Saltar al contenido principal

Privacidad

Tu privacidad

Las cookies esenciales mantienen este sitio en funcionamiento. Los análisis opcionales nos ayudan a comprender qué funciona y solo se habilitan si usted acepta.

LIBRARY
QuebecExtension of timeJurisdiction article

Delay penalties and the clause pénale in Quebec

Quebec has no penalty versus liquidated-damages distinction. A clause pénale is valid under art 1622 C.c.Q. and enforceable without proof of loss under art 1623 para 1. The remedy is reduction, not nullity: art 1623 para 2 allows a court to reduce the penalty where the obligation has been performed in part or where the clause is abusive.

Reviewed 8 ago 202624 min read28 sources
Same topic inCAQC

Disponible solo en inglés Este artículo aún no se ha traducido. Los plazos, el derecho a reclamar y el procedimiento descritos aquí rozan lo jurídico, y una traducción automática sería un riesgo de credibilidad más que una comodidad: por eso se sirve el original inglés íntegro hasta que exista una traducción revisada.

At a glance

Quebec
Class
Doctrine
Jurisdiction
Quebec, Canada, civil law
Scope
Quebec only
Primary instrument
Code civil du Québec, arts 1622–1623
§ 00

Key facts

  1. 01

    The short answer

    A delay penalty is valid in Quebec. Art 1622 C.c.Q. recognises the clause pénale as an anticipated assessment of damages, and art 1623 para 1 lets the creditor recover the stipulated sum without proving the injury suffered. There is no genuine-pre-estimate test to run.

  2. 02

    The inversion to make first

    The common-law attack (penalty or liquidated damages) is not available and not needed. Quebec asks a different question (is the clause abusive, or has the obligation been performed in part?) and gives a different remedy (reduction, not nullity).

  3. 03

    The reduction power

    Art 1623 para 2 C.c.Q.. The stipulated sum may be reduced where partial performance has benefited the creditor or where the clause is abusive. It is available in any contract, not only adhesion contracts.

  4. 04

    Performance and the penalty together

    Art 1622 para 2 C.c.Q. normally puts the creditor to an election between performance and the penalty: except where the penalty was stipulated for delay alone, in which case both may be claimed. A delay penalty should be drafted as being for delay alone.

  5. 05

    The three routes of attack

    No prejudice at all (Constructions BSL, 2022 QCCA 1682, Gestess Plus, 2008 QCCA 314), the owner's own fault, and circumstantial abusiveness under art 1623 para 2 (EBC, 2026 QCCS 855, where the penalty was reduced from $2,997,500 to $2,000,000).

  6. 06

    The second, independent route

    Art 1437 C.c.Q.. An abusive clause in a contract of adhesion is null, or the obligation may be reduced. A public-body construction contract can be one of adhesion: Hydro-Québec c. Terrassement St-Louis, 2025 QCCA 900. Different test, different consequence.

  7. 07

    What is not available

    "Time at large" does not exist in Quebec. Where a term is indeterminate, art 1512 C.c.Q. requires the court to fix the term. A defective extension mechanism does not void the penalty. The penalty is defeated on the merits or reduced.

  8. 08

    Public work

    The MTMD Cahier des charges et devis généraux has no express delay-penalty clause, and the operative text of arts 7.8 and 8.8 could not be retrieved, so the CCDG quantum of late-completion damages cannot be stated. Check the devis spécial. Cite the edition every time.

In Quebec the distinction between a penalty and liquidated damages does not exist. A delay penalty is valid, it is enforceable without proof of loss, and a court may cut it down. That single inversion is where a common-law practitioner is most likely to reason themselves into a losing argument on a Quebec job, because the familiar attack is unavailable, and it is also unnecessary.

Under the common law the question is whether the clause is a genuine pre-estimate of loss or an unenforceable penalty, and the answer is all-or-nothing: the clause stands in full or falls entirely. Under Quebec law there is no characterisation question at all. Art 1622 C.c.Q.1 defines the clause pénale (the penal clause, by which the parties assess their damages in advance) and treats it as valid. Art 1623 C.c.Q.2 then does two things: para 1 lets the creditor recover the stipulated sum without proving the injury it suffered, and para 2 lets the court reduce that sum where the obligation has been performed in part to the creditor's benefit, or where the clause is abusive.

Different question, different remedy, different evidence. A contractor's file built to prove that the daily rate bears no relation to the owner's likely loss is a file built for the wrong forum. This page sets out what replaces it. The wider Quebec material sits at the extension-of-time hub for Quebec.

Common-law Canada

A characterisation question, answered once

Is the clause a genuine pre-estimate of loss, or a penalty out of all proportion to a legitimate interest in enforcement? Win and the clause is unenforceable in its entirety. The owner is put to proof of its actual damages. Lose and the clause applies in full. The evidence is directed at what the parties contemplated when they contracted.

Quebec

A reduction question, answered on the facts

The clause is valid and the owner need not prove its loss. The questions are whether any prejudice exists at all, whether the owner's own fault caused the delay, and whether full application of the clause is abusive on these facts. The usual outcome of a successful abusiveness argument is a smaller number, not no number.

§ 01

Is a delay penalty enforceable in Quebec, and can the owner claim performance as well?

Yes, it is enforceable. Art 1622 C.c.Q. recognises the clause pénale (the penal clause) as a valid advance assessment of damages, and no Quebec court asks whether the stipulated rate is a genuine pre-estimate. On the second question, art 1622 para 2 normally puts the creditor to an election between enforcing performance and claiming the penalty, but not where the penalty was stipulated for delay alone, in which case both may be claimed.

The French text of art 1622 C.c.Q. is worth reading closely, because the last limb is the statutory validation of the whole delay-damages model in Quebec:

« La clause pénale est celle par laquelle les parties évaluent par anticipation les dommages-intérêts en stipulant que le débiteur se soumettra à une peine au cas où il n'exécuterait pas son obligation. Elle donne au créancier le droit de se prévaloir de cette clause au lieu de poursuivre… l'exécution en nature de l'obligation. Mais il ne peut en aucun cas demander en même temps l'exécution et la peine, à moins que celle-ci n'ait été stipulée que pour le seul retard dans l'exécution de l'obligation. »

Two consequences follow immediately, and the second is a drafting point that gets missed.

There is nothing to elect between on a properly drafted delay penalty. A common lawyer arriving with an instinct that the owner must choose between compelling completion and levying delay damages will find that instinct is half right in Quebec. It is the general rule under art 1622 para 2 C.c.Q., and then displaced by the express carve-out for a penalty stipulated « pour le seul retard ». The owner may have the works finished and the penalty.

A delay penalty must be drafted as being for delay alone. Where a clause bundles delay consequences together with the consequences of defective or incomplete performance, the owner has drafted itself back into the election. That is an avoidable exposure created entirely by loose drafting, and it is the single most useful thing to check on a Quebec form before a dispute starts.

One further structural point, because it decides where the argument is run. The reduction power in art 1623 para 2 C.c.Q. is available in any contract. It does not depend on establishing a contract of adhesion, on a consumer relationship, or on any inequality between the parties. The adhesion route under art 1437 C.c.Q.3 is a separate argument with a separate threshold, dealt with below.

§ 02

What art 1623 para 1 removes from the owner's case, and what it does not

It removes proof of quantum, not proof of liability. Art 1623 para 1 C.c.Q. entitles the creditor to the stipulated sum « sans avoir à prouver le préjudice », without having to prove the injury suffered. It does not dispense the owner from the ordinary elements of civil responsibility, so the contractor may still contest whether any prejudice exists at all, and whether the owner's own fault caused the delay.

Say plainly what para 1 does to the contractor's position, because it is a serious practical disadvantage and it is easy to understate. On a common-law project the contractor cross-examines the owner on its actual loss and on how the rate was built up. In Quebec that cross-examination has no purchase on the amount claimed: the owner deducts or claims the stipulated sum, and the contractor carries the burden of running a positive case to get it back. Combined with the rule that meeting the completion date is an obligation de résultat (an obligation of result) under Ville de Pointe-Claire c. Asphalte Béton Carrières Rive-Nord inc.4 2023 QCCA 1565, which requires the contractor to positively prove force majeure or the owner's fault rather than merely to disprove its own, the starting position for a late contractor in Quebec is worse than the equivalent starting position in Ontario.

The counterweight is the one appellate proposition that every Quebec delay-penalty file should be built around. In Ville de Québec c. Constructions BSL inc.5 2022 QCCA 1682 the Court of Appeal is reported as holding that merely including a penalty clause in the tender documents does not guarantee its enforceability, that a penal clause is conventional damages substituting for judicially assessed damages, and that « l'absence de préjudice fait échec à un recours fondé sur une clause pénale », the absence of prejudice defeats a claim founded on a penal clause. Gestess Plus (9088-0964 Québec inc.) c. Harvey6 2008 QCCA 314 is reported to the same effect.

The reconciliation between art 1623 para 1 and Constructions BSL is the most important open point on this topic, and it should be published as a reconciliation rather than as a settled rule. The reading that makes both work is that art 1623 removes proof of the amount of the loss, not proof that a loss exists at all: a penal clause substitutes a conventional figure for a judicially assessed one, and both still rest on fault, prejudice and causation under the ordinary law. On that reading the owner is relieved of quantification and nothing else. On the facts of Constructions BSL the owner obtained, in the reported phrase, a very robust bridge for the price of a pedestrian footbridge, and suffered no actual harm, so there was nothing for the conventional figure to substitute for.

Layer: jurisdictional. Art 1623 C.c.Q. is primary-verified against LégisQuébec in French and in the official English. The Constructions BSL and Gestess Plus holdings rest on secondary law-firm commentary (no Quebec judgment was read in original text for this corpus) and no paragraph pinpoint is available for either.

§ 03

The three routes of attack that replace the penalty argument

A Quebec contractor attacks a delay penalty on three main routes: that the owner suffered no prejudice at all, that the owner's own fault caused the delay, and that full application of the clause is abusive under art 1623 para 2 C.c.Q. The first two can defeat the claim outright. The third produces a reduction: sometimes a substantial one, but a reduction.

RouteBasisAssessment
No prejudice at allArt 1623 para 1 C.c.Q. read with Constructions BSL, 2022 QCCA 1682, and Gestess Plus, 2008 QCCA 314Strong where the owner genuinely suffered no loss. It is a complete answer, not a discount
The owner's own fault caused the delayContractual fault under art 1458 C.c.Q., abuse of contractual right under arts 6, 7 and 1375 C.c.Q., Constructions BSL, Constructions ConCreate ltée c. Procureure générale du Québec7 2020 QCCA 570Strongest in practice. Reported in Constructions BSL: « la Ville ne pouvait certes pas ignorer sa propre faute au moment de réclamer la pénalité contractuelle »
Circumstantial abusivenessArt 1623 para 2 C.c.Q., second limb. 3903460 Canada inc. c. Elphin inc.8 2022 QCCA 1445. EBC inc. c. Ville de Montréal9 2026 QCCS 855Reduction only, and the reported discount in EBC was partial
Partial performance benefiting the ownerArt 1623 para 2 C.c.Q., first limb. Sintra inc. c. Ville de Léry10 2019 QCCS 2616 (partial possession)Real, and under-pleaded
Superior force (force majeure)Arts 1470 and 1600 para 2 C.c.Q.11: art 1470's own term is "superior force", not cause étrangèreStrong: but check the contractor was not already in demeure (in default), because art 1600 para 2 defeats the defence and puts even superior-force losses on the debtor
Owner's tolerance or waiver of the delayCompagnie d'assurances Travelers du Canada c. Ville de Montréal12 2020 QCCS 1414Fact-heavy. Lives or dies on the contemporaneous record
Owner failed to follow its own delay procedureContractualUnder-used. Read the clause's own conditions before conceding the deduction
Apportionment where responsibility is sharedQuebec courts apportion faultRoutine in practice, but see the caution below on the article usually cited for it
Art 1437 nullity or reductionContracts of adhesion only. Hydro-Québec c. Terrassement St-Louis inc.13 2025 QCCA 900Requires winning the adhesion point first

Layer: jurisdictional. The statutory rows rest on the Code, primary-verified against LégisQuébec. Every case row rests on secondary law-firm commentary, not on the judgment. The appellate rows are Constructions BSL, ConCreate, Gestess Plus, Elphin and Terrassement St-Louis, and the remainder are first instance.

The owner's-fault route is where this page meets the Quebec treatment of prevention. Quebec has no named prevention principle, and it does not need one: the owner's conduct does not blow up the completion date, it defeats the owner's claim on the merits, in whole or in proportion, through contractual fault under art 1458 C.c.Q. and abuse of contractual right under arts 6, 7 and 1375 C.c.Q. In Constructions ConCreate ltée c. Procureure générale du Québec, 2020 QCCA 570, the owner's refusal of a lane closure the contractor needed in order to work safely is reported as « un comportement déraisonnable et un abus de droit contractuel », and the contractual allocation of that risk to the contractor did not license the owner to obstruct. The closest doctrinal analogue to prevention is the discretionary fin de non-recevoir (a peremptory exception that bars a party from asserting an otherwise existing right) but the recorded finding is that no Quebec judgment expressly using the words fin de non-recevoir in a construction delay context was located. Plead the outcome, which is well supported. Do not present the label as a settled line of construction cases.

On apportionment, one caution belongs on the page. Quebec courts do apportion responsibility for delay between owner and contractor, and that is the mechanism that does the work an English court would do through concurrency analysis: there is no Quebec doctrine of concurrent delay, and none was located in any Quebec statutory, judicial or professional source. But art 1478 C.c.Q.14 sits in the extracontractual chapter, and art 1458 para 2 C.c.Q. forbids co-contractants from opting into that regime. Cite the practice. Do not cite art 1478 C.c.Q. as though its contractual application were settled.

Circumstantial abusiveness, EBC inc. c. Ville de Montréal, 2026 QCCS 855

Quebec distinguishes intrinsic abusiveness, where the clause is bad on its face, from circumstantial abusiveness, where a reasonable clause becomes excessive because of what its complete application produces on the facts, 3903460 Canada inc. c. Elphin inc., 2022 QCCA 1445. The leading recent construction application is EBC inc. c. Ville de Montréal, 2026 QCCS 855, decided 16 March 2026.

$29.975MContract value: Phase I underground infrastructure to reduce sewage discharge, awarded October 2017
193daysDelay, 45% of the 425-day contractual period
$2,997,500Penalty applied by the City at 0.1% of contract price per day, capped at 10%
$2,000,000Reduced sum, full application held abusive on the facts

Every figure above is reported in secondary law-firm commentary. No Quebec judgment was read in original text for this corpus, and no paragraph pinpoint is available. Verify on CanLII or SOQUIJ before relying on any of it.

The reported reasoning is more useful than the numbers, because it tells a contractor what evidence to assemble. Abusiveness is assessed in context, not in a vacuum, and the reported analysis runs on five factors:

  1. Party autonomy. The 10% cap had been requested by the contractor itself, which was treated as recognition that the clause was determinative. Evidence that your own client negotiated the clause is evidence against your own argument.
  2. Proportionality. The penalty was around three times projected profit, and this carried limited weight, because allowing thin-margin contractors to escape would gut penalty clauses generally.
  3. Fault attribution. The contractor bore sole responsibility. There was no force majeure and no municipal fault. This is the factor that connects abusiveness back to the owner's-fault route.
  4. Relation to the damage. The actual harm was likely to have exceeded the penalty, and the clause exists precisely to dispense with proof of extent.
  5. Dissuasive intent. There was no clear agreement confining the clause to a purely dissuasive function.

The clause was not intrinsically abusive. Its full application became abusive because it permitted enrichment « qui dépasse largement son rôle compensatoire et dissuasif ». Note also what the court is reported as saying about public contracts specifically, because it cuts against reduction: procurement on the lowest-compliant-bid basis with no post-award negotiation, all bidders having priced the stated clause, so that a retroactive reduction distorts competitive fairness, and the inherent difficulty a public body faces in quantifying its damage.

The outcomes reported across the Quebec cases show the same pattern: clauses are enforced far more often than they are struck, and the successful arguments produce adjusted figures.

CaseThe clauseReported outcome
Excavation Gilbert Théorêt inc. c. Montréal15 2016 QCCS 2325900 mm water conduit, 140-day period, 56 days late. $378,324.49 withheldClauses of this kind « ne peuvent être considérées comme abusives à leur face même », 0.35% of contract value not unreasonable, the City's moderate application (penalty on the delayed portion only) supported enforcement. Reduced to $209,482
Coffrage Alliance ltée c. Procureure générale du Québec16 2018 QCCS 3782$500 to $2,000 per day. $94,000 deductedUpheld, « Les pénalités ne sont pas excessives ou déraisonnables »
Ville de Pointe-Claire c. Asphalte Béton Carrières Rive-Nord, 2023 QCCA 1565$1,500 to $2,500 per day$712,500 for 475 days upheld. The art 1623 abusiveness argument failed notwithstanding partial utility of the work
2957-4928 Québec inc. (Clôtures spécialisées) c. Québec (Procureur général)17 2016 QCCS 1262Transport-ministry penalty of $132,000Reduced to $50,000, documented ground conditions beyond the contractor's control
EBC inc. c. Ville de Montréal, 2026 QCCS 8550.1% per day, 10% cap$2,997,500 reduced to $2,000,000

Layer: illustrative, and every row rests on secondary law-firm commentary rather than on the judgment. One row is appellate (Pointe-Claire, 2023 QCCA 1565). The rest are first instance. Treat every figure as single-source and verify before pleading a comparable.

§ 04

Partial performance benefiting the owner is an express statutory ground for reduction

Art 1623 para 2 C.c.Q. has two limbs, and the first is routinely overlooked. The stipulated penalty may be reduced « si l'exécution partielle de l'obligation a profité au créancier », where partial performance of the obligation has benefited the creditor. A contractor that finished late but finished, or whose work was taken into partial use during the delay, has an argument on the face of the Code that has no common-law equivalent.

The common-law reader should register how unusual this is. In England or Ontario, partial or late performance does not reduce liquidated damages. The clause runs to the completion date and the fact that the employer has been using half the building is, at best, an evidential point about loss. In Quebec it is a statutory ground of reduction, pleaded directly under art 1623 para 2 C.c.Q., and it does not require proof that the clause is abusive.

The factual patterns that engage it are ordinary ones on a delayed project:

  • Partial possession or sectional occupation. The owner taking beneficial use of part of the works while the remainder is completed. Sintra inc. c. Ville de Léry, 2019 QCCS 2616, is reported in this connection.
  • Phased or milestone completion, where the owner has received the benefit of the earlier phases on time.
  • A penalty levied on the whole contract value where only a discrete portion was late. That is the mirror image of the point that supported enforcement in Excavation Gilbert Théorêt inc. c. Montréal, 2016 QCCS 2325, where the owner's moderate application of the clause to the delayed portion only was treated as a reason to enforce it.

Two adjacent points determine how much benefit there is to argue about, because both fix the date on which the penalty stops running. Consortium GAS c. Hôpital général du Lakeshore18 2016 QCCS 4547 is reported as holding that completion of the works is a discrete event occurring when the contractual obligations are fulfilled, regardless of deficiencies. The corollary for a delay penalty is that an owner cannot run it on into the snagging period. And the Quebec statutory completion concept is fin des travaux. The end of the work under art 2110 C.c.Q., an objective factual state determined by the court rather than certified by a consultant. Neither substantial performance nor Ready-for-Takeover is a Quebec concept.

§ 05

Adhesion under art 1437 C.c.Q.: a second route, and a different test

There is a second and independent route to reduction that a Quebec contractor should keep separate from art 1623 para 2 C.c.Q. Where the contract is one of adhesion, art 1379 C.c.Q.19 opens arts 1435 and 1436 C.c.Q.20 and, most importantly, art 1437 C.c.Q., under which an abusive clause is null, or the obligation arising from it may be reduced. In Hydro-Québec c. Terrassement St-Louis inc., 2025 QCCA 900, a public-body construction contract was held to meet the art 1379 C.c.Q. definition.

Note what the art 1379 C.c.Q. adhesion test is not. It is not a consumer test. It requires no inequality of bargaining power, no small size, and no lack of sophistication. It asks whether the essential stipulations were imposed or drawn up by one party and were not freely discussable. A commercial contractor that bid competitively for a public contract can satisfy it, and in Terrassement St-Louis the key terms were reported to have been imposed without negotiation. The Court of Appeal is reported as having gone on to find the arbitration clause unfair under art 1437 C.c.Q. as an unreasonable obstacle to justice, on an analysis turning on proportionality, the economic realities of the parties and access to justice: three arbitrators in Montreal against a claim of $253,128 by a regional SME.

Keep the two routes distinct, because they are different tests with different consequences and they need different evidence.

Art 1623 para 2 C.c.Q.Art 1437 C.c.Q.
AvailabilityAny contract. No threshold to crossOnly a consumer contract or a contract of adhesion. The adhesion point must be won first, under art 1379 C.c.Q.
TestPartial performance benefiting the creditor, or the clause is abusive: in EBC, assessed on the five contextual factorsThe clause is excessively and unreasonably detrimental to the adhering party and therefore contrary to the requirements of good faith
RemedyReduction only. The clause is not annulledNullity of the clause, or reduction of the obligation arising from it
EvidenceThe project facts: benefit received, fault attribution, proportion, the relation between the penalty and the damageFormation facts: who drafted, what was negotiable, whether the clause was in an external document, plus proportionality and the parties' economic realities

Layer: jurisdictional, and both columns rest on the Code, primary-verified against LégisQuébec in French and in the official English. The EBC five factors and the Terrassement St-Louis holding rest on secondary law-firm commentary.

State the counterweight fairly, because it comes from the same case that supplies the best abusiveness material. EBC inc. c. Ville de Montréal, 2026 QCCS 855, is reported as declining to characterise a City of Montreal construction contract as one of adhesion, stressing the distinctive character of public procurement (lowest compliant bidder, no post-award negotiation, all bidders having priced the stated clause) and recording that the contractor had itself asked for the 10% cap. The two decisions are coherent: adhesion under art 1379 C.c.Q. is a fact-specific determination about whether the essential stipulations could be freely discussed, and evidence that the specific clause was negotiated defeats the argument.

A related recorded finding belongs here, because it marks the edge of what can be asserted. No Quebec construction case applying art 1435 or art 1436 C.c.Q. to a claim-procedure time bar was located. The theory is squarely available after Terrassement St-Louis: claim procedures and penalty regimes usually live in an external document incorporated by reference, and art 1435 C.c.Q. nullifies an external clause in an adhesion contract that was not expressly brought to the adherent's attention at formation, but it has not been run to judgment, and it should be pleaded as a novel argument with that acknowledged.

§ 06

"Time at large" is not the escape from a Quebec delay penalty

The concept of "time at large" does not exist in Quebec. No statutory, judicial, doctrinal or professional source uses it. A contractor whose extension mechanism is defective, or whose contract has none, does not thereby escape the penalty: where a term is indeterminate art 1512 C.c.Q.21 requires the court, on the application of either party, to fix the term. That is the opposite of the common-law consequence.

This is the single most dangerous assumption a common-law practitioner can import into a Quebec delay-penalty file, so it is worth setting out why the concept has no structural place here rather than merely asserting the negative finding.

There is no statutory completion date to set at large. The Code civil du Québec imposes none. Every article of the contrat d'entreprise chapter, arts 2098–2129 C.c.Q., was read individually for this corpus, and time is mentioned once: at art 2102 C.c.Q., as a pre-contractual disclosure duty on the contractor. There is no default time obligation for the doctrine to fall back on. The detail is at the Civil Code framework for delay in Quebec, which also explains why the forfait (fixed-price) contract sum does not move under art 2109 C.c.Q.22 even where the conditions of performance change.

Quebec's answer to temporal indeterminacy is judicial gap-filling. Art 1512 C.c.Q. directs the court to fix the term having regard to the nature of the obligation, the situation of the parties and any appropriate circumstances. Where the common law dissolves the obligation, Quebec supplies its missing content.

The penalty does not fall away, because the reduction power is graduated. Art 1623 para 2 C.c.Q. gives courts a power to reduce. There is no all-or-nothing collapse of the delay-damages regime, so there is nothing for a "time at large" argument to achieve that the merits do not achieve better. The route to relief is to defeat the claim on prejudice or on the owner's fault, or to reduce it for partial performance or abusiveness.

The practical instruction is short. Delete "time at large" from a Quebec pleading and from any drafting that assumes it, and replace the assumption with an express extension mechanism, because the Code supplies none. The row-by-row account of what else has to change is at Quebec vs common-law Canada on delay.

§ 07

Delay penalties on Quebec public work. The CCDG, the devis spécial, and what cannot be stated

Most reported Quebec delay-penalty litigation is public work, and a practitioner looking for the delay-penalty clause in the provincial roadworks general conditions will not find one. The MTMD Cahier des charges et devis généraux23 has no express delay-penalty clause and no dedicated extension-of-time clause. That is a recorded negative finding. The penalty, where there is one, is in the devis spécial, the project-specific specification.

Two further constraints follow, and both should be stated rather than papered over.

The quantum of CCDG late-completion damages cannot be stated. The structure is verified from the official édition 2024 table of contents: art 7.8 Délais et ordonnancement, with 7.8.1 Intempéries (weather) and 7.8.2 Défaut de terminer les travaux dans le délai prescrit (late completion), and art 8.8 Procédure de réclamation. The operative text of arts 7.8 and 8.8 could not be retrieved, so neither the CCDG's mechanism for prolongation of the contract period nor the quantum of its late-completion damages can be given here. There is no article in the édition 2024 table of contents headed « prolongation du délai contractuel ».

Always give the edition with the clause number. The claim procedure was art 9.7 in the December 2000 edition and art 8.8 from 2017 onward. Délais et ordonnancement was art 8.4 and is now art 7.8. The current construction book is CCDG – Infrastructures routières – Construction et réparation, édition 2026, and it is reissued annually. A reference to a "2025 CCDG" is usually the Services professionnels book, which is the wrong volume for delay work.

For municipal work in Montreal the position is different and more conventional: the Ville de Montréal Cahier des clauses administratives générales (CCAG)24, rév. 2022-12-13, carries modification of the periods at art 5.1.9, Pénalités at art 5.1.12, and claims at art 4.3.11. That is the form behind several of the reported Montreal penalty decisions, including EBC inc. c. Ville de Montréal, 2026 QCCS 855, and Excavation Gilbert Théorêt inc. c. Montréal, 2016 QCCS 2325.

One procedural trap on public work is worth flagging alongside the penalty, because it kills more claims than abusiveness saves. In Coffrage Alliance ltée c. Procureure générale du Québec, 2018 QCCS 3782, a cyclone was reported to have been accepted as force majeure and the contractor's claim was nonetheless dismissed for want of a detailed claim within the contractual 120 days, while $94,000 of penalties stood. A good substantive answer to a penalty is worth nothing if the claim procedure has already been missed.

§ 08

Around the penalty: heads of damage, the indemnité additionnelle, and the clauses that do not survive

Three things sit immediately around a Quebec delay penalty and are regularly handled wrongly in a draft written for a common-law jurisdiction: what the owner may recover where it sues for damages instead of relying on the clause. The interest top-up at art 1619 C.c.Q.25 that has no common-law equivalent. And the clauses (deemed default, and termination for trivial delay) that Quebec public order simply will not enforce.

Heads of damage, and remoteness. Where an owner claims damages rather than levying the penalty, the reported heads are unremarkable: the cost of a replacement contractor, extended professional fees for supervision and resident engineers, extended insurance premiums, lost rental income, temporary accommodation, administrative overhead during the delay, and lost operational income during a closure. The filter is art 1613 C.c.Q.26: only damages foreseen or foreseeable at the time the obligation was contracted, and only what is « une suite immédiate et directe » of the non-performance, with the carve-out that intentional or gross fault removes the foreseeability filter entirely. Two corrections belong on the page because they circulate widely: art 1614 C.c.Q. is the discount rate for prospective bodily-injury damages, not a general damages article, and art 1612 C.c.Q. is the trade-secret article. Neither has any application to a construction delay claim. The general assessment provisions are arts 1607, 1611 and 1613 C.c.Q.. The neutral treatment of the cost heads themselves is at prolongation and delay costs.

The indemnité additionnelle: art 1619 C.c.Q. An indemnity may be added to the damages awarded, computed by applying to that amount a percentage equal to the excess of the rate of interest payable on debts due to the Crown over the agreed or legal rate, from the date of default or any later date the court considers appropriate. It is discretionary, it has no common-law equivalent, it is materially valuable on a large multi-year delay award, and the recorded finding is that it is routinely under-pleaded. Claim it expressly. The Crown-debt rate changes quarterly, so check it at the date of judgment. This cuts both ways. An owner claiming delay damages beyond the penalty can plead it too.

Deemed-default drafting does not work. Art 1598 C.c.Q.27 provides that the creditor must prove that one of the cases of default by operation of law has occurred, « malgré toute déclaration ou stipulation contraire ». A clause that deems the contractor in default, deems notice to have been given, or reverses that burden is ineffective on that point, however clearly it is drafted. Note the separate point that where the contract stipulates a completion date, arts 1594 and 1597 C.c.Q. already dispense the owner from serving a mise en demeure (a formal notice of default) so the deeming clause was usually unnecessary as well as ineffective.

Termination for trivial delay does not survive. Art 1604 para 2 C.c.Q.28 provides that, « malgré toute stipulation contraire », there is no right to resolve or resiliate the contract where the debtor's default is « de peu d'importance », of minor importance. The rule is of public order, so a right to terminate for any delay however small, imported from a common-law form, is ineffective to that extent. The qualification matters to owners: in an obligation of successive performance (and a construction contract is one) a default that occurs repeatedly does justify resiliation. Where resiliation is barred, the intermediate remedy is proportional reduction of the correlative obligation, which has no clean common-law equivalent. The neutral account of how a liquidated-damages regime and the extension machinery interlock, and how differently the common-law forms build it, is at extension of time.

Notes

Sources and authorities

28 cited
  1. *
    Verification, unless noted

    No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.

  2. 1
    Code civil du Québec, art 1622, the clause pénaleC.c.Q., art 1622

    A penal clause is one by which the parties assess the anticipated damages by stipulating that the debtor will suffer a penalty if it fails to perform its obligation. It gives the creditor the right to avail itself of the clause instead of enforcing the obligation in kind, but the creditor may not in any case demand both performance and the penalty unless the penalty has been stipulated for mere delay in the performance of the obligation.

    LégisQuébec

  3. 2
    Code civil du Québec, art 1623: recovery without proof, and reductionC.c.Q., art 1623

    Para 1. A creditor who avails itself of the penal clause is entitled to the amount of the stipulated penalty without having to prove the injury it has suffered. Para 2: however, the amount of the stipulated penalty may be reduced if the creditor has benefited from partial performance of the obligation or if the clause is abusive. Both paragraphs verified verbatim against LégisQuébec. The reduction power is not confined to contracts of adhesion.

    LégisQuébec

  4. 3
    Code civil du Québec, art 1437, abusive clauseC.c.Q., art 1437

    An abusive clause in a consumer contract or a contract of adhesion is null, or the obligation arising from it may be reduced. An abusive clause is one that is excessively and unreasonably detrimental to the consumer or adhering party and therefore contrary to the requirements of good faith. Note that the remedy expressly includes nullity, which art 1623 para 2 does not.

    LégisQuébec

  5. 4
    Ville de Pointe-Claire c. Asphalte Béton Carrières Rive-Nord inc.2023 QCCA 1565, Court of Appeal of Quebec

    Meeting the completion date is an obligation de résultat: the contractor must positively prove force majeure or the owner's fault, and proving the absence of its own fault is not enough. On a penalty of $1,500 to $2,500 per day, $712,500 for 475 days was upheld and the art 1623 abusiveness argument failed notwithstanding the partial utility of the work.

    Buscar en CanLII

  6. 5
    Ville de Québec c. Constructions BSL inc.2022 QCCA 1682, Court of Appeal of Quebec

    Including a penalty clause in the tender documents does not guarantee its enforceability. A penal clause is conventional damages substituting for judicially assessed damages, and both require proof of liability under the ordinary rules of civil responsibility. The absence of prejudice defeats a claim founded on a penal clause. Reported as holding that the City could not ignore its own fault when claiming the contractual penalty.

    Buscar en CanLII

  7. 6
    Gestess Plus (9088-0964 Québec inc.) c. Harvey2008 QCCA 314, Court of Appeal of Quebec

    Reported as authority that the debtor may defeat a penal clause by proving that no prejudice occurred, concordant with the later reasoning in Constructions BSL.

    Buscar en CanLII

  8. 7
    Constructions ConCreate ltée c. Procureure générale du Québec2020 QCCA 570, Court of Appeal of Quebec

    Reported as holding that the owner's refusal of a lane closure the contractor needed in order to work safely, and its inaction after the workplace-safety regulator intervened, amounted to unreasonable conduct and an abuse of contractual right. The contractual allocation of a risk to the contractor does not license the owner to obstruct.

    Buscar en CanLII

  9. 8
    3903460 Canada inc. c. Elphin inc.2022 QCCA 1445, Court of Appeal of Quebec

    Reported for the distinction between intrinsic abusiveness (the clause is abusive on its face) and circumstantial abusiveness, where a reasonable clause becomes excessive when applied in full on the facts.

    Buscar en CanLII

  10. 9
    EBC inc. c. Ville de Montréal2026 QCCS 855, Superior Court of Quebec

    Reported as the leading recent application of art 1623 para 2 C.c.Q. to a construction delay penalty, decided 16 March 2026. On a contract of about $29.975M with a 425-day period and a penalty of 0.1% of the contract price per day capped at 10% at the contractor's own request, a 193-day delay produced a penalty of $2,997,500. Abusiveness is assessed in context and not in a vacuum, on five factors: party autonomy, proportionality, fault attribution, relation to the damage actually suffered, and dissuasive intent. The clause was not intrinsically abusive, but its full application became abusive and the penalty was reduced to $2,000,000. The court declined to characterise the contract as one of adhesion.

    Buscar en CanLII

  11. 10
    Sintra inc. c. Ville de Léry2019 QCCS 2616, Superior Court of Quebec

    Reported in connection with force majeure and with partial possession of the works by the owner, the latter being the factual pattern that engages the partial-performance limb of art 1623 para 2 C.c.Q.

    Buscar en CanLII

  12. 11
    Code civil du Québec, arts 1470 and 1600, superior force (force majeure) and demeureC.c.Q., arts 1470, 1600 para 2

    Art 1470. The Code's own term is "superior force", the French text's force majeure. It does not use the doctrinal expression cause étrangère. Superior force is an unforeseeable and irresistible event, and external causes count only where they present those same characteristics. The article does not refer to the fault of a third person: a third party's act qualifies only if it is itself unforeseeable and irresistible. Art 1600 para 2 does not create an excuse. It removes one: from the time of default the debtor is liable for any loss resulting from superior force, unless it is thereby released. Once the contractor is in default the superior-force defence is defeated.

    LégisQuébec

  13. 12
    Compagnie d'assurances Travelers du Canada c. Ville de Montréal2020 QCCS 1414, Superior Court of Quebec

    Reported in connection with an owner's tolerance or waiver of delay as an answer to a subsequent claim under the penalty clause. A fact-heavy route that depends entirely on the contemporaneous record.

    Buscar en CanLII

  14. 13
    Hydro-Québec c. Terrassement St-Louis inc.2025 QCCA 900, Court of Appeal of Quebec

    Reported as confirming that a public-body construction contract met the art 1379 C.c.Q. definition of a contract of adhesion, the key terms having been imposed without negotiation, and that the arbitration clause was unfair under art 1437 C.c.Q. as an unreasonable obstacle to justice, the analysis turning on proportionality and the economic realities of the parties.

    Buscar en CanLII

  15. 14
    Code civil du Québec, art 1478, apportionmentC.c.Q., art 1478

    Liability is shared where injury is caused by several persons, and where the victim has contributed to the injury liability is shared according to the gravity of the respective faults. The article sits in the extracontractual chapter, and art 1458 para 2 forbids co-contractants opting into that regime. Quebec courts apportion in contract regardless, but the contractual application of art 1478 is not settled and should not be cited as though it were.

    LégisQuébec

  16. 15
    Excavation Gilbert Théorêt inc. c. Montréal2016 QCCS 2325, Superior Court of Quebec

    Reported as holding that delay-penalty clauses of this kind cannot be considered abusive on their face, that a rate of 0.35% of contract value was not unreasonable, and that the owner's moderate application of the clause (levying the penalty on the delayed portion only) supported enforcement. The $378,324.49 withheld was reduced to $209,482.

    Buscar en CanLII

  17. 16
    Coffrage Alliance ltée c. Procureure générale du Québec2018 QCCS 3782, Superior Court of Quebec

    Reported as upholding delay penalties of $500 to $2,000 per day, $94,000 in total, as neither excessive nor unreasonable, their purpose being to secure compliance with the contractual periods. A cyclone was accepted as force majeure but the claim failed for want of a detailed claim within the contractual 120 days.

    Buscar en CanLII

  18. 17
    2957-4928 Québec inc. (Clôtures spécialisées) c. Québec (Procureur général)2016 QCCS 1262, Superior Court of Quebec

    Reported as reducing a transport-ministry delay penalty of $132,000 to $50,000 on documented ground conditions beyond the contractor's control.

    Buscar en CanLII

  19. 18
    Consortium GAS c. Hôpital général du Lakeshore2016 QCCS 4547, Superior Court of Quebec

    Reported as holding that completion of the works is a discrete event occurring when the contractual obligations are fulfilled, regardless of deficiencies. The corollary for a delay penalty (that it stops running on that date) is an inference from the holding, not part of it.

    Buscar en CanLII

  20. 19
    Code civil du Québec, art 1379, contract of adhesionC.c.Q., art 1379

    A contract is one of adhesion where its essential stipulations were imposed or drawn up by one of the parties and were not freely discussable. The test is not a consumer test and requires no inequality of bargaining power, small size or lack of sophistication.

    LégisQuébec

  21. 20
    Code civil du Québec, arts 1435 and 1436, external and illegible clausesC.c.Q., arts 1435, 1436

    Art 1435. An external clause referred to in a contract of adhesion or a consumer contract is null if, at the time of formation, it was not expressly brought to the attention of the adhering or consumer party. Art 1436. An illegible or incomprehensible clause in such a contract is null if the party suffers injury by it.

    LégisQuébec

  22. 21
    Code civil du Québec, art 1512, the court fixes an indeterminate termC.c.Q., art 1512

    Where the parties have agreed to delay the determination of the term and a reasonable period has expired without their doing so, the court may, on the application of either of them, fix the term having regard to the nature of the obligation, the situation of the parties and any appropriate circumstances. The consequence of temporal indeterminacy in Quebec is judicial gap-filling, not the collapse of the time obligation.

    LégisQuébec

  23. 22
    Code civil du Québec, art 2109, the forfait ruleC.c.Q., art 2109

    Where the contract is a fixed-price (forfait) contract, the contractor may not claim an increase in the price, and unless otherwise agreed the price remains unchanged notwithstanding any modification of the original terms and conditions of performance. A prolongation claim in Quebec is therefore pleaded as fault, not as an entitlement to additional payment.

    LégisQuébec

  24. 23
    MTMD Cahier des charges et devis généraux: Infrastructures routières, Construction et réparationédition 2026 (reissued annually) · claim procedure art 8.8 from 2017, art 9.7 in the December 2000 edition

    The general conditions for Quebec provincial roadworks, published by the Ministère des Transports et de la Mobilité durable. It contains no dedicated extension-of-time clause and no express delay-penalty clause. Art 7.8 is Délais et ordonnancement, with 7.8.1 Intempéries and 7.8.2 Défaut de terminer les travaux dans le délai prescrit. Art 8.8 is the Procédure de réclamation. Headings are verified from the édition 2024 table of contents. The operative text of arts 7.8 and 8.8 could not be retrieved, so the quantum of late-completion damages cannot be stated.

  25. 24
    Ville de Montréal, Cahier des clauses administratives générales (CCAG)rév. 2022-12-13

    The City of Montreal general administrative conditions. Art 5.1.9 addresses modification of the periods, art 5.1.12 Pénalités, and art 4.3.11 claims. This is the form behind several of the reported Montreal delay-penalty decisions.

  26. 25
    Code civil du Québec, art 1619, the indemnité additionnelleC.c.Q., art 1619

    An indemnity may be added to the amount of damages awarded, computed by applying to that amount, from the date of default or from any other later date the court considers appropriate, a percentage equal to the excess of the rate of interest payable on debts due to the Crown over the agreed or legal rate of interest. The award is discretionary, and the Crown-debt rate changes quarterly.

    LégisQuébec

  27. 26
    Code civil du Québec, art 1613, foreseeability and immediate consequenceC.c.Q., art 1613

    In contractual matters the debtor is liable only for damages that were foreseen or foreseeable at the time the obligation was contracted, where the failure to perform is not due to intentional or gross fault, and even then the damages include only what is an immediate and direct consequence of the non-performance. Art 1613 is the remoteness provision. Art 1614 is the discount rate for prospective bodily-injury damages and art 1612 is the trade-secret article. Neither applies to construction quantum.

    LégisQuébec

  28. 27
    Code civil du Québec, art 1598, proof of default by operation of lawC.c.Q., art 1598

    The creditor must prove that one of the cases where the debtor is in default by operation of law has occurred, notwithstanding any declaration or stipulation to the contrary. A clause deeming default, deeming notice given, or reversing that burden is ineffective on that point.

    LégisQuébec

  29. 28
    Code civil du Québec, art 1604 para 2, no resiliation for a trivial defaultC.c.Q., art 1604 para 2

    Notwithstanding any stipulation to the contrary, a creditor may not resolve or resiliate the contract where the debtor's default is of minor importance, unless, in the case of an obligation of successive performance, the default occurs repeatedly. The rule is of public order, and proportional reduction of the correlative obligation is the intermediate remedy.

    LégisQuébec

General information, not legal advice. Reviewed 8 ago 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Modelos de aviso de retraso para AS 4000, FIDIC 2017 y CCDC 2Un aviso de retraso deja constancia a tiempo de un solo hecho: que algo ha retrasado, o…

Each issue links to the full articles in the Storia Library.

Penalidades por retraso y la clause pénale · Storia