Claims in United States
Articles12
- Extension of time in United States construction claimsIn US construction, there is no single EOT rule: federal contracting, private AIA-form work, and each state's law on no-damage-for-delay clauses can give materially different answers on the same facts, and critical-path proof is…Reviewed Sep 1, 2026
- Extension of time: the claim clocks in US constructionA 'claim clock' is a contractual or statutory deadline that can extinguish or cap a US construction delay claim if missed. US practice layers three kinds: AIA's 21-day Claim window, FAR's stacked notice/cost-cutoff/proposal…Reviewed Sep 1, 2026
- The Claim-Within-a-Claim Trap in US Notice MachineryNotice-and-time-bar mechanics in US construction turn on structural questions a deadline calendar can't answer: whether a bare time request is itself a Claim, why owner LD assessment skips the Claims machinery entirely, and why a…Reviewed Sep 1, 2026
- There Is No Prevention Principle in US Construction LawUS law has no doctrine called "the prevention principle" and no concept of "time at large." A practitioner trained in English law looking for either will find neither. The same commercial result, that an owner who caused delay…Reviewed Sep 1, 2026
- Concurrent Delay: Why the Contractor's Burden Is the TrapIn US federal practice, concurrent delay is a rule of proof, not substantive law: where both parties contribute to a delay, neither recovers unless the evidence permits clear apportionment, and it is the contractor, not the…Reviewed Oct 6, 2026
- No-Damage-for-Delay Clauses: Enforceable in Texas, Void in OhioA no-damage-for-delay (NDFD) clause limits a contractor's delay remedy to a time extension only. US enforceability is not uniform: it turns on state law, judicially created exceptions, and, in a minority of states, statutory…Reviewed Sep 1, 2026
- Constructive Acceleration: A Claim Parasitic on the EOT ClaimConstructive acceleration is a US claim theory arising when an owner refuses or fails to act on a valid extension-of-time request and instead insists on the original completion date, forcing the contractor to expend extra…Reviewed Sep 1, 2026
- Change orders in the United StatesAmerican change-order practice runs on two doctrines no other jurisdiction this site covers has by name, constructive change and cardinal change, and the most common way a sound change claim dies is not a lost argument about…Reviewed Sep 22, 2026
- Written instruction and waiver in the United StatesWhether a contractor recovers for a change performed without a signed change order depends first on who the owner is. On private work a written-change-order requirement is a contract term the owner can waive by conduct. On state…Reviewed Sep 22, 2026
- Constructive change in the United StatesA constructive change is work beyond the contract requirements that the owner ordered, expressly or impliedly, without issuing a formal change order. On federal construction, FAR 52.243-4(b) treats such an order from the…Reviewed Sep 22, 2026
- Cardinal change in the United StatesA cardinal change is an alteration so drastic that it effectively requires the contractor to perform duties materially different from those originally bargained for. It falls outside the changes clause, so it is a breach of…Reviewed Sep 22, 2026
- Change order releases and reservation of rights in the United StatesA change order release is wording in an executed change order or bilateral modification by which the contractor accepts the stated adjustment as full compensation and gives up further claims arising from the change. Tribunals…Reviewed Oct 6, 2026
The notice brief
One email a month on claims, notices and the cases that decided them.
The notice briefIssue 01 · sample
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.