- The short answer
- A contractual notice or claim deadline is enforced strictly. Quebec courts require compliance so the owner can address problems in real time and keep cost control, and they dismiss meritorious claims that miss the window.
- The three ways round one
- Waiver (renonciation). Breach of the owner's duty to inform under art 1375 C.c.Q. and Banque de Montréal c. Bail Ltée, and breach of good faith. Nothing else has been shown to work.
- Not a fourth exception
- Opron, 2022 QCCA 98. A claim under an avenant (an amendment, written or verbal) is not a "claim" under the claim procedure at all. That is a characterisation argument about scope, not an exception.
- It is not a limitation period
- Infrabec, 2012 QCCA 2304: a contractual claim deadline « crée un droit » rather than extinguishing one, so art 2884 C.c.Q. is not engaged.
- But no conventional prescription period is valid
- Art 2884 C.c.Q. prohibits any conventional prescription period, shortening as well as lengthening. Ontario's Limitations Act, 2002 permits variation in business agreements. Quebec does not.
- Two clocks, not one
- Art 2925 C.c.Q. gives three years, and art 2116 C.c.Q. defers the start to fin des travaux. A contractor can be comfortably inside prescription and completely out of time under the contract.
- The periods that bite
- MTMD CCDG: 15 days notice of intent, 120 days for the detailed claim: art 8.8 from 2017 onward, art 9.7 in the December 2000 edition. CCDC 2 – 2020 GC 6.5.4: 10 Working Days from the commencement of the delay. The CCDC 2CcQ – 2024 text is not publicly available.
- The untested argument
- Arts 1435 and 1436 C.c.Q. against an external claim procedure in a contract of adhesion, after Hydro-Québec c. Terrassement St-Louis, 2025 QCCA 900. No Quebec construction case applying them to a time bar was located.
A Quebec construction contract can make notice and a claim deadline a condition of the entitlement, and Quebec courts enforce it strictly: more strictly, on the authorities collected here, than common-law Canada. There are exactly three arguments that get round one: waiver, breach of the owner's duty to inform, and breach of good faith.
Three doors, and nothing else. That is the practical shape of a Quebec time-bar problem, and it is worth learning as a shape, because the instinctive common-law moves mostly do not travel. Relief from forfeiture is not the Quebec analysis, actual knowledge and absence of prejudice to the owner are not answers, and "time at large" does not exist in Quebec: no statutory, judicial, doctrinal or professional Quebec source uses the concept. There is also a manoeuvre that is not a door at all but a characterisation argument about whether the claim procedure applies in the first place, and it is taken separately below.
One evidential warning governs everything that follows. No Quebec judgment was read in original text for this article. CanLII, SOQUIJ, CAIJ and RIM were all inaccessible to the research pass behind it. Every article of the Code civil du Québec cited here is primary-verified against LégisQuébec in French and official English and can be relied on. Every case name, neutral citation, holding and quantum rests on secondary law-firm commentary and should be checked against the judgment before it is pleaded.
It is also worth fixing the comparison at the outset. Across the common-law standard forms, notice clauses cluster into three philosophies: no deadline, no forfeiture and no deemed grant, as under JCT, a hard deadline with express forfeiture but a self-healing deeming mechanism, as under NEC4 and FIDIC 2017, and a hard deadline with express forfeiture and no safety valve at all, as under FIDIC 1999, CCDC and AIA. The Quebec forms in common use (CCDC 2 – 2020, CCDC 2CcQ – 2024, the CCDG and the municipal general conditions) sit in the third group, and then add a Civil Code overlay of good faith, adhesion and prescription that has no counterpart in any of the three. For the common-law picture see the neutral treatment of notice and time bars. For the Quebec machinery as a whole, the Quebec extension-of-time hub.
Yes, a Quebec claim-procedure clause bites, and these are the deadlines
Quebec courts require strict compliance with a contractual claim procedure, on the reasoning that the owner must be able to address problems in real time and maintain cost control. The consequence is ordinary and harsh: a meritorious claim filed late is dismissed. Corpex (1977) Inc. v The Queen in right of Canada 1982 CanLII 213 (SCC) is the foundational Supreme Court authority for that approach.
| Regime | Notice of intent | Detailed claim | Clause and edition |
|---|---|---|---|
| MTMD CCDG (provincial roadworks) | 15 days from the onset of the difficulty, by registered letter to the directeur territorial | 120 days from receipt of the estimation finale, the final estimate | art 8.8 from 2017 onward. Art 9.7 in the December 2000 edition |
| CCDG differing site conditions | 15 days maximum, written | – | art 3.6, édition 2024 |
| CCDC 2 – 2020 | 10 Working Days after the commencement of the delay, to the Consultant. One notice suffices for a continuing cause | "timely Notice in Writing of intent to claim", no fixed period | GC 6.5.4. GC 6.6.1 |
| CCDC 2CcQ – 2024 | Unverified. Clause numbers and headings confirmed identical to CCDC 2 – 2020. The operative text is not publicly available | Unverified | GC 6.5 |
| CCA 1 – 2021 subcontract | 7 Working Days, three fewer than the main contract | – | – |
| Ville de Montréal CCAG | – | – | art 4.3.11 Réclamations. Art 5.1.9 Modification apportée aux délais, rév. 2022-12-13 |
Layer, form-default. These are the published clause numbers and periods. Read the executed contract, because supplementary conditions routinely change them. The CCDG and CCDC rows rest on the forms themselves, not on case commentary. The CCDC 2CcQ – 2024 row records a verified gap rather than clause text.
Four points about that table matter more than the numbers. First, the MTMD Cahier des charges et devis généraux should never be cited as "art 8.8" without the edition year. The claim procedure was art 9.7 in the December 2000 edition and 8.8 from 2017 onward, and the Construction et réparation book is reissued annually, currently the 2026 edition. Second, CCDC 2CcQ – 2024 is the highest-priority Quebec gap in this material: the numbers and headings at GC 6.5 are confirmed identical to CCDC 2 – 2020, but the text is not publicly available and whether the Quebec form retains the 10 Working Days notice at GC 6.5.4 is specifically unverified. Do not state the CcQ notice period as fact. Read the executed document. Third, a general contractor on a CCDG head contract and a CCA 1 – 2021 subcontract is running three unaligned clocks: 7 working days down, 15 days up, 120 days for the detailed claim. Fourth, municipal work is on the owner's own general conditions and the addresses change again: on a City of Montreal project the Ville de Montréal Cahier des clauses administratives générales (rév. 2022-12-13) puts claims at art 4.3.11, adjustment of the contract period at art 5.1.9 and penalties at art 5.1.12.
What happens when they are missed is best learned from the cases. Coffrage Alliance ltée c. Procureure générale du Québec 2018 QCCS 3782 is the teaching case: force majeure was established (cyclone Irene and four floods) and the claim was still dismissed for want of a claim to the Minister within 120 days, with $94,000 of penalties upheld. In Construction R.I.C. (2006) inc. c. Procureur général du Québec 2024 QCCS 474 the detailed claim arrived 519 days after reception instead of 120, and the court treated CCDG art 8.8 as a condition precedent, failure being « un désistement de tout droit ». That report is single-source. In C.F.G. Construction inc. c. Construction Bau-Val inc. (C.S., 9 November 2017) the 15-day notice was given but the 120-day claim was missed while the claimant waited for its subcontractor's numbers, and the court held that quantification is not a precondition to notice. A proposition worth having, but one for which no neutral citation was located. And in Construction BLH (1997) inc. c. Carrières Bob-Son inc. 2013 QCCS 2200 a 120-day deadline incorporated by reference from the head contract into the subcontract was enforced: flow-down of a time bar works.
One further example circulates widely and should be handled with care. Cegerco inc. c. Les Équipements J.V.C. inc. et SEBJ (Que CA, 12 January 2018) is reported as rejecting a subcontractor's $1.5 million differing-site-conditions claim in its entirety as out of time under a 5-day written claim requirement and a 3-month detailed claim requirement. No neutral citation for it was located, and the report is single-source. It is included here because the periods are instructive, not because the case can be cited as it stands.
The one structural limit worth naming alongside all of that is art 2878 C.c.Q.: « Cette déchéance ne se présume pas elle résulte d'un texte exprès. » A contractual forfeiture is not a statutory déchéance, so the court will not raise it of its own motion, and a clause that is not explicit about loss of rights should not be construed as producing forfeiture. That is an argument about the clause you are actually facing, and it is worth running before the three doors.
Door 1: waiver, and what it takes to establish it
Waiver (renonciation, the abandonment of a right) defeats a Quebec time bar where the owner's conduct shows an unequivocal intention not to insist on the procedure. It may be tacit: « Cette renonciation peut être implicite, mais elle doit être non équivoque ». It is fact-heavy, it is the door most often pleaded, and it fails more often than contractors expect.
The recorded indicia are conduct-based: approving invoices for extra work without objecting to the procedural default, agreeing to partial payment despite non-compliance, responding to the claim on its merits, including proposing a settlement, without raising the defect, and a consistent practice of non-enforcement. Compagnie d'assurances Travelers du Canada c. Ville de Montréal 2020 QCCS 1414 is the worked example: a claim of $1,040,097.84 was served late, the City said it "would be treated" without declaring it inadmissible, it had processed and paid 45 supplementary work requests that did not strictly comply, and it did not invoke the defect until trial in 2017 despite opportunities in 2013. The court found the City had renounced « au formalisme de la procédure de réclamation ». That account is single-source.
Two qualifications keep the door realistic. In Rochette Excavation inc. c. Zurich Compagnie d'assurance 2024 QCCS 1408 waiver was not established even though the owner never raised the procedural defect before litigation: from which it follows, though the report does not say so in terms, that silence alone is not renunciation. And David S. Laflamme Construction inc. c. Procureur général du Canada 2024 QCCS 4077 records that waiver requires a reiterated attitude evidencing an intention to modify the contract permanently, so that on a long-duration contract the owner may reinstate the procedure on reasonable notice. Both reports are single-source. The practical consequence is that a contractor relying on waiver needs a documented pattern, not an anecdote, and an owner that has been lax should reinstate the procedure in writing rather than assume its rights survive.
Door 2. The obligation de renseignement, and why it has no common-law analogue
The owner's obligation de renseignement (its duty to inform) is the Quebec overlay with no clean common-law equivalent, and it is capable of defeating a contractual time bar. Where the owner concealed or failed to disclose material information, paradigmatically ground conditions, such that the contractor's tender was vitiated, the contractor may claim notwithstanding procedural non-compliance.
Banque de Montréal c. Bail Ltée [1992] 2 R.C.S. 554 is the anchor, and it is itself a construction case. Codified good faith: arts 6, 7 and 1375 C.c.Q., generates a duty with three elements: knowledge, actual or presumed, of the information by the party owing the duty, the determinative nature of that information for the other party, and the impossibility for the other party of informing itself, or its legitimate reliance on the first party.
The duty applies at formation and during performance, it is not defeated by an exculpatory clause, and it can defeat a contractual time bar. That combination has no clean common-law analogue, and it is the single most useful thing on this page for a contractor that has missed a deadline.
Each limb does work. The performance limb is the one most often missed: art 1375 C.c.Q. governs conduct « tant au moment de la naissance de l'obligation qu'à celui de son exécution ou de son extinction », so late design, undisclosed third-party interference and known programme impossibility are all in scope mid-project, not just at tender. The exculpatory-clause point matters because owner's standard conditions routinely include "verify for yourself" and "no reliance" provisions. They do not neutralise the duty. And the time-bar application is not theoretical: Laflamme 2024 QCCS 4077 is reported as holding that ground-conditions information concealed by the owner had vitiated the original bid, justifying an exception to the claim deadline: single-source, though the underlying principle is independently corroborated.
The functional comparison for a US practitioner is the superior-knowledge doctrine, but the Quebec duty is broader, because it rests on a general codified good-faith obligation rather than a procurement-specific rule. For an English or common-law Canadian practitioner there is no comparator at all.
Door 3, bad faith bars the owner from invoking its own claim procedure
Where the owner's own conduct is in bad faith, a Quebec court may bar it from invoking the claim procedure altogether, even where the contractor was in procedural default and even where no waiver is established. The doctrinal home is the extinction limb of art 1375 C.c.Q., which requires good faith at the extinction of an obligation as well as at its birth and performance.
The authority is PG4 Construction Corp. c. Énergir 2024 QCCS 4179, where over $15 million was awarded despite procedural default and the absence of waiver, because the owner's non-cooperative and misleading conduct (encouraging the contractor to implement acceleration measures while promising later resolution) breached the duty of good faith and estopped it from relying on the contractual claim procedure. An appeal was filed on 18 December 2024 and the decision may not survive it. It is single-source, like every Quebec case on this page, and the combination of an unread judgment, a very large award and a pending appeal means it should be presented to a tribunal as a first-instance decision under appeal, never as settled law.
Two boundary markers belong with it. The first is a terminological one, and it is better stated than glossed: the Quebec vocabulary for "you cannot rely on a state of affairs you brought about" is the discretionary fin de non-recevoir (a peremptory exception on the merits that paralyses an otherwise existing right of action) but no Quebec judgment expressly using the words fin de non-recevoir in a construction delay context was located. The doctrine is squarely established in Quebec private law generally and the construction outcomes are functionally identical. The terminological link is an inference, not a line of authority.
The second is that good faith in Quebec is a conduct standard, not a hardship doctrine. It polices how a right is exercised. It does not rewrite the bargain, and it will not convert a hard bargain into a claim. Bad faith on the owner's part must be shown as conduct, in documents, in the same way any other fault is shown.
What the clause is not. An avenant is not a "claim", and the deadline is not a limitation period
Two characterisation questions come before the three escape routes above, and both ask what the clause is rather than whether an exception applies. Does the claim procedure catch this claim at all? Procureur général du Québec c. Opron inc. 2022 QCCA 98 says an avenant (an amendment) is not a "claim". Is the deadline a prescription period? Construction Infrabec inc. c. Paul Savard, Entrepreneur électricien inc. 2012 QCCA 2304 says it is not.
Take Opron first, because it is pleaded first and separately. The Court of Appeal held that CCDG cl 8.8 did not apply to a claim arising from an avenant: an amendment to the contract, written or verbal. That is a characterisation argument about the scope of the clause, not an exception to it, and it is not a fourth door.
The reasoning is worth following because it generalises. The claim procedure is « une exception à la règle selon laquelle, dans le cadre d'un contrat à forfait, l'entrepreneur doit exécuter les travaux à gain ou à perte »: an exception to the forfait principle in art 2109 C.c.Q., under which the lump-sum price does not move, and an exception must be interpreted narrowly. Where the contractor claims payment under an amendment, « il n'y a rien d'exorbitant au droit commun et la clause 8.8 ne s'applique pas ». The procedure exists for the case where the contractor feels aggrieved. On the facts the difficulty « a été réglée lorsque les parties ont conclu l'entente ». On a roughly $8.25 million viaduct reconstruction, a claim of $866,975.38 survived.
The pleading move is: this is not a claim under the claims procedure, it is enforcement of an amendment reached during the works. There is no clean common-law equivalent: variation instruction, agreed variation and estoppel by convention are all narrower. The operational corollary is a documentary one: if the parties agree a way forward during the works, even verbally, write the agreement up the same day, because the value of the Opron route depends entirely on proving the avenant. The report of the case is subject to the same law-firm-commentary caveat as every other Quebec judgment cited here.
Now the second question, and the answer that closes off an argument common lawyers reach for. A Quebec contractual claim deadline is not a prescription period, so the prescription rules do not invalidate it. Infrabec, 2012 QCCA 2304, holds that such a clause « ne crée ni délai de rigueur ni déchéance d'ordre public » and that « les 120 jours ne forment pas un délai de prescription ». The rationale is the key to everything downstream, and it cuts against the contractor.
On a forfait contract the contractor normally bears the risk of the difficulties it encounters. The claims procedure « confère à un entrepreneur la possibilité d'obtenir une réparation à laquelle il n'aurait normalement pas droit ». It therefore creates a right rather than extinguishing one. Because it extinguishes nothing, art 2884 C.c.Q. is not engaged, and the argument that the clause is a void conventional prescription period fails. That holding rests on law-firm commentary. The paragraph numbers circulating for it were not verified and are not given here.
Now the flip side, which surprises common-law practitioners in the opposite direction. Art 2884 C.c.Q. provides that « on ne peut pas convenir d'un délai de prescription autre que celui prévu par la loi », and it prohibits any conventional prescription period, shortening as well as lengthening. A drafter who imports a "no action shall be brought after twelve months" clause from an Ontario precedent is producing something Quebec law will not enforce: Ontario's Limitations Act, 2002 permits variation of limitation periods in business agreements, and Quebec permits none.
That yields a drafting distinction which, on the material reviewed, has never been tested: a clause drafted to bar the claim entitlement survives Infrabec, while a clause drafted to bar the action would be a conventional prescription period and void under art 2884. No case testing it was located. It is a real point, and it is available to both sides, which is why a Quebec claim procedure should be drafted as constitutive of the entitlement rather than as a bar on suit. On the underlying architecture of forfait pricing and demeure, see the Civil Code framework for delay.
Prescription is generous in Quebec, and it is no answer to a time bar
Quebec prescription is long and starts late, and neither fact helps with a missed claim deadline. Art 2925 C.c.Q. gives three years for a personal action, and arts 2110 and 2116 C.c.Q. defer the start of prescription for claims between the parties to the fin des travaux (the end of the work) even for items reserved at acceptance. The two clocks run independently.
The correction matters, because the point is widely misstated. Art 2116 C.c.Q. does not run from réception, and it is not a warranty provision. It is a deferral provision, and its trigger is the objective factual state defined by art 2110 C.c.Q.: the work is executed and fit for the use for which it is intended. Réception (acceptance, with or without reservation) is a juridical act, and it is a different event in law. Nor does prescription run from the delaying event. On a project with a long tail of work, the effective window is substantially longer than a common-law practitioner will assume.
The legal clock
Prescription: three years, deferred
Art 2925 C.c.Q. gives three years for a personal action, and art 2116 C.c.Q. does not start it running until fin des travaux under art 2110 C.c.Q. Both the contractor's prolongation claim and the owner's delay-damages claim are « recours entre les parties » and both start there. Generous, objective, and determined by the court rather than by a certificate.
The contractual clock
The claim procedure, days
The CCDG runs 15 days from the onset of the difficulty and 120 days from the estimation finale. CCDC 2 – 2020 GC 6.5.4 runs 10 Working Days from the commencement of the delay, not from awareness of it. Missing it forfeits the entitlement, and being inside prescription is irrelevant to that.
Layer: jurisdictional, and the two sides rest on different footings. The prescription side is statute, primary-verified from the Code. The contractual side is form text for CCDG and CCDC 2 – 2020. The CCDC 2CcQ – 2024 equivalent is unverified.
State the consequence plainly: a Quebec contractor can be comfortably inside the three-year prescription period and completely out of time under its contract. The converse is rarer but real, a claim notified impeccably under the contract and then left to prescribe. Diarise both clocks separately, from different events, at the start of the job.
The owner's own notice problem, and the deemed-notice drafting that fails
The mirror question is under-discussed: what notice must the owner give before levying delay damages? In Quebec, usually none. Arts 1594 and 1597 C.c.Q. dispense the owner from serving a mise en demeure (a formal notice putting the debtor in default) where the contract stipulates a completion date, because the obligation « ne pouvait être exécutée utilement que dans un certain temps qu'il a laissé s'écouler ».
Art 1597 C.c.Q. goes further, and it is a powerful and under-used owner tool: a debtor is in default by operation of law where it has repeatedly refused or neglected an obligation of successive performance. A construction contract is an obligation à exécution successive, so persistent under-resourcing or repeatedly missed milestones puts a contractor in default automatically, without any notice at all. Where the contract stipulates no completion date, the position reverses: the owner must formally put the contractor in default before claiming delay damages.
There is a counter-current, and it should be raised as a question rather than asserted as a holding. A 2014 Superior Court decision is reported as refusing delay damages to a municipality for want of an adequate mise en demeure notwithstanding a stipulated completion date, on the footing that the notice had to state the owner's intention to claim specific damages. The case name and citation are unverified and could not be located. The proposition therefore cannot be relied on, but the question it raises is real: must an owner warn a contractor that it will levy delay damages, or may they accumulate silently and be deducted at the end? The prudent Quebec answer is to warn, in writing, specifying the intention to claim and the basis for it.
What an owner cannot do is draft around the proof. Art 1598 C.c.Q. provides that the creditor must prove the occurrence of one of the cases of demeure de plein droit « malgré toute déclaration ou stipulation contraire ». A clause deeming the contractor in default, deeming notice to have been given, or reversing the burden of proof is ineffective on that point. Deemed-default and deemed-notice provisions imported from a common-law form do not work in Quebec, and they are one of the first things to strike out of a precedent being adapted for a Quebec project.
The largest unexploited argument, arts 1435 and 1436 after Terrassement St-Louis
The strongest untested attack on a Quebec claim-procedure time bar is that it is an external clause in a contract of adhesion, and therefore null under art 1435 C.c.Q. unless it was expressly brought to the adherent's attention at formation. It is recorded here as the largest unexploited argument identified in the research behind this article, and it must be stated as an available theory, not as law.
Two steps make it available. The first is Hydro-Québec c. Terrassement St-Louis inc. 2025 QCCA 900, in which the Court of Appeal confirmed that a public-body construction contract met the art 1379 C.c.Q. definition of a contract of adhesion, its key terms having been imposed without negotiation, and held the arbitration clause unfair under art 1437 C.c.Q. as an unreasonable obstacle to justice, the analysis turning on proportionality and the economic realities of the parties. Note what the adhesion test is not: it is not a consumer test, and it requires no inequality of bargaining power or lack of sophistication. The second step is structural: on most Quebec projects the claim procedure and the time bar do not live in the contract the parties signed. They live in an external document incorporated by reference: the CCDG, a municipal cahier des charges, an owner's standard general conditions. Art 1435 C.c.Q. nullifies an external clause not expressly brought to the adherent's attention at formation. Art 1436 C.c.Q. addresses illegible or incomprehensible clauses.
The recorded negative finding: no Quebec construction case applying art 1435 or art 1436 to a claim-procedure time bar was located. Nor was any Quebec decision striking down a construction notice or time-bar clause under art 1437 C.c.Q. The theory is squarely available after Terrassement St-Louis. It has not been run to judgment, and it should be pleaded as a novel argument with that acknowledged.
Two things cut against it, and a contractor should price them in. The first is Infrabec, 2012 QCCA 2304, which points the other way: a claim procedure that creates a right which the forfait rule in art 2109 C.c.Q. would otherwise deny is a difficult clause to characterise as abusive. The second is EBC inc. c. Ville de Montréal 2026 QCCS 855, which declined to treat a City of Montreal construction contract as one of adhesion, stressing the distinctive character of public procurement (lowest compliant bidder, no post-award negotiation, all bidders having priced the stated clause) and recording that the contractor had itself negotiated the relevant cap. The two decisions are coherent, because adhesion under art 1379 C.c.Q. is a fact-specific determination turning on whether the essential stipulations could be freely discussed. Evidence that the specific clause was negotiated defeats the argument. The best framing, on the material available, is Terrassement St-Louis-style disproportion (a 10-working-day bar on a complex differing-site-conditions claim in a public adhesion contract) rather than an attack on the notice requirement as such.
Fuentes y jurisprudencia
- Construction Infrabec inc. c. Paul Savard, Entrepreneur électricien inc. 2012 QCCA 2304, Court of Appeal of QuebecA contractual claim deadline is not a prescription period. It « ne crée ni délai de rigueur ni déchéance d'ordre public », and « les 120 jours ne forment pas un délai de prescription ». On a lump-sum contract the claims procedure « confère à un entrepreneur la possibilité d'obtenir une réparation à laquelle il n'aurait normalement pas droit »: it creates a right rather than extinguishing one, so art 2884 C.c.Q. is not engaged.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- Procureur général du Québec c. Opron inc. 2022 QCCA 98, Court of Appeal of QuebecThe CCDG claim procedure is « une exception à la règle selon laquelle, dans le cadre d'un contrat à forfait, l'entrepreneur doit exécuter les travaux à gain ou à perte » and must be interpreted narrowly. Where the contractor claims payment under an amendment, written or verbal, « il n'y a rien d'exorbitant au droit commun et la clause 8.8 ne s'applique pas ». Claim of $866,975.38 survived.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- Banque de Montréal c. Bail Ltée [1992] 2 R.C.S. 554, Supreme Court of CanadaCodified good faith generates an obligation de renseignement with three elements: knowledge, actual or presumed, of the information, the determinative nature of the information for the other party, and the impossibility for that party of informing itself, or its legitimate reliance. The duty applies at formation and during performance and is not defeated by an exculpatory clause.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.
- David S. Laflamme Construction inc. c. Procureur général du Canada 2024 QCCS 4077, Superior Court of QuebecGround-conditions information concealed by the owner had vitiated the original bid, justifying an exception to the contractual claim deadline. Also the source of the nuance on waiver: waiver requires a reiterated attitude evidencing an intention to modify the contract permanently, and on a long-duration contract the owner may reinstate the procedure on reasonable notice.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- PG4 Construction Corp. c. Énergir 2024 QCCS 4179, Superior Court of Quebec, appeal filed 18 December 2024Despite the contractor's procedural default and the absence of waiver, over $15 million was awarded because the owner's non-cooperative and misleading conduct (encouraging acceleration measures while promising later resolution) breached the duty of good faith and barred the owner from invoking the contractual claim procedure.Under appeal, filed 18 December 2024, and the outcome may change. No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- Compagnie d'assurances Travelers du Canada c. Ville de Montréal 2020 QCCS 1414, Superior Court of QuebecTacit waiver established. The City said the late claim of $1,040,097.84 "would be treated" without declaring it inadmissible, had processed and paid 45 supplementary work requests that did not strictly comply, and did not invoke the defect until trial in 2017 despite opportunities in 2013.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- Rochette Excavation inc. c. Zurich Compagnie d'assurance 2024 QCCS 1408, Superior Court of QuebecWaiver was not established even though the owner never raised the procedural defect before litigation.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- Corpex (1977) Inc. v The Queen in right of Canada 1982 CanLII 213 (SCC)The foundational Supreme Court authority for strict enforcement of contractual claim procedures in construction.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. The CanLII identifier is recorded. The parallel [1982] 2 SCR 643 report is unverified. Verify before pleading.Buscar en CanLII →
- Coffrage Alliance ltée c. Procureure générale du Québec 2018 QCCS 3782, Superior Court of QuebecForce majeure was established (cyclone Irene and four floods) and the claim was still dismissed for want of a claim to the Minister within 120 days. $244,493.83 claimed for 38 days lost. $94,000 of penalties upheld.No Quebec judgment was read in original text for this corpus. The citation, holding and figures rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- Construction R.I.C. (2006) inc. c. Procureur général du Québec 2024 QCCS 474, Superior Court of QuebecCCDG art 8.8 operates as a condition precedent: « Si l'avis d'intention ou la réclamation ne sont pas produits dans les délais prescrits, un tel comportement est considéré comme un désistement de tout droit ». The detailed claim came 519 days after reception instead of 120 and was dismissed.Single-source. No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- C.F.G. Construction inc. c. Construction Bau-Val inc. Superior Court of Quebec, 9 November 2017, no neutral citation locatedThe 15-day notice was given but the 120-day detailed claim was missed while the claimant awaited its subcontractor's quantified claim. Rejected: quantification is not a precondition to notice.Single-source, and no neutral citation was obtained. No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.
- Cegerco inc. c. Les Équipements J.V.C. inc. et SEBJ Court of Appeal of Quebec, 12 January 2018, no neutral citation locatedA subcontractor's $1.5 million differing-site-conditions claim was wholly rejected as out of time under a 5-day written claim requirement and a 3-month detailed claim requirement.Single-source, and no neutral citation was located. No Quebec judgment was read in original text for this corpus. The citation, holding and quantum rest on secondary law-firm commentary. Do not cite without first locating the judgment on CanLII or SOQUIJ.
- Construction BLH (1997) inc. c. Carrières Bob-Son inc. 2013 QCCS 2200, Superior Court of QuebecA 120-day claim deadline incorporated by reference from the head contract into the subcontract was enforced. Flow-down of a time bar works.Single-source. No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- Hydro-Québec c. Terrassement St-Louis inc. 2025 QCCA 900, Court of Appeal of QuebecA Hydro-Québec construction contract met the art 1379 C.c.Q. definition of a contract of adhesion, the key terms having been imposed without negotiation, and the arbitration clause was unfair under art 1437 C.c.Q. as an unreasonable obstacle to justice: three arbitrators in Montreal against a $253,128 claim by a regional SME.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- EBC inc. c. Ville de Montréal 2026 QCCS 855, Superior Court of QuebecDeclined to characterise a City of Montreal construction contract as one of adhesion, stressing the distinctive character of public contracts (lowest compliant bidder procurement with no post-award negotiation, all bidders having priced the stated clause) and recording that the contractor had itself negotiated the penalty cap.No Quebec judgment was read in original text for this corpus. The citation and holding rest on secondary law-firm commentary. Verify on CanLII or SOQUIJ before pleading.Buscar en CanLII →
- Art 2878 C.c.Q., forfeiture is not presumed Code civil du Québec, art 2878« Le tribunal ne peut suppléer d'office le moyen résultant de la prescription. Toutefois, le tribunal doit déclarer d'office la déchéance du recours, lorsque celle-ci est prévue par la loi. Cette déchéance ne se présume pas. Elle résulte d'un texte exprès. » A contractual forfeiture is not a statutory déchéance, so the court will not raise it of its own motion, and a clause that is not explicit about loss of rights should not be read as producing forfeiture.LégisQuébec →
- Art 2884 C.c.Q., no conventional prescription period Code civil du Québec, art 2884« On ne peut pas convenir d'un délai de prescription autre que celui prévu par la loi. » The prohibition covers any conventional period, shortening as well as lengthening.LégisQuébec →
- Art 2925 C.c.Q., three-year prescription Code civil du Québec, art 2925« L'action qui tend à faire valoir un droit personnel… se prescrit par trois ans. » A construction claim between contracting parties is a personal action.LégisQuébec →
- Arts 2110 and 2116 C.c.Q., fin des travaux and the deferred start Code civil du Québec, arts 2110 and 2116Art 2110: the client must receive the work at the fin des travaux, which occurs when the work is executed and fit for its intended use. Réception is the juridical act by which the client declares that it accepts, with or without reservation. Art 2116: « La prescription des recours entre les parties ne commence à courir qu'à compter de la fin des travaux, même à l'égard de ceux qui ont fait l'objet de réserves lors de la réception de l'ouvrage. » It is a deferral provision keyed to the objective factual state, not to acceptance.LégisQuébec →
- Arts 6, 7 and 1375 C.c.Q., the good-faith trilogy Code civil du Québec, arts 6, 7 and 1375Art 6 requires civil rights to be exercised in good faith. Art 7 supplies two independent standards: exercise with intent to injure, and exercise in an excessive and unreasonable manner, the second objective and requiring no malice. Art 1375 requires good faith « tant au moment de la naissance de l'obligation qu'à celui de son exécution ou de son extinction ». The extinction limb is the doctrinal home of the argument that an owner cannot in bad faith invoke a time bar.LégisQuébec →
- Arts 1594 and 1597 C.c.Q., default without a mise en demeure Code civil du Québec, arts 1594 and 1597Where the contract stipulates a completion date, arts 1594 and 1597 dispense the creditor from serving a mise en demeure. Art 1597 also puts a debtor in default by operation of law where it has repeatedly refused or neglected an obligation of successive performance: automatically, without notice.LégisQuébec →
- Art 1598 C.c.Q., the burden of proving demeure de plein droit Code civil du Québec, art 1598« Le créancier doit prouver la survenance de l'un des cas où il y a demeure de plein droit, malgré toute déclaration ou stipulation contraire. » A clause deeming default, deeming notice given, or reversing the burden is ineffective on that point.LégisQuébec →
- Arts 1379, 1435, 1436 and 1437 C.c.Q., adhesion and external clauses Code civil du Québec, arts 1379, 1435, 1436 and 1437Art 1379 defines a contract of adhesion as one whose essential stipulations were imposed or drafted by one party and could not be freely discussed. There is no requirement of inequality of bargaining power. Art 1435 makes an external clause null where, at the time of formation, it was not expressly brought to the attention of the adhering party. Art 1436 addresses illegible or incomprehensible clauses, and art 1437 abusive clauses.LégisQuébec →
- Art 2109 C.c.Q., the forfait rule Code civil du Québec, art 2109On a lump-sum contract the client pays the agreed price, and « le prix forfaitaire reste le même, bien que des modifications aient été apportées aux conditions d'exécution initialement prévues, à moins que les parties n'en aient convenu autrement ». The contractor performs at a profit or a loss.LégisQuébec →
- MTMD Cahier des charges et devis généraux: Infrastructures routières, Construction et réparation Art 8.8 Procédure de réclamation, 2017 onward (art 9.7 in the December 2000 edition) · art 3.6, édition 2024 · current edition 2026Notice of intent within 15 days of the onset of the difficulty, by registered letter to the directeur territorial. Detailed claim within 120 days of receipt of the estimation finale. A separate 15-day maximum written notice applies to differing site conditions at art 3.6. The book is reissued annually and the numbering is edition-sensitive. The operative text of arts 7.8, 8.8.1 and 8.8.2 could not be retrieved for this corpus, and the CCDG contains no dedicated extension-of-time clause.No form text was read in original for this corpus. Clause numbering and content rest on independent secondary sources. Check the executed contract and its supplementary conditions.
- CCDC 2 – 2020, GC 6.5 Delays and GC 6.6 Claims for a Change in Contract Price CCDC 2 – 2020, GC 6.5.4 and GC 6.6.1GC 6.5.4: « No extension shall be made for delay unless Notice in Writing of the cause of delay is given to the Consultant not later than 10 Working Days after the commencement of the delay. In the case of a continuing cause of delay only one Notice in Writing shall be necessary. » GC 6.6.1 requires only "timely Notice in Writing of intent to claim" and fixes no period. CCDC 2 – 2020 is not withdrawn and remains current alongside the Quebec form.No form text was read in original for this corpus. Clause numbering and content rest on independent secondary sources. Check the executed contract and its supplementary conditions.CCDC →
- CCDC 2CcQ – 2024, GC 6.5 Delays CCDC 2CcQ – 2024, released 21 May 2024, GC 6.5 · operative text unverifiedThe first CCDC contract designed for the Code civil du Québec. Clause numbers and headings at GC 6.5 are confirmed identical to CCDC 2 – 2020. The operative text is not publicly available, and whether the CcQ form retains the 10 Working Days notice at GC 6.5.4 is specifically unverified. The delay clause of the Quebec form is uncommented in accessible public sources as at August 2026.No form text was read in original for this corpus. Clause numbering and content rest on independent secondary sources. Check the executed contract and its supplementary conditions.CCDC →
- CCA 1 – 2021 subcontract, notice period CCA 1 – 2021 · companion Quebec form CCA 1CcQ – 2024 (ACC 1CcQ – 2024 is its French designation)The subcontract notice period is 7 Working Days, three fewer than the main contract's 10 Working Days.No form text was read in original for this corpus. Clause numbering and content rest on independent secondary sources. Check the executed contract and its supplementary conditions.CCA →
- Ville de Montréal, Cahier des clauses administratives générales CCAG, rév. 2022-12-13, art 4.3.11 Réclamations · art 5.1.9 Modification apportée aux délaisThe municipal general conditions behind most City of Montreal construction disputes. Claims are at art 4.3.11, adjustment of the contract period at art 5.1.9, penalties at art 5.1.12.No form text was read in original for this corpus. Clause numbering and content rest on independent secondary sources. Check the executed contract and its supplementary conditions.
Sobre este material El contenido de la biblioteca es información general sobre la práctica de las reclamaciones de construcción, no asesoramiento jurídico. El derecho a reclamar, los plazos y el procedimiento se rigen por su propio contrato y por el derecho del lugar donde se ejecuta la obra. Revisado el 8 de agosto de 2026 · Informar de una corrección
En este artículo
- Yes, a Quebec claim-procedure clause bites, and these are the deadlines
- Door 1: waiver, and what it takes to establish it
- Door 2. The obligation de renseignement, and why it has no common-law analogue
- Door 3, bad faith bars the owner from invoking its own claim procedure
- What the clause is not. An avenant is not a "claim", and the deadline is not a limitation period
- Prescription is generous in Quebec, and it is no answer to a time bar
- The owner's own notice problem, and the deemed-notice drafting that fails
- The largest unexploited argument, arts 1435 and 1436 after Terrassement St-Louis