acting for" the owner voids the NDFD clause. Directly useful wherever third-party utility delay is in play, and an under-cited point
Plato General Construction v Dormitory Authority of the State of New York21Narrows Corinno Civetta sharply. Do not cite Corinno Civetta's "delay not contemplated" exception in New York without reading Plato first
Asset Recovery Contracting, LLC v Walsh Construction Co.22 (Ill.)Sets out Illinois's four exceptions. The cleanest single-state statement of the exception structure

And the Kentucky refinement, now pinned to a subsection: the KFCA kills the NDFD clause, but notice and claim-preservation requirements survive and are strictly enforced under KRS § 371.405(3)(b), a separate subsection from the delay-waiver ban itself (see the Kentucky row in the verified table above).

§ 05

What 2024–2026 did not bring

No new state statute voiding or limiting NDFD clauses was enacted in 2024, 2025, or the first seven months of 2026. The legislative energy in that window went elsewhere: New York SB 5655 (signed December 2025) and California SB 61 (effective January 2026) both cap retention at 5%. Those bills matter to cash flow during a delay dispute, but they are retainage and prompt-payment law, not NDFD law, and should not be conflated with the subject of this survey.

§ 06

Practice notes

Notice compliance is analyzed separately. See the notice-and-time-bars article in this cluster for the mechanics of what a valid notice requires and when the clock starts.

Notes

Sources and authorities

22 cited
  1. *
    Verification, unless noted

    Verified from statutory text

  2. 1
    Port of Houston Authority v Zachry Construction Corp.(Tex.). Reporter citation not supplied by the source

    Active interference, including refusal to issue warranted time extensions, as an exception to an NDFD clause.

  3. 2
    Corinno Civetta Constr. Corp. v City of New York67 N.Y.2d 297 (1986)

    The leading US authority for the "delay not contemplated by the parties" exception to NDFD clauses. Many jurisdictions reject this exception.

    Find on CourtListener

  4. 3
    California: Cal. Pub. Contract Code § 7102Cal. Pub. Contract Code § 7102 (am. Stats. 1987, ch. 98, § 1)

    Public agency construction contracts and subcontracts thereunder: clauses limiting recovery to a time extension do not preclude damages for unreasonable, uncontemplated delay. Agencies cannot require waiver of the section. Preserves notice, arbitration/settlement and liquidated damages.

  5. 4
    Ohio: Ohio Rev. Code § 4113.62(C)(1)-(2)Ohio Rev. Code § 4113.62(C)(1), (C)(2) (eff. 22 Mar 2001)

    Public and private, prime contracts and subcontracts: void and unenforceable as against public policy where the delay is a proximate result of the owner's act or failure to act, with no "unreasonableness" qualifier, the broadest ban in the US.

  6. 5
    Washington: RCW 4.24.360RCW 4.24.360

    Public and private construction contracts: clauses waiving damages or an equitable adjustment for unreasonable delay caused by the contractee are void and unenforceable as against public policy. The statute preserves notice, arbitration/settlement and reasonable liquidated damages.

  7. 6
    Virginia: Va. Code § 2.2-4335(A)Va. Code § 2.2-4335(A)

    Public construction contracts: void as against public policy for unreasonable delay caused by acts or omissions of the public body within its control, (B) preserves the public body's own recovery, notice, LDs and dispute procedures.

  8. 7
    Blake Constr. Co./Poole & Kent v Upper Occoquan Sewage Auth.587 S.E.2d 711 (Va. 2003)

    Leading Virginia case applying Va. Code § 2.2-4335(A)'s NDFD override.

    Find on CourtListener

  9. 8
    Oregon: ORS 279C.315ORS 279C.315

    Public improvement contracts: void for unreasonable delay caused by the contracting agency. Preserves notice, arbitration/settlement and reasonable liquidated damages.

  10. 9
    Minnesota: Minn. Stat. § 15.411Minn. Stat. § 15.411 (2002 Minn. Laws ch. 299, § 1)

    Public works contracts of the state and political subdivisions: subd. 2 voids clauses waiving rights to costs, damages or an equitable adjustment for entity-caused delay. Subd. 4 preserves notice, reasonable LDs and arbitration.

  11. 10
    Missouri: Mo. Rev. Stat. § 8.962Mo. Rev. Stat. § 8.962 (post-2022. Formerly § 34.058)

    Public works contracts of the state, counties, cities and political subdivisions, excluding MoDOT: void where delay is within the contracting public entity's control. Preserves contractor-caused-delay limits, notice, reasonable LDs and arbitration.

  12. 11
    Kentucky: KRS § 371.405(2)(d) (Kentucky Fairness in Construction Act)KRS § 371.405(2)(d)

    Public and private: void a provision purporting to waive a contractor's or subcontractor's right to costs, additional time, or damages, or an equitable adjustment, for delay within the contracting entity's control. Claim-preservation and notice requirements are not barred by the KFCA and are strictly enforced, and that survival is itself pinned to a separate subsection, KRS § 371.405(3)(b).

  13. 12
    Colorado: Colo. Rev. Stat. § 24-91-103.5Colo. Rev. Stat. § 24-91-103.5

    Reported to void NDFD in public contracts where the delay is caused by the contracting public entity.

  14. 13
    Louisiana: La. R.S. 38:2216(H)La. R.S. 38:2216(H)

    Reported to void NDFD in public contracts.

  15. 14
    North Carolina: N.C. Gen. Stat. § 143-134.3N.C. Gen. Stat. § 143-134.3

    Public contracts: unenforceable only where delay is caused solely by the owner or its agent, narrower than most states in the survey.

  16. 15
    Kansas: Kan. Stat. Ann. § 16-1907Kan. Stat. Ann. § 16-1907

    Reported void, unenforceable and against public policy for public contracts.

  17. 16
    Nevada: Nev. Rev. Stat. § 338.485Nev. Rev. Stat. § 338.485

    Public contracts: reported unenforceable for unreasonable-length delay or delay from fraud, active interference or scope additions. Private contracts generally enforceable.

  18. 17
    New Jersey: N.J. Stat. Ann. § 2A:58B-3N.J. Stat. Ann. § 2A:58B-3

    Public contracts: reported unenforceable where the entity's negligence, bad faith, active interference or other tortious conduct caused the delay.

  19. 18
    Arizona: A.R.S. § 41-2617A.R.S. § 41-2617

    State governmental contracts: does not void NDFD outright. Requires a provision obliging the parties to negotiate recovery for unreasonable, uncontemplated owner-caused delay.

  20. 19
    Indiana: no citation locatedNot supplied by the source

    Reported as prohibited "in the case of unforeseen conditions encountered during a project". No statutory citation given.

  21. 20
    Scoccolo Construction, Inc. v City of Renton158 Wn.2d 506 (Wash.)

    A utility "acting for" the owner falls inside the NDFD clause's scope for purposes of voiding it: third-party utility delay is not automatically outside an NDFD clause's reach just because the utility itself isn't the owner.

  22. 21
    Plato General Construction Corp. v Dormitory Authority of the State of New York(N.Y.)

    Sharply narrows the Corinno Civetta "delay not contemplated by the parties" exception. A court should not apply Corinno Civetta's exception in New York without reading Plato first.

  23. 22
    Asset Recovery Contracting, LLC v Walsh Construction Co.(Ill.)

    Sets out Illinois's four common-law exceptions to NDFD enforceability: the cleanest single-state statement of the exception structure in the corpus.

General information, not legal advice. Reviewed Sep 1, 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…

Each issue links to the full articles in the Storia Library.

No-Damage-for-Delay Clauses in the US: State-by-State Survey · Storia