General practiceConstruction claimsTopic guide

Construction claims: types, process and why they fail

A construction claim is a request for time, money or both, made under the contract (or under a payment statute) when an event outside your risk affects the works. It is not a change request, which is the contract's routine route for agreed change, and it is not yet a dispute, which is what a rejected or ignored claim becomes. Across the decisions gathered in this library, most claims turn on three things the project did at the time: notice served in time, records made as the work happened, and proof that the event caused the effect claimed.

Reviewed Nov 10, 202615 min read8 sources

At a glance

General practice
Last reviewed
10 November 2026
Class
Topic hub. What a claim is, the five claim families, the life of a claim, and where the library covers each jurisdiction
Scope
Jurisdiction-neutral, with routes to Canada, the United States, Australia and England and Wales
Not legal advice
A map of the subject. Check the executed contract, its amendments and the governing law before you rely on any of it
§ 00

Key facts

  1. 01

    What a claim is

    A request for time, money or both, made under a clause or a statute, for an event that was not your risk.

  2. 02

    The five families

    Time (extension of time) · change (variations) · disruption (lost productivity) · site conditions · payment.

  3. 03

    Time and money

    Separate gateways. An extension of time moves the completion date. It does not pay for the extra weeks: SCL Delay and Disruption Protocol, 2nd Edition (February 2017), Core Principle 12.

  4. 04

    The deadline that kills

    The notice clock, which usually starts long before the claim is ready. Under CCDC 2 – 2020 GC 6.5.4 it runs from the commencement of the delay, not from awareness.

  5. 05

    The proof

    Contemporaneous records, event by event. The records a project keeps decide which delay analysis it can run, and that set closes before anyone knows there is a dispute.

  6. 06

    The quiet killer

    A signed change order or release that settled the same event without a reservation. Impact claims die in signed change orders, not in tribunals.

  7. 07

    Where it gets decided

    Determination under the contract, then negotiation, then a dispute board, expert determination, adjudication, arbitration or the courts. Statutory adjudication reaches delay in every Australian jurisdiction and in England and Wales, in Alberta by consent on private and municipal work, in Ontario only as an ancillary head on newer contracts, and not at all in the United States.

A construction claim is a request for time, money or both, made under the contract when an event that was not your risk affects the works. There are five families of claim, and every one of them runs the same life from event to decision. Across the decisions gathered in this library the same failures recur: late notice, thin records, unproved causation, global claims and, on variations, a missing written instruction or a signed release. (Inference.)

This page is the map: it routes each question to the library page that takes it further, and says where the library does not yet go.

The executed contract decides. Bespoke amendment is normal on major projects, so every form-level statement below is a form-default position, and the pages it links to say which edition they read.

§ 01

What a construction claim is, and what it is not

Three words get used as if they meant the same thing. They do not.

What it isWhat it usually looks likeWhat decides it
Change requestThe contract's routine route for a change both sides accept: an instruction, a quotation, a change orderA variation or change order or, under NEC4, a compensation event for a change to the Scope (cl 60.1(1)), priced and agreedThe contract's change and pricing clauses
ClaimA party says the contract (or a statute) entitles it to time or money, and the other side has not agreedA notice, then a substantiated claim document with recordsEntitlement, notice, causation and quantum
DisputeA claim that has been rejected, ignored or cut down, and is now on the dispute ladderA referral to a dispute board, an adjudicator, an arbitrator or a courtThe forum, its timetable and its rules

How this library uses the three words. Forms and statutes have their own vocabulary: under NEC4 a disputed delay also runs as a compensation event, so the label does not tell you which row you are in.

A change request becomes a claim the moment the price, the time or the scope is contested. On US federal work the line is formal: a Request for Equitable Adjustment is a request to negotiate, while a Contract Disputes Act claim demands a Contracting Officer's final decision, and treating an REA as though it were a claim is itself an error (change orders in the United States).

§ 02

The five families of construction claim

Name the family first, because each has its own entitlement test, its own notice and its own way of measuring the money. One event can start several: a late design change can be a variation, a time claim and a disruption claim at once, each on its own clock.

FamilyWhat it asks forWhat it has to proveWhere the library covers it
TimeMore time, so delay damages do not runA qualifying event, delay to completion, notice, the daysExtension of time, with jurisdiction pages
ChangePayment (and often time) for changed workOutside scope, instructed, notices, valuation, not releasedVariations, with US and Australian pages
DisruptionThe cost of working less productivelyLost productivity against an unaffected comparisonCovered inside prolongation and delay costs. No dedicated page yet
Site conditionsTime and money for conditions the contract did not allocate to youDepends on the form's clausePartly covered on form-specific pages. No dedicated page yet
PaymentMoney due now, on a statutory or contractual timetableA valid payment claim and the statute's stepsBy jurisdiction: security of payment in Australia, Ontario adjudication, adjudicating extensions of time in England and Wales. No neutral page yet

Time: extension of time

An extension of time moves the completion date because an event that was not the contractor's risk delayed the works. It establishes four things: a qualifying event, causation to completion, notice, and the extent in days (extension of time). It does not pay for the delay. Time and money are separate gateways (SCL Delay and Disruption Protocol1, 2nd Edition (February 2017), Core Principle 12), and the money claim is worked under prolongation and delay costs.

Delay to progress is not delay to completion (SCL Protocol Core Principle 5): an event that held up an activity with float to spare earns no extension.

Change: variations and change orders

A variation claim has to establish five things: the work was outside the scope, it was instructed, the notices were given, it was valued on the right rung of the pricing ladder, and the claim survived the change orders signed along the way (variations).

Whether something is a variation is a question of reading the contract, not of fairness. In Uniform Building Contractors Ltd v Water and Sewerage Authority of Trinidad and Tobago2 [2026] UKPC 2 the Privy Council held that reasoning from how the parties behaved on site is an error of law (what counts as a variation). Unwritten instructions divide the regimes: England enforces the formality, Australia never adopted Rock Advertising, and US public work often treats writing as jurisdictional (written instruction and waiver). Constructive change is a United States doctrine, and no doctrine of that name exists elsewhere (constructive and deemed variations).

Disruption and productivity

Disruption is loss of productivity: the same work done less efficiently. It is a different claim from prolongation, it affects the rate of working rather than completion, and it can succeed with no critical-path delay at all. It is proved by comparison: a measured mile, a benchmark, or for the cumulative effect of many changes the framework in AACE International RP 130R-23 (15 May 2023) (prolongation and delay costs).

Two traps recur: disruption pleaded inside the variation account, which prices the changed work and not its effect on unchanged work, and site overhead claimed twice, as prolongation and inside the productivity calculation. No Canadian measured-mile authority exists (prolongation in Canada).

Differing or unforeseen site conditions

What the library covers is form-specific. Under AS 4000, latent conditions sit in cl 25, and published summaries report that the 2025 edition moved notification to as soon as practicable after the Contractor becomes aware. The 1997 edition prices a latent condition as a Variation (whether the 2025 edition does is not yet confirmed), and AS 2124, as summarised in commentary, gives the extra cost incurred instead (deemed variations and latent conditions in Australia). On US federal work, FAR 52.236-2(d) bars a differing site conditions claim after final payment, whatever the limitation period (notice and time bars in the United States). On any other form, read the site conditions clause and its notice first.

Payment

A payment claim asks for money due now, often on a statutory timetable with a fast route to a decision. How far that route reaches into delay varies sharply. Every Australian jurisdiction now lets an adjudicator value a delay or prolongation claim (security of payment in Australia). Ontario allows an extension of time to be adjudicated only as an ancillary head, with conditions, on contracts signed from 1 January 2026 (Ontario adjudication). In England and Wales either party can refer an extension of time dispute to adjudication at any time (adjudicating extensions of time), and the United States has no statutory construction adjudication scheme (extension of time in the United States). Liens are a separate layer again: in Ontario a lien secures a delay claim only in part (Ontario liens and holdback).

§ 03

Construction claim examples

Illustrative, drawn from the pages linked.

§ 04

The construction claims process, from event to resolution

Every claim runs the same life, and the early stages decide most of it. A missed notice is the one thing that cannot be repaired later, and records rebuilt after the event invite the attack that they were reconstructed for the claim.

StageWhat happensWhat decides itWhere to read more
1. The eventAn instruction, a late drawing, a condition, a non-paymentWhether the contract puts that risk on youExtension of time, variations
2. NoticeYou tell the named person, in the required form, inside the windowThe trigger and the period in your contract, and whether missing it forfeits the claimNotice and time bars
3. RecordsDated documents that prove what happened, kept as it happensWhether a stranger could check each assertion against a dated recordRecords and evidence
4. Claim submissionA substantiated claim: basis, chronology, causation, time and cost, records indexWhether each event is linked to its effectHow to write an EOT claim
5. Assessment or determinationThe engineer, superintendent, consultant or contracting officer decidesThe contract's response deadlines, and any deemed outcome for silenceNotice and time bars
6. ResolutionNegotiation, then a dispute board, expert determination, adjudication, arbitration or the courtsThe contract's dispute ladder, any statutory route, and the limitation periodThe jurisdiction pages below

The notice clock usually starts long before the claim is ready. FIDIC 2017 wants a Notice of Claim within 28 days after you became aware, or should have become aware, of the event, and a fully detailed Claim within 84, as published commentary summarises it. CCDC 2 – 2020 wants Notice in Writing within 10 Working Days after the delay commences, whether or not you knew (delay notice templates). Under NEC4 ECC, cl 61.3 is a hard bar at 8 weeks from awareness, with one exception (notice and time bars in England and Wales).

More than one clock runs at once. Ontario runs five on a delay claim (contractual notice, adjudication, lien, holdback and limitation), and none of them saves any of the others (Ontario claim clocks).

§ 05

Why construction claims fail

Across the decisions gathered in this library, sound claims fail in a consistent pattern, rarely because the event did not happen. (Inference.) The pattern comes from a collected set of decisions, not a statistical sample.

Every one of these failures is set up while the work is going on. The claim document can only report what the notice and the records already decided.

§ 06

Where the library covers each jurisdiction

Doctrine differs across these borders (concurrent delay, constructive change and global claims all get different answers), and so do deadlines, forums and payment machinery. Start with the place whose law governs the contract.

JurisdictionTime (extension of time)Change (variations)Payment and forumWhat is distinctive
CanadaCanada, provincial comparisonNo Canadian variations page yet. The neutral variations pages cover Canadian waiver by conductBy province, belowNotice is a condition precedent and concurrent delay is apportioned
OntarioOntarioNeutral pagesPrompt payment and adjudicationSince 1 January 2026 an extension of time can be adjudicated, as an ancillary head only, not on P3 projects, and only on contracts from that date
AlbertaAlbertaNeutral pagesPrompt payment and adjudicationTwo regimes. Private and municipal work: delay is adjudicable by consent. Provincial Crown public works: excluded by statute
British ColumbiaBritish ColumbiaNeutral pagesPrompt payment and adjudicationPrompt payment Act has Royal Assent but was not in force as at 8 September 2026, so there is no adjudication. Lien clocks police the claim
QuebecQuebecNeutral pagesNo Quebec payment or adjudication page yet. See notice and time barsCivil law: no statutory extension mechanism, and time bars enforced strictly
United StatesUnited StatesChange orders, CaliforniaClaim clocksConstructive and cardinal change; no construction adjudication
AustraliaAustraliaVariationsSecurity of paymentOne common law, eight statutory payment regimes
VictoriaVia AustraliaVictoriaAdjudicating the variation accountSince 15 April 2026 an unfair notice-based time bar can be set aside for a particular entitlement
England and WalesEngland and WalesNeutral variations pages, which cover the English casesAdjudicating extensions of timeStatutory adjudication at any time; concurrency not settled at appellate level

"Neutral pages" means the jurisdiction-neutral variations cluster. Every place in scope: claims by location.

§ 07

Templates, how-to guides and checklists

The practical pages turn the law into work a project team can do this week.

§ 08

Where Storia fits

The failures above come down to records and timing. Storia reads one project's tools in place, including Aconex, SharePoint, Outlook and Primavera P6, and reads every page, scans included. It builds the project narrative while the job runs, traces a schedule slip to the documents behind it, and writes a delay report that sets every slip against the baseline, names the event behind it and counts the days each party added (schedule intelligence). The same record becomes a claim draft in days, every paragraph citing its page, with the exhibits labelled and placed. That draft is a structured first draft, not a filing: it is editable, and it is ready for your expert and counsel. Storia does not decide entitlement or give legal advice, and it does not replace your delay expert or your lawyer. Book a demo with one of your projects.

§ 09

Frequently asked questions

What is a construction claim?

A request for time, money or both, made under the contract or a payment statute, because an event that was not your risk affected the works. It is not a change request (the agreed route for routine change) and not yet a dispute (what a rejected claim becomes).

What are the main types of construction claims?

Five families: time (extension of time), change (variations and change orders), disruption (lost productivity), differing or unforeseen site conditions, and payment. One event often produces more than one, each with its own notice and its own proof.

What is the construction claims process?

Event, notice, records, claim submission, assessment or determination, then negotiation, a dispute board, expert determination, adjudication, arbitration or the courts. A missed notice is the stage you cannot repair later.

How long do I have to make a construction claim?

As long as your contract says, and often less than you expect. There is usually a short notice deadline and a longer one for the detailed claim. Statutory payment deadlines, lien clocks and limitation periods run separately. Check the executed contract, then the notice and time bars comparison and the page for your jurisdiction.

Why do construction claims fail?

Across the decisions gathered in this library: late notice, thin records, causation asserted rather than shown on the critical path, and global claims. Variation claims add two more: no written instruction from the person the contract names, and a signed change order that settled the same event without a reservation. (Inference.)

§ 10

Articles

2 articles
Notes

Sources and authorities

8 cited
  1. 1
    Society of Construction Law Delay and Disruption Protocol, 2nd Edition2nd Edition (February 2017), Society of Construction Law

    Guidance, not law. Core Principle 5 confines extension of time entitlement to delay to completion rather than delay to progress. Core Principle 12 keeps time and money as separate gateways. Core Principle 17 discourages global claims.

    Protocol

  2. 2
    Uniform Building Contractors Ltd v Water and Sewerage Authority of Trinidad and Tobago[2026] UKPC 2 (22 January 2026), Privy Council, on appeal from Trinidad and Tobago

    Whether an item of work is a variation "is primarily a function of the contract terms", and reasoning from how the parties behaved on site is an error of law. Sub-Clause 20.1 of the 1999 FIDIC form is a condition precedent.

    Find on Find Case Law

  3. 3
    Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC[2022] DIFC CA 016 (judgment 12 May 2023), DIFC Court of Appeal

    The contractor lost its extension of time entitlement on notice grounds (amended FIDIC 1999 Red Book, Sub-Clause 20.1) despite the employer having caused 306 of the 325 days of delay.

    DIFC Courts

  4. 4
    Elite Construction Inc. v Canada (Attorney General)2021 ONSC 562, aff'd 2021 ONCA 803, Ontario

    A CAD 4.1 million delay and extras claim was dismissed on summary judgment for missing a ten-working-day notice.

    Find on CanLII

  5. 5
    Alares Construction, Inc. v Department of Veterans AffairsCBCA 6149, 7071, 7597 (21 March 2025), Civilian Board of Contract Appeals

    Of 765 days Alares attributed to the VA, the Board found the VA responsible for 218 days of critical path delay, and rejected a mid-project logic revision in Alares' schedule as making "no sense".

    CBCA

  6. 6
    George Sollitt Construction Co. v United States64 Fed. Cl. 229 (2005), US Court of Federal Claims

    Delay affecting only non-critical activities does not delay completion, so it generates no extension of time.

    Court of Federal Claims

  7. 7
    Walter Lilly & Co Ltd v Mackay[2012] EWHC 1773 (TCC), Technology and Construction Court (Akenhead J)

    There is no rule of law preventing recovery where a contractor has not allocated loss to each event. The global approach goes to proof rather than to admissibility or validity, and the claimant must still comply with notice requirements and prove causation with contemporaneous evidence.

    Find Case Law

  8. 8
    Bell BCI Co. v United States570 F.3d 1337 (Fed. Cir. 2009), United States Court of Appeals for the Federal Circuit

    The release in a bilateral modification was unambiguous and barred the contractor's cumulative impact and delay claims: "If parties intend to leave some things open and unsettled, their intent so to do should be made manifest."

    Justia

General information, not legal advice. Reviewed Nov 10, 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…

Each issue links to the full articles in the Storia Library.

Construction claims: types, process and examples · Storia