Concurrent delay in England and Wales

In England and Wales the working default on concurrent delay is time yes, money no: where a Relevant Event and a Contractor-risk event are both effective causes of the same critical delay, the Contractor gets a full extension of time and no loss and expense. That default is a first-instance consensus, not binding appellate law. The only Court of Appeal decision, North Midland v Cyden (2018), upheld an express clause contracting out of it and left the default itself open.

Disponible solo en inglésEste artículo aún no se ha traducido. Los plazos, el derecho a reclamar y el procedimiento descritos aquí rozan lo jurídico, y una traducción automática sería un riesgo de credibilidad más que una comodidad: por eso se sirve el original inglés íntegro hasta que exista una traducción revisada.

Concurrent delay in England and Wales: at a glance
The default
Full extension of time, no loss and expense where a Relevant Event is an effective cause of the delay even though a Contractor-risk cause runs concurrently. The money rule is the De Beers [177] formulation, quoted in Walter Lilly ¶368.
How strong it is
First instance only. Malmaison recorded an agreed position; Walter Lilly, Adyard and Thomas Barnes are High Court decisions. The Court of Appeal called the position "not entirely free from doubt" (North Midland ¶17).
The threshold question
Concurrency exists only if both events in fact delay the progress of the works and their delaying effect is felt at the same time (Adyard ¶279). Where the Contractor was already in critical delay, the Employer may argue there is no concurrency to apply a rule to; the Court of Appeal left that view open (North Midland ¶¶17–18).
Contracting out
Valid. A bespoke clause disregarding concurrent Relevant Event delay was upheld in North Midland v Cyden [2018] EWCA Civ 1744. Prevention is not "an overriding rule of public or legal policy" (¶30).
Scotland
By a majority, City Inn [2010] CSIH 68 allows the decision-maker to "apportion the delay"; Lord Carloway rejected apportionment. Walter Lilly ¶370: "the City Inn case is inapplicable within this jurisdiction".
The standard forms
Neither JCT 2024 nor NEC4 ECC addresses concurrency. Under NEC4 the question is absorbed into the cl 63.5 assessment of the change to the Completion Date against the Accepted Programme. No English judgment decides NEC concurrency.
Latest position
As at 13 October 2026, no English decision since 2023 squarely reconsiders the default. TTSJV v BapCo [2026] EWHC 2047 (TCC) only noted a bespoke bar (¶46).

Where a Relevant Event and a Contractor-risk event are both effective causes of the same critical delay, an English tribunal will ordinarily give the Contractor the full extension of time and no loss and expense. That is the working rule. It is also a first-instance consensus that began as an agreed position, and the only Court of Appeal decision, North Midland Building Ltd v Cyden Homes Ltd, declined to decide it and upheld a clause contracting out of it. Advise on the rule with confidence and on its foundations with care.

Definitions and the cross-border comparison are on the neutral concurrent delay page; the forms and the wider authority map are on the England and Wales extension of time hub.

The default is time yes, money no, and every step of its chain is first instance

StepAuthorityWhat it addsWeight
1Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con LR 32Extension of time for a Relevant Event even though a Contractor-risk event also caused the delayRecorded as agreed between the parties
2De Beers UK Ltd v Atos Origin IT Services UK Ltd [2010] EWHC 3276 (TCC) at [177]The money half: time but no recovery of the loss caused by the concurrent delayFirst instance; an IT contract
3Walter Lilly & Co Ltd v Mackay [2012] EWHC 1773 (TCC) ¶¶366–370Full extension where a Relevant Event is one of two or more effective causes; City Inn rejectedFirst instance; the strongest statement
4Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm) ¶¶264, 279, 288A strict threshold: concurrency only where both events in fact delay progress and are felt at the same timeFirst instance; the narrower view (North Midland ¶17)
5Thomas Barnes & Sons plc (in administration) v Blackburn with Darwen BC [2022] EWHC 2598 (TCC) ¶¶110, 118, 140–148The agreed law applied to delays found to be concurrentFirst instance; law agreed by counsel
6North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA Civ 1744 ¶¶17, 18, 30Express terms can displace the default; the default itself left openCourt of Appeal, on express terms only

Jurisdictional: England and Wales. Only step 6 is appellate, and it did not decide the default.

Read in order, the chain shows its weakness: a concession at the foundation, a High Court judgment as the clearest statement, and a recent application on agreed law. In the Court of Appeal, Coulson LJ called the position "not entirely free from doubt" (¶17) but found it "unnecessary to resolve" (¶18). A TCC judge or adjudicator can be expected to apply the default. (Opinion.) It is still not settled law.

Walter Lilly gives the full extension; the money rule is borrowed from De Beers

On time, in Walter Lilly & Co Ltd v Mackay (11 July 2012) Akenhead J set out the English and Scottish approaches (¶366) and chose the English one. On the extension of time clause in that contract, where delay is caused by two or more effective causes, one of them a Relevant Event, "the Contractor is entitled to a full extension of time" (¶370). He then dealt with Scotland directly: "the City Inn case is inapplicable within this jurisdiction" (¶370). His reasoning was that a duty to fix a fair and reasonable date does not imply apportionment where there is concurrency.

On money, the judgment quotes the rule rather than making it. At ¶368 Akenhead J sets out the formulation of Edwards-Stuart J in De Beers at [177]: where concurrent delay to completion is caused by matters for which both employer and contractor are responsible, the contractor gets the extension of time but cannot recover the loss caused by the delay. De Beers was an IT services contract; its reasoning, in paraphrase, is that the contractor must have a reasonable time to complete, so it does not matter that it would have missed the contractual date anyway.

The two halves rest on different tests. Time asks whether the Relevant Event was an effective cause. Money asks whether the loss would have been suffered but for the Employer's event, and a concurrent Contractor cause defeats that.

Adyard narrows concurrency before the rule is ever reached

The rule only bites if the delays are genuinely concurrent, and Adyard Abu Dhabi v SD Marine Services (Hamblen J, 11 April 2011) sets a strict threshold for that:

"there is only concurrency if both events in fact cause delay to the progress of the works and the delaying effect of the two events is felt at the same time" (¶279)

The test is factual and actual. Prevention means "prevention in fact; not prevention on some notional or hypothetical basis" (¶264). Where the Contractor was already in critical delay on its own account when the Employer's event arrived, the Employer will argue that its event delayed nothing that was not already late, and that there is no concurrency to apply a rule to. (Inference.) Adyard also states the English answer where genuine concurrency is found: in contrast to the last of the scenarios Lord Osborne described in City Inn, "the builder is entitled to an extension of time, not an apportionment" (¶288), citing Malmaison.

That first-in-time argument is contested. The Court of Appeal in North Midland quoted ¶279 and noted that Walter Lilly points the other way from the textbook view relying on Adyard (¶17), then left the difference unresolved (¶18). Even so, the Employer's best line is often not to attack the rule but to show that the Contractor's delay came first and was already critical. (Opinion.)

Thomas Barnes applied the agreed rule to concurrent delay and split the outcome

Thomas Barnes & Sons plc (in administration) v Blackburn with Darwen BC (HHJ Stephen Davies, 17 October 2022) concerned a bus station built under a JCT form with cl 2.29A (Amendment 1A) applying (¶146). It is the leading recent trial decision applying the default.

The law was agreed, not argued. At ¶118 counsel agreed the test (from Keating, citing De Beers [177], Adyard and Walter Lilly [370]): an extension of time is due if the Relevant Event was an effective cause of delay even if there was a concurrent Contractor cause; loss and expense requires the but-for test, and showing a dominant cause is not enough.

The delays were found concurrent. The hub steelwork remedial delay (an Employer risk) and the roof coverings delay (a Contractor risk) were both causes of the critical delay (¶¶140, 143–144). This was a concurrency case on its facts, not a case where concurrency failed.

The outcome split time from money. The Contractor received an extension of time of 119 days (¶148; to 10 August 2015, ¶14(a)). It recovered no loss and expense for the concurrent period (¶147), and prolongation only for "27 days net of the concurrent delay" (¶148).

119Days of extension of time, concurrent delay included (Thomas Barnes ¶148)
27Days of prolongation recovered, net of the concurrent delay (¶148)
1Court of Appeal decision on concurrency located, and it decided express terms

On method, the court did not prescribe one. At ¶110 the judge rejected the submission that an expert is "only allowed to choose one such method and any deviation from that stated approach renders their opinion fundamentally unreliable"; a manifestly inappropriate method goes to weight. The as-built critical path approach was the claimant's expert's method (¶137), not a direction by the court. See delay analysis methods.

North Midland: you can contract out, and the Court of Appeal left the default open

North Midland Building Ltd v Cyden Homes Ltd (Sir Terence Etherton MR, Sir Ernest Ryder SPT and Coulson LJ, 30 July 2018) concerned an amended JCT Design and Build 2005 contract with a bespoke cl 2.25.1.3(b): "any delay caused by a Relevant Event which is concurrent with another delay for which the Contractor is responsible shall not be taken into account". The Contractor's prevention argument failed and the appeal was dismissed.

  • The prevention principle is not "an overriding rule of public or legal policy" (¶30). It can be displaced by clear words, and these words were clear.
  • No term could be implied to stop the Employer levying liquidated damages for the concurrent period; it would contradict the express terms (¶45).
  • The default position, absent such a clause, was "not entirely free from doubt" (¶17) and "unnecessary to resolve" (¶18).

A Cyden clause reverses the outcome on the same facts: no extension for the concurrent period, and liquidated damages run. Employer amendments to JCT and NEC forms increasingly include one, and they appear in English-law EPC contracts too. (Opinion.) TTSJV W.L.L. v BapCo Refining [2026] EWHC 2047 (TCC) only noted such a bar (cl 8.3(d), ¶46); the extension argument failed on other grounds (¶¶48–51). On how such clauses interact with prevention, see the prevention principle and time at large page.

A Cyden clause bites only on delay that is genuinely concurrent, so the Adyard threshold still has to be crossed. (Inference.) Because it removes time for Employer-caused delay, expect it to be read strictly; the North Midland wording was unambiguous. (Opinion.)

Scotland apportions, and England has said it will not

City Inn Ltd v Shepherd Construction Ltd [2010] CSIH 68 (Extra Division: Lord Osborne, Lord Kingarth, Lord Carloway; 22 July 2010), affirming Lord Drummond Young at first instance, holds by a majority (Lord Osborne and Lord Kingarth) that where both causes operate and neither is dominant, it is open to the decision-maker to "apportion the delay". Lord Carloway concurred in the result but rejected apportionment. [SINGLE-SOURCE] It is an appellate decision and it has not been overruled.

English courts have refused to follow it: Walter Lilly ¶370 held it inapplicable in England, and Adyard ¶288 put the English answer as an extension of time, not an apportionment. The split is unresolved and would need the UK Supreme Court to close it. (Opinion.) Until then, a project in Scotland or a contract governed by Scots law can produce a different day count on identical facts, so the governing law clause matters on any cross-border job. (Inference.) Compare the form-driven answers in Australia and the apportionment trend in Canada.

JCT 2024 and NEC4 leave concurrency to the general law

FormConcurrency clause in the printed formHow time is assessedMoney
JCT Design and Build 2024NoneEmployer fixes a later Completion Date for Relevant Events (cl 2.25, events in cl 2.26) on a fair and reasonable basisLoss and expense separately, for Relevant Matters (cl 4.21); epidemic (4.21.6) and change in law (4.21.7) only if selected
NEC4 ECCNoneChange to the Completion Date for a compensation event, measured prospectively against the Accepted Programme (cl 63.5)Assessed in the same compensation event, as changes to the Prices

JCT 2024. The printed form does not address concurrency, although North Midland (2018) showed how a clause could. The default therefore applies unless the parties amend. The form's own time-without-money outcome for epidemic and change in law (Relevant Events, but Relevant Matters only if selected) is contractual allocation, not concurrency. [NEGATIVE FINDING] No reported English judgment construes the JCT 2024 extension of time provisions as at 13 October 2026; every reported 2025–26 JCT decision Storia found was on a 2016 or earlier edition. On the Standard Building Contract the 2016 numbering is 2.27 / 2.28 / 2.29; check the 2024 form.

NEC4 ECC. NEC has no extension of time clause: time relief is a change to the Completion Date, assessed under cl 63.5 against planned Completion on the Accepted Programme. There is no concurrency provision. Since the January 2019 amendments, cl 63.5 takes account of delay already in the Accepted Programme and of events between the Accepted Programme date and the dividing date (paraphrased). The Contractor's own slippage is therefore dealt with implicitly: if the Accepted Programme already shows the Contractor late, the compensation event is measured from that late position. (Inference.) [NEGATIVE FINDING] No English judgment on NEC concurrency was located (searched 13 October 2026). Under NEC the question may never arise, because a compensation event notified late under cl 61.3 (8 weeks from awareness) changes neither the Prices nor the Completion Date, unless it arises from the Project Manager or Supervisor giving an instruction or notification, issuing a certificate or changing an earlier decision. (Opinion.) See notice and time bars.

The money side turns on segregation, not on the label

Because loss and expense needs the but-for test (Thomas Barnes ¶118), concurrency usually defeats prolongation for the concurrent period. The way back is to separate the costs. The SCL Delay and Disruption Protocol, 2nd edition (February 2017) takes the same line as the English default on both halves: Core Principle 10 says concurrent Contractor Delay should not reduce the extension of time due, and Core Principle 14 allows prolongation cost only where the Contractor separates the costs caused by Employer Delay from those caused by its own. (Opinion.) The Protocol is guidance, not law. Thomas Barnes shows the time-based version: prolongation for the 27 days of delay left once the concurrent period was netted off (¶148), not for the whole 119.

Where the Contractor runs a global claim instead, Walter Lilly ¶486(e) holds that matters at the Contractor's own risk do not necessarily defeat the claim: the sum attributable to them is deducted from the global loss. Quantum is covered on prolongation and delay costs.

What is not settled

  • The default itself. Every authority on the rule absent express words is first instance, resting on an agreed position (Malmaison), and the Court of Appeal left it open (North Midland ¶¶17–18).
  • Recent reconsideration. [NEGATIVE FINDING] No English decision between 2023 and 13 October 2026 squarely reconsiders the default rule (searches re-run 13 October 2026).
  • NEC concurrency and JCT 2024. No English authority on either.
  • The England and Scotland split. Unresolved.
Have you read the executed contract for a Cyden clause?

Search the amendments for any provision that disregards concurrent Relevant Event delay. If it is there and clearly worded, North Midland makes it effective and the default never applies.

Have you crossed the Adyard threshold on the records?

Concurrency exists only if both events in fact delayed the progress of the works and their effect was felt at the same time (¶279). Establish what was critical, and when, from the as-built record and the programme updates, before arguing about any rule.

Is your expert's method explained and appropriate to the records?

Thomas Barnes ¶110 does not tie an expert to one SCL method, but a manifestly inappropriate method goes to weight. The report should say what concurrency means for its analysis.

Can the costs be separated?

Without segregation the concurrent period earns time and no money. Tie cost codes, labour returns and plant records to each delay so that the non-concurrent period can be priced. (Opinion.) In Thomas Barnes money followed only the 27 days left once the concurrent period was netted off (¶148).

Under NEC4, is the Accepted Programme current?

The cl 63.5 assessment starts from the Accepted Programme. If it does not show the Contractor's own slippage, the concurrency argument is being run on the wrong baseline.

Which law governs, and where is the project?

Scots law permits apportionment under the City Inn majority. An English-law contract on a Scottish site, or the reverse, should be checked before the delay analysis is commissioned.

Where Storia fits

Concurrency in England is decided on the record of what was critical, when, and whether the two delays were felt at the same time. Storia's claims and dispute resolution tools link each delay event to the programme update, the site records and the cost codes that existed at the time, so the Adyard question and the cost separation can be answered from contemporaneous evidence rather than reconstructed for an adjudication.

Fuentes y jurisprudencia

  1. Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con LR 32, High Court (TCC), Dyson J, 1999The origin of the English approach: where a Relevant Event and a Contractor-risk event both cause delay, the Contractor is entitled to an extension of time for the period caused by the Relevant Event even though the other event also caused it. The formulation was recorded as agreed between the parties rather than determined after argument.Paraphrase. The formulation was agreed between the parties, so the foundation of the English default is a concession.Buscar en BAILII →
  2. De Beers UK Ltd v Atos Origin IT Services UK Ltd [2010] EWHC 3276 (TCC), Edwards-Stuart J, 16 December 2010At [177]: the general rule in construction and engineering cases is that where concurrent delay to completion is caused by matters for which both parties are responsible, the contractor gets an extension of time but cannot recover the loss caused by the delay. The source of "time yes, money no". for the wording: [177] was located through Find Case Law phrase search and later citations, and the full judgment was not checked, so it is paraphrased here. An IT services contract, not a construction contract.Find Case Law →
  3. Walter Lilly & Co Ltd v Mackay [2012] EWHC 1773 (TCC), Akenhead J, 11 July 2012¶370: "where delay is caused by two or more effective causes, one of which entitles the Contractor to an extension of time as being a Relevant Event, the Contractor is entitled to a full extension of time", and "the City Inn case is inapplicable within this jurisdiction". ¶366 sets out the English and Scottish approaches; ¶368 quotes the De Beers [177] money rule. ¶486(e): on a global claim, the sum attributable to matters at the claimant's own risk is deducted from the global loss.The time-yes-money-no formulation is De Beers [177], quoted at ¶368. ¶486(e) is a deduction, not an apportionment.Find Case Law →
  4. Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm), Commercial Court, Hamblen J, 11 April 2011¶264: "prevention in fact; not prevention on some notional or hypothetical basis". ¶279: "there is only concurrency if both events in fact cause delay to the progress of the works and the delaying effect of the two events is felt at the same time". ¶288: "the builder is entitled to an extension of time, not an apportionment", citing Malmaison.¶279 is quoted by the Court of Appeal in North Midland ¶17.Find Case Law →
  5. Thomas Barnes & Sons plc (in administration) v Blackburn with Darwen Borough Council [2022] EWHC 2598 (TCC), HHJ Stephen Davies, 17 October 2022¶118: counsel agreed the law. An extension is due if the Relevant Event was an effective cause of delay even if there was a concurrent Contractor cause; loss and expense requires the but-for test, and a dominant cause is not enough. ¶¶140, 143–144: the hub steelwork remedial delay (Employer risk) and the roof coverings delay (Contractor risk) were both causes of the critical delay, so the delay was concurrent. ¶¶147–148: no loss and expense for the concurrent period; extension of time of 119 days; prolongation for "27 days net of the concurrent delay".¶110 rejected the submission that an expert may choose only one SCL method; a manifestly inappropriate method goes to weight. The as-built critical path approach (¶137) was the claimant's expert's method, not a direction by the court. A JCT form with cl 2.29A (Amendment 1A) applied (¶146).Find Case Law →
  6. North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA Civ 1744, Court of Appeal (Sir Terence Etherton MR, Sir Ernest Ryder SPT, Coulson LJ), 30 July 2018A bespoke cl 2.25.1.3(b) in an amended JCT Design and Build 2005 contract, providing that "any delay caused by a Relevant Event which is concurrent with another delay for which the Contractor is responsible shall not be taken into account", was valid and effective. The prevention principle is not "an overriding rule of public or legal policy" (¶30). The default position is "not entirely free from doubt" (¶17) and it was "unnecessary to resolve" it (¶18). Appeal dismissed.Lead judgment Coulson LJ. The only Court of Appeal decision on concurrency, and it decided express terms. No implied term could remove the Employer's entitlement to liquidated damages for the concurrent period (¶45).Find Case Law →
  7. TTSJV W.L.L. v BapCo Refining [2026] EWHC 2047 (TCC), Pepperall J, 4 August 2026On an interim injunction application to restrain a call on a performance guarantee under a 2018 EPC contract governed by English law, the court noted that cl 8.3(d) excluded any extension for concurrent delay (¶46). The extension of time argument failed on other grounds (¶¶48–51), and the judgment says nothing about the default rule.Interlocutory. The court did not construe cl 8.3(d). Useful only as an example of a Cyden-style bar in an English-law EPC contract.Find Case Law →
  8. City Inn Ltd v Shepherd Construction Ltd [2010] CSIH 68, Inner House, Extra Division (Lord Osborne, Lord Kingarth, Lord Carloway), 22 July 2010, affirming [2007] CSOH 190 (Lord Drummond Young)Lord Osborne (Lord Kingarth agreeing): where a Relevant Event and a Contractor-risk event both cause delay and neither is dominant, it is open to the decision-maker to "apportion the delay". Lord Carloway concurred in the result but rejected apportionment. majority and dissent from Fenwick Elliott commentary; judgment not retrieved. Scottish. Persuasive only in England and Wales and not followed there (Walter Lilly ¶370). Not overruled in Scotland.Buscar en Find Case Law →
  9. Society of Construction Law Delay and Disruption Protocol, 2nd Edition 2nd Edition, February 2017, Core Principles 10 and 14Core Principle 10 (concurrent delay and entitlement to an extension of time): concurrent Contractor Delay should not reduce the extension of time due for Employer Delay. Core Principle 14 (concurrent delay and compensation for prolongation): the Contractor recovers prolongation cost only if it separates the costs caused by Employer Delay from those caused by Contractor Delay.Checked against the SCL PDF on 13 October 2026. Guidance, not law. It records that true concurrent delay is rare. No 3rd edition exists.Protocol →
  10. JCT Design and Build Contract 2024 JCT DB 2024, cl 2.24 (notice of delay), 2.25 (Fixing Completion Date), 2.26 (Relevant Events), 4.21 (Relevant Matters)The printed form does not address concurrency. The Employer fixes such later Completion Date as it considers fair and reasonable for Relevant Events; loss and expense runs separately through Relevant Matters, with epidemic (4.21.6) and change in law (4.21.7) Relevant Matters applying only if selected.Clause numbers and headings only. No reported English judgment construes the JCT 2024 extension of time provisions as at 13 October 2026. SBC 2016 uses 2.27 / 2.28 / 2.29; check the SBC 2024 numbering against the form.
  11. NEC4 Engineering and Construction Contract NEC4 ECC, June 2017, with amendments in January 2019, October 2020 and January 2023, cl 60.1, 61.3, 63.5No extension of time clause and no concurrency provision. A compensation event changes the Completion Date by the amount planned Completion moves later than shown on the Accepted Programme (cl 63.5, paraphrased). The January 2019 amendments revised cl 63.5 to take account of delay already in the Accepted Programme and of events between the Accepted Programme date and the dividing date (paraphrase; NEC4 Amendments January 2019, neccontract.com). No English judgment directly on concurrency under NEC was located (Farrelly v Byrne Bros [2013] EWHC 1186 (TCC) concerns prospective assessment under an NEC3 subcontract, not concurrency).