Prevention principle and time at large in Canada
In Canada an owner that has prevented the contractor from completing on time cannot insist on liquidated damages, and where no extension is granted the completion date can fall away. Perini Pacific is the anchor, but the domestic authority is thin and no Ontario decision addresses either doctrine.
Disponible solo en inglés Este artículo aún no se ha traducido. Los plazos, el derecho a reclamar y el procedimiento descritos aquí rozan lo jurídico, y una traducción automática sería un riesgo de credibilidad más que una comodidad: por eso se sirve el original inglés íntegro hasta que exista una traducción revisada.
At a glance
- Doctrine
- Canada, common-law provinces
- CCDC 2 – 2020
- Excludes Quebec
Key facts
- 01
The short answer
An owner who has interfered with the contractor's performance cannot insist on liquidated damages. Where the owner causes delay and no corresponding extension is granted, the LD clause becomes inoperative and time is at large. Where an extension is properly granted under the contractual mechanism, a new completion date is fixed and the LD entitlement revives.
- 02
The anchor
Perini Pacific Ltd v Greater Vancouver Sewerage and Drainage District, (1966), 57 DLR (2d) 307 (BCCA): the Canadian statement of the classical English rule. Cite it to the Court of Appeal. The liquidated damages counterclaim was not in issue on the further appeal, [1967] SCR 189, which decided a different question. Hawl-Mac Construction v Campbell River (1985), 10 CLR 177 (BCSC) is the closer candidate for time at large itself, subject to primary-text verification.
- 03
The open contradiction
One source in the corpus attributes an enforced no-damage-for-delay clause to "Perini" (1967 SCC), the same case. Resolved: prevention defeated the owner's liquidated damages in the Court of Appeal, and the exculpatory clause defeated the contractor's own delay costs in the Supreme Court. Opposite parties' claims, one litigation.
- 04
The owner's answer
A competent sweep-up EOT provision keeps the completion date in place. CCDC 2 – 2020 GC 6.5.1 is narrower than most: it reaches only Owner or Consultant delay "contrary to the provisions of the Contract Documents", which leaves more room for an act of prevention to fall outside the machinery altogether.
- 05
Notice bites first
CCDC 2 – 2020 GC 6.5.4 requires Notice in Writing within 10 Working Days after the commencement of the delay. Canadian courts enforce notice strictly and the owner need not prove prejudice, so in most Canadian delay disputes the prevention argument is never reached.
- 06
Ontario
There is no Ontario authority on the prevention principle or on time at large. Both Canadian anchors are British Columbia cases. An Ontario contractor running the defence is arguing on BC and English authority and should say so.
- 07
What courts do instead
Canadian courts apportion where multiple parties contribute overlapping delay, and the Bhasin / Callow / Wastech good-faith line gives a route against an owner who administers the EOT clause abusively, a cause of action with no English equivalent.
- 08
Quebec
The concept does not exist. Article 1512 of the Civil Code of Québec requires the court to fix an indeterminate term: judicial gap-filling, the opposite of the common-law consequence.
Canada follows the English prevention principle closely, and has done since a British Columbia sewer contract in 1966. An owner who has interfered with the contractor's performance cannot insist on liquidated damages. What Canada does not have is a developed body of law telling you when that happens, what the remedy is called, or how a court will measure it.
The doctrine matters most in the gap between two things a Canadian contract does well: allocating named delay events, and barring late claims. Between them sits the act of prevention that the extension-of-time clause does not reach, and that is where the argument lives. Everything below is Canadian common law. Quebec runs a different system and is addressed only by way of contrast at the end.
A structural warning applies to every citation on this page and is not a formality. No Canadian judgment and no provincial statutory text was read in original form for the corpus behind this page. CanLII, the Supreme Court portal and the provincial e-laws sites all blocked automated retrieval. Case content rests on independent secondary sources that agree with one another. Check every judgment and every clause number against an authenticated source before pleading it. For the wider framework, start at extension of time in Canada.
What the prevention principle is, and what triggers it
The prevention principle is a default rule of contractual risk allocation: an owner that causes delay to the contractor's performance cannot then insist on the delay remedy it bargained for. Where the owner causes delay and no corresponding extension of time is granted, the liquidated damages clause becomes inoperative and time is at large. Where an extension is properly granted under the contractual mechanism, a new completion date is fixed and the liquidated damages entitlement revives.
Three things trigger it in practice. First, an owner act that delays completion and falls outside the events the extension-of-time clause covers: the classic gap identified in Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd1 (1970) 1 BLR 111. Second, a breakdown in the operation of the mechanism: nobody appointed to certify, a certifier who refuses to operate the clause at all, or a clause too uncertain to work. Third, the absence of any completion date at all, which is rarer in an executed contract than in a letter of intent or a notice to proceed followed by heavy scope change.
It is a default, not an overriding rule of law, and clear express words displace it. That proposition is settled at appellate level in England. It has not been tested at appellate level in Canada on a bespoke amendment, and a Canadian court faced with drafting that expressly allocates owner-caused delay to the contractor would be deciding the point for the first time.
Perini Pacific. The Canadian anchor, and exactly how far it goes
The Canadian anchor is Perini Pacific Ltd v Greater Vancouver Sewerage & Drainage District2, (1966) BCCA, affirmed [1967] SCR 189. It is the Canadian statement of the classical English rule and it remains the starting point for any prevention argument in a common-law province.
A building owner is not allowed to insist upon the penalty for delay if, by ordering extra, he has prevented the builder from completing the work by a specified time.
Note what that sentence does and does not do. It states the rule in its narrowest classical form (ordering extras, defeating a penalty) and it does so in a British Columbia appeal affirmed by the Supreme Court of Canada. It is not a modern restatement, it does not address concurrency, it does not address condition-precedent notice, and it does not set out a test for measuring the period during which the completion date is displaced. The companion Canadian authority, N.B.C. Mechanical Inc v A H Lundberg Equipment Ltd3, 1999 BCCA 775, applies the rule on construction facts: the owner's $200,000 liquidated damages counterclaim failed because its own requests for extras caused a significant part of the delay, and the trial judge held that whether the contractor could have finished on time but for those delays was irrelevant. The Court of Appeal dismissed the appeal on a deference standard, treating the attribution of delay as "an assessment of the whole of the evidence" and the contractor's own admitted 80 per cent completion at the deadline as "only one factor to be considered". ★ It contains no extension-of-time clause at all, so the further proposition that an owner may enforce liquidated damages from an extended date where the machinery was properly operated does not come from this case. That is the Peak Construction line.
Both anchors are British Columbia cases. That is the single most important practical fact about the Canadian prevention principle, and it is developed below.
One case must not be added to that list. CIMIC Morningstar Investments Ltd v Chandos Construction Ltd4, 2026 BCCA 2, is sometimes offered as a recent appellate statement of the doctrine. It is not. It is a decision refusing leave to appeal an arbitral award. It confirms curial deference to an arbitrator's contextual reading of a notice clause and to a prevention finding, it does not restate doctrine, and the underlying award is not public. Do not cite it as a Canadian appellate statement of the prevention principle.
The Perini no-damage-for-delay point, resolved
The corpus carried this as an unresolved conflict: alongside the prevention holding, a source attributed to a 1967 Supreme Court of Canada decision called "Perini" the enforcement of a no-damage-for-delay clause. It is the same case, and there is no contradiction: the two propositions concern opposite parties' claims in the same litigation.
The owner's liquidated damages counterclaim was dismissed by the Court of Appeal on prevention grounds and was not in issue before the Supreme Court, which said so in terms. The contractor's own claim for delay-caused head-office overhead is what went up, and it failed: Martland J enforced clause 6-04 (no "claim or right of action … for damages, costs, expenses, loss of profits or otherwise howsoever because or by reason of any delay in the fulfilment of the contract") as barring that loss "even though the respondent had caused such delay".
The corpus's working reconciliation was right and is now confirmed against the primary text: the prevention principle governs the owner's claim against the contractor, and a no-damage-for-delay clause governs the contractor's claim against the owner. They point in opposite directions because they answer opposite questions.
★ The practical lesson is sharper than either proposition alone. In one case, on one project, prevention defeated the owner's liquidated damages and an exculpatory clause defeated the contractor's delay costs. A contractor that wins the prevention argument has not thereby won its own prolongation claim. Check the exculpatory clause before treating prevention as a victory.
The stakes are higher in Canada than a reader from the United States will expect, because there is no statutory prohibition on no-damage-for-delay clauses anywhere in Canada: federal, provincial or territorial. Canadian construction and lien statutes bar contracting out of the lien, trust and prompt-payment provisions and say nothing about delay-damages exculpation. No-damage-for-delay clauses are enforceable in Canada if clearly drafted. They fail on clarity, not on policy, and the governing framework is the three-stage exclusion-clause analysis in Tercon Contractors Ltd v British Columbia (Transportation and Highways)5, 2010 SCC 4. The Canadian battleground is stage one (construction and clarity), and the contractor's route is ambiguity plus the prevention principle, not public policy. See liquidated damages and the penalty rule in Canada.
The extension-of-time clause is the owner's answer, and CCDC 2's is narrow
An owner defeats a prevention argument by pointing to an extension-of-time clause that covers the act complained of. If the clause reaches the event, the completion date survives, an extension is assessed, and liquidated damages run from the extended date. That is why modern forms carry wide sweep-up provisions, and it is why the doctrine rarely succeeds where the drafting is competent.
The English authority puts it squarely: acts of prevention by an employer do not set time at large if the contract provides for extension of time in respect of those events, and an ambiguous extension-of-time clause is construed in favour of the contractor: Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2)6 [2007] EWHC 447 (TCC). No Canadian appellate decision states either proposition in those terms, but the first follows from the contract itself and a Canadian court applying an operative extension-of-time clause will reach the same place.
CCDC 2 – 20207 is the standard Canadian form and is still current. There is no 2025 or 2026 update to CCDC 2. Its sweep-up is narrower than the international equivalents. GC 6.5.1 covers delay "by the Owner, the Consultant, or anyone employed or engaged by them directly or indirectly, contrary to the provisions of the Contract Documents". The qualifier does real work: the delay must be contrary to the Contract Documents, not merely attributable to the Owner. That is narrower than a JCT-style "any impediment, prevention or default by the Employer" and narrower than the FIDIC equivalent. GC 6.5.3.4, "any cause beyond the Contractor's control", is expressly time-only unless the delay in fact results from Owner or Consultant action, in which case it converts to a compensable GC 6.5.1-type claim.
The practical consequence is that the CCDC sweep-up leaves more room for an owner act to fall outside the machinery altogether than the English, FIDIC or NEC equivalents do. Whether that produces time at large in Canada, and how often, is under-litigated. And it is only ever a starting point: supplementary conditions almost universally amend GC 6.5, with the notable exception of the Ontario industry-agreed package, the OAA/OGCA Agreed-to Recommended Supplementary Conditions for CCDC 2 – 2020 contain no supplementary condition amending GC 6.5. Read the supplementary conditions before running any prevention analysis.
| England and Wales | Canada, common-law provinces | |
|---|---|---|
| Status of the principle | A default rule of risk allocation, displaceable by clear express words. Settled at Court of Appeal level | Followed closely, but stated in its classical form only. No appellate ruling on a bespoke risk-shifting amendment |
| Prevention where the clause covers the event | Does not set time at large. Settled in the Technology and Construction Court | Same result follows from the contract, but no Canadian appellate authority states the proposition in those terms |
| Contractor fails to serve a condition-precedent notice, then pleads prevention | Answered firmly in the negative: the contractor cannot bootstrap its way out of a time bar | Live and under-tested. No Canadian appellate authority squarely resolving it was located. Expect it to be argued |
| Concurrent delay | Contractor generally gets the full extension | Courts apportion where multiple parties contribute overlapping delay |
| Statutory control of no-damage-for-delay clauses | None | None anywhere in Canada, unlike the United States |
Comparative and jurisdictional. The English rows state appellate or first-instance authority of England and Wales. The Canadian rows rest on British Columbia and Ontario authority read from secondary sources only. No Canadian judgment was read in original form for this corpus.
Does "time at large" exist in Canada, and how thin is the authority
Yes, as a doctrine imported with the English common law: where there is no valid, operable completion date, the contractor's obligation becomes to complete within a reasonable time, the liquidated damages machinery collapses because there is no date from which to compute anything, and the owner is thrown back on proving general damages. What Canada does not have is much authority saying so.
Take the negatives in order, because they are more useful than a paragraph of hedging. There is no Ontario authority on the prevention principle or on time at large. Both Canadian anchors, Perini Pacific and N.B.C. Mechanical, are British Columbia cases. An Ontario contractor running the prevention defence is arguing on British Columbia and English authority, and should say so in the pleading rather than be caught by it on the other side's reply. There is also no Ontario construction liquidated-damages decision at all between 2018 and 2026, the Ontario liquidated damages authorities are real-estate deposit, franchise and employment cases, so the remedy the prevention argument is aimed at is itself thinly evidenced in that province.
Neither of the two anchors above squarely reaches time at large as a doctrine, Perini Pacific is about defeating liquidated damages, and N.B.C. Mechanical is about the extension-of-time machinery working properly, not failing to operate at all. The closer candidate is Hawl-Mac Construction Ltd v Campbell River (District)8, (1985), 10 CLR 177 (BCSC). The engineer there had a seven-day contractual duty to decide an extension application and missed it. The court held the owner could not then rely on the original completion date, and liquidated damages failed, which is the operative consequence of time at large, whatever label the judgment itself used. This is the strongest candidate for a Canadian finding of time at large, and national commentary asserting flatly that no Canadian court has ever found it should be read against Hawl-Mac, not treated as settled. The primary text has not been confirmed in this corpus, so treat the doctrinal label (prevention, time at large, or simple breach of an express EOT obligation) as open, while treating the practical result as solid. If your form has an express EOT decision deadline, Hawl-Mac is the cleanest route to arguing that a missed one displaces the completion date. Where there is no express deadline, it also supplies the argument for an implied "reasonable time" to decide.
Two further limits are worth pleading around. Prevention is reached late in a Canadian dispute, because notice is reached first: a notice provision can bar a claim even without express "failing which" language (Corpex (1977) Inc v The Queen in right of Canada9, 1982 CanLII 213 (SCC)), the owner need not prove prejudice (Technicore Underground Inc v Toronto (City)10, 2012 ONCA 597), and a CAD 4.1M claim was dismissed on summary judgment for missing a 10-working-day notice in Elite Construction Inc v Canada (Attorney General)11, 2021 ONSC 562, affirmed on appeal at 2021 ONCA 803. In most Canadian delay disputes the prevention argument is never reached at all. See notice and time bars in Canada.
Quebec is the sharp contrast, and it is a contrast of consequence rather than of degree. The concept of time at large does not exist in Quebec at all. Where a term is indeterminate, article 1512 of the Civil Code of Québec12 requires the court to fix the term. Quebec's answer to temporal indeterminacy is judicial gap-filling. The common law's is to discharge the date. Nothing on this page should be extended to a Quebec contract. See Quebec versus common-law Canada on delay.
One further point should be modelled before time at large is pleaded in any common-law province, and it turns on the contract rather than on Canadian law. Where the liquidated damages rate also capped the contractor's delay liability, putting time at large removes the cap along with the clause and exposes the contractor to uncapped general damages for failure to complete within a reasonable time. For the doctrine in its jurisdiction-neutral form, see extension of time.
What a Canadian court does instead: apportionment, and the good-faith route
Where an English court would face a binary choice, a Canadian court apportions. Canadian courts have been willing to divide responsibility where multiple parties contribute overlapping delay, which orthodox English law does not do. That is an inference drawn from the authorities rather than a proposition any Canadian court has stated in those terms, but it is the single most important practical difference for an English or Australian practitioner running a Canadian job.
The evidentiary standard comes from Schindler Elevator Corp v Walsh Construction Company of Canada13, 2021 ONSC 283, the leading Canadian concurrency authority: the postponement must be broken into its component parts so that time, responsibility and costs can be apportioned, with concurrency found where delays to co-critical and co-controlling activities overlap. Walsh Construction v Toronto Transit Commission14, 2024 ONSC 2782, endorsed the same flexible approach and required a clear and rational expert opinion grounded in contemporaneous records. No Canadian appellate decision squarely on concurrent delay was located for 2024–2026, so this rests on first-instance authority. See concurrent delay in Canada.
The modern Canadian route runs through good faith, and it has no English equivalent. Bhasin v Hrynew15, 2014 SCC 71, and C.M. Callow Inc v Zollinger16, 2020 SCC 45, establish the duty of honest performance. Wastech Services Ltd v Greater Vancouver Sewerage and Drainage District17, 2021 SCC 7, holds that a contractual discretion must be exercised reasonably and consistently with the purpose for which it was conferred. An owner assessing an extension-of-time application under CCDC 2 – 2020 GC 6.5 is exercising exactly such a discretion. An owner that sits on a valid application, or refuses it in bad faith, is therefore exposed to a claim in its own right rather than merely to a prevention defence. That argument has not yet been run in a reported Canadian delay case. It is structurally sound, it is uniquely available in Canada, and it is the most promising untested argument in this area.
Evidence carries the rest. The shape of a winning Canadian prevention case is owner design changes plus late approvals, actual owner knowledge evidenced through contemporaneous emails, meeting minutes and schedule updates, and a tribunal willing to read the notice clause in context. Each of those elements is evidential, not doctrinal, and the limit is set by Northland Kaska Corp v R18, 2001 BCSC 929: "the grumblings of a contractor are not sufficient to constitute notice".
The qualifying-events interface, GC 6.5.2 versus GC 6.5.3
CCDC 2 – 2020 GC 6.5 allocates delay by cause, and the allocation decides money. GC 6.5.1 (Owner or Consultant delay contrary to the Contract Documents) and GC 6.5.2 (a stop work order issued by a court or other public authority) are compensable. GC 6.5.3, labour disputes, fire and unavoidable casualties, abnormally adverse weather, and any cause beyond the Contractor's control, is time-only. Which limb an event falls into is usually where all the money is.
| GC 6.5 limb | Cause | Time | Cost |
|---|---|---|---|
| 6.5.1 | Owner, Consultant or their people, contrary to the provisions of the Contract Documents | Reasonable time as the Consultant may recommend in consultation with the Contractor | Yes, reasonable costs reimbursed by the Owner |
| 6.5.2 | Stop work order issued by a court or other public authority, not caused by the Contractor, resulting in failure to attain Ready-for-Takeover by the Article A-1 date | Same formula | Yes, reasonable costs reimbursed |
| 6.5.3 | .1 labour disputes, strikes and lock-outs, .2 fire, unusual delay by common carriers, unavoidable casualties, .3 abnormally adverse weather conditions, .4 any cause beyond the Contractor's control | Reasonable time, and not less than the time lost unless the Contractor agrees to a shorter extension | No, unless the delay results from Owner or Consultant action |
| 6.5.4 | Notice | Notice in Writing not later than 10 Working Days after the commencement of the delay. One notice suffices for a continuing cause | – |
Form-default, CCDC 2 – 2020 printed general conditions. Supplementary conditions almost universally amend GC 6.5, so an executed contract may allocate differently. Clause numbers and headings rest on secondary sources. The printed text was not read in original form for this corpus.
The highest-value open question in the whole Canadian CCDC field sits inside that table. Whether a provincial public-health order is a "stop work order" under GC 6.5.2 has never been decided by a Canadian court. It matters because the answer decides compensable against time-only. The routing argument runs like this: in Porter Airlines Inc v Nieuport Aviation Infrastructure Partners GP19, 2022 ONSC 5922, a licence agreement, not a construction contract: the court held that "the pandemic itself is not the reason for the prevention of performance under a contract. Rather, it is the associated government and regulatory responses". If the operative cause is the order rather than the disease, the pandemic-relief argument must run through GC 6.5.2, which carries money, rather than through GC 6.5.3, which does not. The point is recorded as UNVERIFIED and expressly open. It will be litigated on the next public-health event. Plead GC 6.5.2 first and GC 6.5.3 in the alternative.
Three more negatives shape any GC 6.5.3 argument, and each should be stated to a client rather than hedged. No Canadian judgment holds COVID-19 to be force majeure under a construction contract at any point between 2020 and 2026, and no Canadian judgment applies GC 6.5.3 to the pandemic. No Canadian authority construes "abnormally adverse weather conditions" in GC 6.5.3.3, none defines the baseline against which "abnormal" is measured, and none endorses any proof method, so a Canadian weather claim is argued on a purely evidential footing with no domestic legal test, and the owner is free to attack both the baseline station and the normals period without contradicting any authority. No Canadian authority construes the GC 6.5.3.1 lock-out carve-in, and none defines "recognized contractors' association", which is doctrinally interesting, because that carve-in is an express contractual override of the "beyond the control of either party" principle in Atlantic Paper Stock Ltd v St Anne-Nackawic Pulp & Paper Co Ltd20, 1975 CanLII 170 (SCC), [1976] 1 SCR 580, deeming the contractor's own association's decision excusable.
Tariffs and escalation: a money event under GC 10.1.2, not a time event
CCDC 2 – 2020 has no general materials-price escalation clause, but it does have a taxes-and-duties adjustment. GC 10.1.2 provides that any increase or decrease in costs to the Contractor due to changes in taxes and duties after the time of the bid closing shall increase or decrease the Contract Price accordingly. The correction matters because the commonly repeated statement that CCDC 2 contains no escalation mechanism at all is wrong.
The consequence for the 2025–26 supply shock is a routing rule, and it is the commonest Canadian claim error of the period. Tariffs imposed after bid closing are a priced-adjustment event under GC 10.1.2, a money event, not a time event. Claim the money under GC 10.1.2. Claim time separately under GC 6.5.3, and only if delivery was in fact delayed. Conflating the two loses both, because the time claim contaminates a straightforward price adjustment and the price claim invites the owner to say the contractor never proved delay to completion.
Force majeure will not fill the gap. Relief in Canada requires actual prevention of performance: supplies becoming more expensive is not enough, though supplies becoming unavailable may be. That follows directly from Atlantic Paper, whose control test and author-of-its-own-misfortune bar are where these claims die.
There is no help available from the institutions either. No CCDC or Canadian Construction Association guidance document, and no model supplementary condition, on tariffs or escalation was located, and there is no Canadian case law on tariff-driven escalation claims in construction for 2025–2026. Cost-plus forms push the risk the other way: under the CCDC cost-plus and construction-management forms, customs, taxes and duties paid during performance are included in the Cost of the Work and therefore sit with the owner.
Sources and authorities
- *Verification, unless noted
No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
- 1Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd(1970) 1 BLR 111, Court of Appeal of England and Wales
Employer delay not covered by the extension-of-time machinery destroys the completion date and with it the liquidated damages clause, and the extension-of-time clause must in terms cover the act of prevention relied on. The source of the "gap" that modern sweep-up provisions are drafted to close.
- 2Perini Pacific Ltd v Greater Vancouver Sewerage & Drainage District(1966), 57 DLR (2d) 307 (BCCA); SCC appeal [1967] SCR 189, 60 DLR (2d) 385, 1967 CanLII 104
The Canadian prevention anchor: "A building owner is not allowed to insist upon the penalty for delay if, by ordering extra, he has prevented the builder from completing the work by a specified time." That holding is the Court of Appeal's, and the liquidated damages counterclaim was not in issue before the Supreme Court of Canada. On the further appeal the Supreme Court enforced clause 6-04, a broad no-damage-for-delay clause, against the contractor's own claim for delay-related overhead. Both propositions are true of the same litigation and concern opposite parties' claims.
- 3N.B.C. Mechanical Inc v A H Lundberg Equipment Ltd1999 BCCA 775, British Columbia Court of Appeal
The owner's liquidated damages counterclaim failed because the owner's own requests for extras caused a significant part of the delay, so the contractor was prevented from completing by the stipulated date. The trial judge held that whether the contractor could have completed on time but for the owner's delays was irrelevant; the Court of Appeal declined to interfere, treating attribution of responsibility for delay as an assessment of the whole of the evidence and the contractor's own incomplete progress as "only one factor to be considered".
- 4CIMIC Morningstar Investments Ltd v Chandos Construction Ltd2026 BCCA 2, Court of Appeal for British Columbia
A leave decision refusing leave to appeal an arbitral award. It confirms curial deference to an arbitrator's contextual reading of a notice clause and to a prevention finding. It does not restate doctrine, and the underlying award is not public. It must not be cited as a Canadian appellate statement of the prevention principle.
- 5Tercon Contractors Ltd v British Columbia (Transportation and Highways)2010 SCC 4, Supreme Court of Canada
The three-stage framework governing any exclusion clause, including a no-damage-for-delay clause: whether the clause applies on its true construction. Whether it was unconscionable at formation, and whether there is an overriding public-policy reason to refuse enforcement.
- 6Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2)[2007] EWHC 447 (TCC), Technology and Construction Court, England and Wales
Acts of prevention by an employer do not set time at large if the contract provides for extension of time in respect of those events. An ambiguous extension-of-time clause is construed in favour of the contractor, and a contractor's own failure to serve a condition-precedent notice does not put time at large.
- 7CCDC 2 – 2020 Stipulated Price ContractGeneral Conditions GC 6.5 (Delays) and GC 10.1 (Taxes and Duties)
GC 6.5.1 covers delay by the Owner, the Consultant or anyone employed or engaged by them, contrary to the provisions of the Contract Documents, and is compensable. GC 6.5.2 covers a stop work order issued by a court or other public authority and is compensable. GC 6.5.3 lists neutral events and is time-only. GC 6.5.4 requires Notice in Writing not later than 10 Working Days after the commencement of the delay. GC 10.1.2 adjusts the Contract Price for changes in taxes and duties after the time of the bid closing.
- 8Hawl-Mac Construction Ltd v Campbell River (District)(1985), 10 CLR 177 (BCSC), 1985 CanLII 342 (BC SC)
The engineer's failure to operate the contract's extension-of-time machinery within its own decision deadline meant the owner could not rely on the original completion date, and liquidated damages failed, the operative consequence of time at large, on facts closer to the doctrine's core than either Perini Pacific or N.B.C. Mechanical. Whether the judgment used the language of "time at large" itself, or reached the result as prevention or as simple breach of an express EOT obligation, cannot be confirmed without the primary text.
- 9Corpex (1977) Inc v The Queen in right of Canada1982 CanLII 213 (SCC), Supreme Court of Canada
A contractual notice provision can bar a claim even without express "failing which" language.
- 10Technicore Underground Inc v Toronto (City)2012 ONCA 597, Court of Appeal for Ontario
Strict compliance with a contractual notice provision is required, and the owner need not prove prejudice from the failure to notify.
- 11Elite Construction Inc v Canada (Attorney General)2021 ONSC 562, Ontario Superior Court of Justice, affirmed on appeal
A CAD 4.1M delay and extras claim dismissed on summary judgment for failure to give written notice within 10 working days, affirmed at 2021 ONCA 803.
- 12Civil Code of Québec, article 1512art 1512 C.c.Q.
Where the parties have agreed to delay the determination of the term or to leave it to one of them to make that determination, and the term has not been determined, the court fixes it on the application of either party. The consequence is judicial gap-filling, not the discharge of the completion date.
- 13Schindler Elevator Corp v Walsh Construction Company of Canada2021 ONSC 283, Ontario Superior Court of Justice
The leading Canadian concurrency authority, and the source of the Canadian critical-path evidentiary standard: the postponement must be broken into its component parts to apportion time, responsibility and costs. Delays are concurrent where delays to co-critical and co-controlling activities overlap.
- 14Walsh Construction v Toronto Transit Commission2024 ONSC 2782, Ontario Superior Court of Justice
Endorsed the flexible, overlapping-events approach to concurrency and required a clear and rational expert opinion based on contemporaneous records. Acceleration costs were awarded where the owner caused delay through design delays and repeated changes.
- 15Bhasin v Hrynew2014 SCC 71, Supreme Court of Canada
Established the duty of honest performance in contract as a general organising principle of good faith in Canadian contract law.
- 16C.M. Callow Inc v Zollinger2020 SCC 45, Supreme Court of Canada
Extended the duty of honest performance: a party may not knowingly mislead its counterparty about matters directly linked to the performance of the contract.
- 17Wastech Services Ltd v Greater Vancouver Sewerage and Drainage District2021 SCC 7, Supreme Court of Canada
A contractual discretion must be exercised reasonably and consistently with the purpose for which it was conferred. An owner administering an extension-of-time clause is exercising a contractual discretion, though that argument has not yet been run in a reported Canadian delay case.
- 18Northland Kaska Corp v R2001 BCSC 929, Supreme Court of British Columbia
"The grumblings of a contractor are not sufficient to constitute notice." The limit on any argument that the owner's actual knowledge substitutes for a contractual notice.
- 19Porter Airlines Inc v Nieuport Aviation Infrastructure Partners GP2022 ONSC 5922, Ontario Superior Court of Justice
A licence agreement, not a construction contract. COVID-19 did not trigger the force majeure clause: "the pandemic itself is not the reason for the prevention of performance under a contract. Rather, it is the associated government and regulatory responses."
- 20Atlantic Paper Stock Ltd v St Anne-Nackawic Pulp & Paper Co Ltd1975 CanLII 170 (SCC), [1976] 1 SCR 580
The Canadian force majeure root. Relief requires "a supervening, sometimes supernatural, event, beyond control of either party". General "beyond our control" wording is read ejusdem generis against the enumerated events, and a party that authored its own misfortune cannot claim relief. Carry both the decision year, 1975, and the report year.
General information, not legal advice. Reviewed 10 sept 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Modelos de aviso de retraso para AS 4000, FIDIC 2017 y CCDC 2Un aviso de retraso deja constancia a tiempo de un solo hecho: que algo ha retrasado, o…
Each issue links to the full articles in the Storia Library.