Oil, gas and industrial delay claims in Alberta
Alberta's oil, gas and industrial construction is the highest-value, least-precedented delay environment in Canada. There is no standard EPC or EPCM form, no turnaround authority, no winter authority and no regulatory-delay authority, but there is a distinctive lien regime: 90 days on a well site, and registration with the Minister of Energy where the minerals are Crown-owned.
At a glance
- Alberta, Canada, common law
- PPCLA, RSA 2000, c P-26.4 (from 29 August 2022) · Builders' Lien Act, RSA 2000, c B-7 (before that date) · Public Works Act, RSA 2000, c P-46
- Bespoke owner-drafted EPC and EPCM · CCDC 17 – 2025 · CCDC 18 – 2023 · no Canadian standard EPC or EPCM form exists
- Secondary sources, no judgment or consolidated statute read in original text
Key facts
- 01
The short answer
This is the layer that makes Alberta different from every other Canadian province, and the layer with almost no law in it. The lien regime has real, distinctive rules. Beyond the lien regime there is very little: no standard form, no turnaround authority, no winter authority, no regulatory-delay authority.
- 02
The contract form
There is no Alberta or Canadian standard EPC or EPCM form in common use. Alberta industrial owners use bespoke owner-drafted forms. CCDC 2 – 2020 GC 6.5 will usually be irrelevant, do not open the analysis with it.
- 03
The lien clock
90 days for an improvement to an oil or gas well or oil or gas well site, against the general 60. On a mixed site the two clocks run side by side and a single contractor can be on both.
- 04
The registry
Where the minerals are Crown-owned, roughly 81 per cent of Alberta mineral rights, the lien attaches to the mineral and is registered with the Minister of Energy, not at Land Titles. Getting the registry wrong is fatal.
- 05
Turnarounds and shutdowns
No Alberta or Canadian judicial authority was located on delay or disruption in a turnaround or shutdown. The disputes appear to be arbitrated under bespoke owner forms and never reported, and that is itself the finding.
- 06
Winter
No Alberta authority on winter work, labour availability, camp or fly-in-fly-out constraints as excusable events. The working rule is that winter is not excusable unless it is a 10-year outlier or the contract carries a seasonal-shutdown clause.
- 07
Regulatory delay
No Alberta authority treats Alberta Energy Regulator approval delay as an extension-of-time ground. Two public-sector contract hooks exist, on a private industrial job you have neither unless you drafted one.
- 08
Which Act
Private industrial work runs on the PPCLA, RSA 2000, c P-26.4, liens, adjudication, no cap. Provincial Crown public works run on the Public Works Act, RSA 2000, c P-46. No liens, delay expressly not adjudicable, 45-day registered-mail notice.
Alberta's oil, gas and industrial construction is the highest-value and least-precedented delay environment in Canada. There is one distinctive body of real rules (the lien regime on wellsites and mineral titles) and, beyond it, close to nothing: no standard EPC or EPCM form, no turnaround authority, no winter authority, no regulatory-delay authority. The absence is the finding, and it should be published as such rather than papered over with general Canadian doctrine.
That framing is not an apology for thin research. It is the operative advice. A practitioner arriving from Ontario, England or the United States expects to reason from a form and a line of cases, and on an Alberta oil sands, wellsite, pipeline or plant job there is usually neither. What there is instead is a bespoke owner-drafted contract, an arbitration clause, and a lien regime that behaves differently from every other province except Saskatchewan.
This page sits under the Alberta place hub, which carries the two Acts, the citation eras and the Alberta authority map. General Canadian delay doctrine: force majeure, concurrency, liquidated damages, prolongation quantum, lives at the Canada hub and is not repeated here.
Why wellsite, oil sands, pipeline and industrial work is not building work
Five things change at once: the schedule is often a fixed production window rather than a completion date, the site is remote and staffed by camp or rotational labour, the work sits on mineral titles rather than ordinary fee simple land, the contract is bespoke rather than standard, and the disputes are arbitrated in private. The result is a category with enormous exposure and almost no citable Alberta law.
The single most consequential difference for a delay claim is the loss. On a building project the delay loss is extended preliminaries and site overhead. On an Alberta industrial project (most sharply on a turnaround) the dominant loss is deferred production. That is not a head of loss the Canadian prolongation authority was built to price, and this page states that as an inference from the case law, not as something a Canadian court has held.
The second difference is that the security analysis starts earlier and matters more. On private industrial work the Prompt Payment and Construction Lien Act1, RSA 2000, c P-26.4 gives a lien, and the lien period depends on how the work is characterised before anyone reaches the merits. On provincial Crown public works there is no lien at all. Which of those two you are on is dealt with in the last substantive section below, and it should be settled on day one.
There is no Canadian standard EPC or EPCM form. So the drafting is the entire answer
No Alberta or Canadian standard EPC or EPCM form is in common use, analogous to FIDIC Silver or NEC4. Nothing surfaced from CCDC, the Alberta Construction Association, the PJVA, whose model agreements are Construction, Ownership and Operation joint-venture agreements, not construction contracts. CAPP, or any Alberta association. On Alberta industrial work there is no default extension-of-time clause to reason from.
What is published and used is CCDC 17 – 2025 and CCDC 18 – 20232, CCDC 17 being the Stipulated Price Contract between Owner and Trade Contractor, both supplemented for Alberta by the Alberta Construction Association. Neither is an EPC or EPCM form. Beyond them, Alberta industrial owners use bespoke owner-drafted EPC and EPCM agreements. That last statement is recorded as UNVERIFIED as a general practice claim, but it is consistent with the complete absence of any published form.
The practical consequence is blunt. Do not open an Alberta industrial delay analysis with CCDC 2 – 20203 GC 6.5. GC 6.5.4's 10 Working Days from the commencement of the delay, and GC 6.6.1's untimed "timely" requirement for money, are the Canadian building default and they will usually be irrelevant to the contract in front of you. Every turnaround or EPCM delay claim is a pure construction-of-the- bespoke-contract exercise: the notice trigger, the notice period, the definition of the excusable event, the relief available and the exclusions all have to be read from the document rather than assumed.
Two consequences follow for research. First, there is no Alberta case law construing an EPC or EPCM extension-of-time clause, so comparative reasoning from FIDIC or NEC4 commentary is argument, not authority. Second, even the CCDC question is open in Alberta: it is UNVERIFIED whether the Alberta Construction Association's supplementary conditions to CCDC 2 – 2020 amend GC 6.5 at all, the corpus records that as the top Alberta verification gap. And the corpus also records that no Consulting Engineers of Alberta recommended supplementary conditions to CCDC 2 exist and no City of Edmonton general conditions were located. Ontario's equivalent question has a clean answer. Alberta's does not.
| Building work in Alberta | Industrial, oil and gas work in Alberta | |
|---|---|---|
| Default form | CCDC 2 – 2020, widely used | None, bespoke owner-drafted EPC or EPCM |
| Default EOT clause | GC 6.5, notice for time within 10 Working Days | No default clause exists |
| Supplementary conditions | ACA package published, effect on GC 6.5 UNVERIFIED | Owner's own schedule of amendments |
| Case law construing the clause | Thin, and none on methodology | None located |
| Lien period | 60 days | 90 days for well and well-site work, 60 for the rest |
| Typical forum | Court or arbitration | Arbitration, unreported |
Layer: form-default in the first two rows, inferential in the last two. Every row rests on secondary sources. No form text and no judgment was read in original form.
Turnarounds and shutdowns: the highest-value delay category in Alberta, with no authority at all
No Alberta or Canadian judicial authority was located on a delay or disruption claim arising out of a turnaround or shutdown. Searches returned only industry-operations material and unrelated regulatory litigation. This is the highest-value and least-precedented delay category in the province, and the void is not an artefact of searching badly, it is what happens when a whole category of dispute is arbitrated privately under bespoke owner forms.
Turnaround delay disputes appear to be arbitrated under bespoke owner forms and never reported, which is itself the finding, and is consistent with the absence of any standard form and with Alberta's pro-finality arbitration line.
Turnaround delay analysis is not building delay analysis. A turnaround is an extreme-compression, fixed-window, resource-saturated scope in which the critical path is measured in shifts rather than weeks, the baseline is a countdown to re-start rather than a completion date, and the dominant loss is deferred production rather than extended preliminaries. None of the Canadian prolongation authority was decided on facts like these. Nor is there any Alberta help on method: the corpus records no Alberta decision on delay-analysis methodology at all, so the choice among the recognised delay analysis methods is made on persuasion and on the contract, not on Alberta precedent.
What a claimant actually does in the absence of precedent:
- Plead the contract, not the doctrine. With no standard form and no case law, the clause is the claim. Establish the notice trigger and period from the document, then prove compliance to the letter.
- Build the record contemporaneously and at shift resolution. A countdown baseline measured in shifts cannot be reconstructed afterwards from monthly progress reports.
- Keep the productivity record on this project. The closest structural Alberta authority is Krupp Canada Inc v JV Driver Projects Inc4, 2014 ABQB 259, JV Driver being a major Alberta industrial and oil sands contractor which held that delay damages form part of a lien only where they relate directly to the work that is the subject of the lien: lost productivity on the liened project yes, inability to work elsewhere no. The corpus flags CONFLICT on what Krupp holds, one source reading it as permitting lienable delay damages and another indexing it for the opposite, and the later and narrower PME Inc v Enerkem Alberta Biofuels LP5, 2021 ABQB 889 does not cite it. Both are cited to the Builders' Lien Act6, RSA 2000, c B-7, because both predate the 29 August 2022 renaming. There is no Alberta appellate resolution, so the line is factual rather than categorical. Even so, Krupp's distinction is a sensible discipline for the claim as well as the lien.
- Expect arbitration, and expect it to be final. In Quanta Canada Holdings II ULC v Bremar Construction Ltd7, 2024 ABKB 317 the Court of King's Bench refused permission to appeal an award on an $8,137,116 delay-and-defects claim because delay causation is mixed fact and law, so no question of law arises under Arbitration Act s 44(2). Arbitrating an Alberta delay dispute is choosing finality on the schedule findings. The corpus also records no Alberta decision from 2020 to 2026 setting aside or varying an arbitral award on a construction delay finding, every located Alberta construction-arbitration decision in the window is pro-finality. See arbitration and forum in Alberta.
Liens on a wellsite: 90 days, the mineral itself, and the Minister of Energy
Three rules distinguish an Alberta wellsite lien from every other Canadian lien except Saskatchewan's. The preservation period is 90 days rather than 60 for an improvement to an oil or gas well or oil or gas well site. The lien attaches to the mineral rather than the surface. And where the minerals are Crown-owned it is registered with the Minister of Energy, not at Land Titles. All three apply to private work under the PPCLA, RSA 2000, c P-26.4, none applies on provincial Crown public works, where there is no lien.
The 90-day period was unchanged by the reforms that raised the general period from 45 to 60 days and set concrete at 90. But the Act does not define "oil or gas well" or "oil or gas well site", and that definitional hole creates real uncertainty for SAGD and other non-conventional operations. The leading interpretation is Davidson Well Drilling Ltd v Bank of Montreal8, 2016 ABQB 416, recorded as SINGLE-SOURCE, in which exploratory drilling on Syncrude oil sands mining sites qualified for the 90-day period because it involved the drilling of exploratory oil or gas wells with potential for oil or gas discovery, notwithstanding a bitumen target. Cite it to the Builders' Lien Act, RSA 2000, c B-7, it predates the 29 August 2022 renaming, and a search that only indexes c P-26.4 will silently drop it.
Davidson Well Drilling creates the split-period site. Well-related work runs on 90 days, non-well construction on the same site runs on the general 60. On a single Alberta industrial site two contractors can be running two different lien clocks, and one contractor can be running both. Get the characterisation wrong and the lien is out of time on the work that mattered. On a mixed scope, diarise both.
The attachment rules sit in the Builders' Lien Act, RSA 2000, c B-7 and are SINGLE-SOURCE on the section numbers, which are UNVERIFIED under the renumbered PPCLA:
- s 6(2), a lien is available for work or materials supplied in preparation for, in connection with, or in abandonment operations related to mineral recovery.
- s 6(3), the lien attaches to minerals in situ and after severance.
- The lien attaches to all estates and interests in the mineral except the fee simple in mines and minerals, unless the fee simple holder expressly requested the work. CONFLICT on the section number: one source says s 6, another s 62.
- s 54, enforcement through a court-appointed receiver or trustee.
The registration venue is the trap. Where the minerals are Crown-owned, roughly 81 per cent of Alberta mineral rights. The lien is registered with the Minister of Energy, not at Land Titles, because the Land Titles Act does not permit registration against Crown mineral titles. That is SINGLE-SOURCE, corroborated in substance by a second source. The corpus does not spell out how this sits alongside the rule that there are no liens against provincial or federal Crown land. The records indicate the answer is the carve-out above, which excludes only the fee simple in mines and minerals and leaves the working interests lienable. That is an inference from the section, not something a court has said. The certificate of lis pendens and the requirement to commence the action within 180 days of registration still apply.
The composite point for a wellsite prolongation claim is that you have 30 extra days to lien, a different registry, and a security interest in the mineral rather than the surface. None of that exists in Ontario or Quebec. Getting the registry wrong is fatal. What the lien actually secures (and why the lien fund is not the trust) is dealt with at liens, the lien fund and trust in Alberta. One point belongs here because of where it bites: on private work the PPCLA s 22 trust arises only on payments received after a Certificate of Substantial Performance (ATB Financial v DLM Oilfield Enterprises Ltd9, 2020 ABQB 562, cited to the Builders' Lien Act, RSA 2000, c B-7), so an industrial project terminated or abandoned mid-delay (the fact pattern delay claims arise in) has no trust at all.
Is Alberta Energy Regulator approval delay an extension-of-time ground?
No Alberta authority was located treating Alberta Energy Regulator approval delay as an extension-of-time ground. There is no case, no statutory entitlement and no standard-form clause to fall back on. If regulatory delay is going to excuse time on an Alberta industrial job, it is because someone drafted a clause allocating it, and on a bespoke owner-drafted EPC or EPCM form, the allocation is usually the contractor's unless it was negotiated out.
The two contract-side hooks the corpus records are both public-sector forms, and each is SINGLE-SOURCE. Alberta Transportation General Specifications Ed 1610 gives an extension of time for Department-caused delay. The Alberta Infrastructure Construction Management Agreement11 gives a Relief Event for unforeseeable public authority orders and mandatory legal changes, with relief only above 10 Business Days and $10,000. Neither is available on a private industrial contract, and neither is directed at the Alberta Energy Regulator as such.
The live development is Alberta's Expedited 120-Day Approvals Act12, Bill 30 (2026), a proposed statutory 120-day approval timeline for major projects. It is SINGLE-SOURCE and UNVERIFIED as to status: whether it is proposed, passed or in force could not be established. If a statutory 120-day regulatory clock does exist, "we were waiting on the regulator" becomes a measurable rather than an open-ended excuse, and a contract's regulatory-delay allocation can be benchmarked against it.
One naming trap, and it silently breaks research. Alberta has two different Bill 30s in the relevant window: Bill 30 (2024) is the Service Alberta Statutes Amendment Act, 2024, carrying the PPCLA and Public Works Act amendments in force 1 April 2025, and Bill 30 (2026) is the Expedited 120-Day Approvals Act. Any reference to "Alberta Bill 30" must carry the year.
Winter, camps, fly-in-fly-out and labour availability
No Alberta authority was located on labour-availability delay, camp or fly-in-fly-out constraints, or winter work as an excusable event. The working Alberta answer is that winter is not an excusable delay unless it is a 10-year outlier or the contract carries a seasonal-shutdown clause. Alberta industry guidance treats winter as a priced-in bidding risk rather than an excuse, and nothing in the reported law contradicts that.
The Calgary Construction Association's winter construction guidance13 tells contractors to price temperature sensitivity, equipment, heating and hoarding at tender, and to check that the schedule allows for winter. Its only legal point is procedural, and it is the right one: concerns regarding the schedule and costs must be quickly raised in writing.
| Hook | Where it sits | What it gives |
|---|---|---|
| Seasonal or Prolonged Shutdown | Alberta Transportation General Specifications Ed 16, s 1.2.43 | Suspension during winter or environmentally sensitive periods |
| Extreme Weather | Alberta Infrastructure CM Agreement | Weather not experienced in the past 10 years, inside a narrow force majeure clause requiring prevention or impossibility |
| Force majeure notice | Alberta Infrastructure CM Agreement | 5 Business Days, either party may terminate if the event exceeds 120 days |
| Abnormally adverse weather | CCDC 2 – 2020, GC 6.5.3.3 | Exists on the building form, but no Canadian authority construes it and no proof method is endorsed |
Layer: form-default. Both Alberta public-sector entries are recorded as single-source and no form text was read in original form. The CCDC row records a negative finding, not a rule.
The 10-year return period is the useful thing here. It is a concrete, testable yardstick far more precise than CCDC 2's silence. And it is the mechanism by which an ordinary Alberta winter is not force majeure. Force majeure doctrine itself is pan-Canadian rather than Albertan, the one Alberta contribution is Atcor Ltd v Continental Energy Marketing Ltd14 (1996), in which the Court of Appeal softened the Atlantic Paper test to a real and substantial problem. The corpus records no neutral citation for Atcor, so do not print one.
For camp availability, rotational crews and fly-in-fly-out constraints there is simply nothing: no Alberta case, no standard clause, no industry guidance the corpus captured. A claimant pleading crew shortage on an Alberta industrial job is pleading breach of a bespoke obligation or nothing.
Which Act you are on decides the claim, and it decides it before the contract does
Ask this before anything else on an industrial job, because the two regimes diverge on liens, on trust, on adjudication and on notice. Most Alberta oil sands, wellsite, pipeline and plant work is private, so it runs on the PPCLA, RSA 2000, c P-26.4. Provincial Crown public works (including industrial and infrastructure work for the province) run on the Public Works Act15, RSA 2000, c P-46, and there almost every route this page describes closes.
| Private industrial work | Provincial Crown public works | |
|---|---|---|
| Statute | PPCLA, RSA 2000, c P-26.4, from 29 August 2022 | Public Works Act, RSA 2000, c P-46 |
| Wellsite lien | Yes, 90 days, Minister of Energy where minerals are Crown-owned | None, no liens against provincial or federal Crown land |
| Trust | s 22, but only on payments received after a Certificate of Substantial Performance | No trust of the Crown's money |
| Delay adjudicable | Yes, by consent under the s 19 catch-all, no monetary cap | No, expressly excluded by s 14.3(2) |
| The gate | Contractual notice under the bespoke form | s 14(3): 45 days, registered mail, statutory form |
| Cap | None | A cap applies, the figure is CONFLICT |
Layer: jurisdictional. Every row rests on secondary sources, no consolidated statutory text was read in original form.
Three points sharpen that table for industrial work. First, PPCLA s 1.1 excludes public works as defined in the Public Works Act and agreements with the provincial Crown or a Crown agent, so on an Alberta government job a delay claimant below first tier has no lien, no trust of the Crown's money and no substantive Public Works Act right, only the contract claim against the party above plus the labour and material payment bond if there is one. Second, on provincial Crown public works the Public Works Act s 14.3(2) exclusion, introduced by Bill 30 (2024) and in force 1 April 2025, carves out changes or delays to a construction schedule, completion or milestone dates, and disputes over the interpretation of relief events, designated changes in law, remedial actions and force majeure events. Every category an extension-of-time claim lives in is excluded by name, and nothing like it exists elsewhere in Canada. Third, the Public Works Act s 14(3) notice is real: in Graham Construction and Engineering Inc v Alberta (Infrastructure)16, 2021 ABQB 184, seventeen claimants who used the statutory form were paid and thirty-two, including Graham, were shut out.
By contrast, on private industrial work Alberta is the most claim-friendly adjudication forum in the country: referral runs up to 30 days after final payment and is available concurrently with litigation, and there is no monetary cap. A cap does apply to Public Works Act adjudication, by cross-reference to Court of Justice Act s 9(1)(i), and the figure is CONFLICT, commentary glosses it as $200,000 while the prescribed Alberta Court of Justice civil limit has been $100,000 since 1 August 2023, so read s 9(1)(i) before printing either number. The mechanics of both regimes are at prompt payment and adjudication in Alberta.
Running an Alberta industrial delay claim without precedent
The sequence below is what the absence of authority actually requires. It front-loads characterisation and record-building, because neither can be repaired later, and it treats the contract as the only source of the entitlement rule.
Two closing cautions on citation, because both silently break research on this subject.
Every Alberta lien and delay authority before 29 August 2022: Krupp, PME v Enerkem,
ATB Financial v DLM and Davidson Well Drilling among them, cites the Builders' Lien
Act, RSA 2000, c B-7, not c P-26.4. The chapter letter changed only on the renaming. And
the Court of Queen's Bench became the Court of King's Bench on 8 September 2022, mid-year,
so Alberta 2022 carries both ABQB and ABKB citations, and an ABQB citation dated 2023
or later is almost certainly a transcription error that should not be propagated. Masters
and Masters in Chambers became Applications Judges in the same period, which matters
because much of the Alberta lien-and-delay jurisprudence is Master-level. And diarise the
clocks that run after the claim is filed, not only the ones that run before it: Alberta's
dismissal-for-delay rules end construction claims that survived every earlier deadline.
Sources and authorities
- *Verification, unless noted
No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
- 1Prompt Payment and Construction Lien ActRSA 2000, c P-26.4 (Alberta), from 29 August 2022
The renamed Builders' Lien Act, RSA 2000, c B-7, renamed by Bill 37 in force 29 August 2022 and amended by Bill 30 (2024) in force 1 April 2025. It governs private and municipal work. The general lien period is 60 days, with 90 days preserved for an oil or gas well or well site and for concrete. s 1.1 excludes public works as defined in the Public Works Act and agreements with the provincial Crown or a Crown agent. s 22 creates a trust only on payments received after a Certificate of Substantial Performance.
- 2CCDC 17 – 2025 and CCDC 18 – 2023CCDC 17 – 2025, Stipulated Price Contract between Owner and Trade Contractor, CCDC 18 – 2023
The two published Canadian forms the corpus records as available and used on Alberta industrial work, both supplemented by the Alberta Construction Association. Neither is an EPC or EPCM form.
- 3CCDC 2 – 2020 Stipulated Price ContractCCDC 2 – 2020, GC 6.5 (Delays), GC 6.6.1
The Canadian building-contract default: GC 6.5.4 requires notice for time within 10 Working Days of the commencement of the delay, GC 6.6.1 requires a timely claim for money with no fixed period. It is a building form and will usually be irrelevant on Alberta industrial work. Whether the Alberta Construction Association supplementary conditions to CCDC 2 – 2020 amend GC 6.5 could not be established and is the top Alberta verification gap.
- 4Krupp Canada Inc v JV Driver Projects Inc2014 ABQB 259, Court of Queen's Bench of Alberta
Delay damages form part of a lien only where they relate directly to the work that is the subject of the lien, lost productivity on the liened project yes, inability to work elsewhere no. The corpus records a conflict on the holding and there is no Alberta appellate resolution.
- 5PME Inc v Enerkem Alberta Biofuels LP2021 ABQB 889, Court of Queen's Bench of Alberta
The later and narrower Alberta lien authority, excluding quantum meruit from the lien. It does not cite Krupp, and no appellate decision reconciles the two.
- 6Builders' Lien ActRSA 2000, c B-7 (Alberta), to 28 August 2022
The pre-29-August-2022 Alberta lien statute. s 6(2) makes a lien available for work supplied in preparation for, in connection with, or in abandonment operations related to mineral recovery, s 6(3) attaches the lien to minerals in situ and after severance, s 54 provides enforcement through a court-appointed receiver or trustee. Section numbers are single-source and unverified under the renumbered Act, and sources conflict between s 6 and s 62 for the rule excluding the fee simple in mines and minerals.
- 7Quanta Canada Holdings II ULC v Bremar Construction Ltd2024 ABKB 317, Court of King's Bench of Alberta
Permission to appeal an arbitral award refused on a delay-and-defects claim of $8,137,116: delay causation is mixed fact and law, so no question of law arises under Arbitration Act s 44(2).
- 8Davidson Well Drilling Ltd v Bank of Montreal2016 ABQB 416, Court of Queen's Bench of Alberta
Exploratory drilling on Syncrude oil sands mining sites qualified for the 90-day oil and gas lien period under the Builders' Lien Act, RSA 2000, c B-7, because the work involved the drilling of exploratory oil or gas wells with potential for oil or gas discovery, notwithstanding a bitumen target. Recorded in the corpus as single-source.
- 9ATB Financial v DLM Oilfield Enterprises Ltd2020 ABQB 562, Court of Queen's Bench of Alberta
The statutory construction trust arises only on payments received after a Certificate of Substantial Performance. A project terminated or abandoned before that certificate has no trust at all.
- 10Alberta Transportation General Specifications Ed 16Alberta Transportation General Specifications Ed 16, s 1.2.43
s 1.2.43 is a Seasonal or Prolonged Shutdown provision covering suspension during winter or environmentally sensitive periods. The form also gives an extension of time for Department-caused delay. No notice-of-claim day count was extractable from the form, and the dispute process refers out to a 1997 document.
- 11Alberta Infrastructure Construction Management AgreementAlberta Infrastructure CM Agreement. Extreme Weather, Force Majeure and Relief Event provisions, Relief Events at Schedule 19
Defines Extreme Weather as weather not experienced in the past 10 years, inside a narrow force majeure clause requiring prevention or impossibility, and gives a Relief Event for unforeseeable public authority orders and mandatory legal changes. Relief Event notice is prompt written notice with relief only above 10 Business Days and $10,000, force majeure notice is 5 Business Days. Recorded as single-source.
- 12Expedited 120-Day Approvals Act (Alberta Bill 30, 2026)Alberta Bill 30 (2026), status unverified in the corpus
A proposed statutory 120-day approval timeline for major projects. Single-source in the corpus, and whether it is proposed, passed or in force could not be established. Not to be confused with Bill 30 (2024), the Service Alberta Statutes Amendment Act, 2024.
- 13Calgary Construction Association winter construction guidanceCalgary Construction Association guidance on winter work
Treats winter as a priced-in bidding risk rather than an excuse: price temperature sensitivity, equipment, heating and hoarding at tender, check that the schedule allows for winter, and raise concerns regarding the schedule and costs quickly in writing.
- 14Atcor Ltd v Continental Energy Marketing Ltd(1996), Court of Appeal of Alberta. The corpus records no neutral citation for this decision
The Alberta Court of Appeal softened the Atlantic Paper force majeure test to a real and substantial problem. Force majeure doctrine in Canada is pan-Canadian, not Alberta-specific.
- 15Public Works ActRSA 2000, c P-46 (Alberta)
Governs provincial Crown public works. s 14(3) requires notice of claim by registered mail within 45 days, strictly enforced. s 14.3(2), introduced by Bill 30 (2024) and in force 1 April 2025, excludes from adjudication changes or delays to a construction schedule, completion or milestone dates, and disputes over relief events, designated changes in law, remedial actions and force majeure events. A monetary cap applies to Public Works Act adjudication only, by cross-reference to Court of Justice Act s 9(1)(i), sources conflict between $200,000 and $100,000.
- 16Graham Construction and Engineering Inc v Alberta (Infrastructure)2021 ABQB 184, Court of Queen's Bench of Alberta
Strict compliance with the Public Works Act s 14(3) 45-day registered-mail notice is mandatory. Seventeen claimants who used the statutory form were paid, thirty-two, including Graham, were shut out.
General information, not legal advice. Reviewed Aug 9, 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.