Skip to main content
17 min readReviewed August 9, 2026Alberta, Canada, common law

Arbitration and forum for Alberta delay claims

The real Alberta risk in a delay claim is the forum, not the doctrine. An arbitral finding on delay causation is effectively unappealable, the courts have no construction list, expert evidence is capped at one expert per subject matter, and a claim that survives the limitation period can still be struck for slow prosecution.

Arbitration and forum for Alberta delay claims, at a glance
The short answer
Alberta delay doctrine is pan-Canadian and unremarkable. What decides Alberta delay claims is procedural: arbitral finality on causation, a court with no construction specialisation, a one-expert cap, and an aggressive dismissal-for-delay regime.
Arbitration
An appeal lies only on a question of law and only with permission, under Arbitration Act s 44(2). Delay causation is mixed fact and law, so permission is refused, Quanta Canada Holdings II ULC v Bremar Construction Ltd, 2024 ABKB 317.
The negative finding that reinforces it
No Alberta decision from 2020 to 2026 set aside or varied an arbitral award on a construction delay finding. Every located Alberta construction-arbitration decision in the window is pro-finality.
The appeal clock
30 days from receipt of the award under Arbitration Act s 46(1), running to the clerk's FILED stamp rather than to submission. The discretion to extend is exercised sparingly.
No construction list
Alberta has no specialist construction list, no construction judges and no construction practice note. The Court of King's Bench Commercial List exists in Calgary and Edmonton only and is insolvency-focused, construction disputes are not qualifying matters.
Expert evidence
A party may call only one expert on any one subject matter unless the Court orders otherwise, Alberta Rules of Court r 8.16(1). Compare Quebec's one per discipline under art 232 CCP. Ontario has no equivalent cap.
Dismissal for delay
Rules 4.31 and 4.33 kill Alberta construction claims. Peters v Countryside Masonry Inc, 2025 ABKB 713 struck a $4M construction claim for inordinate delay, and rejected complexity as an excuse.
Summary judgment
The test is Weir-Jones Technical Services Incorporated v Purolator Courier Ltd, 2019 ABCA 49, a courier dispute, not a construction case. Payment and lien claims go summarily in Alberta. No located decision has summarily disposed of a delay claim itself.

The real Alberta risk in a delay claim is the forum, not the doctrine. Alberta's delay doctrine is pan-Canadian and unremarkable. What is distinctive, and what actually decides Alberta delay claims, is procedural: an arbitral finding on delay causation is effectively unappealable, the courts have no construction list and no construction judges, expert evidence is capped at one expert per subject matter, and a claim that survives the limitation period can still be struck for taking too long to prosecute.

A practitioner arriving from Ontario, England or the United States will look for the Alberta rule on concurrency, on notice as a condition precedent, on no-damage-for-delay clauses. There is very little there, and what there is sits on the Alberta place hub. The doctrine that governs an Alberta delay claim is the general Canadian doctrine at the Canada hub, and it is not repeated on this page. What is repeated nowhere else is the procedural environment, and it is the procedural environment that will decide the case.

Two consequences follow immediately, and both bite at contract-signing rather than at dispute. First, an arbitration clause in an Alberta construction contract is a decision to make the schedule findings final. Second, choosing litigation instead does not buy a specialist forum: it buys a general civil judge and exposure to two dismissal-for-delay rules that have no counterpart in the way most practitioners plan a construction action.

An arbitral finding on delay causation is effectively unappealable in Alberta

Delay causation is quintessentially mixed fact and law, and the Alberta Arbitration Act, RSA 2000, c A-43 permits an appeal only on a question of law and only with the court's permission. So there is nothing for the appeal to attach to. A party that arbitrates an Alberta delay dispute is choosing finality on the schedule findings, and should price that choice before signing the clause, not after receiving the award.

The architecture is short. Section 44(2) provides that, absent an arbitration agreement conferring broader rights, an appeal lies only on a question of law and only with the court's permission. Section 44(2.1) requires both limbs to be satisfied: "(a) the importance to the parties of the matters at stake in the arbitration justifies an appeal, and (b) the determination of the question of law at issue will significantly affect the rights of the parties." Section 46(1) gives 30 days from receipt of the award to commence the appeal. And permission is a mandatory, bifurcated first step decided separately before any merits appeal Esfahani v Samimi, 2022 ABCA 178 describes s 44(2) as "a screening provision which restricts appeals to questions of law alone."

The Alberta construction-delay arbitration authority is Quanta Canada Holdings II ULC v Bremar Construction Ltd, 2024 ABKB 317. Quanta engaged Bremar to install an underground duct bank system in Calgary under a CCA 1-2008 Stipulated Price Subcontract. Quanta withheld payment for defects said to require removal and replacement. Bremar arbitrated for C$8,137,116, alleging that Quanta had caused delays and performed poorly. The arbitrator found for Bremar. Permission to appeal was refused: the arbitrator's legal conclusions were inseparable from the factual findings, so no question of law arose, notwithstanding that the importance limb was met.

8,137,116 CADThe delay-and-defects claim in Quanta v Bremar, on which permission to appeal was refused
1 expertPer subject matter in the Court of King's Bench, under Alberta Rules of Court r 8.16(1), unless the Court orders otherwise
3 yearsWithout a significant advance, and dismissal under r 4.33 is mandatory once triggered

The negative finding reinforces the case rather than sitting beside it. No Alberta decision from 2020 to 2026 set aside or varied an arbitral award on a construction delay finding. Every located Alberta construction-arbitration decision in that window is pro-finality. A party that expects to appeal a bad critical-path finding has misread the province.

Arbitrating an Alberta delay dispute is choosing finality on the schedule findings. That is not a risk to be managed after the award. It is a term of the bargain struck when the arbitration clause was signed.

What appellate room is left, and the 30-day clock that closes it

If you want an appealable Alberta delay decision, the question of law must be isolable which in practice means contract interpretation, not causation. Frame the dispute so that something turns on what a clause means, keep that issue separable from the schedule findings, and diarise 30 days from receipt of the award. Everything else in an Alberta delay award is beyond appellate reach.

The route commonly proposed for that is Ledcor Construction Ltd v Northbridge Indemnity Insurance Co, 2016 SCC 37 (an Alberta-origin appeal) which holds that standard form contracts are reviewed for correctness, and which therefore supports an argument that the interpretation of a standard construction form such as CCDC 2 – 2020 GC 6.5 (Delays) is a question of law. That link is the corpus's own inference, marked , and it should be tested before it is relied on in a permission application.

Two yardsticks reported from Quanta itself go to the importance limb, and both are in the corpus: the court is reported to have proposed a materiality threshold of roughly 25 per cent or more of the award value, and a separate commentary gives a satisfied example at $5.1M representing 63 per cent of the award, together with interpretation of widely used construction contract language. Treat them as indicative of how the limb is argued, not as a rule.

The 30-day clock is unforgiving in a way that catches out-of-province counsel. Frog Lake First Nation v 2250657 Alberta Ltd, 2025 ABKB 206 holds that the s 46(1) period runs to the moment the clerk stamps the documents "FILED", not to when they are submitted. The court's inherent discretion to extend is exercised "sparingly and only in the most obvious cases of unfairness", and bureaucratic filing delay is not enough. File early, and treat the registry's processing time as your risk.

One further Alberta-particular point belongs in the arbitration file: Arbitration Act s 53(7) provides that settlement offers may not be disclosed until costs are determined. The corpus records it as , and it is worth carrying because a delay dispute generates offers early and often.

Alberta has no construction list, no construction judges and no construction practice note

There is no specialist construction forum in Alberta. The Court of King's Bench Commercial List exists in Calgary and Edmonton only and is confined to insolvency, receivership, CCAA, BIA, Winding-Up, Bank Act realizations and corporate reorganizations, builders' lien and construction disputes are not qualifying matters. An Alberta delay claim therefore goes into the general civil stream, before a judge with no construction specialisation.

The contrast with Ontario's Toronto Construction List is the point. On the Construction List the judge has seen critical-path evidence before, the procedural expectations for a delay action are settled, and case management is calibrated to a document-heavy schedule dispute. In Alberta none of that is assumed. Practically, that changes how the claim must be run:

  • The schedule case has to be taught, not referenced. Nothing about float, longest path, windows analysis or contemporaneous updating can be treated as judicially familiar. This is compounded by the corpus's finding that there is no Alberta decision on delay-analysis methodology at all, so the choice among the recognised delay analysis methods is argued on persuasion and on the contract, not on Alberta precedent.
  • Case management is what you make of it. There is no construction practice note setting the sequence for a delay action, so the sequencing of expert reports, the trial estimate and the document plan come from orders you ask for.
  • The pace of the action is your problem, not the court's. A general civil stream plus rr 4.31 and 4.33 is a combination that punishes the natural rhythm of a construction file, where parties wait for completion, for as-builts, for the final account.

That combination: a non-specialist forum, delay pressure on the action itself, and a one-expert cap, and not any doctrinal difference, is the real Alberta-specific risk profile.

One expert per subject matter. Alberta Rules of Court r 8.16(1)

A party may call only one expert on any one subject matter unless the Court orders otherwise. On a delay claim that needs a scheduling expert and a quantum expert, that rule has to be answered at the pleading stage, because the answer determines who is retained, what each is asked to opine on, and whether an application for leave is needed before reports are commissioned rather than after.

The operative question is whether schedule and quantum are one subject matter or two. Nothing in the corpus resolves it, and r 8.16(1) is itself recorded as and flagged for verification against the Rules. It is the single most operationally important Alberta expert rule for a delay claim, and it is the one least well evidenced. The practical consequences follow from taking the constraint seriously rather than from resolving it:

  • You cannot stack a planner, a productivity expert and a forensic accountant on what a judge may characterise as a single subject matter. If you need all three, seek leave, and seek it early enough that the reports are not wasted.
  • Define each expert's subject matter in the retainer so that the boundary you are asserting is on the record before it is challenged.
  • r 8.16(2) blocks the affiliated-entity workaround. Where several affiliated corporate parties cannot agree, the Court may direct which of them calls the expert, so a group structure cannot be used to field one delay expert per entity.
JurisdictionCap on expert evidenceSource
AlbertaOne expert per subject matter, unless the Court orders otherwise. The Court may direct which of several affiliated corporate parties calls the expertAlberta Rules of Court rr 8.16(1), 8.16(2),
QuebecOne expert per discipline, absent leave. A similar constraint reached by a different route, in a civil-law systemart 232 CCP
OntarioNo equivalent cap

Layer: jurisdictional comparison. Every row rests on secondary sources, the Alberta row is recorded in the corpus as single-source and should be verified against the Rules before it is relied on.

The rest of the Alberta expert machinery is unremarkable but has to be diarised, and it is all recorded as except the Form 25 content requirements. Under rr 5.34 and 5.35 an expert's report must be in Form 25 and must state the expert's name, qualifications, the information and assumptions on which the opinion is based, and a summary of the opinion. Rule 5.35(2) sets a sequenced service order: the party bearing the primary burden serves first, others serve rebuttal (which may raise new issues) and the first party may serve surrebuttal limited to those new issues. Rule 5.36 requires reasonable notice of an admissibility objection and its basis. Rule 5.37 permits questioning an expert before trial only by agreement or, in exceptional circumstances, by court order. Rule 8.4 expects reports to be exchanged before the trial date is set.

Two negative findings complete the picture. No Alberta rule imposes a separate signed expert certification of duty to the court (there is no Ontario Form 53 analogue) so the duty content is carried by the Form 25 requirements plus the common law of White Burgess Langille Inman v Abbott and Haliburton Co, 2015 SCC 23, under which independence is a threshold question of admissibility. And there is no fixed day count for service of expert reports: Alberta works from the sequencing rule plus r 8.4 and case-management orders.

Dismissal for delay: rules 4.31 and 4.33, and the claim that dies after it was filed

A claim that survives the Alberta Limitations Act can still be struck for taking too long to prosecute. This is the Alberta-specific sting, and it belongs at the front of any forum analysis. Two rules do the work: r 4.31 permits dismissal for inordinate and inexcusable delay plus prejudice, with prejudice presumed on long delay, and r 4.33 (the drop-dead rule) requires dismissal where three or more years pass without a significant advance in the action. Once r 4.33 is triggered it is mandatory.

Peters v Countryside Masonry Inc, 2025 ABKB 713 is the warning: a $4M construction claim struck for inordinate delay, with the submission that construction litigation is complex rejected as an excuse. Complexity is the defence every construction plaintiff reaches for, and in Alberta it has been tried and refused.

The limitation clock and the prosecution clock are different animals and answer to different logic. The Alberta Limitations Act runs a basic two-year period from the three-limb discovery test in s 3(1)(a), which includes the requirement that the injury warrants bringing a proceeding. And a ten-year ultimate period, and under s 7(2) a contractual reduction of the period is invalid, so an Alberta limitation period can be extended by agreement but never shortened. None of that helps once the statement of claim is filed. From that point the only clock that matters is the pace of the action itself, and it is the clock nobody diarises. The full set is laid out at the Alberta delay claim clocks matrix.

The interaction with delay claims is unlucky in a specific way. A construction delay claim naturally sits idle while the project finishes, the as-built record is assembled, the final account is negotiated and an expert is instructed. Each of those is a reason not to advance the action, and none of them is a significant advance. Three years of that is enough.

Summary judgment: Weir-Jones, and what Alberta does not use it for

The Alberta summary judgment test is Weir-Jones Technical Services Incorporated v Purolator Courier Ltd, 2019 ABCA 49. Two things about it matter more than the test. It is a commercial courier and services dispute, not a construction case. And there is no located Alberta decision in which a delay claim itself was summarily dismissed or granted under it payment and lien claims go summarily in Alberta, delay claims do not.

Do not cite "Weir-Jones Equipment Co v Fox Creek, 2019 ABCA 25". No such case exists. The name circulates in commentary and in research notes, and reproducing it is a publication defect rather than a citation quibble. It will not be found on any database, because there is nothing there to find.

The test itself has four parts, in the Court's own words. Is it possible to "fairly resolve the dispute on a summary basis, or do uncertainties in the facts, the record, or the law reveal a genuine issue for trial?" Has "the moving party met its burden of proof that there is no merit/defence and that there is no genuine issue requiring a trial?" If so, "the resisting party must put its best foot forward and demonstrate there is a genuine issue requiring a trial." And the presiding judge must be left with "enough confidence in the record … to exercise judicial discretion and summarily resolve the dispute." The moving party proves the factual elements on the balance of probabilities, the resisting party need only show a genuine issue, or a failure of the moving party's burden.

The nearest Alberta decision to a summary delay outcome is Tempo Alberta Electrical Contractors Co Ltd v Man-Shield Construction Inc, 2023 ABKB 44: partial summary judgment of $678,261 on the payment claim, the general contractor's delay and staffing backcharge failing for want of written notice and an opportunity to cure, and the delay damages expressly reserved for trial. That is the pattern the money moves summarily, the schedule question goes to trial. On the security side, A.G. Clark Holdings Ltd v 1352986 Alberta Ltd, 2023 ABKB 219, recorded as , upheld a lien summarily against a bare "delay and poor quality" defence.

The Ontario contrast is sharp and cuts both ways. In Ontario, summary disposition of eight-figure delay claims at the notice gate is an established pattern Elite Construction Inc v Canada (Attorney General), 2021 ONSC 562 dismissed a CAD 4.1M claim for failure to notify within 10 working days and was affirmed on appeal, though the corpus records the appellate neutral citation as unverified. Alberta does not do this. The Alberta claimant's delay claim survives to trial. And so does the cost of getting there. See the Ontario place hub for how the Ontario gate operates.

Getting the court and the chapter right, because a forum page is where the citation work happens

Two Alberta renamings silently break research, and both fall inside the window that matters for delay authority. The Court of Queen's Bench of Alberta became the Court of King's Bench on 8 September 2022: mid-year, not at the year boundary. And the Builders' Lien Act, RSA 2000, c B-7 became the Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 on 29 August 2022, also mid-year.

ChangeEffectiveConsequence for citation
Court of Queen's Bench → Court of King's Bench8 September 2022Alberta 2022 has both 2022 ABQB nnn (to 7 September) and 2022 ABKB nnn (from 8 September). an ABQB citation dated 2023 or later is almost certainly a transcription error for ABKB, do not propagate it
Masters and Masters in Chambers → Applications JudgesSame periodMuch of the Alberta lien-and-delay jurisprudence is Master-level, so the retitling affects how the authority is described as well as how it is found
Provincial Court → Alberta Court of Justice (ACJ)1 April 2023, civil limit $100,000 from 1 August 2023The civil limit is also the figure behind the disputed adjudication cap discussed below
Builders' Lien Act, c B-7 → PPCLA, c P-26.429 August 2022Every Alberta lien and delay authority before that date cites c B-7. A search indexing only P-26.4 silently drops most of the useful material
Two Bill 30sBill 30 (2024) in force 1 April 2025. Bill 30 (2026) as to statusBill 30 (2024) is the Service Alberta Statutes Amendment Act, 2024. The PPCLA and Public Works Act amendments. Bill 30 (2026) is the Expedited 120-Day Approvals Act. Always give the year

Layer: jurisdictional. Both renaming dates are recorded in the corpus as agreed between two independent secondary sources. The Bill 30 (2026) status is unverified.

The authorities on this page illustrate the trap. Graham Construction and Engineering Inc v Alberta (Infrastructure), 2021 ABQB 184 is correctly ABQB because it predates 8 September 2022. Tempo, 2023 ABKB 44, A.G. Clark, 2023 ABKB 219, Quanta, 2024 ABKB 317, Welcome Homes, 2024 ABKB 301, Frog Lake, 2025 ABKB 206 and Peters, 2025 ABKB 713 are all correctly ABKB. Any version of those citations rendered ABQB is wrong.

Arbitration, adjudication and litigation after Bill 30 (2024). And the choice at signature

On private and municipal work under the PPCLA, RSA 2000, c P-26.4, adjudication no longer competes with the other two forums: since the Bill 30 (2024) amendments in force 1 April 2025 a referral may be made up to 30 days after final payment, and it runs concurrently with litigation. On provincial Crown public works under the Public Works Act, RSA 2000, c P-46, none of that is available for a delay claim, because s 14.3(2) excludes schedule changes, completion and milestone dates, and disputes over relief events, designated changes in law, remedial actions and force majeure from adjudication by name.

On the private and municipal side, lien rights and adjudication are independent processes, and a determination may be filed as an order of the court and has the same effect Welcome Homes Construction Inc v Atlas Granite Inc, 2024 ABKB 301. So an Alberta private-sector delay claimant can run an adjudication for cash flow while the action proceeds, and convert the determination into an enforceable order without waiting for trial. Judicial review of a determination is available within 30 days, though the corpus records on whether the operative provision is PPCLA s 33.7 or s 33.8, and there is no reported Alberta judicial review of an adjudicator's determination at all. There is no monetary cap on PPCLA private-sector adjudication.

On the provincial Crown side the position is the reverse of every reader's expectation. Delay is not adjudicable, there is no lien against provincial or federal Crown land, there is no trust of the Crown's money, and the route that matters is the Graham Construction and Engineering Inc v Alberta (Infrastructure), 2021 ABQB 184 route: PWA s 14(3) notice by registered mail within 45 days, strictly enforced: 17 claimants who used the statutory form were paid, 32, including Graham, were shut out. A monetary cap applies to Public Works Act adjudication only, by cross-reference to Court of Justice Act s 9(1)(i), the corpus records on the figure, commentary glossing it as $200,000 while the prescribed Alberta Court of Justice civil limit has been $100,000 since 1 August 2023, and s 9(1)(i) has not been read. Do not print either number without reading the provision. The mechanics of both regimes are set out at prompt payment and adjudication in Alberta.

That leaves the choice a party actually faces when the dispute clause is drafted, which is between arbitration and the Court of King's Bench.

Arbitration
Court of King's Bench of Alberta
Appeal on the schedule findings
None in practice. Delay causation is mixed fact and law, so no question of law arises under Arbitration Act s 44(2), Quanta, 2024 ABKB 317
Ordinary appellate rights on the findings, subject to the usual standards of review
Decision-maker
You appoint someone who has seen a critical path before
A general civil judge. Alberta has no construction list, no construction judges and no construction practice note
Speed and privacy
Faster, private, and the award is not reported, which is part of why Alberta delay law is so thin
Public, slower, and subject to the court's own calendar
Risk to the claim itself
No r 4.31 or r 4.33 exposure
rr 4.31 and 4.33 apply. A $4M construction claim was struck for inordinate delay in Peters, 2025 ABKB 713
Expert evidence
Whatever the tribunal's procedural order allows. An inference from the scope of the Rules of Court, not something the corpus records a decision on
One expert per subject matter under r 8.16(1) unless the Court orders otherwise, and r 8.16(2) constrains affiliated corporate parties
Clock to watch
30 days from receipt of the award to commence any appeal, running to the clerk's FILED stamp, Frog Lake, 2025 ABKB 206
Three years without a significant advance and dismissal under r 4.33 is mandatory

Layer: jurisdictional, and inferential where marked. Every row rests on secondary sources, and the arbitration expert row is the corpus's own inference from the scope of the Alberta Rules of Court.

Arbitration buys speed and privacy at the price of finality on the schedule findings. Litigation keeps appeal rights but exposes the claim to rr 4.31 and 4.33 and puts it before a court with no construction specialisation. There is no option that gives a delay claimant both a specialist decision-maker and a real appeal, and the Alberta answer to which risk is worse is a commercial judgement made at signature rather than a legal one made at dispute.

Two drafting consequences follow. The Arbitration Act permits an arbitration agreement to confer broader appeal rights than s 44(2) allows, so a party that genuinely wants review of a schedule finding must negotiate for it in the clause, because no court will supply it later. And a party that accepts an ordinary arbitration clause should invest at the front end: in the tribunal appointment, in the contemporaneous record, and in the delay expert because the arbitrator's first view of the critical path will be the last.

Authorities

  1. Quanta Canada Holdings II ULC v Bremar Construction Ltd 2024 ABKB 317, Court of King's Bench of AlbertaThe Alberta construction-delay arbitration authority. A Calgary underground duct bank under a CCA 1-2008 Stipulated Price Subcontract. A C$8,137,116 delay-and-defects claim arbitrated and won by the subcontractor. Permission to appeal refused: the arbitrator's legal conclusions were inseparable from the factual findings, so no question of law arose under Arbitration Act s 44(2), notwithstanding that the importance limb was met. Two reported materiality yardsticks, a threshold of roughly 25 per cent or more of the award value, and a satisfied example at $5.1M representing 63 per cent of the award, are recorded in the corpus as single-source.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  2. Esfahani v Samimi 2022 ABCA 178, Court of Appeal of AlbertaPermission to appeal under Arbitration Act s 44(2) is a mandatory, bifurcated first step decided separately before any merits appeal. Section 44(2) is a screening provision which restricts appeals to questions of law alone.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  3. Frog Lake First Nation v 2250657 Alberta Ltd 2025 ABKB 206, Court of King's Bench of AlbertaThe 30-day appeal period in Arbitration Act s 46(1) runs to the moment the clerk stamps the documents FILED, not to when they are submitted. The court's inherent discretion to extend is exercised sparingly and only in the most obvious cases of unfairness, and bureaucratic filing delay is not enough.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  4. Ledcor Construction Ltd v Northbridge Indemnity Insurance Co 2016 SCC 37, Supreme Court of Canada, an Alberta-origin appealStandard form contracts are reviewed on a correctness standard. The corpus records the link from that holding to an argument that interpretation of a standard construction form such as CCDC 2 – 2020 GC 6.5 is an isolable question of law as its own inference, marked unverified, and it should be tested before it is relied on.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  5. Weir-Jones Technical Services Incorporated v Purolator Courier Ltd 2019 ABCA 49, Court of Appeal of AlbertaThe Alberta summary judgment test, in four parts: whether the dispute can fairly be resolved summarily, whether the moving party has met its burden, whether the resisting party has put its best foot forward and shown a genuine issue requiring a trial, and whether the judge is left with enough confidence in the record to resolve the dispute summarily. It is a commercial courier and services dispute, not a construction case. The corpus records as a correction that there is no decision called Weir-Jones Equipment Co v Fox Creek, 2019 ABCA 25.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  6. Tempo Alberta Electrical Contractors Co Ltd v Man-Shield Construction Inc 2023 ABKB 44, Court of King's Bench of AlbertaPartial summary judgment of $678,261 on the payment claim. The general contractor's delay and staffing backcharge failed for want of written notice and an opportunity to cure, and the delay damages were expressly reserved for trial.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  7. A.G. Clark Holdings Ltd v 1352986 Alberta Ltd 2023 ABKB 219, Court of King's Bench of AlbertaA lien summarily upheld against a bare delay and poor quality defence. Recorded in the corpus as single-source.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  8. Peters v Countryside Masonry Inc 2025 ABKB 713, Court of King's Bench of AlbertaA $4M construction claim struck for inordinate delay in prosecuting the action. The submission that construction litigation is complex was rejected as an excuse for the delay.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  9. Welcome Homes Construction Inc v Atlas Granite Inc 2024 ABKB 301, Court of King's Bench of AlbertaLien rights and adjudication under the Prompt Payment and Construction Lien Act are independent processes, and an adjudicator's determination may be filed as an order of the court and has the same effect. Private and municipal work only.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  10. Graham Construction and Engineering Inc v Alberta (Infrastructure) 2021 ABQB 184, Court of Queen's Bench of AlbertaStrict compliance with the Public Works Act s 14(3) 45-day registered-mail notice of claim is mandatory on provincial Crown public works. Seventeen claimants who used the statutory form were paid, thirty-two, including Graham, were shut out.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  11. Elite Construction Inc v Canada (Attorney General) 2021 ONSC 562, Ontario Superior Court of Justice, affirmed on appeal, the appellate neutral citation is recorded in the corpus as unverifiedAn Ontario contrast, not Alberta law. A CAD 4.1M claim dismissed on summary judgment for failure to give notice within 10 working days, and affirmed on appeal. Ontario disposes of large delay claims summarily at the notice gate, Alberta does not.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  12. White Burgess Langille Inman v Abbott and Haliburton Co 2015 SCC 23, Supreme Court of CanadaExpert independence and impartiality are a threshold question of admissibility. In Alberta the duty content is carried by the Form 25 report requirements plus this common law, because no Alberta rule imposes a separate signed certification of duty to the court.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  13. Arbitration Act RSA 2000, c A-43 (Alberta)s 44(2), absent an arbitration agreement conferring broader rights, an appeal lies only on a question of law and only with the court's permission. s 44(2.1), permission requires both that the importance to the parties of the matters at stake justifies an appeal and that determination of the question of law will significantly affect the parties' rights. s 46(1), an appeal must be commenced within 30 days after the appellant received the award. s 53(7), settlement offers may not be disclosed until costs are determined, recorded in the corpus as single-source and Alberta-particular.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  14. Alberta Rules of Court Alberta Rules of Court, rr 4.31, 4.33, 5.34–5.37, 8.4, 8.16r 4.31, dismissal for inordinate and inexcusable delay plus prejudice, discretionary, with prejudice presumed on long delay. r 4.33. The drop-dead rule, dismissal where three or more years pass without a significant advance, mandatory once triggered. rr 5.34 and 5.35, expert reports in Form 25, with sequenced service. r 5.36 reasonable notice of admissibility objections. r 5.37, pre-trial questioning of an expert only by agreement or, exceptionally, by court order. r 8.4, reports ordinarily exchanged before the trial date is set. r 8.16(1). One expert per subject matter unless the Court orders otherwise, r 8.16(2). The Court may direct which of several affiliated corporate parties may call the expert. The expert rules are recorded in the corpus as single-source and r 8.16 is flagged for verification against the Rules.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
  15. Prompt Payment and Construction Lien Act RSA 2000, c P-26.4 (Alberta), from 29 August 2022The renamed Builders' Lien Act, RSA 2000, c B-7, renamed by Bill 37 in force 29 August 2022 and amended by Bill 30 (2024), the Service Alberta Statutes Amendment Act, 2024, in force 1 April 2025. It governs private and municipal work. Adjudication may be referred up to 30 days after final payment and runs concurrently with litigation, delay is adjudicable by consent under the s 19 catch-all, there is no monetary cap. Judicial review of a determination is available within 30 days, with the corpus recording a conflict between s 33.7 and s 33.8 as the operative section. s 1.1 excludes public works as defined in the Public Works Act and agreements with the provincial Crown or a Crown agent.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  16. Public Works Act RSA 2000, c P-46 (Alberta)Governs provincial Crown public works. s 14(3) requires notice of claim by registered mail within 45 days, strictly enforced. s 14.3(2), introduced by Bill 30 (2024) and in force for contracts entered on or after 1 April 2025, excludes from adjudication changes or delays to a construction schedule, completion or milestone dates, and disputes over the interpretation of relief events, designated changes in law, remedial actions and force majeure events. A monetary cap applies to Public Works Act adjudication only.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  17. Court of Justice Act Court of Justice Act (Alberta), s 9(1)(i)The cross-reference that fixes the monetary cap on Public Works Act adjudication. Commentary glosses it as $200,000, but the prescribed Alberta Court of Justice civil limit has been $100,000 since 1 August 2023. The corpus records the figure as conflicted and the provision as unread.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
  18. Limitations Act Alberta, the corpus does not record a chapter number for this statute, so none is printed hereA basic two-year period running from the three-limb discovery test in s 3(1)(a), including the requirement that the injury warrants bringing a proceeding, and a ten-year ultimate period. s 7(2) invalidates a contractual reduction of the period, so an Alberta limitation period may be extended by agreement but not shortened.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on CanLII
  19. CCDC 2 – 2020 Stipulated Price Contract CCDC 2 – 2020, GC 6.5 (Delays)The Canadian building-contract default, cited here only as the example of a standard form whose interpretation may present an isolable question of law. GC 6.5.4 requires notice for time within 10 Working Days of the commencement of the delay. Whether the Alberta Construction Association supplementary conditions package ACA SC CCDC2-2020 amends GC 6.5 could not be established and is recorded in the corpus as the top Alberta verification gap.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
  20. Code of Civil Procedure (Quebec) art 232 CCP (Quebec)Caps expert evidence at one expert per discipline absent leave. Cited here only as the comparator to Alberta's one expert per subject matter under Alberta Rules of Court r 8.16(1). Quebec is a civil-law jurisdiction and no common-law proposition on this page extends to it.No Canadian judgment or consolidated statutory text was read in original form for this corpus, the citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.Find on LégisQuébec

Arbitration and forum in Alberta · Storia