Concurrent delay in Australia
Australia has no judicial default on concurrent delay. The answer is set entirely by contract. AS 4000-1997 cl 34.4 apportions overlapping delay. AS 2124-1992 cl 35.5 denies an extension of time for the concurrent period outright. Whether AS 4000:2025 retained apportionment is unverified, and most executed contracts amend the clause anyway.
Disponible solo en inglés Este artículo aún no se ha traducido. Los plazos, el derecho a reclamar y el procedimiento descritos aquí rozan lo jurídico, y una traducción automática sería un riesgo de credibilidad más que una comodidad: por eso se sirve el original inglés íntegro hasta que exista una traducción revisada.
At a glance
- 1 September 2026
- Doctrine. Contract-driven, not judicial
- Australia. Uniform across all states and territories
- Set by the printed form. No common-law default exists
- AS 4000-1997 cl 34.4 apportions. AS 2124-1992 cl 35.5 denies
- First instance only. No appellate decision located
Key facts
- 01
The short answer
There is no Australian judicial default. Concurrent delay is governed entirely by the printed contract. "Under Australian law, concurrent delay…" is not a sentence that can be completed accurately until the form and edition are named.
- 02
The form-level split
AS 4000-1997 cl 34.4 apportions the resulting delay according to each cause's contribution. AS 2124-1992 cl 35.5 denies an extension of time for the concurrent period outright. Two forms, opposite answers, on identical facts.
- 03
AS 4000:2025
Whether cl 34.4 apportionment survived is UNVERIFIED. Standards Australia was paywalled during research and the 2025 clause text was not read. Cite apportionment to AS 4000-1997 only, never to the 2025 edition.
- 04
The undercut
★ 84% of Australian standard forms are amended, and the EOT clause specifically in 76%, so the famous divergence describes clauses absent from most real contracts. Read the executed contract before advising on either rule.
- 05
How courts define concurrency
Narrowly, and causation-first. Delays are not concurrent where the contractor-risk event starts first, causes actual delay, and ends after the qualifying event finishes (Australian Development Corp v White Constructions, 1996). "Actual delay" means critical-path delay, not potential delay.
- 06
Methodology
Fact-driven, not protocol-driven. White Constructions v PBS Holdings [2019] NSWSC 1166 rejected both parties' experts and held the SCL Protocol is not a rule of law.
- 07
The Superintendent's power
Under AS 2124, a principal that caused part of the delay and then levies liquidated damages must still confront the duty in Probuild v DDI Group to exercise its unilateral EOT power for delays it caused. partially reopening what cl 35.5 closes. Under-litigated.
- 08
What is missing
No Australian appellate authority on concurrent delay or delay methodology for 2024–2026 was located. The field runs on four first-instance decisions.
Australia has no judicial default on concurrent delay. There is no Australian Malmaison, no Australian apportionment rule handed down by a court, and no Australian equivalent of the American burden-of-proof line. Because the question never has to reach a judge in the shape it does elsewhere. Two standard forms in everyday use answer it themselves, in the printed clause, and they give opposite answers on identical facts. Name the form and the edition before saying anything else about Australian concurrency.
That framing is deliberate rather than a stylistic choice: it is the correct starting point because Australian courts have had comparatively little occasion to develop a general concurrency doctrine of their own. What first-instance authority does exist narrows the definition of concurrency sharply. Often disposing of a pleaded concurrency argument before any rule of entitlement is needed, and leaves the remedy for genuine concurrency to the contract. For the wider setting see extension of time in Australia.
The form-level split: apportionment against outright denial
| Form | Concurrency rule |
|---|---|
| AS 4000-1997 cl 34.41 (and AS 4902-2000) | Apportionment. Where qualifying and non-qualifying causes overlap, "the Superintendent shall apportion the resulting delay to WUC according to the respective causes' contribution." |
| AS 2124-1992 cl 35.52 (and AS 4300-1995, identically save "cause" → "cause of delay") | No EOT for concurrency. "To the extent that the delays are concurrent, the Contractor shall not be entitled to an extension of time for Practical Completion." |
Both forms are live on Australian projects today. AS 2124 remains widely used, especially in government work. AS 4000 is the current general form. The AS 2124 position is brutal for contractors, and it is the closest thing in the common-law world to a standard-form version of the England-and-Wales allocation-by-amendment approach. Except that in Australia it sits in the printed form, not a bespoke amendment layered on top of it.
AS 2124 cl 35.5 is also structurally different from AS 4000's clause in another respect: it splits into two limbs. Limb (a) covers delays before practical completion from any cause beyond the Contractor's reasonable control, expressly including industrial conditions and inclement weather. Limb (b) covers a narrower enumerated list. Principal-caused delay, quantity variations, latent conditions, directed variations, nominated- subcontractor issues, changes in law, and statutory-authority acts and delays. Applicable before, during or after completion. The concurrency denial in cl 35.5 bites only where one of the overlapping causes falls outside these qualifying categories.
Did apportionment survive into AS 4000:2025?
This is the single most important open question in Australian concurrent delay, and it should not be resolved by assumption. AS 4000:20253 superseded AS 4000-1997 in 2025, and Standards Australia's own framing is that "there has been no significant change to the allocation of risk". Which, because concurrency apportionment is squarely a risk-allocation question, implies the clause survived. But no source consulted for this corpus quotes the 2025 apportionment wording, confirms its retention, or even confirms its clause number, and the 2025 standard sits behind the Standards Australia paywall. Sources also disagree on whether the assessment and unilateral-power sub-clauses shifted numbering in 2025 at all.
The safe formulation, and the one this page uses throughout: the apportionment position is attributed to AS 4000-1997 cl 34.4, the edition where the wording is verified, and not to "AS 4000" unqualified or to the 2025 edition. Writing that "AS 4000:2025 cl 34.4 apportions concurrent delay" is not supportable on present sources. If the 2025 edition dropped or reworded apportionment, the Australian concurrency contrast described on this page would need rewriting for every new contract signed on the current form. Resolve this against the published standard before relying on it in a live matter.
The 84% problem: read the executed contract
The AS 2124 / AS 4000 divergence is the thing every Australian delay article leads with. It is also, on the numbers, describing a minority of real contracts.
Source: Melbourne Law School survey, 295 respondents4.
So the famous divergence. Apportionment under AS 4000 against outright denial under AS 2124. Describes clauses absent from roughly three quarters of real Australian contracts. Read the executed contract, including its special conditions, before advising on either rule. The standard form tells you what was probably negotiated away, not what governs the project in front of you.
One recurring amendment is worth naming specifically because it attacks a different lever entirely: the duty that makes the Superintendent's unilateral power meaningful. Queensland TMR special conditions cl 2.2(j)5 provide that absolute discretions need not be exercised for the Contractor's benefit. A direct attack on the Peninsula Balmain / Probuild duty discussed below. The same device is reported to have succeeded in other matters and appears in amended AS forms generally. Where it is present, the reopening effect described in the next section may simply not exist on that project.
How Australian courts define concurrency
Where the contract's own wording does not resolve a dispute. Or where the parties are arguing about whether concurrency exists at all before reaching the contractual consequence. A thin body of first-instance authority supplies the definition, and it is narrow.
Australian Development Corporation Pty Ltd v White Constructions (ACT) Pty Ltd6 (1996) 12 BCL 317 at 345 (Giles CJ Comm D) holds that delays are not concurrent where the contractor-risk event starts first, causes actual delay, and ends after the qualifying event has finished. That is a causation-first move: it disposes of many pleaded concurrency cases without needing a rule of entitlement at all, because on those facts there was never a genuine overlap to begin with.
"Actual delay" carries its own gloss. In Turner Corporation Ltd v Coordinated Industries Pty Ltd7 (Rolfe J), the court held that potential delay is insufficient. Concurrency requires delay to the critical path, not merely to an activity that happened to be running alongside a qualifying cause.
On methodology, White Constructions Pty Ltd v PBS Holdings Pty Ltd8 [2019] NSWSC 1166 (Hammerschlag J) is the dominant modern authority. Both parties' delay experts were rejected. The court held that the choice of delay methodology must be driven by the factual evidence, and that the SCL Delay and Disruption Protocol is not a rule of law. Earlier, Alstom Ltd v Yokogawa Australia Pty Ltd (No 7)9 [2012] SASC 49 (Bleby J) rejected delay methodologies lacking widespread recognition in construction law, while Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd10 (Flanagan J) took the more permissive position that both prospective and retrospective methodologies were permitted. Read together, the direction of travel is toward the fact-led approach in White Constructions. Expect the Protocol to be cited, and expect it not to be decisive. No 2024–2026 Australian appellate authority on concurrent delay or delay analysis was located. The field is governed entirely by these first-instance decisions.
Why the Superintendent's power matters here
Australian standard forms give the Superintendent a unilateral power to extend time, exercisable even where the contractor has not claimed or is out of time, and that power must be exercised honestly and fairly (Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd11 [2002] NSWCA 211). Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd12 [2017] NSWCA 151 went further: to claim liquidated damages, the principal was obliged to exercise that power for delays it had itself caused.
The practical consequence for concurrency is specific to AS 2124. Where the form denies an EOT for the concurrent period under cl 35.5, a principal that caused part of the delay and then levies liquidated damages must still confront the Probuild obligation. The unilateral power partially reopens what cl 35.5 closes. A principal cannot simply point to the concurrency denial and walk away from delay it caused itself. That interaction is under-litigated and remains a genuine open question rather than a settled rule. It also underscores why a special condition like Queensland TMR's cl 2.2(j), which removes the duty to exercise discretions for the contractor's benefit, is such a consequential drafting move. See the prevention principle and time at large in Australia.
Under AS 4000, the same assessment machinery carries a deemed-approval consequence in the contractor's favour: where the Superintendent fails to assess an EOT claim within 28 days, the Contractor is deemed to have been granted the full extension claimed. Sources disagree on whether this sits within the same sub-clause as apportionment or in a separate one, so this page publishes the rule and not a sub-clause number. It is a powerful contractor remedy, and. Consistently with the 84% amendment picture above. It is frequently amended out or reversed into deemed rejection.
What Australian law on concurrent delay does not contain
The gaps are as load-bearing as the rules, and none of them should be smoothed over.
- There is no Australian judicial default rule on concurrent delay. Every Australian statement of "the" concurrency position is a statement about a contract clause, not about the common law.
- No 2024–2026 Australian appellate authority on concurrent delay or delay analysis was located. The field runs on four first-instance decisions. Australian Development Corp v White Constructions (1996), Turner v Coordinated Industries, Alstom v Yokogawa [2012] SASC 49, and Civil Mining & Construction v Wiggins Island. Plus White Constructions v PBS Holdings [2019] NSWSC 1166 on methodology.
- Whether AS 4000:2025 retained cl 34.4 apportionment is unresolved. Publish the apportionment position as AS 4000-1997's, not the current edition's, until the published 2025 standard has been checked.
- The exact sub-clause carrying the AS 4000 deemed-approval rule is disputed between sources. Publish the 28-day rule, not a sub-clause number.
- The interaction between the Superintendent's unilateral power and AS 2124 cl 35.5's concurrency denial has not been squarely litigated. What is recorded here. That Probuild partially reopens what cl 35.5 closes. Is a reasoned inference from the two lines of authority, not a holding on point.
- No Australian decision has adopted or rejected the SCL Delay and Disruption Protocol as a matter of law. It is cited, and it is not decisive. White Constructions (2019) is explicit on that point.
One consequence follows for anyone advising on an Australian delay claim: the citation list is short, contested at the edges, and thin above first instance. The record. The contract, its special conditions, and the critical-path evidence. Is doing more work in Australia than the case law is.
Sources and authorities
- 1AS 4000-1997, General Conditions of Contract, cl 34.4AS 4000-1997 cl 34.4. Wording mirrored in AS 4902-2000
Where qualifying and non-qualifying causes of delay overlap, "the Superintendent shall apportion the resulting delay to WUC according to the respective causes' contribution." This is the verified wording for the 1997 edition. Retention in AS 4000:2025 is unverified. See the AS 4000:2025 entry below.
- 2AS 2124-1992, General Conditions of Contract, cl 35.5AS 2124-1992 cl 35.5, AS 4300-1995 identical save 'cause' for 'cause of delay'
Where more than one event causes concurrent delays and the cause of at least one of those events, but not all of them, is not a qualifying cause, then "to the extent that the delays are concurrent, the Contractor shall not be entitled to an extension of time for Practical Completion." Splits into limb (a). Any cause beyond the Contractor's reasonable control, expressly including industrial conditions and inclement weather, and limb (b), a narrower enumerated list of Principal-caused delay, quantity variations, latent conditions, directed variations, nominated-subcontractor issues, and changes in law or statutory-authority acts.
- 3AS 4000:2025, General Conditions of ContractAS 4000:2025, superseding AS 4000-1997, Standards Australia paywalled, clause text not read for this corpus
Standards Australia states there has been "no significant change to the allocation of risk" in the 2025 edition, which implies apportionment survived, since concurrency apportionment is squarely risk allocation. But no source consulted quotes the 2025 apportionment wording, confirms its retention, or confirms its clause number. UNVERIFIED. This is the single most consequential open question in the Australian concurrency picture and should be resolved against the published standard before pleading.
- 4Melbourne Law School standard-form amendment studyMelbourne Law School survey, 295 respondents
84% of Australian standard-form contracts are amended (100% on projects above A$500m). The EOT clause specifically is amended in 76% of contracts, and the delay/liquidated-damages provisions in 71%.
- 5Queensland TMR special conditions cl 2.2(j): the neutering deviceQueensland Department of Transport and Main Roads standard contract special conditions, cl 2.2(j)
Provides that absolute discretions need not be exercised for the Contractor's benefit. A direct drafting attack on the Peninsula Balmain / Probuild duty that makes the Superintendent's unilateral power meaningful. The same device is reported to have succeeded in Growthbuilt and CMA Assets, and it appears generally in amended AS forms.
- 6Australian Development Corporation Pty Ltd v White Constructions (ACT) Pty Ltd(1996) 12 BCL 317 at 345, Giles CJ Comm D UNVERIFIED
Delays are not concurrent where the contractor-risk event starts first, causes actual delay, and ends after the qualifying event has finished. A causation-first test that disposes of many pleaded concurrency cases without needing a rule of entitlement.
- 7Turner Corporation Ltd v Coordinated Industries Pty LtdRolfe J. Full citation not identified in the source note UNVERIFIED
"Actual delay" for concurrency purposes means critical-path delay. Potential delay to an activity that was never on the critical path is insufficient.
- 8White Constructions Pty Ltd v PBS Holdings Pty Ltd[2019] NSWSC 1166, Hammerschlag J
The dominant modern Australian authority on delay methodology. Both parties' delay experts were rejected. The choice of delay methodology must be driven by the factual evidence, not by the SCL Delay and Disruption Protocol, which is not a rule of law.
- 9Alstom Ltd v Yokogawa Australia Pty Ltd (No 7)[2012] SASC 49, Bleby J UNVERIFIED
Rejected delay methodologies lacking widespread recognition in construction law. An earlier, stricter methodology gate than White Constructions later applied.
- 10Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty LtdFlanagan J. Full citation not identified in the source note UNVERIFIED
Permitted both prospective and retrospective delay methodologies, taking a more permissive line on method than Alstom.
- 11Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd[2002] NSWCA 211
The Superintendent's unilateral power to extend time. Exercisable even where the Contractor has not claimed, or is out of time. Must be exercised honestly and fairly. The Superintendent was required to grant an EOT even though the contractor was out of time.
- 12Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd[2017] NSWCA 151
To claim liquidated damages, the Principal was obliged to exercise its unilateral power to extend time for delays it had itself caused. Under AS 2124, that duty confronts a principal seeking to rely on cl 35.5's concurrency denial where it contributed to the delay. The unilateral power partially reopens what cl 35.5 closes.
General information, not legal advice. Reviewed 1 sept 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Modelos de aviso de retraso para AS 4000, FIDIC 2017 y CCDC 2Un aviso de retraso deja constancia a tiempo de un solo hecho: que algo ha retrasado, o…
Each issue links to the full articles in the Storia Library.