Aller au contenu principal

Confidentialité

À propos des témoins

Les témoins essentiels font fonctionner ce site. Les témoins d’analyse facultatifs nous aident à comprendre ce qui fonctionne, activés seulement si vous acceptez.

LIBRARY
Colombie-BritanniqueExtension of timeJurisdiction article

Arbitration, Experts and Forum in British Columbia

British Columbia decides most large delay disputes in confidential arbitration, and the Arbitration Act permits appeal only on a question of law. Because contract interpretation is mixed fact and law, an arbitrator's reading of an extension of time clause is near-unreviewable. That is why BC's reported delay doctrine stopped developing.

Reviewed 8 sept. 202622 min read18 sources
Same topic inBCAB

Disponible en anglais seulement Cet article n'a pas encore été traduit. Les délais, le droit à réclamation et la procédure décrits ici touchent au droit, et une traduction automatique constituerait un risque de crédibilité plutôt qu'une commodité : l'original anglais est donc servi intégralement jusqu'à ce qu'une traduction révisée existe.

At a glance

Colombie-Britannique
Jurisdiction
British Columbia, Canada, common law
Practice area
Construction claims, extension of time and delay
Evidence basis
Supreme Court Civil Rules primary-verified from BC Laws; Arbitration Act from the Bill 7 (2020) third-reading text, not the consolidation; case law secondary only
§ 00

Key facts

  1. 01

    Appeal from an arbitral award

    Question of law only, direct to the Court of Appeal, by consent of all parties or leave of a single justice (Arbitration Act, SBC 2020, c 2, s 59). Section numbers from the Bill 7 third-reading text, re-check

  2. 02

    What that excludes

    Fact, and mixed fact and law. Which delay method applies, whether concurrency exists, whether the critical path was correctly identified none of it is appealable

  3. 03

    Expert duty in arbitration

    Section 35, not s 34. It binds party-appointed experts and requires certification in any report, so a delay report lacking it is non-compliant on its face

  4. 04

    Cap on the number of experts

    None, and there never has been one in a construction action. Alberta caps at one expert per subject matter (r 8.16(1)) and Quebec at one expertise per discipline (art 232 CCP), both rules of general application

  5. 05

    Expert report service

    84 days before trial, and 42 days for a responding report (Supreme Court Civil Rules, Rule 11-6)

  6. 06

    Specialist construction forum

    None. No construction list, no designated construction judges, and no construction practice direction, a searched negative finding

  7. 07

    The distinctive BC procedural tool

    Rule 9-7 summary trial, a final judgment on affidavit evidence, used in delay disputes as a notice and time-bar knockout

  8. 08

    Adjudication as an alternative forum

    None as at 8 September 2026. The Construction Prompt Payment Act is not in force, and on proclamation it will reach only contracts entered into after commencement

British Columbia's reported delay doctrine stopped developing, and this page is about the mechanism that stopped it. Large BC delay disputes go to confidential arbitration, the Arbitration Act allows an appeal only on a question of law, and contractual interpretation is mixed fact and law. Whoever decides your extension of time clause first decides it finally.

Most jurisdiction pages on forum are housekeeping. Where to file, what the deadlines are, which rules apply. In British Columbia the forum question is the substantive question. The province supplied a disproportionate share of the Canadian delay canon and then went quiet, and the reason it went quiet is procedural rather than doctrinal. Delay findings are made in private, they are made in a form that cannot be appealed, and the only appellate activity they generate is a refusal of leave.

That is why this page sits underneath the British Columbia extension of time hub rather than beside it. Everything else in the BC cluster: notice, prevention, concurrency, quantum, is being argued today from judgments of the 1980s and 1990s, and the explanation is here. Read it alongside Alberta's arbitration and forum position, which reaches a similar finality outcome through a different statute and then diverges sharply on expert evidence.

§ 01

Why BC delay doctrine stopped developing

Because the decisions are being made and not reported, and the ones that reach the Court of Appeal cannot be turned into doctrine. NEGATIVE FINDING No BC first-instance or appellate judgment between 2015 and 2026 is squarely a large-project extension of time or delay decision. That is a searched finding, not a gap in the research. The only BC appellate delay activity in the window is CIMIC Morningstar Investments Ltd v Chandos Construction Ltd, 2026 BCCA 21 and it is a leave refusal on an arbitral award, never an appellate statement of doctrine.

Two of the four evidenced causes are mechanical, and both are on this page.

Arbitration capture. Time at large "has featured prominently in private arbitrations", and BC delay claims are "resolved outside of court or in confidential arbitration". The doctrine is being made. It is not being reported, it is not citable, and it does not bind anyone else's arbitrator. A BC delay practitioner is therefore in the unusual position of knowing that a body of current, sophisticated reasoning on their question exists, and having no access to it.

The Sattva lock. Contractual interpretation is a question of mixed fact and law. An appeal from a BC arbitral award lies only on a question of law. So an arbitrator's (or a trial judge's) reading of an extension of time or notice clause is near-insulated from appellate correction. Appeals produce leave refusals, not restatements. The two causes compound: arbitration takes the disputes out of the reports, and the appeal provision stops the survivors from becoming precedent.

The other two causes sit outside this page. Docket composition, the BC construction docket reaching judgment is dominated by residential and lien practice, and commentary migration, with BC firms now writing about Ontario cases and the national concurrency surveys of 2021 and 2025 citing no BC case at all.

§ 02

Section 59, and the narrow door out of a delay award

Section 59 of the Arbitration Act, SBC 2020, c 22 is the whole of the appeal route: "there is no appeal to a court from an arbitral award other than as provided under this section." An appeal lies to the Court of Appeal. Not to the Supreme Court of BC, a change from the 1996 Act, on a question of law, either on the consent of all parties or with leave of a justice of that court. The Act's text used here was obtained from the Bill 7 (2020) third-reading text and not from the consolidation, and every section number on this page should be re-checked against the consolidated Act.

Leave may be granted where the importance of the result to the parties justifies the intervention of the court and determining the point of law may prevent a miscarriage of justice. Or where the point matters to some class or body of persons of which the applicant is a member. Or where it is of general or public importance. The three grounds are disjunctive, but the first is a two-part conjunctive test, and it is the route a private commercial party will normally be on. Leave remains discretionary even where a ground is made out, the section says "may". On a successful appeal the court may confirm, amend or set aside the award, or remit it with the court's opinion.

Feature of s 59Effect on a delay award
Question of law onlyNo appeal on fact, and none on mixed fact and law
Direct to the Court of AppealNo intermediate review in the Supreme Court of BC
Leave from a single justiceConsistent with the disposition in CIMIC
Ground (a) is conjunctiveImportance to the parties is not enough on its own
Leave is discretionaryA satisfied ground does not produce leave
Contracting out is permittedBut only by express words, see below

Layer: jurisdictional. The rows rest on the Arbitration Act text obtained from the Bill 7 (2020) third-reading version. A primary document, but not the consolidation. The characterisation of the CIMIC disposition rests on the secondary tier.

The practical consequence is severe and specific. The determinations that decide a delay arbitration are overwhelmingly questions of mixed fact and law which method of delay analysis to apply, whether concurrency exists on these facts, whether the critical path was properly identified, whether a particular event was on it. None of that is appealable. What is realistically appealable is narrow: the construction of the contract, whether notice was a condition precedent, the legal test for concurrency, and the legal availability of a total cost or modified total cost approach.

And even contract construction is largely closed off, because Sattva Capital Corp v Creston Moly Corp, 2014 SCC 533 makes interpretation mixed fact and law. That is the mechanism by which leave failed in CIMIC: each proposed ground was recharacterised as a factual disagreement rather than an extricable question of law. UNVERIFIED, the outcome is corroborated but that reasoning rests on secondary commentary. Teal Cedar Products Ltd v British Columbia, 2017 SCC 324, itself a BC appeal, is the background unpacking Sattva for appellate review of awards, and is also UNVERIFIED in this corpus.

NEGATIVE FINDING No BC decision expressly applies Sattva to construe an extension of time clause or a construction notice clause. In BC construction work, Sattva operates only through the appellate-review route. That is a strange and revealing state of affairs: the case that most constrains BC delay doctrine has never been applied to a BC delay clause in a reported judgment.

The escape route, such as it is, runs through Escape 101 Ventures Inc v March of Dimes Canada, 2022 BCCA 2945 UNVERIFIED, where a material misapprehension of evidence that is central to the reasoning process was treated as an extricable question of law, with the court entitled to look beyond the award itself to identify it. It is not a construction case (the underlying dispute was an earnout) but it is the doorway a delay-award challenger in BC has to use. On the same secondary footing, the alleged error must be material to the result and the appeal must have arguable merit. An extricable question of law may arise where the arbitrator applies an incorrect legal principle, fails to consider a required element of a legal test, or where evidence has been "forgotten, ignored or misconceived" in a way that materially affects the result.

One reported BC decision comes closer to an EOT question than any other. The Graham-Aecon Joint Venture v Malcolm Drilling Company Inc, 2022 BCCA 3196 arose from a sewage treatment facility where a drill tool became lodged underground and was abandoned, and the arbitration turned on when the claim was discovered under Limitation Act s 8(d). Limited leave was granted on the interpretation of s 8(d), and NEGATIVE FINDING leave was refused on whether a change order process postponed the limitation period, which is precisely the question BC delay practitioners most need answered. The existence of the decision is corroborated, the detail is UNVERIFIED. See BC limitation periods and claim accrual.

A procedural trap sits alongside. Sinclair v T.D.M.C. Holdings Ltd, 2025 BCCA 4027 UNVERIFIED addresses the deadline to cross-appeal an award, and the corpus separately records, from a firm bulletin title only, that the Court of Appeal cannot extend the time to seek leave to appeal an award. Those are very likely the same decision or the same line, and they are not printed here as two authorities. Identify the decision before relying on the proposition either way.

Contracting out of appeals, and whether you should

Section 59(3) expressly permits it: leave may be sought "unless the arbitration agreement expressly states that the parties to the agreement may not appeal any question of law arising out of an arbitral award." Three drafting points follow, and only the first is a reading of the text.

The exclusion must be express and must address appeals on questions of law. A generic "the award shall be final and binding" is unlikely to satisfy an "expressly states" standard. That is an inference from the statutory language, but a strong one. The default is appealable with leave, silence preserves the s 59 route, so a party who wants finality has to say so. And note the asymmetry: the consent route in s 59(2) is not expressed to be subject to subsection (3), so an exclusion clause appears to bar the leave route while leaving the parties free to agree to an appeal after the award. That last point is inference, not record.

The drafting decision on a delay-heavy BC project is narrower than it looks. Excluding appeals buys finality on schedule findings that would very likely be unappealable anyway. What it costs is the narrow contract-construction door. On a project where the extension of time and notice clauses are unusual or contested, that door is worth keeping.

§ 03

Seat, institution, and a default rule that may have disappeared

The Vancouver International Arbitration Centre: VanIAC, formerly BCICAC, renamed to coincide with the new Act, is the designated appointing authority. Section 1 defines that term by reference to s 67, which empowers the Lieutenant Governor in Council to designate an entity by regulation, and VanIAC is the entity designated. The fact of designation is corroborated. The section numbers again come from the Bill 7 third-reading text and should be re-checked. The designating instrument is recorded as the Arbitration Regulation, BC Reg 160/2020, but UNVERIFIED (BC Laws blocked retrieval) so do not cite that regulation number for a specific proposition.

NEGATIVE FINDING No provision was found making VanIAC's Domestic Arbitration Rules apply by default, and the retrieved text of the Act expressly records that it contains no default rules specifying which arbitration rules apply or identifying any particular institution. Two things are routinely conflated here and should not be: VanIAC as appointing authority is statutory and real. VanIAC's Rules as the default procedural rules is not established.

That matters because the predecessor regime worked the other way. Under the former Commercial Arbitration Act / Arbitration Act, RSBC 1996, c 55, the BCICAC Rules applied by default where the parties had not agreed otherwise. The inference (moderate confidence, and it is an inference) is that the 2020 Act abandoned that default, so a BC domestic arbitration clause naming no rules now falls to be conducted under the Act's own procedural provisions plus the tribunal's discretion. If that is right it is a significant and under-appreciated change, and it should be verified against the consolidated Act before anyone drafts around it.

Section 2(5) does not reach BC public construction contracts. Its only government-related limb, s 2(5)(c), excludes arbitrations under a prescribed agreement entered into by the government of British Columbia or of Canada and the government of another jurisdiction in or outside Canada, an intergovernmental carve-out. A construction contract between the Province and a private contractor is not such an agreement. So an arbitration under the dispute ladder at General Conditions 58.00 to 61.00 of the Ministry of Transportation and Infrastructure Major Works General Conditions, version 2026-04-018 falls under the Act, with the s 59 appeal route and the s 35 expert duty intact. See BC public works and infrastructure contracts.

There is, on 8 September 2026, no adjudication alternative to any of this. NEGATIVE FINDING No BC decision on delay in an adjudication or prompt-payment context exists, and none is possible, the Construction Prompt Payment Act is not in force, and when proclaimed it will apply only to contracts entered into after commencement, so essentially every BC contract live today will never be subject to BC adjudication.

§ 04

The expert duty is section 35, not section 34

CORRECTION The corpus previously recorded the Arbitration Act expert certification duty at s 34. It is s 35. The substance is real and important, the section number was wrong, and publishing the wrong one is a defect.

Section 34 is headed "Expert appointed by arbitral tribunal" and is a power: the tribunal may appoint an expert to report, may order a party to deliver information or provide access for inspection, and may order the expert to participate in a hearing at which the parties question the expert. It contains no certification and no duty of independence.

Section 35 is headed "Duty of expert" and is the provision. An expert appointed by one or more parties or by the arbitral tribunal has a duty to assist the arbitral tribunal and is not to be an advocate for any party, and the expert must, in any report the expert prepares, certify that the expert is aware of that duty, has made the report in conformity with it, and will give any testimony in conformity with it. Again from the Bill 7 (2020) third-reading text, to be re-checked against the consolidation, though the corroboration here is unusually good, because s 35 is a near-verbatim transposition of Supreme Court Civil Rule 11-2, obtained separately from BC Laws, matching word for word save "court" for "arbitral tribunal".

Four consequences, and none of them is cosmetic.

  1. It binds party-appointed experts. A delay analyst retained by a contractor for a BC arbitration is under a statutory duty to assist the tribunal and not to be an advocate. Not merely a professional or common law one.
  2. The certification is mandatory and must be in the report. "Must, in any report the expert prepares, certify." A delay report lacking the s 35(2) certification is non-compliant on its face, before anyone reads a word of the analysis.
  3. BC is unusual in this. Most Canadian domestic arbitration statutes do not import a court-style expert independence duty at all. BC has legislated the Rule 11-2 standard into arbitration.
  4. It is a live cross-examination target. A schedule expert who has behaved as an advocate, the classic complaint about an impacted-as-planned or an as-planned-versus-as-built analysis prepared to a brief, faces a statutory attack, not merely a rhetorical one.

The working view is that this makes BC arbitration a comparatively hostile forum for results-driven delay analysis, and that the certification should be treated as a real constraint when expert instructions are scoped rather than as boilerplate to be pasted in at the end. That is judgement, not record.

§ 05

Experts in the BC courts: no cap, and no methodology to apply

In court the duty provision is Rule 11-2 of the Supreme Court Civil Rules, BC Reg 168/20099 the court-side twin of s 35, with the same duty to assist and the same mandatory certification in the report. Service runs on Rule 11-6: an expert report at least 84 days before trial, a responding report at least 42 days.

There is no limit on the number of experts a party may call in the BC Supreme Court in a construction action, and there never has been. Rule 11-8, the only expert-number cap BC has ever had, applied solely to vehicle injury proceedings, was struck down in Crowder v British Columbia (Attorney General), 2019 BCSC 1824, and was repealed by BC Reg 207/2020, s 4. Alberta's r 8.16(1), by contrast, is a rule of general application. This is a sharp divergence from the neighbouring jurisdictions.

JurisdictionCap on expertsSpecialist construction forum
British ColumbiaNone, and never has been in a construction actionNone
AlbertaOne expert per subject matter, r 8.16(1)None
OntarioNoneToronto Construction List
QuebecOne expertise per discipline, art 232 CCPCivil law, addressed separately

*Layer: comparative and jurisdictional. The BC row rests on the primary tier, * the Supreme Court Civil Rules were obtained from BC Laws. The Alberta row is single-source and flagged for verification. The Quebec row is drawn from the corpus's Quebec material and no common law proposition here extends to it.

The practical effect on a delay claim is direct. In BC you may run schedule, quantum and productivity experts separately, and so may your opponent. Under Alberta Rules of Court r 8.16(1)10 recorded in this corpus as single-source and requiring verification, a party must decide whether schedule and quantum are one subject matter or two, and cannot stack a planner, a productivity expert and a forensic accountant on what a judge may characterise as a single subject. Quebec reaches a similar constraint by a different route under art 232 of the Code of Civil Procedure11. On a multi-issue delay claim that difference should drive the forum analysis, and it is a reason a BC-seated dispute is materially easier to present than an Alberta one.

Then the other half of the picture, and it is the more important half.

NEGATIVE FINDING No BC judgment comments on the admissibility, weight or preferred methodology of delay-analysis expert evidence. Not one. Not critical path method, not as-planned versus as-built, not windows, not retrospective time impact analysis. And NEGATIVE FINDING no BC judgment comments on the SCL Protocol or on AACE. On the available survey, none anywhere in Canada does.

So a BC court hearing a delay expert applies White Burgess Langille Inman v Abbott and Haliburton Co Ltd, 2015 SCC 2312 – independence as a threshold admissibility question at the qualification stage, with a low threshold. And the four-part test in R v Mohan, [1994] 2 SCR 913, with no BC methodological authority to apply on top of them. There is no BC judgment telling a court that a windows analysis is preferable to a collapsed as-built, or that either is acceptable. Whichever method your expert has chosen, no BC judge has approved it and no BC judge has rejected it. The neutral delay analysis methods material is doing work here that in Ontario or England would be done by authority.

35The Arbitration Act section carrying the expert duty and the mandatory certification, not s 34
84daysService of an expert report before trial under Rule 11-6, 42 days for a responding report
0BC judgments commenting on the admissibility, weight or methodology of delay-analysis expert evidence
2hoursDiscovery under fast track, against seven ordinary, fatal to any real delay case
§ 06

No construction list, and Rule 9-7 instead

NEGATIVE FINDING British Columbia has no construction list and no designated construction judges. A targeted search returned no court practice direction, no notice to the profession and no Supreme Court page of that kind. Confidence is moderate to high. This is absence of evidence from a targeted search, corroborated by the fact that BC has never operated such a list. Alberta is in the same position. Ontario is not: the Toronto Construction List has dedicated judges and its own practice direction, and England and Wales have the Technology and Construction Court.

Three consequences follow. There is less predictability on technical delay-analysis questions, because there is no accumulated bench expertise on critical-path methodology to draw on, which compounds the absence of any BC methodological authority. Rule 9-7 partly compensates, by letting discrete construction-law questions be resolved efficiently before a chambers judge, and that is arguably part of why BC has felt less need for a specialist list. And it strengthens the case for arbitration, where the parties can appoint a construction-experienced tribunal, subject to the narrow s 59 appeal and the s 35 expert duty, which is where this page began.

Rule 9-7 summary trial, formerly Rule 18A, permits a final judgment on affidavit evidence. It is a true trial, not a summary-judgment screening exercise, and it is the distinctive BC procedural instrument. The evidence permitted is affidavits on personal knowledge, answers to interrogatories, examination for discovery transcripts against the examined party only, admissions and expert reports complying with Rule 11-6(1), affidavits on information and belief are admissible only to argue that the matter should not proceed summarily. The test is that the court may grant judgment if it is able to find the facts necessary to decide the issues and it would not be unjust to decide them on the application, and the court may dismiss the application where the issues are unsuitable or where it will not assist the efficient resolution of the proceeding. UNVERIFIED, the Rule 9-7 evidentiary provisions were not obtained as primary text.

The suitability factors: amount involved, complexity, urgency, prejudice from delay, cost relative to the amount, the course of the proceedings, whether credibility is critical, and whether the application amounts to "litigating in slices", come from a line of BC authority that this corpus flags [UNVERIFIED, citations not confirmed]. The case names came from a single practitioner source and the neutral citations were not verified, so none of them is named here. One negative is worth carrying: Hryniak v Mauldin, 2014 SCC 714 is reported not to have changed BC law, because Rule 9-7(15) is discretionary where the Ontario rule was mandatory, UNVERIFIED, citation not confirmed. Do not import Ontario's post-Hryniak culture-shift reasoning into BC without qualification.

NEGATIVE FINDING No usage statistics for Rule 9-7 in construction disputes were located, and none is invented here. What the sources support is a structural conclusion about which parts of a delay claim are summarily determinable and which are not.

Suited to Rule 9-7Not suited
Whether a notice provision is a condition precedentCausation
Whether notice was givenConcurrency
Interpretation of an extension of time clauseCritical path
Whether a lien was filed in timeCompeting expert opinion
Whether a release bars the claimContested as-built facts over a multi-year chronology

Layer: inferential. The corpus records no BC decision allocating delay issues between these columns. The division is drawn from the structure of Rule 9-7 and the suitability factors, and the underlying authorities are unverified.

The realistic BC use of Rule 9-7 in a delay dispute is as a notice and time-bar knockout tool. An owner arguing that a contractor's delay claim is barred for want of compliant notice will very often bring that as a summary trial, because it is a pure documents-and-construction question. So a BC contractor's notice file is not merely a merits issue. It is what determines whether the claim survives to trial at all.

That is where Rule 9-7 meets the BC notice authorities. Doyle Construction Co v Carling O'Keefe Breweries, 1988 CanLII 2844 (BCCA)15 on notice as a condition precedent, and Northland Kaska Corp v R, 2001 BCSC 929, (2001), 10 CLR (3d) 19016 on owner knowledge of difficulty not being knowledge of an intention to claim, are the authorities an owner will deploy, and both are exactly the kind of documents-and-construction question a chambers judge can decide on affidavits. Both are also, and this is the point the whole cluster keeps making, judgments of 1988 and 2001. See BC notice and time bars.

The mirror-image problem faces a claimant. An application to determine entitlement summarily while quantum proceeds conventionally invites the "litigating in slices" objection directly, which is why Rule 9-7 is in practice a defendant's instrument in delay litigation. And a large delay claim may be unsuitable altogether. A BC practitioner source records a major construction dispute in which summary trial was held unsuitable, the prejudice factors including aging witnesses and increasing difficulty locating project participants. No citation is printed here: the only one in circulation for that decision is incomplete and could not be resolved, and an incomplete citation is of no use to anyone.

§ 07

Fast track, dormancy, and the lien action you parked

Two procedural regimes catch delay claims that are not being actively managed, and both interact with the lien machinery rather than with the merits.

Fast track, Rule 15-1. UNVERIFIED, the rule text was not obtained. Eligibility covers claims for money, real property, personal property or builders liens with a total value of $100,000 or less, or a trial completable within three days. Or by agreement or court order. Entry is by notice of fast track action, the target is filing to trial within eight months, costs are fixed at $8,000, $9,500 or $11,000, and there is no jury. The restriction that matters is that examination for discovery is limited to two hours, against seven ordinarily.

Builders lien claims are expressly named in the eligibility criteria, so a small lien claim with an embedded delay component can be fast-tracked. But two hours of discovery is fatal to any real delay case. You cannot examine a project manager on a multi-year as-built chronology in two hours. The working view is that fast track is unsuitable for a genuine delay claim and should be actively resisted, or exited under the removal provision, where an opponent is using it to suppress the evidentiary record. The converse is also true, and is a real tactic: an owner facing a modest lien claim inflated by a delay allegation has an interest in keeping it there.

Dormancy, Rules 22-7(7) and 22-4(4). The court may dismiss a proceeding for want of prosecution, and where no step has been taken for one year a party must not proceed until proper notice is served and filed. Both rule numbers are primary-verified from BC Laws. NEGATIVE FINDING The leading BC authority for the four-part want-of-prosecution test was not verified and is deliberately not cited here.

This is a live risk in exactly the fact pattern a delay claim produces. An action is commenced to protect the one-year deadline in Builders Lien Act, SBC 1997, c 4517 s 33, which the owner can compress to 21 days on notice, and is then parked while the parties negotiate the delay claim through the contract's own machinery. A year passes without a step. The delay claim is alive on the merits and the proceeding protecting it is not.

§ 08

Choosing the forum on a BC delay project

One further piece of the BC arbitration landscape belongs on the record even though it is not a delay decision. Peace River Hydro Partners v Petrowest Corp, 2022 SCC 4118 arose out of Site C and is the leading Canadian authority on whether a receiver may disclaim an arbitration agreement. On a BC megaproject where a delayed subcontractor chain is heading into insolvency, that is the case that decides whether the delay dispute is arbitrated at all: and it is, tellingly, the only Site C dispute to have produced a reported appellate judgment. NEGATIVE FINDING No reported BC decision on Site C delay entitlement exists, and none on LNG Canada at Kitimat.

Notes

Sources and authorities

18 cited
  1. 1
    CIMIC Morningstar Investments Ltd v Chandos Construction Ltd2026 BCCA 2

    Leave to appeal an arbitral award refused. On a CCDC 2 fixed price contract the arbitrator found that design changes and late approvals materially contributed to delay and made an award of over CAD 6.47 million, reading a ten working day notice requirement in context and relying on the owner's knowledge through email, meetings and schedule updates. Each proposed ground was recharacterised as a factual disagreement rather than an extricable question of law.

    Chercher sur CanLII

  2. 2
    Arbitration ActSBC 2020, c 2

    Section 34 confers a power to appoint a tribunal expert and contains no certification and no duty of independence. Section 35 imposes the duty of an expert appointed by one or more parties or by the tribunal to assist the tribunal and not to be an advocate, and requires the expert to certify in any report that the expert is aware of the duty, has made the report in conformity with it, and will testify in conformity with it. Section 59 permits an appeal to the Court of Appeal on a question of law only, on consent of all parties or with leave of a justice, unless the arbitration agreement expressly excludes appeals on questions of law. Sections 1 and 67 provide for a designated appointing authority. Section 2(5)(c) excludes only arbitrations under a prescribed agreement between the government of British Columbia or of Canada and the government of another jurisdiction. It cannot reach a construction contract with a private contractor.

    Chercher sur CanLII

  3. 3
    Sattva Capital Corp v Creston Moly Corp2014 SCC 53

    Contractual interpretation is a question of mixed fact and law, which places it outside a statutory appeal confined to questions of law absent an extricable legal error.

    Chercher sur CanLII

  4. 4
    Teal Cedar Products Ltd v British Columbia2017 SCC 32

    A British Columbia appeal unpacking Sattva for the purposes of appellate review of arbitral awards.

    Chercher sur CanLII

  5. 5
    Escape 101 Ventures Inc v March of Dimes Canada2022 BCCA 294

    A material misapprehension of evidence that is central to the reasoning process is an extricable question of law for the purposes of an appeal from an arbitral award, and the court may look beyond the award itself to identify it.

    Chercher sur CanLII

  6. 6
    The Graham-Aecon Joint Venture v Malcolm Drilling Company Inc2022 BCCA 319

    A construction arbitration leave decision. On a sewage treatment facility where a drill tool became lodged underground and was abandoned, the arbitration turned on when the claim was discovered under Limitation Act s 8(d). Limited leave was granted on the interpretation of s 8(d) and refused on whether a change order process postponed the limitation period.

    Chercher sur CanLII

  7. 7
    Sinclair v T.D.M.C. Holdings Ltd2025 BCCA 402

    Addresses the deadline to cross-appeal an arbitral award.

    Chercher sur CanLII

  8. 8
    Ministry of Transportation and Infrastructure, Major Works General Conditionsversion 2026-04-01

    General Conditions 58.00 to 61.00 set a four-tier dispute ladder, dispute resolution, formal claim, appeal and arbitration.

  9. 9
    Supreme Court Civil RulesBC Reg 168/2009

    Rule 11-2 imposes on an expert a duty to assist the court and not to be an advocate, with a mandatory certification in the report. Rule 11-6 requires service of an expert report at least 84 days before trial and a responding report at least 42 days before trial. Rule 11-8, which limited the number of experts in vehicle injury proceedings only, was struck down and repealed. Rule 9-7 permits a final judgment on affidavit evidence. Rule 15-1 provides the fast track procedure. Rule 22-7(7) permits dismissal for want of prosecution, and Rule 22-4(4) requires notice before proceeding where no step has been taken for a year.

  10. 10
    Alberta Rules of CourtAlta Reg 124/2010

    Rule 8.16(1) permits a party to call only one expert on any one subject matter unless the Court orders otherwise, and r 8.16(2) allows the Court to direct which of several affiliated corporate parties may call the expert.

  11. 11
    Code of Civil Procedure (Quebec)CQLR c C-25.01

    Article 232 limits the parties to one expertise per discipline absent leave.

  12. 12
    White Burgess Langille Inman v Abbott and Haliburton Co Ltd2015 SCC 23

    Independence, impartiality and the absence of bias are a threshold admissibility question at the qualification stage, not merely a matter of weight. The threshold is low: an expert is excluded only where unable or unwilling to comply, and residual concerns go to weight.

    Chercher sur CanLII

  13. 13
    R v Mohan[1994] 2 SCR 9

    Supplies the four-part admissibility test for expert evidence, relevance, necessity in assisting the trier of fact, absence of an exclusionary rule, and a properly qualified expert.

    Chercher sur CanLII

  14. 14
    Hryniak v Mauldin2014 SCC 7

    The proportionality and culture-shift reasoning on summary disposition. Reported as not having changed BC law, because Rule 9-7(15) is discretionary where the Ontario rule was mandatory.

    Chercher sur CanLII

  15. 15
    Doyle Construction Co v Carling O'Keefe Breweries1988 CanLII 2844 (BCCA)

    Notice may operate as a condition precedent to maintaining a claim.

    Chercher sur CanLII

  16. 16
    Northland Kaska Corp v R2001 BCSC 929, (2001), 10 CLR (3d) 190

    Owner knowledge of difficulty is not knowledge of an intention to claim. Complaints, or grumblings, are not notice.

    Chercher sur CanLII

  17. 17
    Builders Lien ActSBC 1997, c 45

    Section 33 requires an action to be commenced and a certificate of pending litigation registered within one year of filing a claim of lien, compressible by the owner to 21 days on notice.

    Chercher sur CanLII

  18. 18
    Peace River Hydro Partners v Petrowest Corp2022 SCC 41

    The leading Canadian authority on arbitration agreements and insolvency, addressing whether a receiver may disclaim an arbitration agreement. It arose out of the Site C project but is not a delay decision.

    Chercher sur CanLII

General information, not legal advice. Reviewed 8 sept. 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou…

Each issue links to the full articles in the Storia Library.

Arbitrage, experts et forum en Colombie-Britannique · Storia