Concurrent delay in Canada
Canadian courts treat delays as concurrent where delays to co-critical and co-controlling activities overlap, and they apportion time and money alike. On remedy that is closer to the United States than to England, which awards a full extension and no money. The corpus records that comparison as an inference from the authorities, not a proposition any court has stated.
At a glance
- Doctrine
- Canada, common-law provinces
- Excludes Quebec
- Functional concurrency, apportionment of time and money
- First instance only, no appellate decision located
Key facts
- 01
The short answer
Canada apportions. Where multiple parties contribute overlapping delay, Canadian courts divide time and money rather than awarding the contractor the whole extension. ★ Do not import the English "full extension of time for concurrency" rule orthodox English law does not apportion, and Canadian law does.
- 02
The test
Functional concurrency. Delays are concurrent where delays to co-critical and co-controlling activities overlap (Schindler Elevator Corp v Walsh Construction Company of Canada, 2021 ONSC 283). A stricter requirement of identical duration or precise parallelism was expressly rejected. It is the broadest of the definitions compared in this corpus.
- 03
Causation
The but-for test applied robustly and with common sense, with material contribution reserved for the exceptional case in which but-for causation cannot be proved.
- 04
Time and money
Both apportioned. On a four-week overrun with an owner event and a contractor event each independently critical, the Canadian outcome is an apportioned extension, apportioned prolongation cost, and liquidated damages recoverable by the owner for the unapportioned balance.
- 05
The evidentiary standard
Schindler requires the overall postponement to be broken "into its component parts to apportion the time, responsibility and costs", with the delays connected to the project's critical path. Decompose, date, connect, apportion. That, not a method label, is the Canadian instruction.
- 06
The defendant's trap
★ Never run a critique-only defence. In Walsh Construction v Toronto Transit Commission, 2024 ONSC 2782 the defendant critiqued without producing a competing analysis, which forced the court into a binary 1,047-versus-411-day outcome. A defendant without its own number invites an all-or-nothing finding.
- 07
What the contract says
Nothing. CCDC 2 – 2020 GC 6.5 allocates delay by cause and says nothing about concurrency. Supplementary conditions rarely address it either, which makes the question a pure common-law and evidential one under Canadian standard forms.
- 08
What is missing
No Canadian appellate decision squarely on concurrent delay was located for 2024–2026. No Canadian judgment cites the SCL Delay and Disruption Protocol. Only Walsh v TTC cites AACE RP 29R-03. The law rests on first-instance authority.
Canada apportions. Where two parties each contribute to the same period of overrun, a Canadian court divides the time and divides the money. It does not hand the contractor the whole extension because an owner event happened to be running. An English practitioner who arrives with Malmaison in hand is bringing the wrong rule, and will find that a Canadian judge is asking a question English law has spent twenty-five years avoiding: how much of this delay is whose?
That places common-law Canada between England and the United States, nearer England on procedure and notice, nearer the United States on remedy. The corpus records that characterisation as an inference from the authorities, not a proposition any Canadian court has stated in those terms, and it should be pleaded that way. There is no Canadian judgment that says "Canada apportions concurrent delay". There are Canadian judgments that apportion.
The second thing to know before the doctrine is that the doctrine's national footprint is thin, but that understates British Columbia specifically. Outside BC, mainstream Canadian concurrency law rests on two first-instance decisions, both Ontario, with no appellate decision squarely on concurrency located for 2024–2026, and there is a third strand in Alberta, SINGLE-SOURCE and unverified, running a but-for / dominant-cause formulation that sits in tension with apportionment. But BC has its own, older apportionment line, including an appellate authority: Foundation Co of Canada Ltd v United Grain Growers Ltd1, (1997), 91 BCAC 254 (BCCA), apportioned 75% to the owner and engineer, 25% to the contractor. Below that, BC first-instance decisions split between precise apportionment (Kraft Construction Co v Martech Electrical Systems Ltd2, 2004 BCSC 703, allocated roughly 50%/25%/25% week-by-week despite an acknowledged inability to match the delays temporally, and Pacific Coast Construction Co Ltd v Greater Vancouver Regional Hospital District3, (1986), 23 CLR 35 (BCSC), allocated day-by-day) and rough-justice apportionment, where Evergreen Building Ltd v H Haebler Co Ltd4, (1983), 5 CLR 70 (BCSC), declined a granular schedule analysis entirely and split responsibility two-thirds/one-third on impression. East Kootenay Community College v Nixon & Browning5, [1985] BCJ No 766 (BCSC), aff'd [1988] BCJ No 313, adds a burden-shifting frame: the owner must prove contractor-caused delay first, and only then does the contractor have to show the project would have been delayed regardless. This line is old, largely invisible to current national commentary, and not being actively developed: a BC court asked to decide concurrency today would probably reach for the Schindler analytical framework even while landing in this apportionment tradition on outcome. Brief both.
That is not a reason to discount any of it. It is the reason the evidence, rather than the rule, decides Canadian concurrency cases. For the wider setting see extension of time in Canada, and for the competing models this page departs from, the neutral treatment of concurrent delay.
What "concurrent delay" means in Canada, and why the definition decides the case
In common-law Canada, delays are concurrent where delays to co-critical and co-controlling activities overlap. That is the test in Schindler Elevator Corporation v Walsh Construction Company of Canada6 2021 ONSC 283, and the court expressly rejected a stricter requirement of identical duration or precise parallelism. Overlap of effect is enough. The definition, not the remedy, is where most Canadian concurrency arguments are won.
That matters because the definition is the widest in circulation. A narrow definition finds concurrency rarely and leaves the tribunal to pick a single dominant cause, a wide definition finds concurrency often, and once concurrency is found in Canada the consequence is apportionment. Canada's breadth on the definition is the reason Canada apportions more than its neighbours do.
| Source | Definition of concurrency | Practical effect |
|---|---|---|
| Canadian case law, Schindler, 2021 ONSC 283 | Delays to co-critical and co-controlling activities that overlap. No requirement of identical duration or precise parallelism | Broadest of the five, and the reason Canada apportions more |
| SCL Delay and Disruption Protocol, 2nd Edition (February 2017), Core Principle 10 | True concurrency, two events occurring at the same time whose effects are felt at the same time. The Protocol notes this is extremely rare. Distinguished from concurrency of effect | Narrow, and contractor-favourable in England because the outcome is a full extension |
| AACE International RP No. 29R-03 (rev. 25 April 2011) | Several working definitions rather than one, emphasises the technical difficulty of isolating impact | Method-driven, forces the analyst to declare an approach |
| ANSI/ASCE/CI 67-2017 (cited in some sources as ASCE 67-17) | "Two or more critical delays occurring at the same time" (recorded in this corpus via a secondary source) | Narrow |
| United States case law | Two aspects, temporal (the same delay period) and causation (each cause independently sufficient) | Narrow, and the burden of disproving concurrency sits with the contractor |
Layer, comparative and inferential. The Canadian row rests on a single first-instance judgment and, like every Canadian entry in this corpus, on secondary sources: no Canadian judgment was read in original text. The other rows describe industry documents and foreign case law, not Canadian law.
The practical consequence for an expert report is that the Canadian definitional threshold is easier to cross than the one an English or American expert is trained to apply. An analyst who imports the true-concurrency test of the Society of Construction Law Delay and Disruption Protocol7 into a Canadian report will find concurrency almost nowhere, will present a single-cause case, and will be met with a Schindler submission that co-critical activities overlapping is all that was ever required: and, separately, will be relying on a document no Canadian judgment has ever cited.
Schindler Elevator Corp v Walsh Construction, 2021 ONSC 283. The leading authority and the Canadian critical-path standard
Schindler Elevator Corporation v Walsh Construction Company of Canada, 2021 ONSC 283 is the leading Canadian statement on concurrency, and it does two jobs. It sets the functional-concurrency definition, overlapping delays to co-critical and co-controlling activities. And it sets the Canadian evidentiary standard for critical-path proof, which is the part that decides cases.
On causation the decision is orthodox and unglamorous: the test is the but-for test applied robustly and with common sense, with material contribution reserved for the exceptional case in which but-for causation cannot be proved. There is no Canadian doctrine of dominant cause sitting on top of it, and no Canadian equivalent of the English approximately-equal-potency formula.
On proof it is demanding. CPM analysis identifying which activities were critical, who controlled them, and their effect on completion is effectively required, and the court warned against oversimplified expert evidence on concurrency. The instruction it gave is the sentence to build a delay report around: the overall postponement must be broken
"into its component parts to apportion the time, responsibility and costs"
Read that as a four-step method rather than as a rule of law: decompose, date, connect, apportion. It is method-agnostic by design. Because there is no Canadian national delay-analysis standard and no Canadian court has accepted or rejected a named methodology as a matter of law, whatever technique delivers a dated, decomposed, apportioned account of the postponement will be received, see the neutral survey of delay analysis methods for the techniques themselves.
Schindler also enumerated the records that do the connecting work: "work tickets, emails, incidents, shop drawings, shutdowns due to safety concerns, monthly reports and schedules", with clear dates and operational connections. That list is the court's own, and it is the most portable thing in the judgment.
Walsh Construction v Toronto Transit Commission et al, 2024 ONSC 2782: functional concurrency, expert credibility, and the critique-only trap
Walsh Construction v Toronto Transit Commission et al8 2024 ONSC 2782 (Hood J) endorsed the flexible, overlapping-events approach to concurrency and required a "clear and rational opinion, based on contemporaneous records". It is now the leading recent Canadian decision on delay-expert practice as much as on concurrency, and it is where the practical lessons live.
Layer, jurisdictional, and first instance. The figures are reported in secondary sources, no Canadian judgment was read in original text for this corpus.
Expert bias was raised and rejected. The challenge was founded on the expert's contemporaneous involvement in the project during the works, and it failed. Prior project involvement does not disqualify a Canadian delay expert.
Methodological latitude was granted, and it was conditional. Departures from AACE International Recommended Practice No. 29R-039 (rev. 25 April 2011) were tolerable because the recommended practice itself "allows for various adjustments and options" and "usually requires subjective decisions by the expert". That is latitude, not licence. A Canadian court will forgive a departure it can follow, and will not forgive one it cannot. Every subjective choice needs a written justification tied to a contemporaneous document.
★ The critique-only trap, which is the defendant's trap and not the claimant's. The Toronto Transit Commission ran a critique with no competing analysis of its own. That forced the court into a binary 1,047-versus-411-day outcome and removed its ability to land anywhere in the middle, which is usually where the truth is, and almost always where a defendant would prefer to be. In a jurisdiction whose remedy is apportionment, refusing to produce a number of your own is the single most expensive tactical decision available. A defendant that wants an apportioned result must give the court the materials to apportion with.
The owner's own documents did the damage. The Commission's own consultant had found that "the average time for responding to RFIs was also excessively high", and that finding materially supported the contractor. RFI turnaround is provable from the owner's records, and in Canada it is routinely decisive.
Walsh v TTC is also an acceleration case: acceleration costs were awarded where the owner caused delay through design delays and repeated changes. One further proposition is attributed to it. That a contractor's genuine acceleration effort supported by contemporaneous records can establish constructive acceleration without any direction to accelerate. That attribution rests on a single source and is unverified in this corpus. It is flagged in the verification register and should be checked against the judgment before it is deployed, because if it is correct it is the most recent significant Canadian acceleration authority.
There is Alberta authority, and it points the other way
Alberta is the exception to the apportionment picture, and a page that says the Canadian law of concurrency is Ontarian is incomplete. In Graham Construction & Engineering (1985) Ltd v LaCaille Developments Inc10, 2006 ABQB 898, a contractor responsible for part of a delay was held able to recover where "the project would not have been completed any sooner" had its own delay not occurred. That is a but-for / dominant-cause formulation from an Alberta superior court, and it is closer to Malmaison-style relief than to apportionment. The corpus records it as SINGLE-SOURCE and unverified against the judgment, and it therefore sits in tension with the apportionment approach taken elsewhere in Canada rather than displacing it. Plead it in Alberta as an available argument, verify it first, and expect the other side to say the rest of Canada apportions.
Two older Alberta decisions sit behind it, both SINGLE-SOURCE. Vanir Construction Services Ltd (Receiver of) v Field Aviation Co11, 1988 CanLII 3845 (AB QB), affirmed 1992 (Alta CA), is the mirror image of the usual case: a contractor defeated the owner's delay claim by showing that owner-initiated changes caused the delay. And Alberta Engineering Co v Blow (1914), 28 WLR 391 allows an owner to reduce its delay damages by counterclaim on proof of contractor contribution, a nineteenth-century-style apportionment instinct predating any of the modern doctrine. The Alberta cluster develops the point at extension of time in Alberta.
How Canada differs from England, the United States, Scotland and Quebec
Canada apportions time and money. England awards the full extension and no prolongation cost. The United States usually excuses the delay but pays nothing unless the evidence permits clear apportionment. Scotland apportions, like Canada. Quebec has no concurrency doctrine at all and resolves overlapping delay through apportionment of fault. On a single fact pattern the spread is total.
| Jurisdiction | Working rule | Time | Money | Authority level |
|---|---|---|---|---|
| Canada (common-law provinces) | Functional concurrency: overlapping delays to co-critical, co-controlling activities, but-for applied robustly, apportionment available | Apportioned | Apportioned | First instance only, no appellate decision located 2024–2026 |
| ★ Alberta | ★ But-for / dominant cause: recovery where "the project would not have been completed any sooner" but for the contractor's own delay (Graham v LaCaille, 2006 ABQB 898). SINGLE-SOURCE, unverified, in tension with apportionment elsewhere | Potentially full | Potentially full | First instance, and unverified |
| England & Wales | Malmaison, full extension where an employer risk event is an effective cause of approximately equal potency | Full | Nil | First instance |
| Scotland | Apportionment of the delay, by a majority (City Inn) | Apportioned | Apportioned | Appellate (Inner House), and expressly rejected in England |
| United States | A rule of proof. No recovery unless the evidence permits clear apportionment | Usually full | Nil unless apportionable | Appellate (Federal Circuit) |
| Quebec (civil law) | No concurrency doctrine. Apportionment of fault under the general law of obligations | Apportioned | Apportioned | Civil-law framework, not a concurrency rule |
Layer, comparative and inferential. The Canadian row rests on first-instance authority and on secondary sources. No Canadian judgment was read in original text for this corpus. The Alberta row rests on a single unverified source and states an outlier, not a settled provincial rule. The England, Scotland and United States rows are included for contrast only and state no Canadian rule.
Worked on identical facts. A four-week overrun, an employer variation and a contractor labour shortage each independently critical over the same four weeks, no express concurrency clause:
| Jurisdiction | Extension of time | Prolongation cost | Liquidated damages recoverable by the owner |
|---|---|---|---|
| Canada | Apportioned | Apportioned | For the unapportioned balance |
| England & Wales | 4 weeks | Nil | Nil for the 4 weeks |
| Scotland | Apportioned, e.g. 2 weeks | Apportioned | For the unapportioned balance |
| United States | 4 weeks (excusable) | Nil, unless clearly apportionable | Nil for the 4 weeks |
Layer, illustrative. A worked comparison on hypothetical facts, not a report of any decided case. The Canadian outcome is the corpus's inference from the authorities.
England. Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd12 (1999) 70 Con LR 32 gives the contractor the whole extension where an employer risk event is an effective cause of approximately equal causative potency, and the concurrency passage is Dyson J at first instance, recording a position the parties agreed, not the later Court of Appeal decision, which was on a different point. ★ Do not import that rule into a Canadian claim. A Canadian contractor arguing "concurrency, therefore full extension of time" is arguing for a remedy Canadian courts do not give, and is declining to put before the court the apportionment material on which it would actually recover.
The United States. The American rule is a rule of proof rather than of entitlement: the delay is usually excusable, but nothing is paid unless the evidence permits clear apportionment, and the burden of disproving concurrency sits with the contractor. Canada arrives at a similar destination, money follows what can be apportioned, by a different route, because Canadian courts will themselves divide the period rather than treating failure to apportion as fatal to the whole claim.
Scotland. City Inn Ltd v Shepherd Construction Ltd13 [2010] CSIH 68 held, by a majority (Lord Carloway rejecting apportionment), that it was open to the decision-maker to apportion the delay, and is appellate authority. It was expressly rejected in England. Canada's working position is closer to Scotland's than to England's on outcome, though no Canadian judgment adopts City Inn as its reasoning, and it should be used as a comparative illustration rather than as authority in a Canadian court.
Quebec is carved out entirely. Quebec is a civil-law jurisdiction with no doctrine of concurrent delay, no time at large and no penalty-versus-liquidated-damages characterisation. Overlapping delay is resolved through apportionment of fault under the general law of obligations, with meeting the completion date treated as an obligation of result, so the burden starts the contractor further back than any common-law rule does. Nothing on this page governs a Quebec project, go to concurrent delay in Quebec.
What CCDC 2 – 2020 says about concurrency: nothing
CCDC 2 – 2020, GC 6.5 (Delays)14 says nothing about concurrency. It allocates delay by cause. Owner or Consultant delay contrary to the Contract Documents (GC 6.5.1, compensable), stop work orders (GC 6.5.2, compensable) and neutral events (GC 6.5.3, time only), without addressing what happens when two causes overlap. CCDC 2 – 2020 remains the current edition as at August 2026, there is no 2025 or 2026 update.
That silence is compounded by GC 6.5.3.4's carve-back: a cause beyond the Contractor's control is time-only unless the delay in fact results from Owner or Consultant action. So the form's own machinery routes a mixed-cause delay straight back into a factual inquiry about who caused what. And supplements it with no rule for splitting the result. Supplementary conditions rarely address concurrency either. The combined effect is that concurrency under Canadian standard forms is a pure common-law and evidential question, decided on the record rather than on the clause. Read the executed supplementary conditions before relying on GC 6.5 in any form, because they almost universally amend it.
One clause does bite before concurrency is ever reached. GC 6.5.4 requires written notice within 10 Working Days of the commencement of the delay, of the commencement, not of its effect. And Ontario courts treat that as a condition precedent. Technicore Underground Inc v Toronto (City)15 2012 ONCA 597 confirms that compliance is strict and that the owner need not prove prejudice. In practice a Canadian concurrency argument is often never reached, because the claim died on notice months earlier, see notice and time bars in Canada.
What actually wins a Canadian concurrency case, and the expert who can carry it
Contemporaneous records win, and the expert who can explain them survives. Canada has no national delay-analysis standard, so there is no method label that confers admissibility and none that forfeits it. What the case law imposes instead is a burden (connect the delay to the critical path, per Schindler) and a documentary expectation, ground every subjective choice in a contemporaneous document, per Walsh v TTC.
The records the Canadian judgments actually relied on are specific enough to build a project filing system around: work tickets, emails, incidents, shop drawings, safety shutdowns, monthly reports and schedules with clear dates and operational connections (Schindler), schedule data and change-condition logs, which in Walsh v TTC meant more than 780 owner-related change conditions across 48 windows, and an RFI and submittal log carrying response times, because the owner's own turnaround is provable and was decisive. The neutral guidance on records and evidence sets out the wider discipline. The Canadian point is that the court will ask for dates and operational connections, not for a narrative.
On the expert, White Burgess Langille Inman v Abbott and Haliburton Co Ltd16 2015 SCC 23 puts independence, impartiality and absence of bias into the threshold admissibility question at the qualification stage. Not into weight. The duty is to give "fair, objective, and non-partisan opinion evidence". The threshold is low: an expert is excluded only where unable or unwilling to comply, and residual concerns go to weight at the gatekeeping stage. This bites harder on delay experts than on most, because the normal Canadian pattern is a delay consultant who worked on the project during the works, which exposes the expert at the threshold rather than merely on weight. It is worth recording that the corpus flags as unverified that the Walsh v TTC judgment contains no express reference to White Burgess. If that is right, the leading Canadian delay-expert case does not itself apply the leading Canadian expert-evidence case, which is a gap worth knowing about when the point is argued.
What Canadian law on concurrency does not contain
The gaps are as load-bearing as the rules, and they should be stated rather than hedged. Outside British Columbia, mainstream Canadian concurrency law is two first-instance Ontario decisions deep, with a single-source and unverified Alberta strand alongside it. It engages one industry standard once, and, outside BC, it has no appellate layer at all. BC is the exception: its own, older apportionment line does reach the Court of Appeal in Foundation Co v UGG, but that line is old, invisible to current national commentary, and has never been reconciled with an earlier BCCA reading of Perini Pacific as denying recovery to both parties without apportionment at all. A submission built on any of the following, outside BC, is a submission built on nothing.
- ★ No Ontario- or Alberta-level Canadian appellate decision squarely on concurrent delay was located for 2024–2026, and BC's own appellate authority is decades old and undeveloped. The mainstream law rests on first-instance authority, the same structural weakness as England's, arrived at from a different starting point.
- ★ No Canadian judgment cites the SCL Delay and Disruption Protocol: not one, in any province, at any level. An expert who leans on the Protocol as authority in a Canadian court is relying on a persuasive industry document with zero Canadian judicial pedigree, and should expect that to be put to them. Use it as a framework and say so.
- ★ No Canadian judgment other than Walsh v TTC cites AACE RP 29R-03. That makes Walsh the first and, so far as can be found, the only Canadian judicial engagement with the recommended practice.
- ★ No Canadian judgment uses the phrase "global claim". There is no Canadian analogue to the English global-claims case law, and therefore no Canadian framework for pleading one.
- ★ Canada has no national delay-analysis standard, guideline or "made in Canada" methodology, and no Canadian court has accepted or rejected a named methodology as a matter of law. Nothing is excluded and nothing is presumptively accepted, the methodology fight is evidentiary and persuasive, not one of legal admissibility. There is no Canadian equivalent of a court holding that a named technique is impermissible.
- ★ No reported decision in England, Canada or Australia turns on pacing as a named doctrine. A pacing argument in Canada is a factual argument about why the contractor slowed, run through causation and the contemporaneous record, not the invocation of a recognised defence.
- No Canadian province or territory has a statute addressing construction delay claims as such, no statutory extension-of-time entitlement, no statutory concurrency rule and no statutory delay-analysis standard, anywhere in Canada.
- Do not press CIMIC into the gap. CIMIC Morningstar Investments Ltd v Chandos Construction Ltd17 2026 BCCA 2 is sometimes cited in this space, but it is a leave decision refusing leave to appeal an arbitral award. The arbitrator had found the owner's design changes and late approvals materially contributed to delay and applied the prevention principle to put time at large, upholding a CAD 6.47M award. It confirms curial deference to arbitral delay findings. It does not restate doctrine, and the underlying award is not public.
One consequence of the thinness is worth stating plainly for anyone deciding how much to invest in a concurrency case: most Canadian delay claims settle confidentially, which suppresses precedent and is the reason the domestic body of authority is as small as it is. The corollary is that the record, the expert and the apportionment arithmetic (not the citation list) are what a Canadian tribunal will be working from.
Sources and authorities
- *Verification, unless noted
No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
- 1Foundation Co of Canada Ltd v United Grain Growers Ltd(1997), 91 BCAC 254 (BCCA)
Percentage apportionment of concurrent delay at appellate level: owner and engineer 75%, contractor 25%, run against the owner in contract and against the consulting engineer in negligent misrepresentation. This is British Columbia's appellate concurrency authority, and it sits in unaddressed tension with an earlier BCCA reading of Perini Pacific as denying recovery to both parties without apportionment.
- 2Kraft Construction Co v Martech Electrical Systems Ltd2004 BCSC 703, 36 CLR (3d) 163
Apportioned concurrent delay week-by-week, roughly 50%/25%/25% among the parties, despite an acknowledged inability to match the delays temporally. Precision is not a precondition to a British Columbia apportionment. (Not to be confused with an earlier, unrelated 2001 BCSC 1306 decision in the same litigation on third- and fourth-party procedure.)
- 3Pacific Coast Construction Co Ltd v Greater Vancouver Regional Hospital District(1986), 23 CLR 35 (BCSC)
Precise, day-by-day apportionment: one period allocated to the contractor, a second to the owner, and a third period to neither party on account of unanticipated conditions.
- 4Evergreen Building Ltd v H Haebler Co Ltd(1983), 5 CLR 70 (BCSC)
"Rough justice" apportionment: the trial judge declined a day-by-day analysis and allocated responsibility two-thirds/one-third instead. British Columbia authority that a court may refuse a granular schedule analysis and apportion impressionistically, a real risk for a claimant who has invested heavily in a windows analysis.
- 5East Kootenay Community College v Nixon & Browning[1985] BCJ No 766 (BCSC), aff'd [1988] BCJ No 313, (1988), 28 CLR 189 (BCCA)
Burden-shifting approach to concurrent delay in British Columbia: the owner bears the burden of proving contractor-caused delay first, and the contractor then shows the project would have been delayed regardless.
- 6Schindler Elevator Corporation v Walsh Construction Company of Canada2021 ONSC 283, Ontario Superior Court of Justice
The leading Canadian concurrency authority. Delays are concurrent where delays to co-critical and co-controlling activities overlap, a stricter requirement of identical duration or precise parallelism was expressly rejected. Causation is the but-for test applied robustly and with common sense, with material contribution reserved for the exceptional case. CPM analysis identifying which activities were critical, who controlled them and their effect on completion is effectively required. It is also the source of the Canadian critical-path evidentiary standard, the overall postponement must be broken "into its component parts to apportion the time, responsibility and costs", and the court enumerated the records that connect a delay to the critical path: work tickets, emails, incidents, shop drawings, shutdowns due to safety concerns, monthly reports and schedules, with clear dates and operational connections.
- 7Society of Construction Law Delay and Disruption Protocol2nd Edition, February 2017
Core Principle 10 defines true concurrency as two events occurring at the same time whose effects are felt at the same time, and notes that it is extremely rare, it is distinguished from concurrency of effect, where events arising at different times produce simultaneous effects. Recorded negative finding, no Canadian judgment cites the Protocol, in any province, at any level. In a Canadian court it is a persuasive industry document with zero domestic judicial pedigree.
- 8Walsh Construction v Toronto Transit Commission et al2024 ONSC 2782, Ontario Superior Court of Justice, Hood J
Endorsed the flexible, overlapping-events approach to concurrency and required a "clear and rational opinion, based on contemporaneous records". The leading recent Canadian decision on delay-expert practice as much as on concurrency. A bias challenge founded on the expert's contemporaneous involvement in the project was rejected. Departures from AACE RP 29R-03 were tolerable because the recommended practice itself "allows for various adjustments and options" and "usually requires subjective decisions by the expert". The accepted expert divided the project into 48 windows and produced 1,047 compensable days, the opposing expert critiqued rather than analysed, leaving the court a binary 1,047-versus-411-day choice. The owner's own consultant had found that "the average time for responding to RFIs was also excessively high". Acceleration costs were awarded where the owner caused delay through design delays and repeated changes. The trial ran 161 days.
- 9AACE International Recommended Practice No. 29R-03, Forensic Schedule AnalysisAACE RP 29R-03, rev. 25 April 2011
Supplies several working definitions of concurrency rather than one, and emphasises the technical difficulty of isolating impact. It is the only delay standard engaged by any Canadian judgment. The public table of contents still shows rev. 25 April 2011. A draft revision existed in 2023 and AACE's member catalogue was not accessible, so the revision status should be checked before the recommended practice is cited in an expert report.
- 10Graham Construction & Engineering (1985) Ltd v LaCaille Developments Inc2006 ABQB 898, Court of Queen's Bench of Alberta
Where a contractor is responsible for part of a delay but the project would not have been completed any sooner had the contractor's delay not occurred, the contractor may still recover notwithstanding its own contribution. That is a but-for or dominant-cause formulation from an Alberta superior court, closer to the Malmaison relief line than to the apportionment approach applied elsewhere in Canada, and it sits in tension with that approach. The corpus records the decision as SINGLE-SOURCE and unverified against the judgment.
- 11The older Alberta line. Vanir Construction and Alberta Engineering v BlowVanir Construction Services Ltd (Receiver of) v Field Aviation Co, 1988 CanLII 3845 (AB QB), aff'd 1992 (Alta CA). Alberta Engineering Co v Blow (1914), 28 WLR 391
In Vanir a contractor defeated the owner's delay claim by showing that owner-initiated changes caused the delay. Alberta Engineering Co v Blow allows an owner to reduce its delay damages by counterclaim on proof of contractor contribution. Both are recorded in the corpus as SINGLE-SOURCE.
- 12Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd(1999) 70 Con LR 32, Dyson J at first instance, England and Wales
Where an employer risk event is an effective cause of delay of approximately equal causative potency with a contractor risk event, the contractor is entitled to the full extension of time notwithstanding the concurrent contractor delay. The concurrency passage is Dyson J at first instance, recording a position the parties agreed. The later Court of Appeal decision was on a different point, and the citation "[2000] EWCA Civ 175" is recorded in this corpus as a widely repeated error.
- 13City Inn Ltd v Shepherd Construction Ltd[2010] CSIH 68, Inner House, Court of Session, Scotland
The majority (Lord Osborne, Lord Kingarth) held it open to the decision-maker to "apportion the delay"; Lord Carloway rejected apportionment while concurring in the result. Appellate authority in Scotland, and expressly rejected in England.
- 14CCDC 2 – 2020, Stipulated Price Contract, GC 6.5 DelaysCCDC 2 – 2020, GC 6.5
Allocates delay by cause. Owner or Consultant delay contrary to the Contract Documents (6.5.1, compensable), stop work orders (6.5.2, compensable) and neutral events (6.5.3, time only). And says nothing about concurrency. GC 6.5.3.4 carves back: a cause beyond the Contractor's control is time-only unless the delay in fact results from Owner or Consultant action. GC 6.5.4 requires written notice within 10 Working Days of the commencement of the delay. CCDC 2 – 2020 remains the current edition as at August 2026, no 2025 or 2026 update exists.
- 15Technicore Underground Inc v Toronto (City)2012 ONCA 597, Court of Appeal for Ontario
Strict compliance with a contractual notice provision is required, and the owner need not prove prejudice from late or absent notice.
- 16White Burgess Langille Inman v Abbott and Haliburton Co Ltd2015 SCC 23, Supreme Court of Canada
Expert independence, impartiality and absence of bias are a threshold admissibility question at the qualification stage, not merely a matter of weight. The expert's duty is to give "fair, objective, and non-partisan opinion evidence". The threshold is low. An expert is excluded only where unable or unwilling to comply, and residual concerns go to weight at the gatekeeping stage.
- 17CIMIC Morningstar Investments Ltd v Chandos Construction Ltd2026 BCCA 2, Court of Appeal for British Columbia
A leave decision refusing leave to appeal an arbitral award under section 59 of British Columbia's Arbitration Act. The arbitrator had found that the owner's design changes and late approvals materially contributed to delay and applied the prevention principle to put time at large, upholding a CAD 6.47M award. It confirms curial deference to arbitral delay findings, it does not restate doctrine, and the underlying award is not public. Do not cite it as an appellate statement of the prevention principle or of concurrency.
General information, not legal advice. Reviewed Oct 13, 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.