Prolongation and delay costs
An extension of time and compensation are separate gateways: winning the time does not win the money. Prolongation cost is assessed for the period when the effect of the employer risk event was actually felt, not the overrun at the end of the job: SCL Delay and Disruption Protocol, 2nd Edition (February 2017), Core Principles 20 and 22.
Disponible en anglais seulement Cet article n'a pas encore été traduit. Les délais, le droit à réclamation et la procédure décrits ici touchent au droit, et une traduction automatique constituerait un risque de crédibilité plutôt qu'une commodité : l'original anglais est donc servi intégralement jusqu'à ce qu'une traduction révisée existe.
At a glance
- Quantum
- prolongation cost · delay cost · extended preliminaries · time-related cost
- Neutral core, with FIDIC 2017, JCT 2024, CCDC 2 – 2020 and US federal detail
- SCL Delay and Disruption Protocol, 2nd Edition (February 2017), no 3rd edition exists
Key facts
- 01
The question it answers
Once an extension of time has been granted, what money follows it, for which weeks, and under which clause.
- 02
The governing separation
SCL Delay and Disruption Protocol, 2nd Edition (February 2017), Core Principle 12: entitlement to an extension of time does not automatically lead to entitlement to compensation, and vice versa.
- 03
The error that costs the most
Pricing the tail end of the job instead of the window in which the effect of the employer risk event was felt (Core Principles 20 and 22). Resource levels at the end of a project rarely resemble those during the impact window.
- 04
The cleanest illustration
FIDIC Red Book 2017 (reprinted 2022), Sub-Clause 8.5 confers no payment entitlement of itself. Grounds (c) exceptionally adverse climatic conditions, (d) Unforeseeable shortages and (e) Employer delay give time only under the standard form.
- 05
The 2024 commercial trap
Under JCT Design and Build 2024, epidemic (cl 2.26.7, new in 2024) and change in law (cl 2.26.8, expanded in 2024) are Relevant Events as of right but Relevant Matters only if the option is selected in the Contract Particulars.
- 06
The double-recovery trap
Prolongation is not disruption. Prolongation is time-related cost over a period of critical delay. Disruption is lost productivity and can succeed with zero critical-path delay. Claiming site overhead in both is the commonest quantum error in this area.
- 07
The US federal profit asymmetry
Equitable adjustments under FAR 52.243-4 Changes and FAR 52.236-2 Differing Site Conditions include profit. The FAR 52.242-14 Suspension of Work adjustment excludes it. Same delay, different clause, different recovery.
- 08
The US state wall
No-damage-for-delay clauses are presumptively enforceable in most US jurisdictions. Eight states' anti-NDFD statutes are verified from statutory text. Rhode Island appears in widely circulated lists but no statute was found.
Winning time and winning money are two separate gateways, and most prolongation claims are lost at the second one. The classic error is not a legal one: it is pricing the overrun weeks at the end of the job instead of the weeks in which the effect of the employer risk event was actually felt.
The two are almost never the same weeks, and the difference is usually large. A project delayed by late design information in month seven, when three subcontractors and a tower crane were on site, does not recover that cost by pricing the final two months of a job that has already demobilised down to a snagging team. The claim is arithmetically wrong before anyone reaches the entitlement argument.
The four-element test every extension of time claim has to satisfy gets you through the first gateway. Everything below is the second one.
Does an extension of time come with money?
No, not of itself, under any of the major standard forms. SCL Delay and Disruption Protocol1, 2nd Edition (February 2017), Core Principle 12 states the position squarely: entitlement to an extension of time does not automatically lead to entitlement to compensation, and entitlement to compensation does not automatically carry an extension of time. Time and money are conferred by different clauses, on different lists, against different tests.
FIDIC Red Book 2017 (reprinted 2022) is the cleanest structural illustration. Sub-Clause 8.5 confers no payment entitlement of itself. Of its five grounds, (c) exceptionally adverse climatic conditions, (d) Unforeseeable shortages of personnel or Goods caused by epidemic or governmental action, and (e) delay, impediment or prevention caused by the Employer all give time only under the standard form. Money must come through ground (b), the cross-referencing limb, and then only where the Sub-Clause engaged grants both extension of time and Cost: Sub-Clause 1.9 Errors in the Employer's Requirements, Sub-Clause 2.1 Right of Access, Sub-Clause 4.12 Unforeseeable Physical Conditions. Ground (e) is the one most often assumed to carry money and does not. A contractor delayed by the Employer under an unamended FIDIC form must look to the governing law, in breach or prevention, for its cost.
(A drafting caution. The substance of the Sub-Clause 8.5 grounds (a)–(e) is verified, but the wording circulating in commentary is paraphrase rather than the printed text. Obtain the form before putting quotation marks around any of it.)
JCT does the same thing with different vocabulary: Relevant Events give time, Relevant Matters give money, and the two lists are not identical. CCDC 2 – 2020 is starker still: GC 6.5.3 is a pure time-only regime.
Which events give time but not money?
The neutral events (weather, epidemic, strikes, casualty) give time and no money under almost every standard form. That is the contract's deliberate decision that some risks belong to neither party's fault but should nonetheless not be paid for: the contractor gets relief from liquidated damages, the employer gets a longer programme at no cost. The grid below is form-default only. The enumerated lists are amended on most major projects.
T = time only. T+M = time and money.
| Event | JCT DB 2024 | FIDIC 2017 | NEC4 ECC | AIA A201–2017 | FAR (fixed-price construction) | CCDC 2 – 2020 | AS 4000-1997 |
|---|---|---|---|---|---|---|---|
| Exceptionally adverse weather | T (2.26.10) | T, 8.5(c) | T: cl 60.1(13), measured at a stated place against a 1-in-10-year return | T, §8.3.1 plus the §15.1.6.2 three-part test | T: "unusually severe weather", 52.249-10(b) | T: "abnormally adverse", GC 6.5.3.3 | T |
| Epidemic / pandemic | T as of right (2.26.7, new 2024). Money only if the Relevant Matter option is selected | T, 8.5(d) | Via 60.1(19) prevention event | Via §8.3.1 "other causes beyond the Contractor's control" | T: "epidemics. Quarantine restrictions", 52.249-10(b) | T, GC 6.5.3.4 | T |
| Change in law | T as of right (2.26.8, expanded 2024 to capture government and Construction Leadership Council guidance). Money only if selected | T+M via 8.5(b) → SC 13.6 | T+M, cl 60.1(19) or Option X2 | Not enumerated | T if a sovereign act. Price relief needs an economic price adjustment clause under FAR Subpart 16.2 | Via GC 6.5.3.4 | Change in law |
| Strikes, lockouts, labour disputes | T (2.26.13) | Via 8.5(d) where shortages result | Via 60.1(19) | T, §8.3.1 | T, 52.249-10(b) | T, GC 6.5.3.1 | T |
| Fire, flood, casualty, Specified Perils | T (2.26.11) | Via 8.5(b) → SC 17/19 | Via 60.1(19) | T, §8.3.1 "unavoidable casualties" | T, 52.249-10(b) | T, GC 6.5.3.2 | T |
Form-default positions. Bespoke amendment to these provisions is normal on major projects, and the executed contract governs.
The JCT 2024 opt-in is the commercially significant entry in that table. Under JCT Design and Build 2024, epidemic at cl 2.26.7 and change in law at cl 2.26.8 give time as of right, but money only where the corresponding Relevant Matter option has been selected in the Contract Particulars. The Relevant Matters sit at cl 4.21. (The sub-clause numbers reported for them, epidemic at 4.21.6 and change in law at 4.21.7, come from a secondary briefing and were not read from the contract text. Check the executed contract rather than relying on those numbers.) A contractor that assumes symmetry between the Relevant Events list and the Relevant Matters list has priced the wrong risk, and this is the point most often missed in tender review. There is also no reported English judgment construing the JCT 2024 extension of time provisions or the new epidemic and change-in-law Relevant Events as at August 2026, every 2025–26 English decision in this area was on a 2016 form.
Which weeks does a prolongation claim actually pay for?
The weeks in which the effect of the employer risk event was felt, not the extended period at the end of the job. SCL Delay and Disruption Protocol, 2nd Edition (February 2017), Core Principles 20 and 22 assess prolongation compensation by reference to the actual window of impact, at the cost levels prevailing then. Claiming the tail-end period is a common error and an easily attacked one.
The reason it is easily attacked is factual rather than doctrinal. Site establishment during an impact window in the middle of a project typically carries full supervision, plant on hire, accommodation, security and temporary works. The same establishment during a two-month overrun after practical completion of the main structure is a fraction of that. A claim priced on the tail therefore either understates recovery, if the impact window was resource-heavy, or overstates it grossly, if the impact window was quiet, and it is the overstatement that gets found, because the respondent's quantum expert only has to overlay the resource records on the claimed period.
The corollary is that a prolongation claim is a windowed claim from the outset. It needs the critical-path analysis to identify the weeks, and it needs cost records mapped to those same weeks. Where the contemporaneous cost records are not tied to identified events and periods, the claim degrades into a total-cost claim, and concurrency then defeats it outright.
What prolongation is made of, and why disruption is a different claim
Prolongation is the time-related cost of running the site and the business for longer than the contract priced for. Disruption is loss of productivity. The same work done less efficiently. They are measured against different things and they must be pleaded and priced separately.
| Head | What it is | The usual attack |
|---|---|---|
| Extended preliminaries / site overhead | Time-related site establishment, supervision, plant, accommodation, security, temporary works | Whether the resource was genuinely time-related rather than quantity-related, and whether it was actually on site during the impact window |
| Unabsorbed home-office overhead | Fixed indirect cost that continued to run while the contract could not absorb it | The standby requirement, in US federal practice |
| Finance and interest | The cost of delayed cash flow | Whether it is recoverable as a head at all under the governing law and the contract |
| Escalation | Labour and material price movement across the extended period | Whether the contract allocates escalation risk elsewhere |
| Loss of profit / loss of opportunity | The contribution the resource would have earned elsewhere | Frequently excluded by a consequential-damages waiver |
| Disruption / productivity loss | A different claim. It affects the rate or method of working, not completion, and can succeed with zero critical-path delay | Do not fold it into prolongation |
The measurement bases are not the same. A prolongation claim is measured against the additional time-related cost actually incurred during a period of critical delay: the question is how long, and what it cost to be there. A disruption claim is measured against the productivity that would have been achieved but for the disturbance: the question is how much less work was got out of the same labour and plant hours, and it is answered by comparison: measured mile, benchmark, or, for the cumulative effect of multiple undifferentiated changes, the framework in AACE International RP 130R-233 (15 May 2023).
The double-recovery trap is the single most common quantum error in this area: claiming site overhead as prolongation and then again inside a loss-of-productivity calculation that has already absorbed it. Segregate the two, and say in the submission how you have segregated them. A claim that does not explain the segregation invites the respondent to assume there is none.
Unabsorbed home-office overhead, Eichleay and the FAR profit asymmetry
In US federal construction the money question is decided largely by which clause you route the claim through, and by whether you can prove standby. Both points are checkable against the clause text and both are worth real money on the same set of facts.
The profit asymmetry. Equitable adjustments under FAR 52.243-4 Changes (Jun 2007) and FAR 52.236-2 Differing Site Conditions include profit. The adjustment under FAR 52.242-14 Suspension of Work (Apr 1984) excludes profit. Same delay period, same underlying facts, different clause, different recovery. FAR 52.242-14 also carries its own bars: paragraph (c) bars recovery of costs incurred more than 20 days before the contractor gives written notice, other than for a formal suspension order, and requires the claim to be asserted not later than final payment. Where the facts permit the election, Changes is the stronger vehicle. Note also the practice warning that applies to all of this in 2025–26: under the Revolutionary FAR Overhaul, model deviation text is effective by class deviation, agency by agency, so read the clause as incorporated in the contract, not the FAR on acquisition.gov.
Eichleay is the exclusive method for unabsorbed home-office overhead in US federal contracting where contract performance has begun. Its origin is Eichleay Corp.4, ASBCA No. 5183, 60-2 BCA ¶ 2688, aff'd on recon., 61-1 BCA ¶ 2894 (1960). A citation that is universally repeated but was not independently verified for this corpus, so confirm it before putting it in a pleading. The formula is three steps: the contract's share of overhead is contract billings divided by total company billings for the contract period, multiplied by total home-office overhead for that period, the daily rate is that allocable overhead divided by actual days of contract performance, recovery is the daily rate multiplied by days of compensable government-caused delay.
The standby requirement is the chokepoint. The prerequisites are stated in P.J. Dick, Inc. v Principi5. The reporter cite generally given is 324 F.3d 1364 (Fed. Cir. 2003), and it too was not independently confirmed: as restated in Nicon, Inc. v United States6, 331 F.3d 878 (Fed. Cir. 2003): government-caused delay of uncertain duration, a delay that extended the original performance period or caused additional cost despite timely completion, and a contractor on standby and unable to take on other work. A suspension with a known end date, or one during which the contractor took on replacement work, defeats the claim. Eichleay is not an extended-general-conditions claim, field overhead is proved directly.
The live 2024–25 development is the CBCA's "sole cause" gloss on FAR 52.242-14, which operates as a concurrency defence against both suspension costs and Eichleay recovery. In Lusk Mechanical Contractors, Inc. v GSA7, CBCA 7759 (30 April 2024), a Governor's COVID stay-at-home order was an equal cause of the suspension alongside the Contracting Officer's order, so the Government was not the sole proximate cause and the suspension claim failed. In Quality Trust, Inc. v Department of the Interior8, CBCA 7451 (4 April 2025), suspension and Eichleay recovery were denied because the Government was not the sole cause and the contractor had agreed to the suspensions. Reconsideration was denied in CBCA 7451-R on 18 August 2025. The practical effect is that where any independent cause contributes to the suspension period, 52.242-14 becomes a weak vehicle, which reinforces the election point above.
That gloss is the federal expression of a general rule: concurrency usually costs the contractor the money rather than the time.
No-damage-for-delay clauses: the wall this claim runs into in the United States
No-damage-for-delay clauses are presumptively enforceable at common law in most US jurisdictions, subject to judicially created exceptions and to statutory override in a minority of states. There is no federal common law of NDFD for private work and no uniform state rule. Any US delay article that does not name the state has not scoped itself. The same clause can be fully enforceable in one state and wholly void in another.
Eight state statutes are verified from statutory text:
| State | Citation | Reach | Threshold |
|---|---|---|---|
| California | Cal. Pub. Contract Code § 7102 | Public agency contracts and subcontracts thereunder | Delay that is unreasonable and not within the contemplation of the parties. Any agency-imposed waiver of the section is void |
| Ohio | Ohio Rev. Code § 4113.62(C)(1), (C)(2) (eff. 22 March 2001) | Public and private, primes and subcontracts | Delay proximately resulting from the owner's act or failure to act. No unreasonableness qualifier, the broadest ban in the US |
| Washington | RCW 4.24.360 | Public and private | Unreasonable delay caused by the contractee |
| Virginia | Va. Code § 2.2-4335(A) | Public construction contracts | Unreasonable delay caused by acts or omissions of the public body and due to causes within their control. Blake Constr. Co./Poole & Kent v Upper Occoquan Sewage Auth.9, 587 S.E.2d 711 (Va. 2003) |
| Oregon | ORS 279C.315 | Public improvement contracts | Unreasonable delay caused by the contracting agency |
| Minnesota | Minn. Stat. § 15.411 | Public works of the state and political subdivisions | Delay caused by the contracting public entity. This is § 15.411, not § 337.10, § 337.10 subd. 4 concerns progress payments and the 5% retainage cap |
| Missouri | Mo. Rev. Stat. § 8.962 (formerly § 34.058, transferred 2022) | Public works of the state, counties, cities and political subdivisions, excluding MoDOT | Delay caused by acts or omissions within the control of the contracting public entity. Cite § 8.962 for post-2022 work |
| Kentucky | KRS § 371.405(2)(d) (Kentucky Fairness in Construction Act) | Public and private | Waiver of costs, additional time, damages or equitable adjustment for delays wholly or partly within the control of the contracting entity. The provision is at subsection (2)(d), not (2)(c) |
Jurisdictional. Read from statutory text in eight named states. Blake (Va. 2003), the only decision cited, is a Supreme Court of Virginia authority.
Eight further states (Colorado, Louisiana, North Carolina, Kansas, Nevada, New Jersey, Arizona and Indiana) are reported to have anti-NDFD provisions on the basis of secondary sources only, and the statutory text was not retrieved for any of them. North Carolina's reported provision is narrower than most, reaching only delay caused solely by the owner or its agent, and Arizona's reported provision does not void NDFD clauses outright at all. Do not cite that second group without checking the statute.
Rhode Island is an error. It appears in several widely circulated fifty-state lists, but no Rhode Island statute voiding or limiting NDFD clauses was located. Rhode Island has construction indemnity and anti-lien-waiver statutes, which are different subject matter. Treat "Rhode Island" in any NDFD list as wrong unless a citation is produced.
Three practical points close this out. First, most anti-NDFD statutes reach public work only: Ohio, Washington and Kentucky are the significant exceptions covering private contracts. Second, the statutes almost universally preserve the notice requirement. Killing the NDFD clause does not rescue a claim that was never notified, and the Kentucky Supreme Court has held that claim- preservation and notice requirements survive the Kentucky Fairness in Construction Act and will be strictly enforced. Third, and stated as a recorded negative finding: no new US state statute voiding or limiting no-damage-for-delay clauses was enacted between 2024 and August 2026. The legislative energy in that window moved to retainage and prompt payment, which affects cash flow during a delay dispute but not NDFD enforceability.
Where no statute applies, the exception that most often works is active interference, and a recognised instance of it is the owner's refusal to issue warranted time extensions.
Delay damages run both ways
Prolongation is the contractor's side of a two-sided mechanism. The owner's side is liquidated damages, and what an extension of time actually buys the contractor is relief from them up to the extended date: nothing more, unless a separate money clause is engaged.
Prolongation cost
Time-related cost incurred during the window in which the effect of the employer risk event was felt. Proved, not stipulated: actual cost, mapped to identified events and periods, with employer-caused and contractor-caused cost separated (SCL Protocol 2nd Ed (Feb 2017), Core Principles 14, 20 and 22). Frequently cut back by a consequential-damages waiver: under AIA A201–2017 §15.1.7 the mutual waiver reaches the contractor's office expenses, personnel compensation, loss of financing, business, reputation and profit, except anticipated profit arising directly from the Work.
Liquidated damages
A stipulated daily or weekly rate running from a fixed date. Not proved. That is the point of the clause, subject to the penalty test in the governing law. Under an unamended AIA A201–2017 the same §15.1.7 waiver expressly preserves liquidated damages, which makes them the owner's only realistic delay remedy. In US federal work, FAR 52.211-13 contemplates equitable adjustment of liquidated damages under revised schedules, but Sauer Inc. v Danzig10, 224 F.3d 1340, 1351 (Fed. Cir. 2000) puts the burden of proving the extent of the excusable delay on the contractor: prove nothing, remit nothing.
(The AIA A201–2017 §15.1.7 section number and the substance of the waiver and the liquidated-damages carve-out are verified. The exact 2017 wording was not confirmed verbatim. Describe it. Do not quote it.)
The asymmetry is worth naming. In a minority but significant group of US states applying the non-apportionment rule, an owner responsible for any portion of the delay under a contract with no apportionment clause loses the entire liquidated damages entitlement rather than a pro-rata share, Biemann & Rowell Co. v Donohoe Cos.11, 556 S.E.2d 1 (N.C. Ct. App. 2001). In those states a contractor's most valuable defensive move is not attacking the rate as a penalty. It is proving one day of owner-caused critical delay. AIA A201–2017 contains no apportionment provision.
Price the weeks in which the effect was felt
The instruction is short and routinely ignored: identify the weeks in which the effect of the employer risk event was actually felt, price those weeks at the resource levels that prevailed then, and keep the prolongation claim on its own footing.
That last point deserves its own sentence, because it is where otherwise sound claims get discounted for double counting. Where a variation arising from the same event has been valued with an overhead and profit allowance built into the rates: AIA A201–2017 §7.3.4 uses a closed cost list with a reasonable allowance for overhead and profit, and CCDC 2 – 2020 GC 6.3 carries a 10% allowance where not otherwise agreed, then recovering the same time-related site overhead again as prolongation for the same period is double recovery. Say which cost sits in the variation valuation and which sits in the prolongation claim, and say it in the submission rather than under cross-examination.
Sources and authorities
- 1Society of Construction Law, Delay and Disruption Protocol, 2nd Edition (February 2017)2nd Edition (February 2017), Society of Construction Law
Core Principle 12 keeps time and money as separate gateways: entitlement to an extension of time does not automatically lead to entitlement to compensation, and vice versa. Core Principles 20 and 22 assess prolongation compensation by reference to the window in which the effect of the employer risk event was felt, at the cost levels prevailing then, not the overrun at the end of the job. Core Principle 14 makes recovery turn on separating employer-caused from contractor-caused cost.
- 2Blinderman Construction Co. v United States695 F.2d 552 (Fed. Cir. 1982), United States Court of Appeals for the Federal Circuit
Where both parties contribute to a delay, neither recovers unless the proof contains "a clear apportionment of the delay and the expense attributable to each party" (at 560). A rule of proof, which is why the cost records have to be built during the works.
- 3AACE International Recommended Practice No. 130R-23, Demonstrating Entitlement to Cumulative Impact Claims in Construction15 May 2023, AACE International
The framework for the cumulative effect of multiple undifferentiated changes. The disruption-side measurement problem that prolongation pricing must be kept separate from.
- 4Eichleay Corp.ASBCA No. 5183, 60-2 BCA ¶ 2688, aff'd on recon., 61-1 BCA ¶ 2894 (1960), Armed Services Board of Contract Appeals
The origin of the formula that is the exclusive method for unabsorbed home-office overhead in US federal contracting where contract performance has begun: the contract's share of overhead, converted to a daily rate over actual days of performance, multiplied by days of compensable government-caused delay.
- 5P.J. Dick, Inc. v Principi324 F.3d 1364 (Fed. Cir. 2003), United States Court of Appeals for the Federal Circuit
States the Eichleay prerequisites: government-caused delay of uncertain duration, a delay that extended the original performance period or caused additional cost despite timely completion, and a contractor on standby and unable to take on other work.
- 6Nicon, Inc. v United States331 F.3d 878 (Fed. Cir. 2003), United States Court of Appeals for the Federal Circuit
Restates the standby prerequisites. A suspension with a known end date, or one during which the contractor took on replacement work, defeats the claim.
- 7Lusk Mechanical Contractors, Inc. v GSACBCA 7759 (30 April 2024), Civilian Board of Contract Appeals
A Governor's COVID stay-at-home order was an equal cause of the suspension alongside the Contracting Officer's order, so the Government was not the sole proximate cause and the suspension claim under FAR 52.242-14 failed.
- 8Quality Trust, Inc. v Department of the InteriorCBCA 7451 (4 April 2025), Civilian Board of Contract Appeals · reconsideration denied, CBCA 7451-R (18 August 2025)
Suspension and Eichleay recovery denied because the Government was not the sole cause and the contractor had agreed to the suspensions. With Lusk, this is the "sole cause" gloss that makes 52.242-14 a weak vehicle wherever any independent cause contributes. Reconsideration was denied in CBCA 7451-R on 18 August 2025, so the decision stands.
- 9Blake Constr. Co./Poole & Kent v Upper Occoquan Sewage Auth.587 S.E.2d 711 (Va. 2003), Supreme Court of Virginia
The Virginia authority on Va. Code § 2.2-4335(A), which voids no-damage-for-delay clauses for unreasonable delay caused by acts or omissions of the public body due to causes within its control.
- 10Sauer Inc. v Danzig224 F.3d 1340 (Fed. Cir. 2000), United States Court of Appeals for the Federal Circuit
The contractor carries the burden of proving the extent of the excusable delay for remission of liquidated damages (at 1351). Prove nothing, remit nothing, which is why FAR 52.211-13 equitable adjustment of liquidated damages is not self-executing.
- 11Biemann & Rowell Co. v Donohoe Cos.556 S.E.2d 1 (N.C. Ct. App. 2001), North Carolina Court of Appeals
The non-apportionment rule: an owner responsible for any portion of the delay under a contract with no apportionment clause loses the entire liquidated damages entitlement rather than a pro-rata share.
General information, not legal advice. Reviewed 7 août 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou…
Each issue links to the full articles in the Storia Library.