Claims in Canada
Articles7
- Extension of time in CanadaCanadian delay and extension-of-time law is almost entirely common law and contract. No province or territory has a statute addressing construction delay as such. On procedure Canada is close to England and strict, on remedy it…Reviewed Sep 10, 2026
- Delay regimes by Canadian province: what changes at the borderNo Canadian province or territory has a statute addressing construction delay as such, so delay law is common law and contract everywhere. What changes at the border is the machinery around the claim: whether a limitation period…Reviewed Sep 8, 2026
- Notice and time bars in CanadaCanadian courts enforce construction notice clauses as conditions precedent, and the owner need not prove prejudice. Under CCDC 2 – 2020 GC 6.5.4 the contractor has 10 Working Days from the commencement of the delay not from its…Reviewed Sep 10, 2026
- Concurrent delay in CanadaCanadian courts treat delays as concurrent where delays to co-critical and co-controlling activities overlap, and they apportion time and money alike. On remedy that is closer to the United States than to England, which awards a…Reviewed Oct 13, 2026
- Liquidated damages and the penalty rule in CanadaCanada has not adopted Cavendish Square v Makdessi. A delay liquidated damages clause is enforceable only if the rate is a genuine pre-estimate of loss, and is separately vulnerable to an unconscionability challenge. Where the…Reviewed Sep 8, 2026
- Prevention principle and time at large in CanadaIn Canada an owner that has prevented the contractor from completing on time cannot insist on liquidated damages, and where no extension is granted the completion date can fall away. Perini Pacific is the anchor, but the domestic…Reviewed Sep 10, 2026
- Prolongation and delay costs in CanadaCanadian law compensates delay through two routes: the contract's own reimbursement clause and damages for breach. Extended site overhead, unabsorbed head-office overhead, equipment standby and acceleration are all recoverable in…Reviewed Sep 8, 2026
The notice brief
One email a month on claims, notices and the cases that decided them.
The notice briefIssue 01 · sample
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.