Skip to main content
13 min readReviewed August 9, 2026Alberta, Canada, common law

Extension of time in Alberta

Alberta is the best Canadian forum for a late-crystallising private delay claim and the worst for a public one. Private-sector adjudication runs post-completion and alongside litigation, on provincial Crown public works delay is excluded from adjudication by statute. The risk here is the forum, not the doctrine.

Extension of time in Alberta, at a glance
Ask which Act first
Private and municipal work runs on the PPCLA. Provincial Crown public works run on the Public Works Act, and the PPCLA expressly does not apply to them.
On a provincial job, delay is not adjudicable
Public Works Act s 14.3(2) excludes schedule changes, completion and milestone dates, relief events, changes in law and force majeure every category an EOT claim lives in. Nothing like it exists elsewhere in Canada.
On a private job, the door stays open longest in Canada
Referral up to 30 days after final payment and concurrently with litigation, since 1 April 2025, with no monetary cap. Ontario's window shuts 90 days after completion.
The arbitration decision is final on the schedule
Delay causation is mixed fact and law, so no question of law arises and permission to appeal is refused Quanta v Bremar, 2024 ABKB 317.
No Certificate of Substantial Performance, no trust
The PPCLA s 22 trust bites only on payments received after CSP. A delayed project terminated or abandoned before CSP has no trust at all and that is the fact pattern delay claims arise in.
The limitation period cannot be shortened
Limitations Act s 7(1)–(2) permits extension only. An owner's clause cutting the period down is invalid – the opposite of Ontario.
Meeting every deadline is not enough
Rules 4.31 and 4.33 strike claims for prosecuting them too slowly. Peters, 2025 ABKB 713, a CAD 4 million claim struck, "construction is complex" was not an excuse.
Get the citation era right
ABQB to 7 September 2022, ABKB after the court renamed mid-year. The lien Act was c B-7 before 29 August 2022, c P-26.4 after.

Alberta does not have an unusual law of delay. It has an unusual set of forums, and they diverge so sharply that the same delay claim can be the easiest in Canada to bring or the hardest, depending on a single question asked before any of the facts matter: is this a provincial Crown public work? If it is not, Alberta gives a claimant more time and more routes than any other province. If it is, the legislature has removed the delay claim from adjudication by name.

Everything below is Albertan. The pan-Canadian doctrine that Alberta sits on, concurrency, the prevention principle, the two-limb penalty rule Canada never abandoned, the Tercon framework for exclusion clauses, lives at extension of time in Canada and is not repeated here.

A standing warning on the evidence base. CanLII, the Supreme Court portal and the Alberta court sites all blocked automated retrieval during the research pass, so no Alberta judgment and no consolidated Alberta statutory text was read in original form. Case content rests on law-firm bulletins, statutory content came from enacting bill texts plus bulletins. Check every citation, section number and day count below against the judgment or the consolidated statute before pleading or relying on it for a deadline-critical step.

Which Act are you on? Ask before anything else

Alberta splits at the front door, and the split is more consequential than the contract form. One statute governs private and municipal work. A different one governs provincial Crown public works, and the first expressly does not apply to the second.

Private and municipalProvincial Crown public works
StatutePrompt Payment and Construction Lien Act, RSA 2000, c P-26.4Public Works Act, RSA 2000, c P-46
In force from29 August 2022 (Bill 37), Bill 30 (2024) amendments 1 April 2025Bill 30 (2024) prompt-payment provisions, contracts entered on or after 1 April 2025
LiensYesNone against provincial or federal Crown land
Trusts 22, but only on payments received after a Certificate of Substantial PerformanceNo trust of the Crown's money
AdjudicationAvailable, delay adjudicable by consent under the s 19 catch-allDelay expressly excluded, s 14.3(2)
Monetary capNoneA cap applies, the figure is unresolved
Claim routeContract, lien, adjudications 14(3) notice, registered mail within 45 days, strictly enforced

Layer: jurisdictional, statute. Neither Act was read in original text for this corpus, the provisions rest on independent secondary sources and enacting bill texts. Verify before relying on any section number.

PPCLA s 1.1 excludes public works as defined in the Public Works Act, and agreements with the provincial Crown or a Crown agent. So on an Alberta government job a delay claimant below first tier has no lien, no trust of the Crown's money and no substantive right under the Public Works Act, only the contract claim against the party immediately above it, plus the labour and material payment bond if one was posted. That is a materially thinner security position than the same subcontractor would have on a private job across the street.

On a provincial public work, delay is not adjudicable at all

Public Works Act s 14.3(2), added by Bill 30 (2024) and in force 1 April 2025, excludes from adjudication "changes or delays to a construction schedule", "completion or milestone dates", and disputes over the interpretation of "relief events, designated changes in law, remedial actions, or force majeure events".

Every category an extension-of-time claim lives in is carved out by name. Nothing like it exists anywhere else in Canada.

What survives is the s 14(3) notice: registered mail, within 45 days, and strictly enforced. Graham Construction and Engineering Inc v Alberta (Infrastructure) 2021 ABQB 184 shows what that costs, seventeen claimants who used the statutory form were paid, thirty-two, including Graham, were shut out. On a provincial job that notice is not one clock among several. It is close to the only one that matters, and the Alberta claim clocks page sets out how it interacts with everything else.

The contrast with Ontario is stark and worth carrying. Ontario made an extension of time adjudicable on 1 January 2026, as an ancillary head on non-P3 contracts. Alberta moved in the opposite direction on the same timescale, and did so for the projects a contractor is least able to walk away from. See prompt payment and adjudication in Ontario.

On private work, the door stays open longer than anywhere in Canada

Turn the page over and Alberta becomes the most claim-friendly adjudication forum in the country. Under the PPCLA, since 1 April 2025, a party may refer a dispute up to 30 days after final payment and concurrently with ongoing litigation, through the widest consent gateway in Canada. And with no monetary cap at all.

That combination is unique. Ontario's window shuts 90 days after the contract is completed, abandoned or terminated. Saskatchewan and Manitoba have no ancillary extension-of-time head. Quebec's adjudicator has no power to grant time. The Northwest Territories has prompt payment and no adjudication mechanism whatsoever. Alberta alone lets a delay claim that crystallised late, as delay claims characteristically do, when the true cost is only visible at the end, still reach an adjudicator.

Welcome Homes Construction Inc v Atlas Granite Inc 2024 ABKB 301 confirms that lien rights and adjudication run as independent processes, and that a determination may be filed as an order of the court. And Canadian Pressure Testing Technologies Ltd v EllisDon Industrial Inc 2022 ABKB 649 settles a point often stated backwards: pay-when-paid is not statutorily prohibited in Alberta. It failed on clarity, and the subcontractor got summary judgment. A drafter who assumes the clause is void will mis-advise. A drafter who assumes it is safe will too.

The real Alberta risk is the forum, not the doctrine

This is the proposition the whole cluster turns on, and it has four parts.

An arbitral finding on delay causation is effectively unappealable

Quanta Canada Holdings II ULC v Bremar Construction Ltd 2024 ABKB 317, a Calgary duct bank, a CCA 1-2008 subcontract and a CAD 8,137,116 delay-and-defects claim. Permission to appeal was refused, because delay causation is mixed fact and law and so no question of law arises under Arbitration Act s 44(2). Arbitrating an Alberta delay dispute is choosing finality on the schedule findings.

Expert evidence is capped at one expert per subject matter

Rule 8.16(1) of the Alberta Rules of Court. On a delay claim needing both a scheduling expert and a quantum expert, that shapes the case from the pleading stage. Quebec caps expertise at one per discipline. Ontario has no cap at all.

There is no construction list and there are no construction judges

No specialist list, no designated judges, no construction practice note, against Ontario's Toronto Construction List. A complex delay trial is heard by a generalist bench.

A claim that survives the limitation period can still be struck for taking too long

Rules 4.31 and 4.33. Peters v Countryside Masonry Inc 2025 ABKB 713 a CAD 4 million construction claim struck for inordinate delay, with "construction is complex" rejected as an excuse. This is not true anywhere else in the cluster.

The arbitration and forum page develops each of these, including what appellate room survives Quanta and how the summary-judgment test in Weir-Jones Technical Services Incorporated v Purolator Courier Ltd 2019 ABCA 49 applies: noting that it is a courier dispute, not a construction case, and that no Alberta decision has yet summarily disposed of a delay claim under it. The nearest is Tempo Alberta Electrical Contractors Co Ltd v Man-Shield Construction Inc 2023 ABKB 44, where partial summary judgment of CAD 678,261 went on the payment claim, the general contractor's delay and staffing backcharge failed for want of written notice and an opportunity to cure, and the delay damages were reserved for trial. That case is worth reading for a reason people miss: in Alberta the notice trap catches the party setting off as readily as the party claiming.

Two traps that silently break Alberta research

Both are mechanical, both are easy to miss, and both quietly remove the most useful material from a search.

The court renamed mid-year. The Court of Queen's Bench of Alberta became the Court of King's Bench on 8 September 2022, not at the year boundary. So 2022 carries both 2022 ABQB nnn (to 7 September) and 2022 ABKB nnn (from 8 September). An ABQB citation dated 2023 or later is almost certainly a transcription error for ABKB, do not propagate it. Masters and Masters in Chambers were retitled Applications Judges, which matters more than it sounds, because much of the Alberta lien-and-delay jurisprudence is Master-level. The Provincial Court became the Alberta Court of Justice on 1 April 2023, with a civil limit of CAD 100,000 from 1 August 2023.

The Act renamed too. The PPCLA is the renamed Builders' Lien Act, RSA 2000, c B-7, renamed by Bill 37 in force 29 August 2022. The chapter letter went B-7 → P-26.4. Every Alberta lien and delay authority before that date cites c B-7. A search that indexes only P-26.4 silently drops Krupp Canada Inc v JV Driver Projects Inc 2014 ABQB 259, PME Inc v Enerkem Alberta Biofuels LP 2021 ABQB 889 and ATB Financial v DLM Oilfield Enterprises Ltd 2020 ABQB 562, which is most of what a delay claimant actually needs.

And there are two Bill 30s. Bill 30 (2024) is the Service Alberta Statutes Amendment Act, 2024 the PPCLA and PWA amendments in force 1 April 2025. Bill 30 (2026) is the Expedited 120-Day Approvals Act, unverified in this corpus as to status. Any reference to "Alberta Bill 30" without a year is ambiguous.

Liens, the lien fund and the trust, three things, not one

The single most common Alberta error is treating the lien fund and the trust as the same protection. They are not. The major and minor lien funds are owner-held security, each split into Part A the 10% statutory holdback, and Part B, the amount payable. The trust is a separate creature of PPCLA s 22, and under ATB Financial v DLM Oilfield Enterprises Ltd 2020 ABQB 562 it arises only on payments received after a Certificate of Substantial Performance.

So a delayed project that is terminated or abandoned before CSP has no trust at all, and that is precisely the fact pattern a delay claim arises in. It is the most useful sentence on the subject and the one least often said.

Whether a lien secures the delay claim runs on a different test from Ontario's. Alberta does not draw a price-versus-damages line. Under Krupp the damages are lienable only where they "relate directly to the work that is the subject of the lien", lost productivity on the liened project yes, inability to work elsewhere no. The corpus records a on that holding, and PME v Enerkem is later, narrower, excludes quantum meruit, and does not cite Krupp. There is no appellate resolution, so the line is factual, not categorical. The liens and lien fund page works through it, and the provincial comparison sets Alberta against Ontario and Quebec.

Where pan-Canadian doctrine governs. And one place it may not

Do not look for an Alberta answer to the penalty rule, force majeure, prolongation quantum or delay-analysis methodology. Those are pan-Canadian and set out at extension of time in Canada. Three Alberta footnotes to them are worth carrying.

On exclusion clauses, there is no Alberta decision on a no-damage-for-delay clause at all, so an Alberta NDFD clause is tested through the Supreme Court's Tercon framework plus Plas-Tex Canada Ltd v Dow Chemical of Canada Ltd 2004 ABCA 309. On force majeure, the Alberta Court of Appeal in Atcor Ltd v Continental Energy Marketing Ltd (1996) softened the Supreme Court's test to "a real and substantial problem". Though the corpus carries no neutral citation for that decision, so obtain one before relying on it. And on anti-deprivation, the leading Canadian authority began here, as Capital Steel Inc v Chandos Construction Ltd 2019 ABCA 32, affirmed 2020 SCC 25.

The place where Alberta may genuinely diverge is concurrency. Graham Construction & Engineering (1985) Ltd v LaCaille Developments Inc 2006 ABQB 898 allows recovery where "the project would not have been completed any sooner" but for the contractor's own delay. A but-for or dominant-cause formulation that sits in tension with the apportionment approach applied elsewhere in Canada. The corpus records it as single-source and unverified, so it is an argument to make rather than a rule to rely on. See concurrent delay in Canada.

What Alberta does not have

The gaps are unusually large here, and each one is an argument nobody has run.

There is no Alberta authority on delay or disruption in a turnaround or shutdown, the highest-value, least-precedented category of work in the province. There is no Alberta or Canadian standard EPC or EPCM form in common use, so on industrial work there is no default extension-of-time clause to reason from and CCDC 2 GC 6.5 will usually be irrelevant. There is no Alberta authority on labour-availability delay, camp or fly-in-fly-out constraints, or winter work as an excusable event. The working answer on winter being no, unless it is a ten-year outlier or the contract carries a seasonal-shutdown clause. And there is no Alberta authority treating regulatory approval delay by the Alberta Energy Regulator as an extension-of-time ground. Those are developed on the oil, gas and industrial page.

On the procedural side: no reported Alberta judicial review of an adjudicator's determination, and no Alberta decision between 2020 and 2026 setting aside or varying an arbitral award on a construction delay finding, every located Alberta construction-arbitration decision in that window is pro-finality. There is no Alberta decision on delay-analysis methodology of any kind. And on notice, the corpus records that Alberta may have no appellate authority at all treating a contractual notice-of-claim clause as a condition precedent: the usual citation, Dilcon Construction Ltd v ANC Developments Inc 2000 ABCA 223, is recorded with a , a substantial source reads the same judgment as establishing an implied term of uninterrupted possession, which is prevention-adjacent and a considerably stronger tool for a claimant. Both may be true. The notice and time bars page sets out what to do with that.

One further gap bears directly on almost every private Alberta contract: it could not be established whether the Alberta Construction Association supplementary conditions to CCDC 2 – 2020 amend GC 6.5 at all. The corpus calls this the top Alberta gap. In Ontario the equivalent industry package verifiably leaves GC 6.5 untouched, in Alberta the answer is simply unknown, which means the executed contract has to be read rather than assumed: which is, in the end, the advice this whole page keeps arriving at.

Six things to settle before running an Alberta delay claim

  1. Is it a provincial Crown public work? If yes, delay is not adjudicable, there is no lien and the Public Works Act s 14(3) 45-day registered-mail notice is the route that matters.
  2. What do the supplementary conditions do to GC 6.5? Read them. Do not assume the Ontario answer travels.
  3. Get the era right. ABQB to 7 September 2022 and ABKB after, c B-7 before 29 August 2022 and c P-26.4 after. And give every Bill 30 its year.
  4. Decide arbitration or litigation with Quanta in front of you. Arbitration buys speed and privacy at the price of finality on the schedule findings.
  5. Check whether a Certificate of Substantial Performance was ever issued. Without one there is no trust, whatever else is true.
  6. Plan the pace of the litigation, not just the notice. Rules 4.31 and 4.33 end Alberta construction claims that meet every other deadline.

The limitation periods page covers the point that ties several of these together: Alberta's Limitations Act permits the parties to extend a limitation period by agreement but not to shorten it, so the one-year-from-substantial-performance bar that binds a contractor in Ontario is a nullity in Alberta. Two provinces, the same clause, opposite answers.

Authorities

  1. Prompt Payment and Construction Lien Act (Alberta) RSA 2000, c P-26.4, formerly the Builders' Lien Act, RSA 2000, c B-7Alberta's lien, holdback, trust, prompt-payment and adjudication scheme for private and municipal work. s 1.1 excludes public works as defined in the Public Works Act and agreements with the provincial Crown or a Crown agent. s 22 creates the trust. s 33.4 permits referral up to 30 days after final payment and concurrently with litigation.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. The Act was renamed from the Builders' Lien Act, RSA 2000, c B-7 by Bill 37 in force 29 August 2022, authorities before that date cite c B-7. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  2. Public Works Act (Alberta) RSA 2000, c P-46, ss 14(3) and 14.3(2)Governs provincial Crown public works. s 14(3) requires notice of claim by registered mail within 45 days. s 14.3(2), added by Bill 30 (2024) and in force 1 April 2025, excludes from adjudication changes or delays to a construction schedule, completion or milestone dates, and disputes over the interpretation of relief events, designated changes in law, remedial actions and force majeure events.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  3. Graham Construction and Engineering Inc v Alberta (Infrastructure) 2021 ABQB 184, Court of Queen's Bench of AlbertaStrict compliance with the Public Works Act s 14(3) 45-day registered-mail notice is mandatory. Seventeen claimants who used the statutory form were paid, thirty-two, including Graham, were shut out.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  4. Quanta Canada Holdings II ULC v Bremar Construction Ltd 2024 ABKB 317, Court of King's Bench of AlbertaPermission to appeal an arbitral award on a CAD 8,137,116 delay-and-defects claim refused. Delay causation is mixed fact and law, so no question of law arises under Arbitration Act s 44(2).No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  5. ATB Financial v DLM Oilfield Enterprises Ltd 2020 ABQB 562, Court of Queen's Bench of AlbertaThe statutory trust arises only on payments received after a Certificate of Substantial Performance. Without a CSP there is no trust.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. The governing statute at the time was the Builders' Lien Act, RSA 2000, c B-7. Verify on CanLII before pleading.Find on CanLII
  6. Krupp Canada Inc v JV Driver Projects Inc 2014 ABQB 259, Court of Queen's Bench of AlbertaDelay damages form part of a lien only where they relate directly to the work that is the subject of the lien, lost productivity on the liened project qualifies, inability to work elsewhere does not.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources, and the corpus records a CONFLICT on the holding itself. The governing statute at the time was the Builders' Lien Act, RSA 2000, c B-7. Verify on CanLII before pleading.Find on CanLII
  7. PME Inc v Enerkem Alberta Biofuels LP 2021 ABQB 889, Court of Queen's Bench of AlbertaA later and narrower statement of the lienable-damages question, excluding quantum meruit from the lien. It does not cite Krupp, and there is no appellate resolution between them.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources. The governing statute at the time was the Builders' Lien Act, RSA 2000, c B-7. Verify on CanLII before pleading.Find on CanLII
  8. Graham Construction & Engineering (1985) Ltd v LaCaille Developments Inc 2006 ABQB 898, Court of Queen's Bench of AlbertaAlberta concurrency authority in a but-for or dominant-cause form: a contractor may recover where the project would not have been completed any sooner but for its own delay.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The corpus records this as SINGLE-SOURCE and unverified, and the formulation sits in tension with the apportionment approach applied elsewhere in Canada. Verify on CanLII before pleading.Find on CanLII
  9. Dilcon Construction Ltd v ANC Developments Inc 2000 ABCA 223, Court of Appeal of AlbertaCarried in the corpus as authority that Alberta enforces contractual notice strictly. A substantial source instead attributes to the same judgment an implied term that the owner will give the contractor uninterrupted possession of the site.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The corpus records a CONFLICT on what this judgment decides, and a further CONFLICT on the styling, the party order is reversed between sources, while the neutral citation is agreed. Read the judgment before relying on either characterisation.Find on CanLII
  10. Peters v Countryside Masonry Inc 2025 ABKB 713, Court of King's Bench of AlbertaA CAD 4 million construction claim struck for inordinate delay in prosecuting it. That construction litigation is complex is not an excuse.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources. Verify on CanLII before pleading.Find on CanLII
  11. Tempo Alberta Electrical Contractors Co Ltd v Man-Shield Construction Inc 2023 ABKB 44, Court of King's Bench of AlbertaPartial summary judgment of CAD 678,261 on the payment claim. The general contractor's delay and staffing backcharge failed for want of written notice and an opportunity to cure, delay damages were reserved for trial.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources. Verify on CanLII before pleading.Find on CanLII
  12. Welcome Homes Construction Inc v Atlas Granite Inc 2024 ABKB 301, Court of King's Bench of AlbertaLien rights and adjudication are independent processes, and an adjudicator's determination may be filed as an order of the court.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources. Verify on CanLII before pleading.Find on CanLII
  13. Canadian Pressure Testing Technologies Ltd v EllisDon Industrial Inc 2022 ABKB 649, Court of King's Bench of AlbertaPay-when-paid is not statutorily prohibited in Alberta. The clause failed on clarity, and summary judgment went to the subcontractor.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources. Verify on CanLII before pleading.Find on CanLII
  14. Weir-Jones Technical Services Incorporated v Purolator Courier Ltd 2019 ABCA 49, Court of Appeal of AlbertaThe Alberta summary judgment test. It is a courier dispute, not a construction case.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources. The corpus records that a decision styled Weir-Jones Equipment Co v Fox Creek, 2019 ABCA 25 does not exist and must not be cited. Verify on CanLII before pleading.Find on CanLII
  15. Plas-Tex Canada Ltd v Dow Chemical of Canada Ltd 2004 ABCA 309, Court of Appeal of AlbertaThe Alberta authority on refusing to enforce an exclusion clause, applied alongside the Supreme Court's Tercon framework where a no-damage-for-delay clause is challenged.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources. Verify on CanLII before pleading.Find on CanLII
  16. Atcor Ltd v Continental Energy Marketing Ltd Court of Appeal of Alberta, 1996. The corpus records no neutral citationSoftens the Supreme Court's force majeure test so that a supplier need show a real and substantial problem rather than absolute impossibility.No Canadian judgment or consolidated statutory text was read in original form for this corpus, and the corpus carries no neutral citation or report reference for this decision. Obtain the citation before relying on it.
  17. Capital Steel Inc v Chandos Construction Ltd 2019 ABCA 32, affirmed 2020 SCC 25The anti-deprivation rule: a forfeiture clause triggered by insolvency is void regardless of whether the sum is a genuine pre-estimate. The Alberta appeal that became the leading Canadian authority.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation and holding rest on independent secondary sources. Verify on CanLII before pleading.Find on CanLII
  18. Alberta Rules of Court rules 4.31, 4.33 and 8.16(1)Rules 4.31 and 4.33 permit dismissal of an action for inordinate or inexcusable delay in prosecuting it. Rule 8.16(1) limits a party to one expert per subject matter.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The rule numbers and their content rest on independent secondary sources. Verify against the consolidated Rules before relying on them.
  19. CCDC 2 – 2020 with the ACA Supplementary Conditions Canadian Construction Documents Committee, 2020 edition. Alberta Construction Association supplementary conditionsGC 6.5.4 requires written notice of delay within 10 Working Days of the commencement of the delay. GC 6.6.1 requires a separate, timely notice of intention to claim a change in the Contract Price.No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading. No form text was read in original for this corpus either, clause numbering and content rest on independent secondary sources. Whether the Alberta Construction Association supplementary conditions amend GC 6.5 could not be established, the corpus records this as the top Alberta gap. Read the executed contract and its supplementary conditions.

Extension of time in Alberta · Storia