Aller au contenu principal

Confidentialité

À propos des témoins

Les témoins essentiels font fonctionner ce site. Les témoins d’analyse facultatifs nous aident à comprendre ce qui fonctionne, activés seulement si vous acceptez.

LIBRARY
General practiceExtension of timePractice article

Notice and time bars

A notice clause is a time bar where the contract makes the extension of time conditional on serving notice within a stated period. Under FIDIC 2017 Sub-Clause 20.2.1 and NEC4 clause 61.3 failure forfeits entitlement outright. Under JCT 2024 it generally does not. The deemed-acceptance safety valve, not the length of the period, is what really separates the forms.

Reviewed 13 oct. 202624 min read18 sources

Disponible en anglais seulement Cet article n'a pas encore été traduit. Les délais, le droit à réclamation et la procédure décrits ici touchent au droit, et une traduction automatique constituerait un risque de crédibilité plutôt qu'une commodité : l'original anglais est donc servi intégralement jusqu'à ce qu'une traduction révisée existe.

At a glance

General practice
Class
Entitlement element
Also called
condition precedent · claim notice · notice-based time bar
Scope
Comparative: JCT, NEC4, FIDIC, AIA, CCDC, FAR, AS 4000
§ 00

Key facts

  1. 01

    The question it answers

    Whether missing the notice deadline forfeits the extension of time entirely, or only exposes the contractor to a reduced assessment.

  2. 02

    The legal test

    Whether, on its true construction, the entitlement is made conditional on the notice. Disclosure and Barring Service v Tata Consultancy Services Ltd [2025] EWCA Civ 380 confirms the words “condition precedent” are not required, and a precise deadline is not essential.

  3. 03

    The three designs

    JCT 2024: no deadline, no forfeiture, no deemed grant. NEC4 and FIDIC 2017: hard deadline, express forfeiture, self-healing on assessor silence. FIDIC 1999, CCDC 2 – 2020 and AIA A201–2017: hard deadline, express forfeiture, no safety valve.

  4. 04

    The earliest-running trigger

    CCDC 2 – 2020 GC 6.5.4 runs 10 Working Days from the commencement of the delay, not from awareness. A contractor can be barred before it knew there was anything to notify.

  5. 05

    The most generous trigger

    AIA A201–2017 §15.1.3.1: 21 days from occurrence or from when the claimant first recognises the condition, whichever is later.

  6. 06

    Where it bites hardest

    Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC [2022] DIFC CA 016: the contractor lost its extension of time despite the employer having caused 306 of 325 days of delay (amended FIDIC 1999 Red Book, Sub-Clause 20.1).

  7. 07

    The live development

    Section 13A of the Building and Construction Industry Security of Payment Act 2002 (Vic), commenced 15 April 2026 and retrospective to all contracts, lets a court, arbitrator, expert determiner or adjudicator declare an EOT time bar unfair and of no effect. No case law anywhere yet.

  8. 08

    The commonest failure mode

    Waiting for the commercial negotiation to settle before filing the time notice. The notice is the cheapest of the four entitlement elements to get right and, across the decisions gathered in this corpus, the most common way entitlement is lost.

Across the decisions gathered in this corpus, notice is the element that most often kills a sound extension of time claim. And the standard forms do not merely differ in how many days they give you, they embody three incompatible philosophies about what happens when the deadline passes.

The framing question is always the same: is the notice provision a condition precedent, so that non-compliance forfeits the entitlement outright, or is it merely procedural, so that non-compliance sounds in something less than forfeiture? Nothing else in extension of time practice turns a meritorious claim into a dead one so quickly. It is the third of the four elements of an extension of time claim, and by a distance the cheapest to get right.

What follows is the mechanism, the comparison across the seven form families in common use, and the two places where the answer is currently moving: Australian security of payment statutes, and the deemed-acceptance provisions that most commentary overlooks.

§ 01

Is the notice clause a condition precedent, or only procedure?

A notice clause bars a claim only if, on its true construction, the entitlement is made conditional on the notice. That is the whole test in English law. The current leading statement is Disclosure and Barring Service v Tata Consultancy Services Ltd1 [2025] EWCA Civ 380 (Coulson, Lewison and Snowden LJJ, 4 April 2025), and it is materially more permissive than the formulation practitioners grew up with.

Coulson LJ's five factors:

  1. It depends on "the precise words used and their contractual context".
  2. There must be something making the relief conditional on the requirement.
  3. Clear language is normally needed, but the label "condition precedent" is not required.
  4. The word "shall" is usually necessary but not sufficient.
  5. A precise time limit is not essential: the examples given are "timely" and "within a reasonable time".

Point 5 is the development. It removes the argument, commonly pleaded until 2025, that a notice clause without a hard deadline cannot be a condition precedent. Applying it, Coulson LJ held that "A clear requirement to provide the NCR promptly was sufficient for the requirement to be a condition precedent" (at [50]), there being "no difference between 'timely' and 'promptly' for these purposes" (at [51]). Note also which way it ran in DBS v TCS: the clause bound the employer, which never served a Non-conformance Report and recovered nothing in Delay Payments. The doctrine is not one-directional.

Two older English authorities still do real work. Steria Ltd v Sigma Wireless Communications Ltd2 [2007] EWHC 3454 (TCC) held that "provided that" plus a clear temporal requirement creates a condition precedent without the magic words and without an express statement of consequence: and, separately, that the notice "must emanate from Steria" (at [82]), so a minute prepared by the other side's representative would not by itself be valid notice. Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2)3 [2007] EWHC 447 (TCC) supplies the standard judicial answer to the unfairness objection: notice provisions "serve a valuable purpose": investigation while the facts are fresh, and the opportunity to withdraw the instruction.

The original formulation, from Bremer Handelsgesellschaft mbH v Vanden Avenne-Izegem PVBA4 [1978] 2 Lloyd's Rep 109 (HL), required the clause to state a precise time and to make plain that failure forfeits the entitlement. DBS v TCS still calls it "the leading case" (at [13]) and builds its second factor on it, but treat the precise-time element as the safe drafting target, not as the threshold a clause must clear to bite.

The English position under JCT 2024 and NEC4 is set out in notice and time bars in England and Wales.

§ 02

The three philosophies the standard forms embody

Standard forms are not merely different in the length of the notice period. They embody three incompatible designs. JCT 2024 has no deadline, no forfeiture and no deemed grant, with discretion sitting with the assessor throughout. NEC4 and FIDIC 2017 have a hard deadline and express forfeiture, but also a self-healing mechanism. FIDIC 1999, CCDC 2 – 2020 and AIA A201–2017 have the deadline and the forfeiture with no safety valve at all, and those are the forms on which claims most often die procedurally. Every table in this article states form-default positions: bespoke amendment to notice provisions is normal on major projects, and the executed contract governs.

Form and editionTriggerPeriodCondition precedent?Consequence stated in the clause?
JCT DB 2024, cl 2.24.1"reasonably apparent" that progress is or is likely to be delayed"forthwith", no fixed periodGenerally noNo
JCT SBC 2024, cl 2.27SameSameGenerally noNo
NEC4 ECC, cl 61.3Contractor becomes aware of the event8 weeksGenerally yesYes. The Prices, the Completion Date and Key Dates are not changed, except for events arising from the PM or Supervisor giving an instruction or notification, issuing a certificate or changing an earlier decision
FIDIC 2017, SC 20.2.1Awareness, or when the Party should have become aware28 daysYesYes: no additional payment, Time for Completion not extended, other Party discharged from liability
FIDIC 1999, SC 20.1Same28 daysYesYes, and with no Engineer duty to challenge, so a late notice simply killed the claim
AIA A201–2017, §15.1.3.1Occurrence of the event, or when the claimant first recognises the condition, whichever is later21 daysContractual barYes by its terms. §15.1.3.2 removes the limit for conditions first arising after the correction period
FAR 52.249-10(b)(1)Causes of delay10 days, extendable by the Contracting OfficerAdministrativeThe CO ascertains the facts and extends
CCDC 2 – 2020, GC 6.5.4Commencement of the delay, not awareness10 Working DaysYes in Canadian practiceYes, "No extension shall be made for delay unless Notice in Writing … is given"
AS 4000-1997 / AS 4902-2000, cl 34.2 / 34.3Delay notice "promptly". EOT claim from when the Contractor should reasonably have become aware28 calendar days for the EOT claimYes, subject to statuteYes, subject to the Superintendent's unilateral power
AS 4000:2025Delay notice "as soon as reasonably practicable"Not verified, see belowYes, subject to statuteSame

Form-default clause machinery. The condition-precedent column is the corpus's reading of how each form is treated in practice. Bespoke amendment is normal, and the executed contract governs.

Two honesty notes on that table. First, AS 4000:2025 is paywalled and was not read for this corpus. The 2025 edition softens the delay-notice trigger from "promptly" to "as soon as reasonably practicable", but the EOT claim period under the 2025 edition was not verified, and the clause numbering in the 2025 edition is itself disputed between reputable secondary sources. The 28-day figure in the row above belongs to the 1997 edition. Do not carry it into a 2025-form analysis without checking the standard. Second, these are form-default positions only. Bespoke amendment is the norm on major projects, and employer amendments routinely convert a non-condition-precedent notice into a condition precedent, most commonly by bolting a fixed period and words of forfeiture onto JCT DB cl 2.24 or SBC cl 2.27. After DBS v TCS such a bespoke clause will bite even without the hard deadline. Never analyse a JCT notice question from the printed form.

§ 03

Why deemed acceptance matters more than the length of the period

The differentiator between the forms is not 21 days versus 28 versus 8 weeks. It is whether the clause protects the claimant against an inattentive assessor. Under NEC4 clause 61.4, if the Project Manager does not reply to a compensation event notification within one week, the Contractor may notify that failure, and a further two weeks' silence means the notification is treated as accepted. FIDIC 2017 Sub-Clause 20.2.2 requires the Engineer to say, with reasons and within 14 days, that it considers a Notice of Claim late, failing which the Notice is deemed valid. Neither mechanism exists in FIDIC 1999, in JCT 2024, in CCDC 2 – 2020 or in AIA A201–2017.

Form and editionDetailed claim deadlineAssessor's deadlineDeemed outcome on assessor's silence
JCT DB 2024Particulars with the notice where practicable (2.24.2). Employer may request further information within 14 days (2.24.4)8 weeks, reduced from 12 in the 2016 edition. Post-practical-completion review 12 weeksNone. There is no deemed grant
JCT SBC 2024Further particulars requested within 14 days8 weeks, post-practical-completion review 12 weeks, sub-contract assessment 10 weeks, down from 16None
NEC4 ECCQuotation within 3 weeks (62.3)Project Manager reply 2 weeksYes, twice over. Cl 61.4: after 1 week's PM silence the Contractor notifies the failure, and a further 2 weeks' silence means the notification is accepted. Cl 62.6: quotation deemed accepted, but only after the Contractor notifies the PM's failure
FIDIC 2017Fully detailed Claim 84 days from awareness (20.2.4), including the statement of contractual and/or legal basisEngineer's determination under SC 3.7, default 42 days for agreementYes, two ways. 20.2.2, Engineer silence for 14 days deems the Notice of Claim valid. 3.7: failure to determine is a deemed rejection, referable to the DAAB
FIDIC 1999Fully detailed claim 42 daysEngineer response 42 daysNone
AIA A201–2017§15.1.6.1, Claim to include an estimate of cost and of the probable effect of delay. One Claim suffices for a continuing delay. The section number and heading are verified. The content usually reported for it is A201–2007 §15.1.5.1 wording carried forward, and was not read from the 2017 text, check the executed contractInitial Decision Maker process under Article 15Not a deemed grant
CCDC 2 – 2020One Notice suffices for a continuing causeConsultant "may recommend" a reasonable timeNo deemed grant, though GC 6.5.3's guarantee that an extension "shall not be less than the time lost" partially substitutes
AS 4000 / AS 4902Claim must evidence the facts of causation and the extent of delay (34.3)Superintendent 28 daysYes, deemed direction for the full EOT claimed if the Superintendent fails to assess in time. Sources in this corpus disagree whether the deeming rule sits at cl 34.4 or 34.5, so the sub-clause is not asserted here

Form-default. Deadlines and deeming mechanisms are read off the published forms. Bespoke amendment is normal on major projects, and the executed contract governs.

The practical consequence: on a FIDIC 2017 or NEC4 project, an Engineer or Project Manager who simply ignores a claim hands the claimant a procedural advantage. On a FIDIC 1999, CCDC or AIA project, silence costs the assessor nothing. That asymmetry is why the 20.2.2 deeming provision is the single most contractor-favourable feature of the 2017 claims regime (and why it is routinely deleted by employer amendment in the Special Provisions) the defined term in the Red Book 2017, though some published texts of the form use "Particular Conditions", so check the printed form. Check for that deletion before advising on any 2017 claim.

Under NEC4 there is a second trap inside the safety valve. The deemed acceptance of a quotation under cl 62.6 does not arise automatically. It arises only after the Contractor notifies the Project Manager's failure. A contractor that waits for the deeming to operate by itself waits forever.

§ 04

Where the clock starts, and why CCDC 2 – 2020 runs earliest

Trigger dates differ more consequentially than periods do. CCDC 2 – 2020 GC 6.5.4 carries the earliest-running trigger of the forms compared here, because the 10 Working Days run from the commencement of the delay, not from awareness of it: "No extension shall be made for delay unless Notice in Writing of the cause of delay is given to the Consultant not later than 10 Working Days after the commencement of the delay." A contractor can be time-barred before it knew there was anything to notify.

Compare the alternatives. FIDIC 2017 Sub-Clause 20.2.1 runs from awareness or from when the Party should have become aware. NEC4 cl 61.3 runs from when the Contractor becomes aware of the event. JCT DB 2024 cl 2.24.1 runs from when delay becomes "reasonably apparent". Only CCDC runs from an objective event that may be invisible at the time. "Working Days" is a defined term excluding Saturdays, Sundays and holidays, so the calendar window is roughly two weeks, which sounds generous until the trigger point is applied to it.

306Of the 325 days of delay in Panther caused by the employer
28 daysThe FIDIC notice period the contractor in Panther missed
4.1MCAD dismissed on summary judgment in Elite for a missed 10-working-day notice

Elite Construction Inc. v Canada (Attorney General)5, 2021 ONSC 562, is the case that makes the point. A CAD 4.1M delay and extras claim was dismissed on summary judgment for failure to give written notice within 10 working days of the neglect or delay. The decision was affirmed on appeal at 2021 ONCA 803. The condition-precedent analysis is the motion judge's: the Court of Appeal dismissed the appeal because summary judgment was available on agreed facts, because the respondent had not waived its right to rely on the strict contractual notice requirements, and because quantum meruit and unjust enrichment had no room to operate where the parties were operating under a contract.

Canadian law is the strictest of the five jurisdictions surveyed here. Corpex (1977) Inc. v The Queen in right of Canada6, 1982 CanLII 213 (SCC), holds that a notice provision can bar a claim even without express "failing which" language. Technicore Underground Inc. v Toronto (City)7, 2012 ONCA 597, holds that the owner need not prove prejudice. Northland Kaska Corp. v R.8, 2001 BCSC 929, supplies the line worth memorising: "the grumblings of a contractor are not sufficient to constitute notice."

At the other end of the range, AIA A201–2017 §15.1.3.1 is more generous than it is usually described. The 21 days run from "occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later." The "whichever is later" limb is routinely dropped from summaries of the clause, and it is the limb that saves latent-condition and cumulative-impact claims. §15.1.3.2 goes further: for conditions first arising after the one-year correction period there is no 21-day limit and no referral to the Initial Decision Maker.

FIDIC has its own soft start. Obrascon Huarte Lain SA v HM Attorney General for Gibraltar9 [2014] EWHC 1028 (TCC), Akenhead J held (at [311]–[312]) that under FIDIC 1999 Sub-Clause 20.1 the 28 days runs from when the contractor was, or should have been, aware that the works is or will be delayed, and that notice is due prospectively, when it is clear delay will occur, or retrospectively, when delay has begun. The Court of Appeal ([2015] EWCA Civ 712) said nothing on Sub-Clause 20.1. A strict bar with a generous start date. It is the contractor's best structural argument on FIDIC timing and it is frequently overlooked.

§ 05

What the US layer adds: administrative notice and cost cut-offs

United States federal practice is structurally different from the common-law norm, and the difference is favourable to contractors on entitlement and unfavourable on money. FAR 52.249-10(b)(1)'s 10 days is administrative, not a forfeiture: the Contracting Officer has express power to extend it, and under (b)(2) the CO ascertains the facts and the extent of the delay and extends the time, with findings of fact final and conclusive subject to appeal under the Disputes clause.

The FAR's real teeth are elsewhere. FAR 52.242-14(c) (Suspension of Work) and FAR 52.243-4(d) (Changes) are cost cut-offs, not entitlement bars: they permit no adjustment for costs incurred more than 20 days before the written notice. They do not kill the claim. They shrink it, silently, by whatever the contractor spent before it wrote the letter. Both carry a final-payment backstop: FAR 52.243-4(f) permits no proposal after final payment, and 52.242-14(c) requires the claim to be asserted not later than final payment. Those two provisions are the quiet killers of otherwise good federal delay claims.

FAR 52.243-4(b) adds a gateway of a different kind. An order not issued as a formal change order is treated as a change order only if the Contractor gives written notice stating "the date, circumstances, and source of the order" and that it regards the order as a change order. Without that notice there is no constructive change to argue about. FAR 52.243-4(e) then requires the right to an adjustment to be asserted within 30 days of the change order or the (b) notice.

Behind all of it sits the Contract Disputes Act six-year bar under FAR 33.206, running from accrual, and accrual runs from the impact, not from the eventual quantification. Watts Constructors, LLC10, ASBCA 63753 (25 September 2025): the six-year bar killed a delay claim about a tardy modification because the contractor knew of the impact when it occurred.

On the private-work side, AIA A201–2017 §1.6.2 is the easiest own goal in US practice. Notice of a Claim, unlike ordinary notices under §1.6.1 which may be electronic, is duly served only if delivered by certified or registered mail, or by a courier providing proof of delivery. An email that satisfies every other notice provision in the contract does not serve a Claim, and §15.1.1 expressly defines a Claim to include "a change in the Contract Time", so every time request is a Claim. Actual owner knowledge does not cure it.

One thing US notice does not buy: Amatea/Grimberg JV v Secretary of the Navy11, No. 24-1006 (Fed. Cir., 25 June 2025) (nonprecedential), holds that a Contracting Officer's grant of a time extension and release of liquidated damages does not establish excusable delay for the contractor's own affirmative claim. Perfect notice and an administrative extension still leave the contractor to prove excusable critical-path delay from scratch, on the strength of its contemporaneous records.

§ 06

Can a statute strike out a time bar as unfair?

In two Australian jurisdictions, yes, and nowhere else in the common-law world covered by this corpus. Section 13A of the Building and Construction Industry Security of Payment Act 2002 (Vic), commenced 15 April 2026, allows a notice-based time bar to be declared unfair and of no effect where compliance "is not reasonably possible" or "would be unreasonably onerous". Western Australia's section 16 of the Building and Construction Industry (Security of Payment) Act 2021 (WA) applies the same test to contracts entered on or after 1 August 2022.

Four features of the Victorian provision make it the most significant recent development in extension of time notice practice anywhere:

  • It expressly reaches extensions of time. A "notice-based time bar" is any provision making contingent on notice an entitlement to payment, "an extension of time for doing a thing that affects an entitlement" to payment or to release of performance security, or release of performance security. EOT notice provisions are caught where the extension affects a payment or security entitlement.
  • It is retrospective to all construction contracts, including those entered into before commencement.
  • It is not confined to adjudication. An adjudicator, a court, an arbitrator or an expert determiner may decide the question. It therefore reaches conventional arbitration and litigation of EOT claims, which is unusual for a security of payment provision.
  • The mandatory considerations under s. 13A(5) cut both ways. When the party would reasonably have become aware of the deadline, when and how notice must be given, the parties' relative bargaining power, a presumption that the parties understood the terms, and a presumption that the notice-giver has the commercial and technical competence of a reasonably competent contractor. Subcontractors on principal-drafted terms have the strongest case. "We were too busy building" is not "not reasonably possible".

There is no case law anywhere on either provision. No Victorian determination under s. 13A has been reported, and (the more telling gap) no Western Australian case law has applied or tested s. 16 in the four years it has been in force. Victorian practitioners therefore have no interpretive guidance at all on a provision retrospectively applied to every construction contract in the state. Expect the first boundaries to be set at adjudication rather than in court.

Two qualifications must travel with any advice on s. 13A. Commentary flags a drafting gap: the definition of "notice" does not expressly include notice of an event occurring, arguably leaving a class of pure event-notification clauses outside the section. That is untested. And the transitional carve-out is recorded as a conflict in this corpus: one reputable firm describes payment claims and adjudication applications pending determination before 15 April 2026 as unaffected, another describes payment claims served before that date as unaffected. Those are close but not identical, and the transitional provision itself should be read before relying on either.

Elsewhere in Australia the position is unchanged. New South Wales has no unfair-time-bar power. The anti-contracting-out provision in s. 34 of the Building and Construction Industry Security of Payment Act 1999 (NSW) is the relevant lever, and on its face it addresses the effect of time bars on security of payment rights rather than EOT time bars generally. For Queensland, this corpus could not confirm the existence of a WA or Victorian-style power under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The working assumption is that there is none, and that assumption should be verified before it is relied on.

Note also what statutory adjudication does not do. In Ontario, the Construction Act and O. Reg. 264/25, s. 19 permit adjudication of an extension of time only as a supporting matter reasonably necessary to resolve a prescribed payment dispute. A contractor cannot commence a freestanding adjudication for a declaration of time entitlement, and adjudication does not reopen a contractual notice bar.

§ 07

What rescues a late notice, and why the rescues are worth less than parties expect

Every rescue route is fact-heavy, and none is reliable enough to plan around. The realistic assessment, route by route:

  • Waiver and estoppel. Needs owner conduct inconsistent with reliance on the bar, the paradigm being repeated payment of unnoticed claims, as in Colautti Construction Ltd v Ottawa (City)12, 1984 CanLII 1969 (ONCA). Usually produces a triable issue rather than a win.
  • Actual knowledge. Rarely enough on its own, because the notice must emanate from the claimant (Steria, 2007) and because "the grumblings of a contractor are not sufficient" (Northland Kaska, 2001 BCSC 929).
  • No prejudice to the owner. Not a defence in Canada at all: Technicore Underground Inc. v Toronto (City), 2012 ONCA 597.
  • Prevention and time at large. The argument in Gaymark Investments Pty Ltd v Walter Construction Group Ltd13 (1999) 16 BCL 449 (NTSC). In Multiplex v Honeywell (No 2) [2007] EWHC 447 (TCC), Jackson J saw "considerable force" in the criticisms of Gaymark. English law does not accept that a contractor's failure to serve a condition-precedent notice sets time at large. Doubted in Australia. Weak.
  • Civil-law good faith and abuse of rights. Available under the UAE and Saudi codes, but unreliable, and the 2023–2026 trend is toward enforcement. Note that Saudi Arabia's Civil Transactions Law (Royal Decree M/191, in force 16 December 2023) art. 470 imposes an additional statutory duty of immediate notification operating alongside FIDIC's 28 days. A trap, not a rescue, because a contractor can satisfy Sub-Clause 20.2.1 and still fall foul of art. 470.

The case that should end the argument is Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC14 [2022] DIFC CA 016 (judgment 12 May 2023). The 28-day notice, on the 1999 form's Sub-Clause 20.1, was held a clear condition precedent, not waivable by subsequent performance or by employer fault, and good faith arguments were rejected on the basis that the contractor was a willing party to a contract containing clear notice requirements. The contractor lost its extension of time entitlement despite the employer having caused 306 of 325 days of delay. That number is the whole argument for serving a notice you think you do not need. (The limitation that travels with Panther: the DIFC is a common-law free zone applying DIFC law, not the onshore UAE Civil Code, so the decision is highly persuasive commercially but is not authority on how the Dubai or Abu Dhabi onshore courts would rule.)

At the highest common-law level the point is now closed for FIDIC. Uniform Building Contractors Ltd v Water and Sewerage Authority of Trinidad and Tobago15 [2026] UKPC 2 held Sub-Clause 20.1 of the 1999 Yellow Book to be a condition precedent, "in classic condition precedent form", the defining feature being "dependency between the requirement and the relief. One must be conditional upon the other". The Board expressly observed that the 2017 form "has a slightly more flexible series of provisions" but remains "clearly a condition precedent."

Panther also decides something useful in the other direction: a valid notice can be "short and to the point" provided it identifies the event, states that the contractor considers itself entitled to an extension of time or payment, arrives within the 28 days, and reaches the Engineer. The bar is strict, but it is not high.

One counterpoint worth knowing and worth handling carefully. In CIMIC Morningstar Investments Ltd v Chandos Construction Ltd16, 2026 BCCA 2, leave to appeal an arbitral award was refused where the arbitrator had read a 10-day written notice requirement "in context", found the owner had actual knowledge from emails, meetings and schedule updates, applied the prevention principle to hold time at large, and awarded CAD 6.47M. It is a leave decision on an arbitral award. It confirms curial deference to an arbitrator's contextual reading of a notice clause. It does not restate the doctrine and it does not displace Technicore or Elite. Do not present it as a softening of Canadian notice law.

§ 08

The notice is the cheapest of the four elements to get right

Of the four elements of an extension of time claim (qualifying event, causation to completion, notice and procedure, and extent) notice is the only one that costs nothing but attention, and it is the one on which entitlement is most often lost. Every other element requires records, programme analysis, expert opinion and argument. Notice requires a letter, on time, to the right person, in the right form.

The failure is almost never ignorance of the clause. It is a contract administrator who treats a monthly report or a progress-meeting minute as notice, or who waits for the commercial negotiation to settle before filing the time notice. Those two habits account for most of the procedural deaths in the cases surveyed here.

Two structural warnings to close on. First, the asymmetry inside JCT: the extension of time machinery is forgiving, but the money machinery is not, and FES is the authority that a contractor can hold its time entitlement and lose its prolongation costs on identical facts for a purely procedural reason. Second, there is no reported English judgment construing the JCT 2024 extension of time provisions as at August 2026. Every reported 2025–26 JCT decision Storia found was on a 2016 or earlier edition. Advice on the 2024 suite is advice on unlitigated text, and should be given as such, which is one more reason to serve the notice rather than to argue afterwards about whether it was required.

Notes

Sources and authorities

18 cited
  1. 1
    Disclosure and Barring Service v Tata Consultancy Services Ltd[2025] EWCA Civ 380 (Coulson, Lewison and Snowden LJJ, 4 April 2025), Court of Appeal of England and Wales

    The current leading statement of when a notice clause is a condition precedent. The label "condition precedent" is not required and a precise time limit is not essential. What matters is whether the relief is made conditional on the requirement.

    Find Case Law

  2. 2
    Steria Ltd v Sigma Wireless Communications Ltd[2007] EWHC 3454 (TCC), Technology and Construction Court

    "Provided that" plus a clear temporal requirement creates a condition precedent without the magic words and without an express statement of consequence. Separately, the notice "must emanate from Steria" (at [82]): a minute prepared by the other side's representative would not by itself be valid notice.

    Find Case Law

  3. 3
    Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2)[2007] EWHC 447 (TCC), Technology and Construction Court

    The standard judicial answer to the unfairness objection: notice provisions "serve a valuable purpose". Jackson J also saw "considerable force" in the criticisms of Gaymark, so a failure to serve a condition-precedent notice does not set time at large in English law.

    Find Case Law

  4. 4
    Bremer Handelsgesellschaft mbH v Vanden Avenne-Izegem PVBA[1978] 2 Lloyd's Rep 109 (HL), House of Lords

    The original formulation: the clause must state a precise time and make plain that failure forfeits the entitlement. Still "the leading case" in DBS v TCS (at [13]), but its precise-time element is now the safe drafting target rather than a threshold a clause must clear to bite.

  5. 5
    Elite Construction Inc. v Canada (Attorney General)2021 ONSC 562 (Pinto J), aff'd 2021 ONCA 803

    A CAD 4.1M delay and extras claim dismissed on summary judgment for failure to give written notice within 10 working days of the neglect or delay. The condition-precedent analysis is the motion judge's; the Court of Appeal dismissed the appeal on the availability of summary judgment and on the absence of any waiver of the strict contractual notice requirements.

    Chercher sur CanLII

  6. 6
    Corpex (1977) Inc. v The Queen in right of Canada1982 CanLII 213 (SCC), Supreme Court of Canada

    A notice provision can bar a claim even without express "failing which" language.

    Chercher sur CanLII

  7. 7
    Technicore Underground Inc. v Toronto (City)2012 ONCA 597, Court of Appeal for Ontario

    The owner need not prove prejudice to rely on a notice bar. Absence of prejudice is not a defence to a Canadian notice provision.

    Chercher sur CanLII

  8. 8
    Northland Kaska Corp. v R.2001 BCSC 929, Supreme Court of British Columbia

    "The grumblings of a contractor are not sufficient to constitute notice", owner awareness of complaint is not service of a notice.

    Chercher sur CanLII

  9. 9
    Obrascon Huarte Lain SA v HM Attorney General for Gibraltar[2014] EWHC 1028 (TCC), affirmed [2015] EWCA Civ 712

    Akenhead J at first instance (at [311]–[312]): FIDIC 1999 Sub-Clause 20.1 is a condition precedent, construed reasonably broadly. The 28 days runs from when the contractor was, or should have been, aware that the works is or will be delayed, and notice is due when it is clear there will be delay (prospectively) or when delay has started (retrospectively). The Court of Appeal said nothing on Sub-Clause 20.1. A strict bar with a generous start date.

    Find Case Law

  10. 10
    Watts Constructors, LLCASBCA 63753 (25 September 2025), Armed Services Board of Contract Appeals

    The Contract Disputes Act six-year bar killed a delay claim about a tardy modification because the contractor knew of the impact when it occurred. Accrual runs from the impact, not from the eventual quantification.

    ASBCA

  11. 11
    Amatea/Grimberg JV v Secretary of the NavyNo. 24-1006 (Fed. Cir., 25 June 2025) (nonprecedential)

    A Contracting Officer's grant of a time extension and release of liquidated damages does not establish excusable delay for the contractor's own affirmative claim.

    Justia

  12. 12
    Colautti Construction Ltd v Ottawa (City)1984 CanLII 1969 (ONCA), (1984) 46 OR (2d) 236, Court of Appeal for Ontario

    Waiver by conduct. Repeated payment of unnoticed claims is the paradigm of owner conduct inconsistent with reliance on the notice bar, though it usually produces a triable issue rather than a win.

    Full text

  13. 13
    Gaymark Investments Pty Ltd v Walter Construction Group Ltd(1999) 16 BCL 449 (NTSC), Supreme Court of the Northern Territory

    The high-water mark of the argument that a contractor's failure to serve a condition-precedent notice sets time at large. Doubted in Australia and not accepted in English law.

    NT Supreme Court

  14. 14
    Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC[2022] DIFC CA 016 (judgment 12 May 2023), DIFC Court of Appeal

    On the amended FIDIC 1999 Red Book, the Sub-Clause 20.1 28-day notice is a clear condition precedent, not waivable by subsequent performance or by employer fault: the contractor lost its extension of time despite the employer having caused 306 of 325 days of delay. A valid notice may be short and to the point, provided it reaches the Engineer within the 28 days.

    DIFC Courts

  15. 15
    Uniform Building Contractors Ltd v Water and Sewerage Authority of Trinidad and Tobago[2026] UKPC 2 (22 January 2026), Privy Council

    Sub-Clause 20.1 of the FIDIC 1999 Yellow Book is a condition precedent "in classic condition precedent form", the defining feature being dependency between the requirement and the relief. The 2017 form is slightly more flexible but remains clearly a condition precedent.

    Chercher sur Find Case Law

  16. 16
    CIMIC Morningstar Investments Ltd v Chandos Construction Ltd2026 BCCA 2, Court of Appeal for British Columbia

    Leave to appeal an arbitral award refused where the arbitrator read a 10-day written notice requirement in context, found actual owner knowledge, applied the prevention principle and awarded CAD 6.47M. A leave decision on an arbitral award, not a restatement of the doctrine.

    Chercher sur CanLII

  17. 17
    Maeda Kensetsu Kogyo Kabushiki Kaisha v Bauer Hong Kong Ltd[2019] HKCFI 916 (9 April 2019), Court of First Instance · affirmed on appeal 18 September 2020

    A notice specifying one contractual basis may not preserve a claim later advanced on a different basis.

  18. 18
    FES Ltd v HFD Construction Group Ltd[2024] CSIH 37, Inner House, Court of Session

    The JCT loss and expense notice is a true condition precedent where cl 4.20 is expressed as subject to cl 4.21, even where the extension of time notice is not. The contractor got the time and lost the money.

    Scottish Courts

General information, not legal advice. Reviewed 13 oct. 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou…

Each issue links to the full articles in the Storia Library.

Avis et délais de forclusion · Storia