Written instruction and waiver
A variation is compensable only if instructed, in writing, by the named person, before the cut-off. Whether an unwritten instruction can still be paid for depends entirely on the regime: England enforces the formality, Australia never adopted Rock Advertising, Canada allows waiver on a paid course of dealing, and US public work often treats writing as jurisdictional.
Disponible solo en inglés Este artículo aún no se ha traducido. Los plazos, el derecho a reclamar y el procedimiento descritos aquí rozan lo jurídico, y una traducción automática sería un riesgo de credibilidad más que una comodidad: por eso se sirve el original inglés íntegro hasta que exista una traducción revisada.
At a glance
- Doctrine
- no-oral-modification · waiver by conduct · confirmation of verbal instruction
- England & Wales · United States · Canada · Australia · FIDIC and civil law
Key facts
- 01
The question it answers
Whether work actually performed without a signed change order is recoverable, and what has to be proved to get there in each of five regimes.
- 02
The sharpest divide in the material
On US private work waiver by course of dealing is orthodox. On US public work the writing requirement is often treated as jurisdictional: a limit on the owner's capacity to contract, which estoppel cannot cure. Verified for California, Ohio and Arizona.
- 03
England and Wales
Brenda Vainker & Anor v Marbank Construction Ltd & Ors [2024] EWHC 667 (TCC) is the first English decision to hold the JCT writing requirement squarely a condition precedent to valuing a variation. It is a first-instance decision.
- 04
Australia
Rock Advertising has not been adopted: it "has repeatedly been said not to reflect the position in Australia" (Sara Stockham [2021] NSWCA 51 at [15]). Liebe v Molloy [1906] HCA 67 still governs, and the post-2019 appellate decisions located left the orthodox position undisturbed without deciding it. Only the High Court can displace Liebe.
- 05
Canada
Colautti waiver by conduct requires oral changes actually made and paid for. Dependable Mechanical Systems Inc v Concord Adex Developments Corp, 2026 ONSC 21 holds that informal email is not a binding waiver.
- 06
What waiver always requires
A pattern, not an incident. Transpower Constructors v Grand River Dam Authority, 905 F.2d 1413 (10th Cir. 1990) waived an anti-waiver clause on sustained non-enforcement. Rissler & McMurry, 929 P.2d 1228 (Wyo. 1996) refused waiver where written field orders were regularly issued.
- 07
The route back, and it is short
JCT DB 2024 clause 3.7 and JCT SBC 2024 clause 3.12 let the Contractor confirm an oral instruction in writing within 7 days. Absent written dissent within a further 7 days it takes effect.
- 08
The live open question
Whether Victoria's s. 13A and Western Australia's s. 16 unfair-time-bar powers reach variation formality clauses, as opposed to claim notices, is unresolved. No decision applying either provision was located on AustLII (searched to about June 2026), and adjudication determinations are not generally published.
The contractor did the work. There is no signed change order, and the file contains a verbal direction, a revised drawing and three months of silence. This is the single most consulted question in variation practice, and the answers diverge so sharply between regimes that the same facts produce recovery in Sydney and nothing in London.
Formality is element two of the five-element variation claim, and, across the decisions gathered in this corpus, it kills more claims than any other element. The standard architecture is that a variation is compensable only if it is instructed, in writing, by the named person, before a cut-off, usually practical completion or taking over. Each limb fails independently. Contractors argue about whether they were instructed and lose on writing, on authority, or on timing.
Before any of that matters, the work has to have been outside the contract scope at all. That is a separate question about what the contract already required, and it is worth settling first, because a formality argument about work the contractor was always obliged to perform is wasted effort.
I did the work and there is no written instruction. Is the claim dead?
It depends on the regime, and the spread is the widest in this corpus. England enforces the formality and treats the JCT writing requirement as a condition precedent. Australia never adopted Rock Advertising1 at all. Canada permits waiver on a paid course of dealing. The United States splits internally: private work is the most permissive regime surveyed, public work close to the strictest.
| Regime | Can the written-instruction requirement be defeated? | What it takes | Governing authority |
|---|---|---|---|
| England & Wales | Hardest. No-oral-modification clauses are effective and the JCT writing requirement is a condition precedent to valuation | Estoppel only, on words or conduct beyond the informal agreement itself. In practice, argue that the drawing revision or RFI response was the writing | Rock Advertising Ltd v MWB Business Exchange Centres Ltd [2018] UKSC 24. Brenda Vainker & Anor v Marbank Construction Ltd & Ors2 [2024] EWHC 667 (TCC) |
| United States, private work | Easiest. Waiver by course of dealing is orthodox, and anti-waiver clauses are themselves waivable | A pattern of oral directives, subsequent payment for them, and failure to enforce the writing requirement across the project | Transpower Constructors v Grand River Dam Authority3, 905 F.2d 1413 (10th Cir. 1990) |
| United States, public and federal work | Effectively impossible. The writing requirement goes to the officer's capacity to contract, not to formality | Nothing founded on waiver or estoppel. On federal work, the constructive change route through the Contracting Officer's actual or imputed knowledge | Kaman Aerospace Corporation v Arizona Board of Regents4, 217 Ariz. 148, 171 P.3d 599 (App. 2007). Winter v Cath-DR/Balti Joint Venture5, 497 F.3d 1339 (Fed. Cir. 2007) |
| Canada | Moderate. A written-change-order requirement can be varied by the parties' conduct | Several oral changes actually made and paid for, pleaded as the Owner's own conduct, with quantum meruit kept in the alternative | Colautti Construction Ltd v Ottawa (City)6, 1984 CanLII 1969 (ON CA). (1984) 46 OR (2d) 236 |
| Australia | Most permissive on formality. A no-oral-modification clause cannot prevent the Principal and Contractor orally agreeing to vary | A fresh bilateral bargain with the Principal, or estoppel, but not an effective direction under the contract's own variation clause | Liebe v Molloy7 [1906] HCA 67; (1906) 4 CLR 347. Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd8 (1990) 20 NSWLR 251 |
| FIDIC and civil-law seats | The code outranks the clause. Civil codes generally require the employer's consent, not a written instruction, and consent may be found from conduct | Consent evidenced by correspondence, site records and acquiescence, but the certifier cannot waive contract procedure, and some codes are stricter than FIDIC | Uniform Building Contractors Ltd v Water and Sewerage Authority of Trinidad and Tobago9 [2026] UKPC 2. French Code civil art. 1793, which runs the other way and demands written authorisation |
Jurisdictional. Every row rests on appellate authority (UKSC, Tenth Circuit, Federal Circuit, Ontario Court of Appeal, High Court of Australia, Privy Council) except Vainker, which is first instance in the TCC.
Two cautions on the civil-law row. The first is that France is the counter-example: the marché à forfait rule in Code civil art. 1793 requires the employer's written authorisation for additional works on a lump-sum building contract for a landowner: a statutory formality stricter than FIDIC's, and one that survives contrary contractual drafting. The second is an edition alert. The UAE replaced Federal Law No. 5 of 1985 with Federal Decree-Law No. 25 of 2025. The muqawala provisions moved from Articles 872–896 to 812–839 and the lump-sum rule from Article 887 to Article 829. Whether new Article 829 reproduces the substance of the old rule could not be verified. Every UAE variation memorandum written before 2026 should be treated as potentially out of date.
Why the American answer flips completely on the public/private line
Identify whether the work is public or private before anything else, because in the United States nothing else in the analysis survives that line. On private work a writing requirement can be waived by conduct, "the parties to a written contract are as free to alter it after it has been made as they were to make it". On public work the requirement is frequently not a formality at all but a limit on the contracting officer's capacity, and estoppel cannot cure a capacity defect.
The private-work rule is well populated. Sitkin v Smith10, 35 Ariz. 226, 276 P. 521 (1929) found the parties had "disregarded the contract" and consented to waive the condition. Cardinal Development Co v Stanley Constr. Co11, 497 S.E.2d 847 (Va. 1998) required a pattern of conduct plus payment, on a standard of clear, unequivocal and convincing evidence. Udevco, Inc v Wagner12, 678 P.2d 679 (Nev. 1984) went further and treated oral directives alone as waiver regardless of subsequent payment. Menard & Co Masonry Building Contractors v Marshall Building Systems, Inc13, 539 A.2d 523 (R.I. 1988) found "don't worry about it, you'll be paid" sufficient. Pioneer Roofing Co v Mardian Constr. Co14, 152 Ariz. 455, 733 P.2d 652 (App. 1986) held emergency conditions waive the requirement.
On public work the reasoning changes shape. In California, waiver and estoppel are not available against a public entity at all, on the public-policy ground that the interest in limiting a public entity's contractual obligations outweighs them, the clearest verified strict rule in the material. In Ohio, Foster Wheeler Enviresponse, Inc v Franklin County Convention Facilities Authority15, 78 Ohio St. 3d 353, 678 N.E.2d 519 (1997) held that an engineer or architect cannot waive the written-order requirement absent express authority, even where authorised to approve changes in writing. In Arizona, Kaman Aerospace Corporation v Arizona Board of Regents, 217 Ariz. 148, 171 P.3d 599 (App. 2007) held public entities bound only by agents with actual authority: a sharp public/private split inside a single state, given O'Malley Investment & Realty Co v Trimble16, 5 Ariz. App. 10, 422 P.2d 740 (1967) on the private side.
On American public work the writing requirement is not a formality but a limit on the officer's capacity to contract, and estoppel will not create authority the legislature withheld.
That is why some states describe the requirement as jurisdictional. Treatment as jurisdictional is verified here for California, Ohio and Arizona only. Practitioners routinely add New York and Texas to that list. Neither could be verified in this research pass, and neither should be asserted without independent checking. Two adjacent evidential markers are worth carrying: the Seventh Circuit requires waiver of an anti-waiver clause to be proved by clear and convincing evidence, Wisconsin Electric Power Co v Union Pacific R.R. Co17, 557 F.3d 504 (7th Cir. 2009), and the Court of Federal Claims requires "strong evidence of implied waiver", Public Service Co v United States18, 91 Fed. Cl. 363 (2010).
On federal work the gap is filled not by waiver but by the constructive change doctrine, which substitutes for authority through the Contracting Officer's actual or imputed knowledge. FAR 52.243-4(b) treats any other written or oral order from the Contracting Officer that causes a change as a change order, provided the Contractor gives written notice of the date, circumstances and source and states that it regards the order as a change order. FAR 52.243-4(c) is the exclusivity provision: except as provided in the clause, no order, statement or conduct of the Contracting Officer is to be treated as a change. The (b) notice is the gateway, not housekeeping.
England and Wales after Vainker: writing as a condition precedent
Brenda Vainker & Anor v Marbank Construction Ltd & Ors [2024] EWHC 667 (TCC) is the first English decision to hold the JCT written-instruction requirement squarely a condition precedent to valuing a variation. It was decided on a JCT Standard Building Contract Without Quantities 2011 with amendments and a Contractor's Designed Portion, and it is a first-instance decision. The reasoning is textual and travels to the 2024 forms: only variations instructed in writing or confirmed under the confirmation clause fall to be valued, the Contract Sum may not be adjusted otherwise than in accordance with the express provisions, and variations enter the account only through valuation. There is no alternative mechanism for adjusting the Contract Sum.
Waiver is hard in England because of Rock Advertising Ltd v MWB Business Exchange Centres Ltd [2018] UKSC 24, in which the Supreme Court unanimously held no-oral-modification clauses effective. Lord Sumption, with Lady Hale, Lord Wilson and Lord Lloyd-Jones, put it that party autonomy operates up to the point when the contract is made, but thereafter only to the extent that the contract allows. (A paragraph number for that passage circulates widely from secondary sources. It is not reproduced here because it has not been checked against the judgment.) The Court rejected the inference that an informal agreement to vary carries an implicit agreement to waive the formality. The natural inference from non-compliance is not that the parties intended to dispense with the requirement but that they overlooked it. Lord Briggs concurred on narrower grounds: a no-oral-modification clause binds unless the oral agreement expressly, or by necessary implication, also varies that clause.
Estoppel survives, narrowly. It requires words or conduct unequivocally representing that the variation was valid notwithstanding its informality, and something more than the informal promise itself, and its scope cannot be so broad as to destroy the certainty for which the parties stipulated. Barclays Bank plc v VEB.RF19 [2024] EWHC 3088 (Comm) extends the point to no-waiver clauses, holding that a clause providing no waiver is effective unless in writing and executed by each party is not confined to consensual waivers, unilateral waiver by words or conduct is excluded too.
The practical escape route is not formality but construction. Vainker accepted that an e-mail or the issue of a drawing may be sufficient writing. On a modern project the real question is therefore whether a drawing revision, an RFI response or a meeting minute, objectively construed, amounts to an instruction. That is a construction question, and it is where the argument should be pitched. A contractor arguing that the formality should be excused loses. A contractor arguing that a revised drawing issued for construction was objectively an instruction to build something different has a case.
Australia never adopted Rock Advertising, and that changes the answer
In Australia a no-oral-modification clause cannot prevent the parties from orally agreeing to vary the contract. Party autonomy is treated as continuing after formation, and the clause is relevant context in deciding whether the parties in fact intended to vary, not a binding constraint. The foundational authority is Liebe v Molloy [1906] HCA 67; (1906) 4 CLR 347, and it is a construction case about extras: a requirement for written orders bars recovery under the contract but "does not exclude altogether" recovery on a separate promise to pay, which may be inferred from the owner's conduct. The owner's knowledge alone is not enough, and the High Court remitted whether such a promise was made to the umpire rather than holding the owner liable.
Rock Advertising has not been adopted. In Bundanoon Sandstone Pty Ltd v Cenric Group Pty Ltd. TWT Property Group Pty Limited v Cenric Group Pty Limited20 [2019] NSWCA 87 at [122], Gleeson JA noted the primary judge's orthodox holding, which was not directly challenged, and found it unnecessary to discuss Rock Advertising. In White v Philips Electronics Australia Ltd21 [2019] NSWCA 115 at [43], Bell P observed, obiter, that no-oral-modification clauses "provide important context" in deciding whether the parties intended to vary. Both left the orthodox Australian position undisturbed without deciding it. Displacing Liebe v Molloy would require the High Court. The negative finding, stated at the strength of the search: no Australian appellate decision located since 2019 has adopted Rock Advertising, and the NSW Court of Appeal has said it "has repeatedly been said not to reflect the position in Australia" (Sara Stockham Pty Ltd v WLD Practice Holdings Pty Ltd [2021] NSWCA 51 at [15], Leeming JA, without deciding the point). The equitable limb runs through Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd (1990) 20 NSWLR 251.
That does not make an oral direction costless under AS 4000:2025. Clause 36.1 (in the 1997 edition as well as 2025) makes writing constitutive: a variation is effective only where directed in writing by the Superintendent and before the Date of Practical Completion, and the 2025 edition now allows Practical Completion to occur before the certificate issues, so the window may close earlier than the paperwork suggests (the sub-clause numbering for Practical Completion in the 2025 edition is reported inconsistently across published summaries and is not given here). The synthesis has three steps. An oral instruction is not an effective clause 36 direction, so the Superintendent's pricing machinery in clause 36 is never engaged and the contractual route is closed. It does not prevent the Principal and Contractor making a binding subsequent oral or implied agreement. It does not displace estoppel. But both surviving routes require proof of consensus with the Principal, not merely a direction from a Superintendent or site representative: a materially harder evidentiary case, and precisely the risk shift the written-direction rule achieves (a rule already in AS 4000-1997, which firm summaries report the 2025 edition restated and tightened).
The statutory overlay that may cut across all of it
Two Australian statutes may now reach formality clauses, and whether they do is undecided. Section 13A of the Building and Construction Industry Security of Payment Act 2002 (Vic), commenced 15 April 2026 and applying to contracts entered into before, on or after that date (s 54(1), subject to the s 54(2) carve-out for payment claims served, and adjudication applications made but not determined, before commencement), and section 16 of the Building and Construction Industry (Security of Payment) Act 2021 (WA), for contracts entered on or after 1 August 2022, allow an adjudicator, court, arbitrator or expert determiner to declare a notice-based time bar unfair where compliance is not reasonably possible or would be unreasonably onerous. The provision then has no effect in that particular case only.
For variation claim notices the position is clear: a clause barring a claim not notified within 7 or 14 days of a direction is a paradigm notice-based time bar, and these provisions reach it, which is why the Victorian and Western Australian analysis now belongs alongside the ordinary notice and time bar analysis. For variation formality clauses (provisions limiting recovery to work performed after scope approval, rather than barring an unnotified claim) the position is genuinely unresolved. The Victorian definition of "notice" is inclusive and may capture them (Inference); Clayton Utz flags a related point, that determiners might be empowered to invalidate notice clauses which bar recovery of costs incurred before the giving of notice, but it does not discuss scope approval or written directions. No decision applying Victoria's s 13A or Western Australia's s 16 was located on AustLII (searched to about June 2026), and adjudication determinations are not generally published. That is the whole of what can be said. If clause 36.1's written-direction requirement were held capable of being declared unfair, the Principal's central protection under clause 36.1 would be substantially undercut in Victoria.
Canada: Colautti waiver by conduct, and its 2026 counterweight
Canada sits between England and Australia. Colautti Construction Ltd v Ottawa (City), 1984 CanLII 1969 (ON CA). (1984) 46 OR (2d) 236 is the leading authority that a written-change-order requirement can be waived or varied by conduct. Cory J.A. held that the parties, by their conduct, had varied the terms of the contract requiring extra costs to be authorised in writing, so that the City could not rely on its strict provisions to escape liability. The appeal was allowed and a new trial ordered.
Two limits have to be stated with the case or it is being cited too widely. First, the finding rested on several oral changes made and paid for: a demonstrated course of dealing, not informal comfort. One unpaid oral instruction will not do it. Second, the onus stays on the contractor: in D & M Steel Ltd v 51 Construction Ltd22, 2018 ONSC 2171 the builder failed on the extras because there was no evidence of approvals for the specific change orders beyond its own uncorroborated evidence. Acquiescence plus a bare oral assertion is not enough.
The modern limit is Dependable Mechanical Systems Inc v Concord Adex Developments Corp23, 2026 ONSC 21, in which the court gave effect to a contractual requirement of written notice within seven working days and held that informal email statements may not constitute a binding waiver of escalation claims. Cite it alongside Colautti: informal comfort is not waiver.
Note also what the CCDC prohibition does and does not do. CCDC 2 – 2020 GC 6.1.2 provides that the Contractor shall not perform a change in the Work without a Change Order or a Change Directive. That is a prohibition on the Contractor, not by its terms a bar on recovery for work actually directed and performed, which is why Colautti does so much work in Canada. And there is a recorded negative finding that shapes the pleading: no Canadian appellate decision on the ostensible authority of a CCDC Consultant to bind an Owner to an extra was located. Given GC 2.1.1's express limitation, plead Colautti waiver by the Owner's own conduct rather than ostensible authority of the Consultant. A counterparty who has read the contract cannot easily assert reliance on apparent authority contradicted by an express clause.
Do anti-waiver clauses waive themselves?
Sometimes. This is a United States question, and the distinction that decides these cases is pattern versus incident. A course of conduct waives. A single indulgence does not, and the threshold is the same wherever waiver is available at all. Transpower Constructors v Grand River Dam Authority, 905 F.2d 1413 (10th Cir. 1990) held that anti-waiver clauses are themselves subject to waiver through a consistent practice of non-enforcement. Rissler & McMurry Co v Sheridan Area Water Supply Joint Powers Bd24, 929 P.2d 1228 (Wyo. 1996) found no waiver where written field orders were regularly issued throughout construction and later rolled into change orders.
The two cases are not in conflict. In Transpower the formality had been abandoned in practice. In Rissler & McMurry it had been observed, and one departure from an observed practice proves nothing. O'Malley Investment & Realty Co v Trimble, 5 Ariz. App. 10, 422 P.2d 740 (1967) puts the Arizona private-work position more strongly still: parties are "wholly unable" to limit future contractual action by a present provision, so an anti-waiver clause cannot bind prospectively.
Across every regime that permits waiver at all, the practical threshold is the same and it is high: repeated, documented, employer-level acceptance of the very informality now disavowed (signing, certifying and paying informal variations over a sustained period) plus contractor reliance. The onus sits on the contractor everywhere. This is the evidence that builds that case, and it has to be assembled contemporaneously, because it cannot be reconstructed at the end of a job.
Who may instruct is a separate question from whether it was written
A written instruction from the wrong person is worth no more than an oral one from the right person, and the two failures are routinely confused. Every standard form names the person whose instruction adjusts the price, and on every project someone with less authority than that gives directions which the contractor follows. The doctrinally sound route out is not ostensible authority (which runs into the express limitation) but the principal's own conduct. The table below states form-default positions: bespoke amendment to the instruction and authority provisions is normal on major projects, and the executed contract governs.
| Form and edition | Who may instruct a change | The trap |
|---|---|---|
| JCT DB 2024 | The Employer, cl 3.9. There is no Architect or Contract Administrator in Design and Build | The Employer's Agent is not the Employer. Its authority depends entirely on the terms of the appointment: see Clerkenwell Lifestyle (UK) Ltd v HG Construction Ltd26 [2026] EWHC 1406 (TCC), where Jefford J said, obiter (¶¶95–101), that the Employer's Agent lacked authority to bind |
| JCT SBC 2024 | Architect / Contract Administrator, cl 3.14 | The CA is the Employer's agent for instructions but a certifier for valuation. It cannot waive the Employer's procedural protections |
| NEC4 ECC | Project Manager, cl 14.3 | There is no writing formality for a Scope change, cl 14.3 is the power and cl 60.1(1) the consequence. The formality bites on notification under cl 61.3 instead |
| FIDIC Red / Yellow 2017 | Engineer, SC 13.1 / 13.3.1 | SC 3.1 gives the Engineer no authority to amend the Contract. Only the parties can waive |
| FIDIC Silver 2017 | The Employer directly. There is no Engineer | Removes the neutral determiner entirely |
| AIA A201–2017 | Change Order §7.2: Owner, Contractor and Architect. Construction Change Directive §7.3: Owner and Architect, without the Contractor's signature. Minor Change §7.4: Architect alone, only where Sum and Time are unaffected | §7.4 carries a waiver trap: a Contractor who believes a minor change will affect Sum or Time must notify the Architect and not proceed, failing which it waives the adjustment. Field and inspection personnel bind nobody |
| FAR construction | Only the Contracting Officer | Winter v Cath-DR/Balti Joint Venture, 497 F.3d 1339 (Fed. Cir. 2007) rejected an implied-authority delegation theory. FAR 52.243-7 (JAN 2017) requires a Specifically Authorized Representative's communications to be reduced to writing promptly |
| CCDC 2 – 2020 | Consultant prepares, GC 2.2.14, Owner signs a Change Directive, Owner and Contractor sign a Change Order | GC 2.1.1 limits the Consultant to acting for the Owner only as the Contract Documents provide, and GC 2.1.2 allows those limits to be modified only by tripartite written consent |
| AS 4000:2025 | Superintendent, cl 36.1, in writing, before the Date of Practical Completion | A written instruction from the Principal direct to the Contractor is not a cl 36.1 direction |
Form-default. Who may instruct is read off the published forms. The trap column is the corpus's reading. Bespoke amendment is normal, and the executed contract governs.
The certifier's inability to waive is now settled at the highest level available. In Uniform Building Contractors Ltd v Water and Sewerage Authority of Trinidad and Tobago [2026] UKPC 2, on FIDIC, Sir Peter Coulson held that the Engineer's role is administrative and certifying, not constitutive of the parties' contractual rights, and that the Engineer cannot waive procedural requirements or dispense with notice, because that would amend the contract beyond its delegated authority. Only the parties can waive. The reasoning is general and applies with equal force to a Contract Administrator, a Project Manager and a Consultant.
Which is exactly why the pleading order matters. Vim Engineering Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd [2023] SGHC(A) 2 makes the point cleanly: at first instance the project manager lacked authority to waive the written-instruction requirement, and yet the Appellate Division found that the employer had waived it by its own representatives' conduct across 32 signed claims. The formality can be waived by the party whose protection it is, even where its agent could not have waived it.
The confirmation route almost nobody uses, and what to do this week
Most standard forms contain a route that converts an oral instruction into a written one, and it is rarely used on site and frequently decisive in the ensuing dispute. Under JCT DB 2024 clause 3.7 and JCT SBC 2024 clause 3.12, an instruction given otherwise than in writing has no immediate effect, but the Contractor may confirm it in writing within 7 days, and if the Employer or Architect does not dissent in writing within a further 7 days, the instruction takes effect at the expiry of the second period.
The rest of the machinery is worth knowing in the same breath. The Employer or Architect may instead confirm at any time before the Final Payment or Final Certificate, and under JCT SBC 2024 the Architect may sanction in writing a Variation made without instruction. JCT retained the procedure unchanged in the 2024 suite. Under FIDIC 2017 Sub-Clause 3.5, where the Engineer issues an instruction not identified as a Variation which the Contractor considers to be one, the Contractor must give Notice immediately and before commencing the work, and the Engineer must respond within 7 days by confirming, reversing or varying it. Under FAR 52.243-4(b) the notice must state the date, circumstances and source of the order and that the Contractor regards it as a change order. Both elements are mandatory.
So, concretely, the same week:
- Send the confirmation letter within seven days, to the named person. Under JCT that is the Employer under DB 2024 or the Architect/Contract Administrator under SBC 2024, under FIDIC the Engineer, under AS 4000:2025 the Superintendent, under FAR the Contracting Officer. A confirmation addressed to the wrong person is worthless. Under AS 4000 this letter does double duty, because the Superintendent's failure to dissent is the evidentiary bridge to agreement or estoppel with the Principal.
- Describe the direction, not the entitlement. Date, who gave it, what was said, what work it requires. The claim can be priced later. The record cannot be created later.
- Diarise the second seven days and check whether a dissent arrived. If it did, the argument moves immediately to whether the direction was a variation at all.
- Keep the alternative pleading alive from day one. Instructed variation first, then constructive or deemed variation, then waiver or estoppel, then quantum meruit. Waiver pleaded on its own is the weakest position available in every regime surveyed, and in three of them it is not available at all.
- Read the supplementary conditions before relying on any of this. Employer amendments routinely tighten the confirmation clause or delete the deemed-effect limb, and Part 6 of CCDC 2 – 2020 is almost universally amended.
Sources and authorities
- 1Rock Advertising Ltd v MWB Business Exchange Centres Ltd[2018] UKSC 24 (16 May 2018), UK Supreme Court
No-oral-modification clauses are enforceable, and something more than the informal promise itself is needed before estoppel will defeat one.
- 2Brenda Vainker & Anor v Marbank Construction Ltd & Ors[2024] EWHC 667 (TCC), Technology and Construction Court
The JCT written-instruction requirement is a condition precedent to valuing a variation. The first English decision to hold it squarely. An e-mail or the issue of a drawing may be sufficient writing.
- 3Transpower Constructors v Grand River Dam Authority905 F.2d 1413 (10th Cir. 1990), United States Court of Appeals for the Tenth Circuit
An anti-waiver clause is itself subject to waiver where the writing requirement was abandoned in practice through a consistent course of non-enforcement.
- 4Kaman Aerospace Corporation v Arizona Board of Regents217 Ariz. 148, 171 P.3d 599 (App. 2007), No. 2 CA-CV 2006-0177, Arizona Court of Appeals, Division 2, 23 August 2007
A public entity is bound only by agents with actual authority, so on public work the written-instruction requirement cannot be defeated by waiver or estoppel.
- 5Winter v Cath-DR/Balti Joint Venture497 F.3d 1339 (Fed. Cir. 2007), United States Court of Appeals for the Federal Circuit
Only a person with actual or imputed authority can bind the government to a change. An argument for implied delegation of the Contracting Officer's authority was rejected.
- 6Colautti Construction Ltd v Ottawa (City)1984 CanLII 1969 (ON CA) · (1984) 46 OR (2d) 236, Court of Appeal for Ontario
The parties, by their conduct, had varied the terms of the contract requiring extra costs to be authorised in writing, so the City could not rely on its strict provisions to escape liability. The finding rested on several oral changes actually made and paid for.
- 7Liebe v Molloy[1906] HCA 67; (1906) 4 CLR 347, High Court of Australia (Griffith CJ for the Court)
A requirement that extras be ordered in writing bars recovery under the contract but "does not exclude altogether" recovery on a separate promise to pay, express or implied from the owner's conduct. The owner's knowledge alone is not enough. Whether such a promise was made was remitted to the umpire; the Court did not hold the owner liable.
- 8Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd(1990) 20 NSWLR 251, New South Wales Court of Appeal
Carries the equitable limb in Australia: where the contractual variation machinery was not engaged, estoppel may still support payment for the work directed.
- 9Uniform Building Contractors Ltd v Water and Sewerage Authority of Trinidad and Tobago[2026] UKPC 2 (22 January 2026), Privy Council, on appeal from Trinidad and Tobago
The Engineer's role is administrative and certifying, not constitutive of the parties' contractual rights. The Engineer cannot waive procedural requirements or dispense with notice, because that would amend the contract beyond the delegated authority. Only the parties can waive.
- 10Sitkin v Smith35 Ariz. 226, 276 P. 521 (1929), Supreme Court of Arizona
The parties had "disregarded the contract" and by consent waived the written-order condition. The private-work starting point in Arizona.
- 11Cardinal Development Co v Stanley Constr. Co497 S.E.2d 847 (Va. 1998), Supreme Court of Virginia
Waiver of a written-change-order requirement on private work requires a pattern of conduct plus payment, proved to a standard of clear, unequivocal and convincing evidence.
- 12Udevco, Inc v Wagner678 P.2d 679 (Nev. 1984), Supreme Court of Nevada
Oral directives alone were treated as waiver of the writing requirement, regardless of whether payment followed. The most permissive of the private-work authorities surveyed.
- 13Menard & Co Masonry Building Contractors v Marshall Building Systems, Inc539 A.2d 523 (R.I. 1988), Supreme Court of Rhode Island
An assurance that the contractor should not worry and would be paid was sufficient to waive the written-order requirement.
- 14Pioneer Roofing Co v Mardian Constr. Co152 Ariz. 455, 733 P.2d 652 (App. 1986), Arizona Court of Appeals
Emergency conditions waive the written-instruction requirement on private work.
- 15Foster Wheeler Enviresponse, Inc v Franklin County Convention Facilities Authority78 Ohio St. 3d 353, 678 N.E.2d 519 (1997), Supreme Court of Ohio
An engineer or architect cannot waive a written-order requirement on public work absent express authority, even where authorised to approve changes in writing.
- 16O'Malley Investment & Realty Co v Trimble5 Ariz. App. 10, 422 P.2d 740 (1967), Arizona Court of Appeals
Parties are "wholly unable" to limit their future contractual action by a present provision, so an anti-waiver clause cannot bind prospectively on private work.
- 17Wisconsin Electric Power Co v Union Pacific R.R. Co557 F.3d 504 (7th Cir. 2009), United States Court of Appeals for the Seventh Circuit
Waiver of an anti-waiver clause must be proved by clear and convincing evidence.
- 18Public Service Co v United States91 Fed. Cl. 363 (2010), United States Court of Federal Claims
Implied waiver requires "strong evidence", the federal evidential marker alongside the Seventh Circuit's clear-and-convincing standard.
- 19Barclays Bank plc v VEB.RF[2024] EWHC 3088 (Comm), London Circuit Commercial Court (KBD)
A clause providing that no waiver is effective unless in writing and executed by each party is not confined to consensual waivers: unilateral waiver by words or conduct is excluded too.
- 20Bundanoon Sandstone Pty Ltd v Cenric Group Pty Ltd. TWT Property Group Pty Limited v Cenric Group Pty Limited[2019] NSWCA 87 (30 April 2019), New South Wales Court of Appeal, Gleeson JA (Meagher and McCallum JJA agreeing), a consolidated appeal
At [122], Gleeson JA noted the primary judge's holding that a no-oral-modification clause cannot prevent the parties agreeing orally to vary, which was not directly challenged, and found it unnecessary to discuss Rock Advertising. The orthodox Australian position was left undisturbed without being decided afresh.
- 21White v Philips Electronics Australia Ltd[2019] NSWCA 115 (17 May 2019), New South Wales Court of Appeal, Bell P (Basten and Gleeson JJA agreeing)
No oral variation was proved on the facts, so the court did not decide whether a no-oral-modification clause precludes oral variation ([42]). Bell P observed, obiter, that such clauses, "even if not necessarily preclusive of oral modifications, provide important context" in deciding whether the intention to vary exists ([43]).
- 22D & M Steel Ltd v 51 Construction Ltd2018 ONSC 2171, Ontario Superior Court of Justice
The builder failed on the extras because there was no evidence of approvals for the specific change orders beyond its own uncorroborated evidence. The onus stays on the contractor.
- 23Dependable Mechanical Systems Inc v Concord Adex Developments Corp2026 ONSC 21, Ontario Superior Court of Justice
A contractual requirement of written notice within seven working days was given effect, and informal email statements may not constitute a binding waiver of escalation claims. The modern counterweight to Colautti.
- 24Rissler & McMurry Co v Sheridan Area Water Supply Joint Powers Bd929 P.2d 1228 (Wyo. 1996), Supreme Court of Wyoming
No waiver where written field orders were regularly issued throughout construction and later rolled into change orders, one departure from an observed practice proves nothing.
- 25Vim Engineering Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd[2023] SGHC(A) 2, Appellate Division of the High Court of Singapore, on appeal from [2021] SGHC 63
The employer's representatives had signed 32 of 34 variation claims and stayed silent. The employer had waived the written-instruction requirement by its own conduct, even though its project manager could not have waived it.
- 26Clerkenwell Lifestyle (UK) Ltd v HG Construction Ltd[2026] EWHC 1406 (TCC), Technology and Construction Court
Jefford J enforced an adjudicator's decision for £955,943.43. The main holding (¶¶91, 94): the EOT emails were the contractual mechanism operating, and no binding agreement was made on 8 February 2023. Obiter, as a fall-back (¶¶95–101): an Employer's Agent under a JCT Design and Build contract lacked authority to bind the Employer to such an agreement. The Agent is not the Employer, and its authority depends entirely on the terms of its appointment.
General information, not legal advice. Reviewed 13 oct 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…