Claim deadline register: construction notice, payment and limitation periods

A register of the claim deadlines this library records for Ontario, British Columbia, United States federal contracts, England and Wales and FIDIC 2017: notices of delay and claims, payment and adjudication steps, liens and limitation periods. Each row gives the instrument and clause, the event that starts the clock, the period, what missing it does, how far the rule has been verified, and the library page that states it.

Reviewed Nov 24, 20262 min read0 sources

At a glance

General practice
Last reviewed
24 November 2026
Class
Tool. A reference register of claim deadlines
Jurisdiction
Ontario, British Columbia, United States (federal), England and Wales, FIDIC 2017
Not legal advice
Default periods. The executed contract, its amendments and the governing law decide the deadline
§ 00

Key facts

  1. 01

    What it lists

    Contract notice periods, statutory payment and adjudication steps, lien periods and limitation periods, one table per regime.

  2. 02

    Evidence levels

    Each row says whether the rule was read in an official source, rests on this library only, or comes from a licensed standard form that was not read.

  3. 03

    Standard forms

    CCDC, AIA, JCT, NEC4 and FIDIC rows give the printed default. Projects routinely amend them.

  4. 04

    To get a date

    Use the claim deadline calculator.

Every claim deadline this library records for Ontario, British Columbia, US federal contracts, England and Wales and FIDIC 2017, in one table per regime. Each row links to the page that states the rule and says how far it has been verified. To turn a row into a date, use the claim deadline calculator.

§ 01

How to read the register

The trigger is the event that starts the clock, in the words of the source. The period is counted from the day after it, or, for a step due before an event, counted back from it. A waiting period ends before you may act: act from the day after it ends. A window gives both ends. Where the library advises working to a shorter period, the period cell says so, and where a rule applies only to some contracts, the condition is shown under the period. Cut-offs, such as costs incurred more than 20 days before a notice, are stated in words. The consequence says what missing the deadline does to the right the row covers: a lien row that bars the lien does not, on its own, bar the debt.

The evidence column has four values. Read in an official source: the statute or regulation was read in an official consolidation or the enacting text. Library only: the period is stated on a library page but was not re-read in an official source. Standard form: the printed default of a licensed form, which projects routinely amend. No fixed date: the rule has no period you can count, is a cut-off rather than a clock, or has no trigger stated in the library; the row then also says whether it was read in an official source or rests on the library only.

§ 02

The register

Ontario: 36 deadlines
DeadlineInstrument and clauseTriggerPeriodConsequenceEvidenceLibrary
Notice of delay (claim for extension of Contract Time)
  • amendments common
CCDC 2 – 2020, GC 6.5.4the commencement of the delay10 working days (last day)Time barThe claim itself. There is nothing left to bringStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Waiting period before requesting an extension for the Consultant's failure to furnish instructions
  • amendments common
CCDC 2 – 2020, GC 6.5.5demand for instructions, where no schedule was made under GC 2.2.1210 working days (a waiting period: act from the day after it ends)Not a time barStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Subcontractor notice of claim for extension of subcontract time
  • amendments common
  • UNVERIFIED
CCA 1 – 2021Not stated7 working days (last day)Probably a time barStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Application to extend the Contract Time
  • amendments common
  • UNVERIFIEDunit of 'Days'
OPSS.MUNI 100 (November 2019), GC 3.06.01the expiration of the Contract Time15 calendar days (counted back from the event)Probably a time barStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Application for extension of Contract Time on MTO form PH-CC-756
  • amendments common
OPSS.PROV 100 (April 2023), GC 3.06the need for the extension becomes evidentNo fixed period (promptly)Probably a time barA contractor that writes a well-drafted letter instead of form PH-CC-756 has not applied for anythingStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Notice of intention to claim a change in Contract Price
  • amendments common
CCDC 2 – 2020, GC 6.6.1intention to claim a change in Contract PriceNo fixed period (promptly)UnsettledStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Compensation Request after cost-estimate submission
  • amendments common
OPSS.PROV 100 (April 2023), GC 3.14cost-estimate submission10 calendar days (last day)UnsettledStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Unresolved change-order pricing
  • amendments common
OPSS.PROV 100 (April 2023), GC 3.14Not stated10 business days (last day)UnsettledStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Verbal notice of a potential claim situation
  • amendments common
OPSS.MUNI 100 (November 2019), GC 3.13.03becoming aware of a potential claim situationNo fixed period (promptly)UnsettledStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Written Notice of Intent to Claim
  • amendments common
  • UNVERIFIEDunit of 'Days'
OPSS.MUNI 100 (November 2019), GC 3.13.03the commencement of any part of the Work affected7 calendar days (last day)Probably a time barStandard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Detailed claim
  • amendments common
  • UNVERIFIEDunit of 'Days'
OPSS.MUNI 100 (November 2019), GC 3.13.03completion of the work affected30 calendar days (last day)Probably a time barFailure to provide sufficient information within 30 days after completion is a failure to provide notice of the claim at all (Ross-Clair, 2016 ONCA 205)Standard formCheck your executed contract.Clock A: contractual notice, and why it is the only one that decides entitlement
Payment of the determined amountConstruction Act, RSO 1990, c C.30 (as amended by 2024, c. 20, Sched. 4), s 13.19(2)the determination being communicated to the parties to the adjudication15 calendar days (last day); the library advises working to 10 calendar days15 days under the Act as amended by 2024, c. 20, Sched. 4; 10 days is the pre-2026 figure, and the 2026 regime attaches to the contract date. The library page says diarise 10 as prudence.Time barInterest from the due date at the prejudgment rate or the higher contractual rate (s 13.19(3))Read in an official sourceHow an Ontario EOT adjudication actually runs
Owner's written notice of deficiency in an invoiceConstruction Act, RSO 1990, c C.30 (as amended by Bill 216, Sch 4), s 6.1receipt of the invoice7 calendar days (last day)Time barThe invoice is deemed to be a proper invoiceLibrary onlyCheck before relying on it.How prompt payment changed the leverage on a delay claim
Owner's prompt payment of a proper invoiceConstruction Act, RSO 1990, c C.30 (as amended), Part I.1the proper invoice28 calendar days (last day)Time barNo fixed dateLibrary onlyHow prompt payment changed the leverage on a delay claim
Owner's Notice of Annual Release of Holdback (Form 6)Construction Act, RSO 1990, c C.30 (as amended by Bill 216, Sch 4 and Bill 60, Sch 2), ss 26 to 27.1each contract anniversary14 calendar days (last day)Contracts running more than one year entered into on or after 1 January 2026; for earlier contracts (other than those under the former Construction Lien Act), from the second contract anniversary after 1 January 2026 (s 87.4(4)). Pre-2026 P3 project agreements with a special purpose entity are exempt.UnsettledLibrary onlyCheck before relying on it.How prompt payment changed the leverage on a delay claim
Payment of annually released holdbackConstruction Act, RSO 1990, c C.30 (as amended by Bill 216, Sch 4 and Bill 60, Sch 2), ss 26 to 27.1publication of the Notice of Annual Release of HoldbackWindow: opens once 60 calendar days have run in full, closes on day 74Contracts running more than one year entered into on or after 1 January 2026; for earlier contracts (other than those under the former Construction Lien Act), from the second contract anniversary after 1 January 2026 (s 87.4(4)). Pre-2026 P3 project agreements with a special purpose entity are exempt.UnsettledLibrary onlyCheck before relying on it.How prompt payment changed the leverage on a delay claim
Cascade of released holdback to subcontractorsConstruction Act, RSO 1990, c C.30 (as amended by Bill 216, Sch 4 and Bill 60, Sch 2), ss 26 to 27.1receipt of the released holdback14 calendar days (last day)UnsettledLibrary onlyCheck before relying on it.How prompt payment changed the leverage on a delay claim
Notice of adjudication, contract disputeConstruction Act, RSO 1990, c C.30 (as amended to 2026), s 13.5(3)the date on which the contract is completed, abandoned or terminated90 calendar days (last day)Only for contracts entered into on or after 1 January 2026 (the 2026 regime); check the contract date first.Time barAdjudication of a contract dispute is unavailable; the claim survives and must be litigated or arbitrated insteadLibrary onlyCheck before relying on it.How an Ontario EOT adjudication actually runs
Notice of adjudication, subcontract disputeConstruction Act, RSO 1990, c C.30 (as amended to 2026), s 13.5(3.1)the earliest of contract completion, abandonment or termination, certification of subcontract completion under s 33, and the date the subcontractor last supplied services or materials90 calendar days (last day)Only for contracts entered into on or after 1 January 2026 (the 2026 regime); check the contract date first.Time barAdjudication unavailable; the claim survivesLibrary onlyCheck before relying on it.How an Ontario EOT adjudication actually runs
Objection to the adjudicator's jurisdictionConstruction Act, RSO 1990, c C.30 (as amended to 2026), s 13.12.1the party first making submissions, or the matter being raisedRaise the objection before the adjudicator: at first submissions, or as soon as the matter is raised.Time barA jurisdictional objection not raised before the adjudicator cannot ground judicial review unless the failure was justifiedNo fixed dateLibrary onlyWhat actually became adjudicable on 1 January 2026
Adjudicator's determinationConstruction Act, RSO 1990, c C.30 (as amended to 2026)Not stated30 calendar days (last day)Not a time barNo fixed dateLibrary onlyHow an Ontario EOT adjudication actually runs
Correction of a slip in a determinationConstruction Act, RSO 1990, c C.30 (as amended to 2026), s 13.17.1Not stated5 calendar days (last day)UnsettledNo fixed dateLibrary onlyHow an Ontario EOT adjudication actually runs
Motion for leave to seek judicial review of a determinationConstruction Act, RSO 1990, c C.30 (as amended by 2024, c. 20, Sched. 4), s 13.18(2)the determination is communicated35 calendar days (last day); the library advises working to 30 calendar days35 days under the Act as amended by 2024, c. 20, Sched. 4; 30 days is the pre-2026 figure, and the 2026 regime attaches to the contract date. The library page says diarise 30 as prudence: the five days lost are unrecoverable.Time bara missed leave deadline is fatalRead in an official sourceHow an Ontario EOT adjudication actually runs
Notice of dispute after the Consultant's finding
  • amendments common
CCDC 2 – 2020, GC 8.3.2receipt of the Consultant's finding15 working days (last day)Not a time barUsually nothing. The periods are minimums, not cut-offsStandard formCheck your executed contract.Clock B: staged ADR, which is a floor rather than a ceiling
Reply to the notice of dispute
  • amendments common
CCDC 2 – 2020, GC 8.3.2receipt of the notice of dispute10 working days (last day)Not a time barUsually nothing. The periods are minimums, not cut-offsStandard formCheck your executed contract.Clock B: staged ADR, which is a floor rather than a ceiling
Negotiation period before the Project Mediator is requested
  • amendments common
CCDC 2 – 2020, GC 8.3.4receipt of the reply10 working days (a waiting period: act from the day after it ends)Not a time barStandard formCheck your executed contract.Clock B: staged ADR, which is a floor rather than a ceiling
Appointment of the Project Mediator
  • amendments common
CCDC 2 – 2020, GC 8.3.1award of the contract20 working days (last day)Not a time barStandard formCheck your executed contract.Clock B: staged ADR, which is a floor rather than a ceiling
Negotiation, then mediation if unresolved
  • amendments common
  • UNVERIFIEDunit of 'Days'
OPSS.MUNI 100 (November 2019), GC 3.13.04–.05the opinion30 calendar days (window closes)Not a time barUsually nothing. The periods are minimums, not cut-offsStandard formCheck your executed contract.Clock B: staged ADR, which is a floor rather than a ceiling
Mediator's review to complete
  • amendments common
  • UNVERIFIEDunit of 'Days'
OPSS.MUNI 100 (November 2019), GC 3.13.04–.05the opinion90 calendar days (window closes)Not a time barUsually nothing. The periods are minimums, not cut-offsStandard formCheck your executed contract.Clock B: staged ADR, which is a floor rather than a ceiling
Notice of arbitration
  • amendments common
  • UNVERIFIEDunit of 'Days'
OPSS.MUNI 100 (November 2019), GC 3.14.01–.02the opinion60 calendar days (last day)UnsettledUsually nothing. The periods are minimums, not cut-offsStandard formCheck your executed contract.Clock B: staged ADR, which is a floor rather than a ceiling
Arbitration hearing to commence
  • amendments common
  • UNVERIFIEDunit of 'Days'
OPSS.MUNI 100 (November 2019), GC 3.14.01–.02appointment of the arbitrator90 calendar days (last day)Not a time barStandard formCheck your executed contract.Clock B: staged ADR, which is a floor rather than a ceiling
Preservation of a lien
  • UNVERIFIEDsection number s 31
Construction Act, RSO 1990, c C.30 (as amended to 2026), s 31Not stated60 calendar days (last day)Time barMissing the 60-day preservation date or the 90-day perfection date destroys the security. It does not destroy the claim.No fixed dateLibrary onlyThe lien clocks: 60 days to preserve, 90 to perfect, and the 7-day notice of termination
Perfection of a lien
  • UNVERIFIEDsection number s 36
Construction Act, RSO 1990, c C.30 (as amended to 2026), s 36Not stated90 calendar days (last day)Time barMissing the 60-day preservation date or the 90-day perfection date destroys the security. It does not destroy the claim.No fixed dateLibrary onlyThe lien clocks: 60 days to preserve, 90 to perfect, and the 7-day notice of termination
Publication of notice of terminationConstruction Act, RSO 1990, c C.30 (as amended by Bill 60, Sch 2), s 31(6)–(8)termination7 calendar days (last day)Only for contracts entered into on or after 1 January 2026 (the 2026 regime); check the contract date first.UnsettledLibrary onlyCheck before relying on it.The lien clocks: 60 days to preserve, 90 to perfect, and the 7-day notice of termination
Basic limitation period
  • contract may shorten or exclude (s 22)
Limitations Act, 2002, SO 2002, c 24, Sch B, s 4the day on which the claim was discovered2 years (last day)Time bara proceeding shall not be commenced in respect of a claim after the second anniversary of the day on which the claim was discoveredLibrary onlyCheck before relying on it.The basic period is two years from discovery, and discovery has four limbs
Ultimate limitation periodLimitations Act, 2002, SO 2002, c 24, Sch B, s 15the day the act or omission on which the claim is based took place15 years (last day)Time barLibrary onlyCheck before relying on it.The basic period is two years from discovery, and discovery has four limbs
British Columbia: 21 deadlines
DeadlineInstrument and clauseTriggerPeriodConsequenceEvidenceLibrary
Notice of delay (claim for extension of Contract Time)
  • amendments common
CCDC 2 – 2020, GC 6.5.4the commencement of the delay10 working days (last day)Probably a time barNothing on that event, subject to waiver, estoppel and the purposive BC reading of noticeStandard formCheck your executed contract.Contractual notice, the condition-precedent clocks
Extension of time notice
  • amendments common
BC MOTI Major Works General Conditions (version 2026-04-01), GC 44.03the occurrence or the detection of the event14 calendar days (last day)Probably a time barNothing on that event, subject to waiver, estoppel and the purposive BC reading of noticeStandard formCheck your executed contract.Contractual notice, the condition-precedent clocks
Waiting period before requesting an extension for the Consultant's failure to furnish instructions
  • amendments common
CCDC 2 – 2020, GC 6.5.5demand for instructions10 working days (a waiting period: act from the day after it ends)Not a time barStandard formCheck your executed contract.The periods you are actually working to
Notice of a supervening event (P3 project agreement)
  • project-specific
  • UNVERIFIEDas a generalisation across Infrastructure BC project agreements
Penticton Regional Hospital Patient Care Tower Project Agreement (6 April 2016), Infrastructure BC, s 8.2(a)the applicant Has Knowledge that a supervening event has caused an entitlement5 business days (last day)Probably a time barNothing on that event, subject to waiver, estoppel and the purposive BC reading of noticeStandard formCheck your executed contract.Contractual notice, the condition-precedent clocks
Supporting details of a supervening event
  • project-specific
  • UNVERIFIEDas a generalisation across Infrastructure BC project agreements
Penticton Regional Hospital Patient Care Tower Project Agreement (6 April 2016), Infrastructure BC, s 8.2(b)delivery of the notice10 business days (last day)Probably a time barStandard formCheck your executed contract.Contractual notice, the condition-precedent clocks
Changed condition notice
  • amendments common
BC MOTI Major Works General Conditions (version 2026-04-01), GC 41.01Not stated7 calendar days (last day)Probably a time barNothing on that event, subject to waiver, estoppel and the purposive BC reading of noticeStandard formCheck your executed contract.Contractual notice, the condition-precedent clocks
Default notice period where no period is stated
  • amendments common
BC MOTI Major Works General Conditions (version 2026-04-01), GC 37.07Not stated7 calendar days (last day)Probably a time barStandard formCheck your executed contract.Contractual notice, the condition-precedent clocks
Written notice of damage to a municipality or regional districtLocal Government Act, RSBC 2015, c 1, s 736the date the damage was sustained2 months (last day)Unsettleda municipality or regional district is in no case liable for damages unless written noticeRead in an official sourceStatutory preconditions to suing. The ones British Columbia does not have
Contractor's notice of suspension for failure to pay holdback into the holdback accountBuilders Lien Act, SBC 1997, c 45, s 5(7)the contractor's notice of suspension10 calendar days (a waiting period: act from the day after it ends)Only where the owner must keep a holdback account: not where s 5(8) exempts it (government, government corporations, designated public bodies, contracts under $100,000).Not a time barRead in an official sourceThe holdback, the holdback account, and the exemption nobody expects
Meeting on the supervening event, then dispute resolution
  • project-specific
Penticton Regional Hospital Patient Care Tower Project Agreement (6 April 2016), Infrastructure BC, s 8.2(h)Not stated15 business days (last day)Not a time barStandard formCheck your executed contract.Contractual notice, the condition-precedent clocks
Serve expert reportSupreme Court Civil Rules (BC), Rule 11-6the trial date84 calendar days (counted back from the event)UnsettledRead in an official sourceThe procedural clocks, and how the whole set interacts
Serve responding expert reportSupreme Court Civil Rules (BC), Rule 11-6the trial date42 calendar days (counted back from the event)UnsettledRead in an official sourceThe procedural clocks, and how the whole set interacts
Dormant proceeding: notice required before proceedingSupreme Court Civil Rules (BC), Rule 22-4(4)the last step taken in the proceeding1 year (last day)Not a time barcannot proceed without notice under Rule 22-4(4)Read in an official sourceThe procedural clocks, and how the whole set interacts
File a claim of lienBuilders Lien Act, SBC 1997, c 45, s 20a certificate of completion, or the head contract completed, abandoned or terminated, or the improvement completed or abandoned45 calendar days (last day)Time barLien extinguished (s 22)Read in an official sourceThe Builders Lien Act clocks: conditions of a security remedy
Holdback period
  • CPPA change pending: 46 days on proclamation
Builders Lien Act, SBC 1997, c 45, s 8certificate of completion, otherwise head contract or improvement completion55 calendar days (last day)Time barPayment out discharges liens unless a lien was filed or proceedings commencedRead in an official sourceThe Builders Lien Act clocks: conditions of a security remedy
Certifier issues a certificate of completion on requestBuilders Lien Act, SBC 1997, c 45, s 7the request10 calendar days (last day)Not a time barThe court may declare completion. The certifier is personally liableRead in an official sourceThe Builders Lien Act clocks: conditions of a security remedy
Commence the lien action and register a certificate of pending litigationBuilders Lien Act, SBC 1997, c 45, s 33the date the lien was filed1 year (last day)Time barthe lien is extinguished if either step is missed (s 33(5))Read in an official sourceThe Builders Lien Act clocks: conditions of a security remedy
Commence the action after a notice to commenceBuilders Lien Act, SBC 1997, c 45, s 33service of the notice to commence21 calendar days (last day)Time barLien extinguishedRead in an official sourceThe Builders Lien Act clocks: conditions of a security remedy
Trust action (s 10 statutory construction trust)Builders Lien Act, SBC 1997, c 45, s 14the head contract being completed, abandoned or terminated1 year (last day)Time barRead in an official sourceThe trust clock, a one-year limitation that runs from an event you may not hear about
Basic limitation periodLimitation Act, SBC 2012, c 13, s 6(1)the day the claim is discovered2 years (last day)Time barRead in an official sourceWhat the Limitation Act actually provides
Ultimate limitation periodLimitation Act, SBC 2012, c 13, s 21(1)the day the act or omission on which the claim is based took place15 years (last day)Time barRead in an official sourceWhat the Limitation Act actually provides
United States (federal): 10 deadlines
DeadlineInstrument and clauseTriggerPeriodConsequenceEvidenceLibrary
Written notice of the causes of delay to the Contracting Officer
  • FAR Overhaul: check for class deviation
FAR 52.249-10, Default (Fixed-Price Construction), 52.249-10(b)(2)the beginning of any delay10 calendar days (last day)Read the clause as incorporated in your contract: the FAR Overhaul is mid-flight and class-deviated text may apply.UnsettledRelief from default termination and delay damages under 52.249-10(b) is conditioned on the noticeRead in an official sourceFAR: notice, cost cut-offs, and the final-payment backstop
Cost cut-off before written notice of a constructive change
  • FAR Overhaul: check for class deviation
FAR 52.243-4, Changes, 52.243-4(d)the written noticeCosts incurred more than 20 days before the written notice are not recoverable, except for an adjustment based on defective specifications. A look-back cut-off, not a filing deadline.Not a time barA cost cut-off, not an entitlement barNo fixed dateRead in an official sourceFAR's notice-vs-cost-cutoff distinction
Cost cut-off before written notice of a suspension
  • FAR Overhaul: check for class deviation
FAR 52.242-14, Suspension of Work, 52.242-14(c)the written noticeCosts incurred more than 20 days before the written notice are not allowed. A look-back cut-off, not a filing deadline; it does not apply to a claim resulting from a suspension order.Not a time barA cost cut-off, not an entitlement barNo fixed dateRead in an official sourceFAR: notice, cost cut-offs, and the final-payment backstop
Initiate a Claim (including a request for additional Contract Time)
  • amendments common
AIA A201-2017, §15.1.3.1the later of the event giving rise to the Claim and the claimant first recognizing the condition21 calendar days (last day)Time barMiss it and the Claim is contractually time-barred.Standard formCheck your executed contract.The §15.1.3.1/.2 split: new in 2017, and it changes which regime applies
Assert the right to an equitable adjustment
  • FAR Overhaul: check for class deviation
FAR 52.243-4, Changes, 52.243-4(e)the change order or the (b) notice30 calendar days (last day)Read the clause as incorporated in your contract: the FAR Overhaul is mid-flight and class-deviated text may apply.UnsettledLibrary onlyCheck before relying on it.FAR: notice, cost cut-offs, and the final-payment backstop
No proposal after final payment
  • FAR Overhaul: check for class deviation
FAR 52.243-4, Changes, 52.243-4(f)final paymentNo proposal or claim after final payment. Final payment is a cut-off, not the start of a clock: assert the adjustment before it.Time barNo proposal or claim after final paymentNo fixed dateLibrary onlyFAR: notice, cost cut-offs, and the final-payment backstop
Assert the suspension claim
  • FAR Overhaul: check for class deviation
FAR 52.242-14, Suspension of Work, 52.242-14(c)the suspension endsNo fixed period (promptly)Time barno claim survives final paymentNo fixed dateRead in an official sourceFAR: notice, cost cut-offs, and the final-payment backstop
Notice of differing site conditions
  • FAR Overhaul: check for class deviation
FAR 52.236-2, Differing Site Conditions, 52.236-2(a), (c)encountering the condition, before the conditions are disturbedNo fixed period (promptly)Probably a time barno adjustment without itNo fixed dateLibrary onlyFAR: notice, cost cut-offs, and the final-payment backstop
No differing-site-conditions request after final payment
  • FAR Overhaul: check for class deviation
FAR 52.236-2, Differing Site Conditions, 52.236-2(d)final paymentNo request for an adjustment under this clause after final payment. Final payment is a cut-off, not the start of a clock.Time barno claim survives final payment under any of the three clausesNo fixed dateLibrary onlyFAR: notice, cost cut-offs, and the final-payment backstop
Submit the claim to the Contracting Officer (CDA limitation period)Contract Disputes Act, as implemented by FAR 33.206, FAR 33.206accrual: when all events that fix the alleged liability were known or should have been known (FAR 33.201)6 years (last day)Time barLibrary onlyCheck before relying on it.The CDA layer: six years, $100,000, and when the clock starts
England and Wales: 14 deadlines
DeadlineInstrument and clauseTriggerPeriodConsequenceEvidenceLibrary
Notice by Contractor of delay to progress
  • amendments common
  • Storia inference: no judgment has construed the 2024 wording
  • amended contracts commonly convert cl 2.24 into a condition precedent
JCT Design and Build Contract 2024, cl 2.24delay to progress becomes reasonably apparentNo fixed period (promptly)Not a time barStandard formCheck your executed contract.On the printed JCT 2024 wording, time has no time bar, but the money notice can forfeit
Employer's request for further information on a delay notice
  • amendments common
JCT Design and Build Contract 2024, cl 2.24.4receipt of the required particulars or of a notice of a material change14 calendar days (last day)UnsettledStandard formCheck your executed contract.Template D. Reply to an Employer's cl 2.24.4 request for further information
Employer's decision fixing a later Completion Date
  • amendments common
JCT Design and Build Contract 2024, cl 2.25.2Not stated8 weeks (last day)Not a time barIf the Employer misses that period, there is no deemed grant.Standard formCheck your executed contract.On the printed JCT 2024 wording, time has no time bar, but the money notice can forfeit
Employer's review of the Completion Date after practical completion
  • amendments common
  • UNVERIFIEDsub-clause number not located
JCT Design and Build Contract 2024practical completion12 weeks (last day)Not a time barStandard formCheck your executed contract.On the printed JCT 2024 wording, time has no time bar, but the money notice can forfeit
Loss and expense notice
  • amendments common
  • Storia inference from FES v HFD [2024] CSIH 37 (Scottish, persuasive)
JCT Design and Build Contract 2024, cl 4.21 Relevant Matter (loss and expense notice clause of the executed contract)it becomes apparent that regular progress is or will be materially affected by a Relevant MatterNo fixed period (promptly)Probably a time barOn the Scottish SBC 2016 in FES (persuasive), the notice was a condition precedent to loss and expense; likely the same under DB 2024 (Inference.)Standard formCheck your executed contract.Which notice, under which form
Contractor notifies a compensation event
  • amendments common
NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 61.3the Contractor becoming aware of the event8 weeks (last day)Time barthe Prices, the Completion Date and the Key Dates are not changedStandard formCheck your executed contract.NEC4 clause 61.3 is a hard bar, with one exception and a two-step safety valve
Project Manager replies to a compensation event notification
  • amendments common
NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 61.4the Contractor's notification of the compensation event1 week (last day)Not a time barStandard formCheck your executed contract.NEC4 clause 61.3 is a hard bar, with one exception and a two-step safety valve
Deemed acceptance of a compensation event after notice of the Project Manager's failure
  • amendments common
NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 61.4the Contractor's notice of the Project Manager's failure to reply2 weeks (a waiting period: act from the day after it ends)Not a time bartreated as acceptance that the event is a compensation eventStandard formCheck your executed contract.NEC4 clause 61.3 is a hard bar, with one exception and a two-step safety valve
Contractor submits quotations for a compensation event
  • amendments common
NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 62.3the instruction to submit quotations3 weeks (last day)UnsettledStandard formCheck your executed contract.NEC4 cl 61.4 and 62.6: silence becomes acceptance only if you say so
Deemed acceptance of a quotation after notice of the Project Manager's failure
  • amendments common
NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 62.6the Contractor's notice of the Project Manager's failure to reply to the quotation2 weeks (a waiting period: act from the day after it ends)Not a time barStandard formCheck your executed contract.NEC4 clause 61.3 is a hard bar, with one exception and a two-step safety valve
Project Manager replies to a quotation
  • amendments common
NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 62.3submission of the quotation2 weeks (last day)Not a time barStandard formCheck your executed contract.NEC4 cl 61.4 and 62.6: silence becomes acceptance only if you say so
Early warning
  • amendments common
NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 15.1becoming aware of a matter that could affect cost, time or qualityNo fixed period (promptly)Not a time barthe compensation event is then assessed as if the warning had been givenStandard formCheck your executed contract.The early warning is not the compensation event notification
Notice of intention to refer a dispute to adjudicationHousing Grants, Construction and Regeneration Act 1996, as amended by LDEDCA 2009 Part 8, s.108Not statedNo fixed periodNot a time barNo fixed dateRead in an official sourceAny EOT dispute can be referred at any time, and the certificate can be reopened
Adjudicator's decisionHousing Grants, Construction and Regeneration Act 1996, as amended by LDEDCA 2009 Part 8, s.108referral28 calendar days (last day)Contracts entered into on or after 1 October 2011 (the current text).UnsettledRead in an official sourceAny EOT dispute can be referred at any time, and the certificate can be reopened
FIDIC 2017: 4 deadlines
DeadlineInstrument and clauseTriggerPeriodConsequenceEvidenceLibrary
Notice of Claim (extension of time under Sub-Clause 8.5, or additional payment)
  • amendments common
FIDIC Conditions of Contract, Second Edition 2017 (2022 reprint), Red, Yellow and Silver Books, Sub-Clause 20.2.1the claiming Party became aware, or should have become aware, of the event or circumstance28 calendar days (last day)Time barExpress bar: no extension, no additional payment.Standard formCheck your executed contract.Which notice, under which form
Engineer gives notice that a Notice of Claim is late
  • amendments common
FIDIC Conditions of Contract, Second Edition 2017 (2022 reprint), Red, Yellow and Silver Books, Sub-Clause 20.2.2Not stated14 calendar days (last day)Time barthe Notice is deemed validStandard formCheck your executed contract.FIDIC 2017 Sub-Clause 20.2.1: the 28-day Notice of Claim
Fully detailed Claim
  • amendments common
FIDIC Conditions of Contract, Second Edition 2017 (2022 reprint), Red, Yellow and Silver Books, Sub-Clause 20.2.4the claiming Party became aware, or should have become aware, of the event84 calendar days (last day)Probably a time barWithout the legal-basis statement, the Notice of Claim is reported to lapse, subject to the Engineer notifying the lapse within 14 daysStandard formCheck your executed contract.FIDIC 2017 Sub-Clause 20.2.4: the fully detailed Claim at 84 days
Engineer's agreement or determination of a Claim
  • amendments common
FIDIC Conditions of Contract, Second Edition 2017 (2022 reprint), Red, Yellow and Silver Books, Sub-Clause 3.7Not stated42 calendar days (last day)Not a time barfailure to determine is a deemed rejection, referable to the DAABStandard formCheck your executed contract.Why deemed acceptance matters more than the length of the period
§ 03

What is not here yet

Alberta, Quebec and Australia are covered on their own library pages, but not every statute behind their deadlines has been read in an official source, so they are not in the register yet.

§ 04

Where Storia fits

A register tells you which clocks exist. Storia keeps the record that shows when each one started and when you acted: it reads the project record where it lives and builds a dated chain of events, every paragraph cited to its page. See Claims and Dispute Resolution or book a demo.

General information, not legal advice. Reviewed Nov 24, 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…

Each issue links to the full articles in the Storia Library.