Liquidated damages and the penalty rule in Canada
Canada has not adopted Cavendish Square v Makdessi. A delay liquidated damages clause is enforceable only if the rate is a genuine pre-estimate of loss, and is separately vulnerable to an unconscionability challenge. Where the contract is silent, valid liquidated damages cap the owner's delay claim rather than supplement it.
Disponible solo en inglés Este artículo aún no se ha traducido. Los plazos, el derecho a reclamar y el procedimiento descritos aquí rozan lo jurídico, y una traducción automática sería un riesgo de credibilidad más que una comodidad: por eso se sirve el original inglés íntegro hasta que exista una traducción revisada.
At a glance
- Doctrine
- Canada, common-law provinces
- Excludes Quebec
- CCDC 2 – 2020 contains no delay LD clause
Key facts
- 01
The short answer
A delay liquidated damages clause is enforceable in the common-law provinces if the stipulated rate is a genuine pre-estimate of the loss the owner would suffer from late completion, and if it is not extravagant and unconscionable. Those are two separate limbs, and they are pleaded separately.
- 02
The proposition that catches foreign drafters
Canada has not adopted Cavendish Square Holding BV v Talal El Makdessi, [2015] UKSC 67. The English and Australian "legitimate interest in enforcement" justification for a high rate has no purchase in Canada. Citing it signals unfamiliarity rather than authority.
- 03
Cap or floor
Where the contract is silent, valid liquidated damages cap the owner's delay damages. Words such as "in addition to and without prejudice to any other remedy available" make them non-exclusive. The Canadian default is cap.
- 04
Where the clause lives
CCDC 2 – 2020 carries no delay liquidated damages clause at all. It is inserted by supplementary conditions, usually the owner's own, so the exclusivity question turns entirely on SC drafting that has never been through an industry negotiation.
- 05
The separate killer
Chandos Construction Ltd v Deloitte Restructuring Inc, 2020 SCC 25 a forfeiture clause triggered by insolvency is void under the anti-deprivation rule regardless of whether it is a genuine pre-estimate. A delay-damages mechanism can fail on a ground entirely outside the penalty rule.
- 06
The owner's own delay
Perini Pacific Ltd v Greater Vancouver Sewerage &, Drainage District, (1966), 57 DLR (2d) 307 (BCCA): an owner who has prevented timely completion cannot insist on the delay penalty. The point was not in issue on the further appeal to the Supreme Court. The exposure is loss of the liquidated damages entirely, not a reduced rate.
- 07
The highest-value negative
There is no statutory prohibition on no-damage-for-delay clauses anywhere in Canada federal, provincial or territorial. That is the sharpest contrast with the United States, and it means there is no legislative safety net for a Canadian contractor.
- 08
What the case law does not contain
No Canadian appellate decision 2024–2026 reformulates the LD/penalty test in construction, and no Ontario construction liquidated-damages decision exists for 2018–2026 the Ontario authorities are real-estate deposit, franchise and employment cases.
An English or Australian practitioner arriving on a Canadian job will reach for the argument that a high delay rate is justified by the owner's legitimate interest in timely completion. That argument does not exist in Canadian law. Canada never followed England's 2015 reformulation of the penalty rule, and the older genuine-pre-estimate test is still the first thing a Canadian court asks about a liquidated damages rate.
The starting point in the common-law provinces is unchanged and easy to state. A clause that fixes the sum payable for late completion is enforceable if the sum is a genuine covenanted pre-estimate of the loss the owner would suffer, it is unenforceable as a penalty if it is not. Canada then adds a second, independent gateway, a sum that is extravagant and unconscionable in amount can be struck even where the pre-estimate reasoning is arguable. Neither limb asks whether the owner had a legitimate interest in enforcement, and Cavendish Square Holding BV v Talal El Makdessi1 [2015] UKSC 67 has not been adopted anywhere in Canada. Three independent sources record the non-adoption expressly, and there is no Ontario decision adopting it.
Two structural points frame everything below, and both surprise readers who come to Canada from a JCT, FIDIC or NEC background. First, Quebec is not part of this page: it is a civil-law jurisdiction with no penalty-versus-liquidated-damages characterisation at all, and it is dealt with separately at the end and on the Quebec delay penalties page. Second, the Canadian standard form does not supply the clause. Everything that follows about rates, caps and exclusivity is being applied to text an owner wrote into its own supplementary conditions. The wider Canadian delay material sits at the extension-of-time hub for Canada, and the mechanism as a doctrine (independent of jurisdiction) sits on the neutral extension-of-time pillar.
A legitimate-interest question
The court asks whether the stipulated sum is out of all proportion to the innocent party's legitimate interest in the performance of the primary obligation. A rate exceeding likely financial loss can still be enforceable where a wider commercial interest justifies it. Deterrence is not automatically fatal, and the enquiry looks beyond compensation.
A pre-estimate question, plus unconscionability
The court asks whether the sum is a genuine covenanted pre-estimate of the damage that late completion would cause, and separately whether it is extravagant and unconscionable in amount. There is no legitimate-interest limb to plead. The appellate courts have twice been invited to abolish the penalty rule and twice declined.
What a delay liquidated damages clause does in a Canadian construction contract. And does it cap the owner's claim?
It fixes a sum, normally per calendar day or per week of late completion, and it relieves the owner of proving what the delay actually cost. Where the contract says nothing more, valid liquidated damages cap the owner's delay damages. Words such as "in addition to and without prejudice to any other remedy available" make them non-exclusive, so the owner keeps a claim for general damages on top. The Canadian default is cap.
The exclusivity authorities in the corpus are Raymer v Stratton Woods Holdings Ltd2 (1988), 65 OR (2d) 16 (ONCA) and Passmore Gates Development v Chung3, 1996 OJ No 1932. Both must be handled carefully. Each is single-source in this corpus and both are marked unverified, and Passmore Gates has no neutral citation and no stated level of court. They support a proposition that is uncontroversial and widely repeated. That express "in addition to" wording defeats exclusivity, but they are not authorities to put in front of a judge without pulling them first.
The point that follows is the one that decides the argument in practice. CCDC 2 – 20204 contains no delay liquidated damages clause at all. GC 6.5 of the CCDC 2 – 2020 General Conditions governs delays and extensions of time. It does not impose delay damages on the contractor. Every delay LD obligation on a CCDC 2 – 2020 job is inserted by supplementary conditions. So whether the owner has preserved a right to general damages above the liquidated sum turns entirely on the SC drafting, and it is the supplementary conditions, not the standard form, that must be read first.
In Ontario the position is sharper still. The OAA/OGCA Agreed-to Recommended Supplementary Conditions for CCDC 2 – 20205 contain no supplementary condition amending GC 6.5 and add no liquidated damages clause either. An Ontario delay LD clause is therefore almost always owner-drafted, in the owner's own supplementary conditions, and has never been through an industry negotiation, which is why the clauses vary so widely from project to project and why the exclusivity wording is worth reading word by word.
Ontario public road work is the exception where a published clause does exist: OPSS.MUNI 100 (November 2019) GC 8.02.096 and OPSS.PROV 100 (April 2023 edition) GC 8.077 are dedicated liquidated damages provisions in the Ontario Provincial Standard Specifications, two separate documents on separate revision cycles, not one publication, so each must be cited with its own edition. The operative text of both was not retrieved for this corpus, so the rate mechanism, the trigger and any cap cannot be stated here and must be read off the specification itself.
| Drafting feature | Consequence for the owner | Consequence for the contractor |
|---|---|---|
| Silent on other remedies | Liquidated damages are the cap on delay recovery | Exposure is known and bounded |
| "In addition to and without prejudice to any other remedy available" | Liquidated damages are not exclusive, general damages survive | Exposure is unbounded above the daily rate |
| Rate not a genuine pre-estimate | Clause unenforceable, owner put to proof of actual loss | Owner may still recover proven damages |
| Triggered on insolvency | Void under the anti-deprivation rule, pre-estimate or not | Complete answer to the clause |
Layer: form-default and jurisdictional. The CCDC 2 – 2020 row states what the standard form does and does not contain. An executed contract will carry supplementary conditions that override it, and those must be read. The exclusivity rows rest on single-source, unverified Ontario authority and on secondary sources only, no Canadian judgment was read in original form for this corpus.
Has Canada adopted Cavendish Square v Makdessi? No. And the divergence is over a decade old
No. Canada has not adopted Cavendish Square Holding BV v Talal El Makdessi, [2015] UKSC 67, and no Ontario decision adopts it either. The "legitimate interest" justification English and Australian drafters have used since 2015 to defend a rate above likely loss has no purchase in Canada. It is not a recognised limb, it is not an answer to a penalty challenge, and citing it in a Canadian court signals unfamiliarity rather than authority.
The Canadian appellate courts have been invited to move and have declined, twice. Haas v Viscardi8, 2019 ONCA 133 states that "the common law of penalty clauses remains in force in Ontario". Eleven years earlier Birch v Union of Taxation Employees, Local 700309, 2008 ONCA 809 questioned the doctrine's future and expressly declined to eliminate it. Those two decisions are the reason the pre-estimate test is still the first question, not a historical curiosity.
Nor has the Supreme Court of Canada intervened. It had the opportunity: leave was granted on 11 July 2019 from Capital Steel Inc v Chandos Construction Ltd10, 2019 ABCA 32, and the Court then decided the appeal on the anti-deprivation rule instead, leaving the penalty test where it found it.
The consequence for anyone pricing risk on a Canadian job: the Canadian penalty test has not moved since 2020. NEGATIVE FINDING No Canadian appellate decision from 2024 to 2026 reformulates the LD/penalty test in a construction context.
Ontario readers need one more warning before relying on Ontario material. NEGATIVE FINDING No Ontario construction liquidated damages decision from 2018 to 2026 was located. The Ontario LD authorities are real-estate deposit, franchise and employment cases. An Ontario delay-LD argument is built out of Haas, Peachtree II and Elsley and applied by analogy to a construction rate. That is a thin footing for a large claim, and it is better said out loud in submissions than discovered in reply.
The two-limb Canadian test, and how a delay rate is actually attacked
Canada runs two limbs, and they are pleaded separately. Limb one is the genuine pre-estimate rule: was the stipulated sum a genuine covenanted pre-estimate of the damage late completion would cause, judged by what the parties could reasonably contemplate. Limb two is an unconscionability overlay: is the sum extravagant and unconscionable in amount. An owner defending its delay LDs in Canada must satisfy the pre-estimate limb. The overlay is a second, independent route to relief for the contractor.
CONFLICT The corpus records this as a genuine doctrinal conflict rather than a research failure: the two limbs are applied inconsistently across the Canadian cases, and the balance between them is unsettled. The two-limb description is the safe working statement for 2026, for the reasons in the table below.
| Limb | Authority | What it asks |
|---|---|---|
| 1, genuine pre-estimate | Canadian General Electric Co v Canadian Rubber Co11 (1915), 52 SCR 349 | "A penalty is the payment of a stipulated sum on breach of the contract, irrespective of the damage sustained. The essence of liquidated damages is a genuine covenanted pre-estimate of damage" |
| 1, still in force | Haas v Viscardi, 2019 ONCA 133. Birch v Union of Taxation Employees, Local 70030, 2008 ONCA 809 | Both appellate decisions declined to abolish the penalty rule |
| 2, unconscionability | H F Clarke Ltd v Thermidaire Corp Ltd12 [1976] 1 SCR 319 | Laskin CJ, is the sum "extravagant and unconscionable in amount", assessed against actual damages rather than only at formation |
| 2, the limiting principle | J G Collins Insurance Agencies Ltd v Elsley Estate13 [1978] 2 SCR 916 | Dickson J, striking a penalty clause is "a blatant interference with freedom of contract" and "has no place where there is no oppression" |
| The general test it borrows | Uber Technologies Inc v Heller14 2020 SCC 16 | Inequality of bargaining power plus an improvident bargain |
Layer: jurisdictional. Four of the five rows are Supreme Court of Canada or Ontario Court of Appeal authority. The fifth is the general unconscionability test rather than a construction decision. Every row rests on secondary sources, no Canadian judgment was read in original form for this corpus.
Which of the two limbs governs is contested for a specific reason worth knowing. The Elsley passage (the one owners quote) is obiter, in a restrictive-covenant case, and appellate courts have twice refused to abolish the pre-estimate rule since. So an owner who runs Elsley alone, arguing that there is no oppression and therefore nothing to strike, is arguing from dicta against two later refusals.
The high-water mark for the other side did not become the law either. Peachtree II Associates – Dallas LP v 857486 Ontario Ltd15, reported sub nom 869163 Ontario Ltd v Torrey Springs II Associates Ltd Partnership, (2005) 76 OR (3d) 362 (ONCA). Sharpe JA suggested abandoning the genuine pre-estimate test in favour of an unconscionability analysis, and subsequent courts declined to adopt the suggestion. Cite Peachtree II with that qualification, never as a statement of the current test. CONFLICT Two CanLII docket numbers for the decision circulate and disagree, so no CanLII number should be printed, the year, court and substance are agreed across the sources, and the report citation (2005) 76 OR (3d) 362 (ONCA) is the safe one.
How a rate is attacked in practice. The pre-estimate limb is an evidential exercise directed at the moment of contracting: what the owner could reasonably have expected late completion to cost it: financing, lost revenue, extended consultant and staff costs, holdover or relocation costs. And whether the number in the supplementary conditions bears any relation to that. A single flat daily rate applied across an entire project regardless of which milestone slips, or a rate carried forward unchanged from an earlier and much larger project, is where the argument starts. The unconscionability limb is a different exercise, measured against what actually happened and against the bargaining circumstances, Konialian v Paletta16, 2020 ONSC 3976, a resale clause at a 75% price reduction held unconscionable, gives some sense of the magnitude at which a first-instance court will intervene, though it is not a construction case.
The trap to avoid is the deposit line of cases. Redstone Enterprises Ltd v Simple Technology Inc17, 2017 ONCA 282 holds that forfeiture of a true deposit is allowed unless the clause is "penal or unconscionable", and Aylward v Rebuild Response Group Inc18, 2020 ONCA 62 holds that deposits are forfeitable even where the innocent party suffered no actual damage. Deposits are a distinct doctrinal category, security for performance paid in advance, not a pre-estimate of loss on breach. And that exception does not transfer to a per-diem delay liquidated damages rate. Use the deposit line as background on the unconscionability standard only. An owner deploying Redstone as delay-LD authority is over-reaching, and saying so is usually enough.
One further route exists in Ontario and is genuinely untested. Section 98 of the Courts of Justice Act, RSO 1990, c C.4319 gives the court a statutory power to grant relief against forfeiture. UNVERIFIED Whether s 98 has ever been applied to a delay liquidated damages clause in a construction contract is not resolved by any source located for this corpus. There is no authority either way. That makes it genuinely open, and an available argument for a contractor whose pre-estimate challenge is weak on the numbers but whose facts are sympathetic.
Chandos: a mechanism triggered by insolvency is void whatever the rate
A delay-damages or forfeiture mechanism that is triggered by the contractor's insolvency fails in Canada on a ground entirely separate from the penalty rule. Chandos Construction Ltd v Deloitte Restructuring Inc20, 2020 SCC 25 applied the anti-deprivation rule: a clause forfeiting a percentage of the contract price on insolvency is unenforceable regardless of whether it is a genuine pre-estimate of damage. The pre-estimate question is simply not reached.
That is a materially different way to lose a clause, and it is easy to miss because the drafting that attracts it often looks like ordinary delay protection. Provisions that convert on insolvency. A percentage of the contract price forfeited, retention or holdback converted to the owner's account, a stipulated sum becoming payable on the appointment of a trustee or receiver, are exposed under Chandos 2020 SCC 25 even where the number would comfortably survive a genuine pre-estimate challenge. The enquiry is about the trigger, not the amount.
UNVERIFIED Whether the Supreme Court in Chandos 2020 SCC 25 expressly reserved the penalty question was not read for this corpus. It matters: if the Court reserved it, the two-limb penalty analysis stands untouched and Chandos is a purely parallel ground. If the Court said more, the balance between the pre-estimate limb and the unconscionability overlay could shift. That should be checked in the judgment before either party builds an argument on what Chandos did or did not decide about penalties.
The practical drafting consequence for an owner is straightforward. Keep the insolvency consequences and the delay consequences in separate provisions, and do not make late completion and insolvency alternative triggers of the same forfeiture. A clause that does both invites Chandos to take out the delay remedy along with the insolvency remedy.
The owner's own delay: prevention, and the risk of losing the liquidated damages entirely
An owner that has itself caused critical delay cannot insist on its liquidated damages. Perini Pacific Ltd v Greater Vancouver Sewerage &, Drainage District21, (1966), 57 DLR (2d) 307 (BCCA), is the Canadian anchor: "A building owner is not allowed to insist upon the penalty for delay if, by ordering extra, he has prevented the builder from completing the work by a specified time." The exposure is loss of the liquidated damages altogether, not a reduced rate. ★ Cite it to the Court of Appeal: the liquidated damages counterclaim was dismissed there and was not in issue on the further appeal, [1967] SCR 189.
N.B.C. Mechanical Inc v A H Lundberg Equipment Ltd22, 1999 BCCA 775 applies that rule on construction facts. The owner's $200,000 liquidated damages counterclaim failed because its own requests for extras had caused a significant part of the delay, and the trial judge held that whether the contractor could have finished on time but for those delays was irrelevant. The Court of Appeal dismissed the appeal, but on a deference standard, treating the attribution of delay as "an assessment of the whole of the evidence" and the contractor's own admitted 80 per cent completion at the deadline as "only one factor to be considered". Plead it as a trial finding upheld on appeal, not as an appellate restatement of the principle.
★ The proposition that an owner may enforce liquidated damages from an extended date where a valid extension-of-time mechanism was properly operated does not come from this case. There is no extension-of-time clause in N.B.C. Mechanical at all. The proposition is sound and it is why an EOT mechanism has to be used rather than merely present (an owner sitting on extension applications while levying delay damages is building the contractor's defence), but its authority is the Peak Construction line, not this judgment.
Two things a reader should know before running this argument in Canada. First, notice bites first, and bites harder: Canadian courts enforce contractual notice provisions strictly and in most delay disputes the prevention argument is never reached because the contractor is out on notice, see notice and time bars in Canada. Second, NEGATIVE FINDING no Ontario authority on the prevention principle or time at large was located, so an Ontario contractor running prevention is arguing on British Columbia and English authority and should say so rather than be caught by it. The full analysis, including how time goes at large and what happens after it does, is on the prevention principle and time at large page for Canada.
There is one item that looks like a contradiction and is not, and a careful reader should know why. Perini Pacific is carried both for the prevention principle and for the enforcement of a broad no-damage-for-delay clause. Both are true of the same litigation, because they concern opposite parties' claims.
The owner's liquidated damages counterclaim, $1,000 per day and pleaded at $53,000, was reduced to $8,000 at trial and then dismissed by the Court of Appeal on prevention grounds. It was not in issue before the Supreme Court of Canada, which recorded exactly that. So the prevention holding is the Court of Appeal's, and the Supreme Court neither adopted nor reviewed it.
The contractor's own claim, for increased head-office overhead caused by owner-caused delay, is what reached the Supreme Court, and it failed. Martland J enforced clause 6-04 of the general conditions (the contractor "shall have no claim or right of action against the Corporation for damages, costs, expenses, loss of profits or otherwise howsoever because or by reason of any delay in the fulfilment of the contract"), holding that it barred exactly that loss "even though the respondent had caused such delay."
The practical lesson is sharper than either proposition alone. Prevention defeated the owner's liquidated damages, and an exculpatory clause defeated the contractor's delay costs, in the same case. A contractor that wins on prevention has not thereby won its own prolongation claim: those are separate questions governed by separate clauses.
No-damage-for-delay clauses in Canada, and the Tercon framework
A no-damage-for-delay clause. One barring the contractor from recovering money for delay however caused, is enforceable in Canada if it is clearly drafted. It fails on clarity, not on policy. The governing framework for any exclusion clause is Tercon Contractors Ltd v British Columbia (Transportation and Highways)23, 2010 SCC 4, which asks three questions in sequence, and the Canadian battleground for a no-damage-for-delay clause is the first of them.
The three Tercon 2010 SCC 4 stages are: (1) does the clause apply on its true construction to the circumstances that arose, (2) was the clause unconscionable at the time of formation. And (3) is there an overriding public-policy reason to refuse to enforce an otherwise valid clause. Stage three is a narrow residual category. Stage two is the unconscionability enquiry now anchored in Uber Technologies Inc v Heller, 2020 SCC 16. Stage one is where Canadian no-damage-for-delay clauses are actually won and lost.
The Nova Scotia cases show what failure at stage one looks like. Westcounty Construction v Nova Scotia24 (1985) refused effect to an exculpatory delay clause because the language was "not clear or express enough", and D J Lowe (1980) Ltd v Nova Scotia (Attorney General)25 (1994), CLR (2d) 181 did the same. A decision also reported as (1993) 121 NSR (2d) 361 (SC), a year and a parallel citation that appear in an index listing and were not confirmed against a source in this corpus. Against that, a clause drafted broadly and expressly, language along the lines of "the Contractor shall have no claim or right of action against the Corporation for damages, costs, expenses, loss of profits or otherwise … by reason of any delay", has been enforced. CONFLICT The attribution of that enforcement is unresolved, as set out above, the drafting lesson survives the conflict.
Plas-Tex Canada Ltd v Dow Chemical of Canada Ltd26, 2004 ABCA 309 supplies the contractor's other lever: an exclusion clause cannot be relied on by a party that engaged in unconscionable conduct or deliberate misconduct. That is a high threshold and is not made out by ordinary owner mismanagement.
NEGATIVE FINDING No Alberta decision on a no-damage-for-delay clause was located at all. Plas-Tex, 2004 ABCA 309 is Alberta appellate authority on exclusion clauses generally, not on a delay exclusion. So an Alberta no-damage-for-delay clause is not tested against any Alberta delay authority: it is tested through the Tercon, 2010 SCC 4 framework plus Plas-Tex, with the Nova Scotia clarity cases as persuasive material on stage one and nothing provincial behind them. A submission that asserts an established Alberta position on a delay exclusion is asserting something the sources do not contain, say so, and argue construction. The Alberta cluster is at extension of time in Alberta.
So the contractor's route against a Canadian no-damage-for-delay clause is ambiguity plus prevention, not public policy. Attack the construction of the clause at Tercon stage 1. What delays it actually covers, whether it reaches owner-caused delay, whether it survives the extension-of-time machinery, and run the prevention principle in parallel. Stage 3 is not where this is won.
Is there a Canadian statute prohibiting no-damage-for-delay clauses?
No, nowhere in Canada, at any level. NEGATIVE FINDING There is no statutory prohibition on no-damage-for-delay clauses anywhere in Canada: federal, provincial or territorial. This is the highest-value negative finding in the Canadian delay corpus, and it is the sharpest single contrast with the United States. Every search on the point returned exclusively American material.
The reason the negative is easy to miss is that Canadian construction and lien statutes do contain anti-contracting-out provisions, they protect the lien, trust and prompt-payment entitlements. Those provisions say nothing about delay-damages exculpation. A reader who knows that a provincial statute bars contracting out of the lien regime should not extrapolate that a delay exculpation clause is equally suspect. It is not.
| Canada, common-law provinces | United States | |
|---|---|---|
| Statutory ban on NDFD clauses | None, at any level of government | A substantial and growing list of states voids or limits them by statute |
| What the construction statutes protect | Lien, trust and prompt-payment provisions only | Varies, but includes delay-damages exculpation in the states that legislate |
| Where the contractor's argument runs | Contract construction under Tercon, 2010 SCC 4, plus prevention | Statute first, then contract |
| Effect on risk pricing | The clause means what it says, price it | The clause may be void before it is construed |
Layer: jurisdictional and comparative. The Canadian column is a recorded negative finding across federal, provincial and territorial legislation, the United States column is a general characterisation of a multi-state position, not a statement about any named state. No statutory text was read in original form for this corpus.
In Canada there is no legislative safety net for a contractor. A clearly drafted no-damage-for-delay clause in a Canadian supplementary condition is a real allocation of risk that will be enforced on its terms, and it should be priced at tender rather than argued about later.
The same negative has a second consequence that matters for delay liquidated damages specifically. Because no statute controls the contractor's side of the delay bargain, and no statute controls the owner's side either, there is no statutory cap on a delay LD rate anywhere in Canada, and NEGATIVE FINDING no Canadian province or territory has a statute addressing construction delay claims as such the entire allocation is contractual. The penalty rule and Tercon 2010 SCC 4 are the only controls on it.
Quebec is different: a clause pénale is valid without proof of loss
Nothing on this page governs Quebec. Quebec is a civil-law jurisdiction and it has no penalty-versus-liquidated-damages characterisation at all. A clause pénale is valid, and under art 1623 C.c.Q.27 para 1 the creditor may recover the stipulated sum without proving the amount of the injury. Proof of quantum is removed, proof of liability is not. There is no genuine pre-estimate test to run and no unconscionability limb of the common-law kind to plead.
The remedy is different too, and this is what a common-law practitioner most often gets wrong on a Quebec job. Art 1623 C.c.Q. para 2 allows the court to reduce the stipulated penalty where the creditor has benefited from partial performance of the obligation, or where the clause is abusive. The outcome of a successful challenge in Quebec is therefore usually a smaller number, not no number, where the outcome of a successful penalty challenge in the common-law provinces is that the clause falls entirely and the owner is put to proof of its actual damages.
Two further Quebec points follow, and both defeat instincts carried over the border. "Time at large" does not exist in Quebec, so a defective extension mechanism does not release the contractor from the completion obligation and does not void the penalty. And there is no Quebec doctrine of concurrent delay. The whole civil-law treatment, including the reduction power, the adhesion-contract route and how a delay penalty should be drafted, is on the Quebec delay penalties page.
| Common-law provinces | Quebec | |
|---|---|---|
| Characterisation question | Penalty or genuine pre-estimate | None, the clause pénale is valid |
| Proof of loss | Not required if the clause is valid, required if it falls | Quantum not required, art 1623 C.c.Q. para 1. Liability still is |
| Remedy on a successful challenge | Clause unenforceable in its entirety | Reduction of the stipulated sum, art 1623 C.c.Q. para 2 |
| Effect of a defective EOT mechanism | Time may go at large and the LDs go with it | No "time at large". The penalty is defeated on the merits or reduced |
Layer: jurisdictional and comparative. The Quebec column rests on Code articles verified verbatim for the Quebec cluster. The common-law column rests on secondary sources, with no Canadian judgment read in original form for this corpus. Do not extend a common-law proposition on this page to a Quebec contract.
Sources and authorities
- *Verification, unless noted
No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
- 1Cavendish Square Holding BV v Talal El Makdessi[2015] UKSC 67, United Kingdom Supreme Court
The English reformulation of the penalty rule, replacing the genuine pre-estimate test with an inquiry into whether the sum is out of all proportion to the innocent party's legitimate interest in enforcement. Canada has not adopted it. Three independent sources record the non-adoption expressly, and no Ontario decision adopts it.
- 2Raymer v Stratton Woods Holdings Ltd(1988), 65 OR (2d) 16 (ONCA), Court of Appeal for Ontario
Cited for the exclusivity proposition. That words such as "in addition to and without prejudice to any other remedy available" prevent the liquidated damages operating as the owner's only remedy for delay.
- 3Passmore Gates Development v Chung1996 OJ No 1932, Ontario
Cited alongside Raymer v Stratton Woods Holdings Ltd for the same exclusivity proposition. There is no neutral citation for this decision in the corpus and the level of court is not stated.
- 4CCDC 2 – 2020 Stipulated Price ContractCCDC 2 – 2020, General Conditions, GC 6.5 (Delays)
The current Canadian stipulated-price standard form. It contains no delay liquidated damages clause. GC 6.5 deals with entitlement to an extension of time and, in defined cases, to costs. Any delay liquidated damages obligation is added by supplementary conditions.
- 5OAA/OGCA Agreed-to Recommended Supplementary Conditions for CCDC 2 – 2020OAA/OGCA Agreed-to Recommended Supplementary Conditions, CCDC 2 – 2020
The Ontario industry-agreed supplementary-condition package contains no supplementary condition amending GC 6.5 and adds no delay liquidated damages clause. An Ontario delay LD clause is therefore almost always owner-drafted and has never been through an industry negotiation.
- 6OPSS.MUNI 100 General Conditions of Contract, liquidated damagesOPSS.MUNI 100, November 2019, GC 8.02.09
The municipal Ontario Provincial Standard Specification general conditions contain a dedicated liquidated damages provision at GC 8.02.09. The operative text was not retrieved for this corpus, so the rate mechanism, the trigger and any cap cannot be stated.
- 7OPSS.PROV 100 MTO General Conditions of Contract, liquidated damagesOPSS.PROV 100, April 2023 edition, GC 8.07
The provincial (MTO) Ontario Provincial Standard Specification general conditions contain a dedicated liquidated damages provision at GC 8.07. The operative text was not retrieved for this corpus, so the rate mechanism, the trigger and any cap cannot be stated.
- 8Haas v Viscardi2019 ONCA 133, Court of Appeal for Ontario
"The common law of penalty clauses remains in force in Ontario." The Court of Appeal declined to collapse the penalty rule into unconscionability, and this is the most recent appellate confirmation that the genuine pre-estimate limb survives.
- 9Birch v Union of Taxation Employees, Local 700302008 ONCA 809, Court of Appeal for Ontario
Armstrong JA questioned the future of the penalty doctrine but expressly declined to eliminate it. Together with Haas, 2019 ONCA 133, this is the second appellate refusal to abolish the rule.
- 10Capital Steel Inc v Chandos Construction Ltd2019 ABCA 32, Court of Appeal of Alberta
The decision below. Leave to appeal was granted on 11 July 2019, and the Supreme Court then decided the appeal as Chandos Construction Ltd v Deloitte Restructuring Inc, 2020 SCC 25, on the anti-deprivation rule rather than on the penalty rule.
- 11Canadian General Electric Co v Canadian Rubber Co(1915), 52 SCR 349, Supreme Court of Canada
The root Canadian statement of the distinction: "A penalty is the payment of a stipulated sum on breach of the contract, irrespective of the damage sustained. The essence of liquidated damages is a genuine covenanted pre-estimate of damage."
- 12H F Clarke Ltd v Thermidaire Corp Ltd[1976] 1 SCR 319, Supreme Court of Canada
Laskin CJ, a stipulated sum is a penalty where it is "extravagant and unconscionable in amount", assessed by reference to the actual damages suffered rather than only at the moment of formation. The source of the Canadian unconscionability overlay.
- 13J G Collins Insurance Agencies Ltd v Elsley Estate[1978] 2 SCR 916, Supreme Court of Canada
Dickson J, "The power to strike down a penalty clause is a blatant interference with freedom of contract and is designed for the sole purpose of providing relief against oppression for the party having to pay the stipulated sum. It has no place where there is no oppression." The passage is obiter in a restrictive-covenant case.
- 14Uber Technologies Inc v Heller2020 SCC 16, Supreme Court of Canada
The controlling Canadian unconscionability test, inequality of bargaining power plus an improvident bargain. It is the analytical partner of the penalty rule's second limb.
- 15Peachtree II Associates – Dallas LP v 857486 Ontario Ltd, sub nom 869163 Ontario Ltd v Torrey Springs II Associates Ltd Partnership(2005) 76 OR (3d) 362 (ONCA), Court of Appeal for Ontario
Sharpe JA suggested abandoning the genuine pre-estimate test in favour of an unconscionability analysis, and subsequent courts declined to adopt the suggestion. The high-water mark that did not become the law.
- 16Konialian v Paletta2020 ONSC 3976, Ontario Superior Court of Justice
A resale clause operating at a 75% price reduction was held unconscionable. A first-instance illustration of the magnitude at which the unconscionability limb bites, and not a construction case.
- 17Redstone Enterprises Ltd v Simple Technology Inc2017 ONCA 282, Court of Appeal for Ontario
Deposits are a distinct doctrinal exception: forfeiture of a true deposit is allowed unless the clause is "penal or unconscionable". A deposit case, not a delay liquidated damages case.
- 18Aylward v Rebuild Response Group Inc2020 ONCA 62, Court of Appeal for Ontario
Deposits motivate performance and are forfeitable even where the innocent party suffered no actual damage. That exception is confined to deposits and does not transfer to a per-diem delay liquidated damages rate.
- 19Courts of Justice Act (Ontario), section 98, relief against forfeitureCourts of Justice Act, RSO 1990, c C.43, s 98
The Ontario statutory relief-against-forfeiture power. Whether it has ever been applied to a delay liquidated damages clause in a construction contract is not resolved by any source located for this corpus, there is no authority either way.
- 20Chandos Construction Ltd v Deloitte Restructuring Inc2020 SCC 25, Supreme Court of Canada
The anti-deprivation rule. A clause forfeiting a percentage of the contract price on insolvency is unenforceable regardless of whether it is a genuine pre-estimate of damage. A delay-damages mechanism triggered by insolvency therefore fails on a ground entirely separate from the penalty rule.
- 21Perini Pacific Ltd v Greater Vancouver Sewerage & Drainage District(1966), 57 DLR (2d) 307 (BCCA); SCC appeal [1967] SCR 189, 60 DLR (2d) 385, 1967 CanLII 104
The Canadian prevention anchor. "A building owner is not allowed to insist upon the penalty for delay if, by ordering extra, he has prevented the builder from completing the work by a specified time." That holding is the Court of Appeal's. On the further appeal the Supreme Court of Canada enforced clause 6-04, a broad no-damage-for-delay clause, against the contractor's own claim for delay-related overhead. Both are true of the same litigation: the owner's liquidated damages counterclaim was defeated by prevention in the Court of Appeal and was not in issue before the Supreme Court; the contractor's delay costs were barred by the exculpatory clause.
- 22N.B.C. Mechanical Inc v A H Lundberg Equipment Ltd1999 BCCA 775, Court of Appeal for British Columbia
The owner's liquidated damages counterclaim failed because the owner's own requests for extras caused a significant part of the delay, so the contractor was prevented from completing by the stipulated date. The trial judge held that whether the contractor could have completed on time but for the owner's delays was irrelevant; the Court of Appeal declined to interfere, treating attribution of responsibility for delay as an assessment of the whole of the evidence and the contractor's own incomplete progress as "only one factor to be considered".
- 23Tercon Contractors Ltd v British Columbia (Transportation and Highways)2010 SCC 4, Supreme Court of Canada
The three-stage framework governing any exclusion clause, including a no-damage-for-delay clause, (1) does the clause apply on its true construction, (2) was it unconscionable at the time of formation, (3) is there an overriding public-policy reason to refuse to enforce it.
- 24Westcounty Construction v Nova Scotia(1985), Supreme Court of Nova Scotia
A no-damage-for-delay clause was refused effect because the language was "not clear or express enough" to exclude the contractor's delay claim.
- 25D J Lowe (1980) Ltd v Nova Scotia (Attorney General)(1994), CLR (2d) 181, Supreme Court of Nova Scotia, reported elsewhere as (1993) 121 NSR (2d) 361 (SC)
A no-damage-for-delay clause again refused effect for insufficient clarity. With Westcounty Construction v Nova Scotia (1985), it establishes that Canadian exculpatory delay clauses fail on construction, not on policy.
- 26Plas-Tex Canada Ltd v Dow Chemical of Canada Ltd2004 ABCA 309, Court of Appeal of Alberta
An exclusion clause cannot be relied on by a party that engaged in unconscionable conduct or deliberate misconduct.
- 27Code civil du Québec, art 1623, recovery without proof, and reductionC.c.Q., art 1623
Para 1, a creditor who avails itself of a penal clause is entitled to the stipulated penalty without having to prove the injury suffered. Para 2, the stipulated sum may be reduced where the creditor has benefited from partial performance or where the clause is abusive. The remedy is reduction, not nullity, and there is no genuine pre-estimate test in Quebec.
General information, not legal advice. Reviewed 8 sept 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Modelos de aviso de retraso para AS 4000, FIDIC 2017 y CCDC 2Un aviso de retraso deja constancia a tiempo de un solo hecho: que algo ha retrasado, o…
Each issue links to the full articles in the Storia Library.