LIBRARY
AlbertaExtension of timeJurisdiction article

Alberta delay claim clocks

Alberta runs six clocks on a delay claim, contractual notice, adjudication, lien, holdback, limitation and prosecution of the action itself. Which of them exist at all depends on which Act you are on: on a provincial Crown public work the Public Works Act 45-day registered-mail notice is effectively the only one that matters.

Reviewed 9 août 202624 min read24 sources
Same topic inONBCABUS

Disponible en anglais seulement Cet article n'a pas encore été traduit. Les délais, le droit à réclamation et la procédure décrits ici touchent au droit, et une traduction automatique constituerait un risque de crédibilité plutôt qu'une commodité : l'original anglais est donc servi intégralement jusqu'à ce qu'une traduction révisée existe.

At a glance

Alberta
Jurisdiction
Alberta, Canada, common law
Governing statutes
PPCLA, RSA 2000, c P-26.4 (from 29 August 2022) · Builders' Lien Act, RSA 2000, c B-7 (before that date) · Public Works Act, RSA 2000, c P-46 · Limitations Act (Alberta) · Alberta Rules of Court
Contract forms
CCDC 2 – 2020 · ACA SC CCDC2-2020 · Alberta Infrastructure Construction Management Agreement · Alberta Transportation Edition 16 · City of Calgary General Conditions v2.0
Evidence basis
Secondary sources, no judgment or consolidated statute read in original text
§ 00

Key facts

  1. 01

    The short answer

    Six clocks, and they are not the same six on every job. Ask which Act governs before you diarise anything: the Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 on private and municipal work, or the Public Works Act, RSA 2000, c P-46 on provincial Crown public works.

  2. 02

    On a provincial Crown public work

    One clock dominates, Public Works Act s 14(3), 45 days from last supply, by registered mail, in the statutory form. There is no lien, no trust of the Crown's money, and delay is expressly not adjudicable under s 14.3(2).

  3. 03

    Contractual notice

    CCDC 2 – 2020 GC 6.5.4 gives 10 Working Days from the commencement of the delay for time. GC 6.6.1 requires only timely notice for money. Public and municipal forms differ sharply, and two of them carry de-minimis thresholds rather than day counts.

  4. 04

    Adjudication

    Private and municipal only. Referral is available up to 30 days after final payment under PPCLA s 33.4 and runs concurrently with litigation, which makes private Alberta the most open adjudication forum in Canada. There is no cap.

  5. 05

    Liens

    60 days generally, 90 days for an oil or gas well or well site, 90 days for concrete other than ready-mix, a $700 minimum claim, and 180 days from registration to commence the action and file a certificate of lis pendens. Private and municipal work only.

  6. 06

    Limitation

    Two years from the three-limb discovery test in s 3(1)(a) of the Limitations Act, and a ten-year ultimate period running from the discrete first actionable breach. The parties may extend it by agreement. A clause shortening it is invalid under s 7(2).

  7. 07

    Prosecution, the clock nobody diarises

    Rule 4.31 dismisses for inordinate and inexcusable delay with prejudice, rule 4.33 is mandatory once three or more years pass without a significant advance. A $4M construction claim was struck in Peters v Countryside Masonry Inc, 2025 ABKB 713.

  8. 08

    The trap for visiting practitioners

    In Alberta a delay claim can meet every notice, adjudication, lien and limitation deadline and still be struck for being prosecuted too slowly. No other regime in this cluster works that way.

Alberta runs six clocks on a delay claim: contractual notice, adjudication, lien, holdback, limitation, and prosecution of the action itself. They have different characters in law, some are conditions precedent to entitlement, some are statutory preconditions to a remedy, one is a limitation period and one is a procedural rule and which of them exist at all depends on which Act the project sits under. On a provincial Crown public work most of them do not exist, and the 45-day registered-mail notice under the Public Works Act is effectively the only clock that matters.

The deadlines below are grouped by clock rather than by chronology, because a delay claimant is never running one clock at a time. A single Alberta project can have a 10-Working-Day contractual notice period, a 60-day lien period, a 28-day payment cycle feeding an adjudication referral, a two-year limitation period and a three-year drop-dead rule all running from different trigger events, none of which is the day the delay was noticed.

This page sits under the Alberta place hub, which carries the two Acts, the citation eras and the Alberta authority map. General Canadian doctrine: force majeure, concurrency, liquidated damages, prolongation quantum, lives at the Canada hub and is not repeated here. What is repeated, deliberately and in every section, is the Act, the section number and the date the regime took effect, because in Alberta the same provision had a different chapter letter before 29 August 2022 and the same court had a different name before 8 September 2022.

§ 01

The first question is not what the deadline is, but which Act you are on

Alberta splits at the front door. Private and municipal work runs on the Prompt Payment and Construction Lien Act1, RSA 2000, c P-26.4, which carries liens, the lien funds, the s 22 trust, prompt payment and adjudication. Provincial Crown public works run on the Public Works Act2, RSA 2000, c P-46, where there are no liens, no trust of the Crown's money, and delay is expressly not adjudicable. That single fact decides which clocks exist before the contract form is even opened.

The exclusion is statutory and it is explicit. PPCLA s 1.1 excludes "public works" as defined in the Public Works Act and agreements with the provincial Crown or a Crown agent. So on an Alberta government job a delay claimant below first tier has no lien, no trust of the Crown's money and no substantive right under the Public Works Act only the contract claim against the party above it, plus the labour and material payment bond if there is one.

Private and municipalProvincial Crown public works
StatutePPCLA, RSA 2000, c P-26.4Public Works Act, RSA 2000, c P-46
In force from29 August 2022 (Bill 37), Bill 30 (2024) amendments 1 April 2025Bill 30 (2024) prompt-payment provisions, contracts entered on or after 1 April 2025
LiensYes, 60 or 90 daysNone against provincial or federal Crown land
Trusts 22, but only on payments received after a Certificate of Substantial PerformanceNo trust of the Crown's money
Delay adjudicableBy consent, under the s 19 catch-all, no monetary capExpressly excluded, s 14.3(2)
The gateContractual notice, then lien, then limitations 14(3): 45 days, registered mail, statutory form

Jurisdictional layer. Both columns rest on secondary sources, no consolidated Alberta statutory text was read in original form for this corpus.

The Public Works Act exclusion is at s 14.3(2), added by Bill 30 (2024), the Service Alberta Statutes Amendment Act, 2024, in force 1 April 2025, and not to be confused with Bill 30 (2026), the Expedited 120-Day Approvals Act, whose status the corpus records as UNVERIFIED. Section 14.3(2) excludes from adjudication changes or delays to a construction schedule, completion or milestone dates, and disputes over the interpretation of relief events, designated changes in law, remedial actions and force majeure events. Every category an extension-of-time claim lives in is carved out by name. Nothing like it exists elsewhere in Canada.

What is left on a provincial job is s 14(3): notice within 45 days, by registered mail, specifying the nature and amount of the claim. It is enforced strictly. In Graham Construction and Engineering Inc v Alberta (Infrastructure)3, 2021 ABQB 184, decided by the Court of Queen's Bench, before the 8 September 2022 renaming, seventeen claimants who used the statutory form were paid and thirty-two, including Graham itself, were shut out. The claimants who succeeded were not the ones with the better delay case. They were the ones who used the form.

45daysPublic Works Act s 14(3) notice on a provincial Crown public work, registered mail, statutory form
17claimantsUsed the statutory form in Graham v Alberta (Infrastructure) and were paid
32claimantsDid not, including Graham, and were shut out

Character in law. The s 14(3) notice is a statutory precondition to the claim against the Crown, not a contractual condition precedent. It is not a limitation period either: it does not bar an action that is otherwise properly constituted against a private party up the chain, and it is not subject to the extension machinery in the Limitations Act. Practically, on a provincial job it does the work of all six clocks at once, and missing it cannot be repaired by the contract.

§ 02

Contractual notice: the entitlement clock, and it changes with the form

The contractual notice clock decides entitlement, and Alberta has no single answer to it because Alberta has no single form. On private work the default is CCDC 2 – 20204 GC 6.5.4, written notice of a claim for extension of the Contract Time within 10 Working Days of the commencement of the delay, with GC 6.6.1 requiring only "timely" notice for the money claim, with no fixed period. The public and municipal forms are stricter, differently shaped, or silent.

Form or provisionWhat the clock governsThe deadline
CCDC 2 – 2020 GC 6.5.4Time10 Working Days from the commencement of the delay
CCDC 2 – 2020 GC 6.6.1Money"Timely", no fixed period
CCDC 2 + ACA supplementary conditionsTimeUNVERIFIED, whether ACA SC CCDC2-2020 amends GC 6.5 could not be established
Public Works Act s 14(3)The whole claim45 days from last supply, by registered mail, statutory form
AB Infrastructure CM Agreement, Sch 19 Relief EventTime and moneyPrompt written notice, relief only above 10 Business Days and $10,000
AB Infrastructure CM Agreement, force majeureTime5 Business Days, either party may terminate if the event exceeds 120 days
AB Transportation Edition 16, s 1.2.39TimeAdjustment of completion dates. UNVERIFIED. No notice day count was extractable
City of Calgary GC v2.0, Art 6.2(5)TimeDesign Professional delay not considered unless more than 14 Days
City of Calgary GC v2.0, Art 7.2Time"Immediately" on becoming aware the Scheduled Operational Date will be missed
City of Calgary GC v2.0, Arts 4.5(1) / 5.3(1)Another contractor's defects1 Business Day to report. The City may remedy on 5 Business Days' notice

Form-default layer. Clause numbers and headings are verified against publicly available sources, operative wording is reconstructed from converging secondary sources, and the Alberta Infrastructure, Alberta Transportation and City of Calgary readings are recorded as single-source.

Three of those rows are traps rather than deadlines. The Alberta Infrastructure Construction Management Agreement5 Schedule 19 gives relief only for time impact beyond 10 Business Days and cost exceeding $10,000, hard de-minimis filters, which make sub-threshold Province-caused disruption uncompensable and push a construction manager toward global or cumulative-impact framing and straight into the usual global-claim objections. The City of Calgary Standard General Conditions6, Version 2.0 of 31 October 2022, do the same thing at Art 6.2(5): a contractor facing forty three-day design-response delays has, on the face of the clause, no extension at all, because no single delay exceeds 14 Days. And Art 7.2's "immediately" runs from awareness that the Scheduled Operational Date will be missed, not from the delay event, a clock that starts inside the contractor's own head.

The Alberta Transportation General Specifications, Edition 16 (2019)7 present the opposite problem. Sections 1.2.39 (adjustment of completion dates), 1.2.43 (seasonal or prolonged shutdown) and 1.2.57 (claims and dispute resolution) are identified, but UNVERIFIED. No notice-of-claim day count was extractable from Edition 16, and s 1.2.57 refers out to a 1997 government dispute document. On highway and bridge work the working assumption should be that a notice period exists and has not been located, serve early and in writing.

On CCDC 2 – 2020 the live Alberta question is the supplementary conditions. Across Canada supplementary conditions almost universally amend GC 6.5, and Ontario's industry-agreed package is the exception that leaves it alone. Alberta has no clean answer: UNVERIFIED whether the ACA SC CCDC2-20208 package amends GC 6.5 could not be established, and the corpus records this as the top Alberta verification gap. The file is distributed as a.docx, the site was unreachable, and a 2021 Advisory discussing Ready-for-Takeover and GC 5.4.5 holdback release is silent on GC 6.5, which is weak evidence rather than a finding. Read the executed supplementary conditions before relying on 10 Working Days. Separately, on Alberta industrial work there is no Alberta or Canadian standard EPC or EPCM form in common use, so CCDC 2 GC 6.5 will usually be irrelevant and there is no default extension-of-time clause to reason from at all.

Character in law. These are conditions precedent to entitlement, that is how the corpus classifies them and how Alberta pleadings run. But the supporting authority is thin, and the honest statement is a negative finding: there is no Alberta appellate authority beyond Dilcon Construction Ltd v ANC Developments Inc9, 2000 ABCA 223 treating a contractual notice-of-claim clause as a condition precedent, and CONFLICT that case may not be a notice case at all, a substantial source attributes to the same judgment an implied term of uninterrupted possession of the site, which is a prevention-adjacent holding and a stronger tool for a claimant than a strict-notice rule. Sources also reverse the party order in the style of cause, the neutral citation is agreed. Both readings may be correct, which would leave Alberta with no appellate condition-precedent authority at all.

Notice cuts both ways, and the reported Alberta consequence has fallen on an owner as readily as on a contractor. In Tempo Alberta Electrical Contractors Co Ltd v Man-Shield Construction Inc10, 2023 ABKB 44 the subcontractor obtained partial summary judgment of $678,261, and the general contractor's delay and staffing backcharge failed for want of written notice and an opportunity to cure. The delay damages themselves were expressly reserved for trial, which is consistent with the recorded finding that no Alberta decision has summarily dismissed or granted a delay claim itself: payment and lien claims go summarily in Alberta, delay claims do not.

§ 03

Adjudication: the clock that reopens after final payment, and the clock that does not exist

On private and municipal work the PPCLA, RSA 2000, c P-26.4 runs a payment cycle whose deadlines feed an adjudication referral, and the referral window is the most generous in Canada: up to 30 days after final payment under s 33.4, and available concurrently with litigation, since 1 April 2025. On provincial Crown public works there is no adjudication of delay at all, because Public Works Act s 14.3(2) excludes it. The two regimes have to be read separately, and a sentence about Alberta adjudication that does not say which side of the line it is on is unsafe.

Clock, private and municipal, PPCLA c P-26.4DeadlineSection
Proper invoice cycleAt least every 31 days, may be shortened but not lengtheneds 32.1(6)
Owner to contractor28 days from the proper invoices 32.2(1)
Owner's notice of dispute (Form 1)14 days from receipts 32.2(2)
Contractor to subcontractor7 days from receipt of the owner's payments 32.3(2)
Contractor to subcontractor where the owner has not paid35 days from the proper invoices 32.3(4)
Contractor's notice of non-payment (Form 2)7 days from the Form 1, or 35 days from the proper invoice. And it must contain an undertaking to adjudicate within 21 dayss 32.3(5)
Subcontractor to sub-subcontractor7 days / 42 daysss 32.5(1), 32.5(5)
Subcontractor notices (Forms 4, 5)7 days from a Form 2 or 3, or 42 days from the proper invoices 32.5(8)
Adjudication referralUp to 30 days after final payment, post-completion, and concurrent with litigations 33.4
Judicial review of a determination30 daysCONFLICT s 33.7 or s 33.8

Jurisdictional layer, private and municipal work only. Section numbers rest on secondary sources, no consolidated Alberta statutory text was read in original form.

Two features of that table are unusual enough to change strategy. The first is the s 32.3(5) notice of non-payment, which must carry an undertaking to adjudicate within 21 days, the notice is not a holding position, it is a commitment to a forum. The prescribed notices themselves are Forms 1 to 5, and UNVERIFIED the corpus does not resolve whether they sit in the Prompt Payment and Construction Lien Forms Regulation, Alta Reg 51/2002, or in Alta Reg 23/202211. Check the regulation before serving.

The second is s 33.4. A referral available up to 30 days after final payment, and running concurrently with litigation, means Alberta private-sector adjudication is not the interim, in-project, cash-flow device it is elsewhere. It is a late-crystallising delay claim's most open door in the country, and the reason the one-sentence orientation for Alberta is that it is the best Canadian forum for a late-crystallising private delay claim and the worst for a public one. Delay itself is adjudicable on private and municipal work by consent, under the s 19 catch-all. The processes do not collapse into each other: Welcome Homes Construction Inc v Atlas Granite Inc12, 2024 ABKB 301 holds that lien rights and adjudication are independent, and that a determination may be filed as an order of the court.

On the Public Works Act side, contracts entered on or after 1 April 2025 have their own payment clocks: proper invoices every 31 days, Crown to contractor 28 days, contractor to subcontractor 35 days, subcontractor to sub-subcontractor 42 days, all measured from the proper invoice. Two differences bite. The contractor must pay undisputed amounts at 35 days even if the Province has not paid it, and the PPCLA's notice-of-non-payment "stop the clock" mechanism is not available. So the payment clocks are tighter and the defensive machinery is thinner. And none of it gets a delay dispute to an adjudicator, because s 14.3(2) has already excluded it.

A monetary cap applies to Public Works Act adjudication only. There is no cap on PPCLA private-sector adjudication. The figure is CONFLICT: commentary glosses the cross-reference to Court of Justice Act13 (Alberta) s 9(1)(i) as $200,000, while the prescribed Alberta Court of Justice civil limit has been $100,000 since 1 August 2023, the Provincial Court having become the Alberta Court of Justice on 1 April 2023. Read s 9(1)(i) before printing either number. Two further recorded negative findings frame how much of this is untested: there is no reported Alberta judicial review of an adjudicator's determination, and the judicial-review section itself is CONFLICT as between s 33.7 and s 33.8, though the 30-day period is agreed. The regime is developed at prompt payment and adjudication in Alberta.

Character in law. The payment deadlines are statutory preconditions to a remedy they create the proper-invoice and notice architecture that a referral depends on, rather than barring the underlying claim. The 30-day judicial-review period is a procedural rule. None of them extends or preserves a limitation period, and none of them exists on a provincial Crown public work.

§ 04

Liens and holdback: 60 days, 90 days, $700, and 180 days to perfect

The lien clock decides security, and it runs only on private and municipal work under the PPCLA, RSA 2000, c P-26.4. There are no liens against provincial or federal Crown land. The period is category-dependent: 60 days generally, 90 days for an improvement to an oil or gas well or well site, and 90 days for concrete other than ready-mix. A registered lien then has to be perfected within 180 days.

ClockDeadline
Lien registration, general60 days
Lien registration, oil or gas well or well site90 days
Lien registration, concrete, excluding ready-mix90 days
Minimum lien claim$700
Enforcement action plus certificate of lis pendens180 days from registration
Non-general-contractor claimants to reach the major lien fund60 days from the Certificate of Substantial Performance being posted
Major lien fund retention60 days after the CSP, or after completion if there is none, 90 days for oil and gas and for concrete
Minor lien fund retention60 days after completion of the prime contract, 90 days for the special categories
Progressive holdback release, s 24.1Annually, where the contract exceeds $10,000,000 and runs more than one year without a milestone regime. UNVERIFIED notice mechanics

Jurisdictional layer, private and municipal work only. Day counts and thresholds rest on secondary sources. No consolidated Alberta statutory text was read in original form.

Two structural points matter more than the numbers. The first is that the lien fund is not the trust. The major and minor lien funds are owner-held security, each split into Part A, the 10 per cent statutory holdback, and Part B, the amount payable. The trust is a separate mechanism at PPCLA s 22, and it arises only on payments received after a Certificate of Substantial Performance ATB Financial v DLM Oilfield Enterprises Ltd14, 2020 ABQB 562, decided under the Builders' Lien Act15, RSA 2000, c B-7, as it then was. A delayed project that is terminated or abandoned before substantial performance has no trust at all, which is precisely the fact pattern delay claims arise in.

The second is what a delay claim can actually put into the lien. Krupp Canada Inc v JV Driver Projects Inc16, 2014 ABQB 259, again under the Builders' Lien Act, RSA 2000, c B-7, holds that delay damages form part of a lien only where they relate directly to the work that is the subject of the lien: lost productivity on the liened project yes, inability to work elsewhere no. CONFLICT the corpus records disagreement on what Krupp holds, one Alberta source reading it as permitting lienable delay damages and a substantial international source indexing the same decision for the opposite proposition, and the later, narrower PME Inc v Enerkem Alberta Biofuels LP, 2021 ABQB 889 does not cite it. There is no appellate resolution, so the line is factual rather than categorical. Note the chapter letter on both: every Alberta lien and delay authority before 29 August 2022 cites c B-7, and a search that only indexes c P-26.4 silently drops most of the useful material.

The holdback clock is separate from the lien clock and easy to miss on a long delayed project. PPCLA s 24.1 provides for progressive release, by default annually, where the contract exceeds $10,000,000 and runs more than one year without a milestone regime, but UNVERIFIED the notice mechanics could not be established: whether a notice of intention to release must be published or served, and on whom, and whether each release starts a fresh 60-day lien period for the released phase. On a multi-year Alberta project that gap sits directly on top of the lien clock. The security analysis is developed at liens, the lien fund and trust in Alberta.

Character in law. Lien registration is a statutory precondition to the existence of the security, not a limitation period on the debt: losing the lien does not lose the contract claim, and it does not lose an adjudication referral, which Welcome Homes Construction Inc v Atlas Granite Inc, 2024 ABKB 301 confirms runs independently. The 180-day perfection requirement operates as a hard extinguishing period on the registered lien itself.

§ 05

Limitation: two years, ten years, and a floor the contract cannot lower

The Limitations Act17 (Alberta) sets a two-year basic period running from the three-limb discovery test in s 3(1)(a), which includes, distinctively, whether the injury "warrants bringing a proceeding", and a ten-year ultimate period. The parties may agree to extend a limitation period under s 7(1). They may not shorten one: s 7(2) makes a reduction clause invalid. That is the opposite of the Ontario position, where a limitation period in the supplementary conditions can lawfully be shortened, and it is one of the sharpest differences a practitioner crossing the border will meet.

ClockDeadline
Basic period2 years from the s 3(1)(a) three-limb discovery test, including whether the injury warrants bringing a proceeding
Ultimate period10 years from when the claim arose, running from the discrete, first actionable breach
Contractual variationExtension only, s 7(1). A clause shortening the period is invalid under s 7(2)
ArbitrationLimitation periods apply, and filing in court does not stop time

Jurisdictional layer. Section numbers and day counts rest on secondary sources, no consolidated Alberta statutory text was read in original form.

The ultimate period is where a long-running delayed project gets caught. In Living Waters v UFA18, 2025 ABKB 319, recorded in the corpus as SINGLE-SOURCE and expressly UNVERIFIED, labels that should be carried in print rather than dropped, and of which the corpus records only this short style of cause, the ten-year period was held to run from the discrete, first actionable breach rather than from a continuing or later-crystallising state of affairs. On a project where the first defective instruction, first denied extension or first suspension is years earlier than the final account dispute the claim is really about, that characterisation can extinguish the claim while the parties are still negotiating.

The arbitration point catches people who think they have started something. In Lafarge Canada Inc v Edmonton (City)19, 2013 ABCA 376 the Court of Appeal held that limitation periods apply to arbitration and that filing in court does not stop time running for arbitration purposes. Where the contract has an arbitration clause and the claimant issues a statement of claim as a protective step, the protective step protects the wrong proceeding.

Two absences are worth stating flat. There is no Alberta equivalent of Ontario's invoice-and-default accrual rule for construction claims, so an Alberta claimant cannot borrow the Ontario accrual analysis. And Alberta's discovery test, unlike a pure knowledge test, imports a proportionality judgment through the "warrants bringing a proceeding" limb, which is a reason to date the clock from the record rather than from argument. The accrual analysis is developed at limitation periods in Alberta.

Character in law. These are true limitation periods. They bar the remedy rather than the entitlement, they are the only clock on this page the parties can lawfully extend by agreement, and they are the only one the parties cannot lawfully shorten.

§ 06

After the award: 30 days, and the stamp that starts it

Two arbitration clocks run after a delay dispute has been decided. Permission to appeal is required and is available on a question of law only, under Arbitration Act20 (Alberta) s 44(2) and (2.1). The appeal must be commenced within 30 days of receipt of the award under s 46(1), and in Frog Lake First Nation v 2250657 Alberta Ltd21, 2025 ABKB 206, that period was held to run to the clerk's "FILED" stamp rather than to the moment of submission. Filing late in the day at the end of the period is not the same as filing.

Expect the permission application to fail on a schedule finding. In Quanta Canada Holdings II ULC v Bremar Construction Ltd22, 2024 ABKB 317: a Calgary duct-bank project with an $8,137,116 delay-and-defects claim permission to appeal was refused because delay causation is mixed fact and law, so no question of law arises under s 44(2). Arbitrating an Alberta delay dispute is choosing finality on the schedule findings, and the corpus records that no Alberta decision from 2020 to 2026 set aside or varied an arbitral award on a construction delay finding: every located Alberta construction-arbitration decision in the window is pro-finality. Forum choice is developed at arbitration and forum in Alberta.

Character in law. The 30-day appeal period is a procedural rule with a statutory source. It does not preserve anything: an award that is not appealed within it is final on the delay findings, whatever the limitation position on the underlying claim.

§ 07

The clock nobody diarises: dismissal for delay under rules 4.31 and 4.33

Alberta dismisses construction actions for being prosecuted too slowly, and this is the clock that ends claims which met every earlier deadline. The Alberta Rules of Court23 run two mechanisms. Rule 4.31 permits dismissal for inordinate and inexcusable delay causing significant prejudice, it is discretionary, and prejudice is presumed on long delay. Rule 4.33 is the drop-dead rule: dismissal where three or more years pass without a significant advance in the action, and it is mandatory once triggered.

The authority is recent and it is a construction case. Peters v Countryside Masonry Inc24, 2025 ABKB 713 struck a construction claim of approximately $4 million for inordinate delay, and the answer to the defence every construction claimant reaches for is that "construction is complex" is not an excuse. A schedule dispute with thousands of documents, several third parties and an expert on each side is exactly the kind of action that drifts past three years without a significant advance, and the rule does not make an allowance for it.

None of the six Alberta clocks saves any of the others. And in Alberta the sixth catches people who did the first five correctly.

Nothing in the Alberta forum will manage the pace for a claimant. The corpus records it flat: Alberta has no specialist construction list, no construction judges and no construction practice note, and the Commercial List is insolvency-only. A construction delay action is a general civil action, carried at whatever pace the parties carry it.

The trial-preparation clocks compound the same problem, because they are sequenced rather than dated. Expert evidence is served in Form 25 under rr 5.34 and 5.35, in sequence: primary burden first, then rebuttal, then surrebuttal limited to new issues with reasonable notice of admissibility objections under rr 5.36 and 5.37 and pre-trial questioning of an expert only by agreement or court order. Under r 8.4 reports are ordinarily exchanged before the trial date is set. And r 8.16(1) limits a party to one expert per subject matter unless the Court orders otherwise, with r 8.16(2) allowing the Court to direct which of several affiliated corporate parties may call the expert. The corpus records r 8.16 as SINGLE-SOURCE and says to verify it against the Rules. Whether schedule and quantum are one subject matter or two is a decision to take early, not at the pre-trial conference. Two further absences are recorded: Alberta has no rule imposing a separate signed expert certification of duty to the court, and no fixed day count for service of expert reports.

Character in law. These are procedural rules of court, not limitation periods and not conditions precedent. Rule 4.31 is discretionary and rule 4.33 is mandatory once its three-year trigger is met, and neither is affected by the strength of the underlying delay claim, the size of it, or compliance with any statutory or contractual deadline that came before.

§ 08

Six clocks, and none of them saves any of the others

The clocks are independent, they run from different triggers, and satisfying one is not evidence of having satisfied another. Contractual notice decides entitlement, and on a provincial job the Public Works Act s 14(3) notice replaces it and is stricter. Adjudication decides forum, and only on private and municipal work. The lien decides security, at 60 or 90 days. The holdback decides cash flow, annually only above $10,000,000 and one year. Limitation decides whether the claim can be sued on, and cannot be shortened by contract in Alberta. Prosecution decides whether the claim already filed survives.

The interactions are where the losses happen, and the following are inferences drawn from the clocks as tabulated rather than propositions any Alberta court has stated in these terms. A Public Works Act s 14(3) notice runs 45 days from last supply, while a contractual delay notice runs 10 Working Days from the commencement of the delay two unrelated triggers, one keyed to the end of the work and one to an event during it, so on a provincial job neither notice satisfies the other and serving the contractual notice on time tells you nothing about whether the statutory notice is still open. A PPCLA s 33.4 referral is available up to 30 days after final payment, but the Limitations Act two-year period is not extended by the availability of that forum, the most open adjudication window in Canada can sit inside a limitation period that has already run. And a lien that expires does not take the contract claim with it, while a limitation period that expires takes everything.

Two citation checks before any of this is researched further, because both silently break Alberta research. The Court of Queen's Bench became the Court of King's Bench on 8 September 2022 (mid-year, not at the year boundary) so Alberta 2022 carries both 2022 ABQB nnn and 2022 ABKB nnn, and an ABQB citation dated 2023 or later is almost certainly a transcription error for ABKB that should not be propagated, Masters and Masters in Chambers became Applications Judges in the same period, which matters because much of the Alberta lien-and-delay jurisprudence is Master-level. And the PPCLA is the renamed Builders' Lien Act, RSA 2000, c B-7, renamed by Bill 37 in force 29 August 2022, so every Alberta lien and delay authority before that date, Krupp, PME v Enerkem, ATB Financial v DLM among them, is cited to c B-7, and c P-26.4 is correct only from 29 August 2022.

The point to carry off this page is the one that has no analogue anywhere else in this cluster. A delay claim in Alberta can serve every contractual notice on time, meet the 45-day statutory notice on a provincial job, register and perfect its lien, refer to adjudication inside the most generous window in the country, and issue well inside both the basic and ultimate limitation periods. And then be struck under rule 4.33 because three years passed without a significant advance. Every other clock on this page is a deadline for doing something. The sixth is a deadline for continuing to do it, and it is the one Alberta construction claims die on.

Notes

Sources and authorities

24 cited
  1. *
    Verification, unless noted

    No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.

  2. 1
    Prompt Payment and Construction Lien ActRSA 2000, c P-26.4 (Alberta), in force under that name from 29 August 2022

    Governs private and municipal construction in Alberta, liens, the lien funds, the s 22 trust, prompt payment and adjudication. Section 1.1 excludes public works as defined in the Public Works Act and agreements with the provincial Crown or a Crown agent. Amendments under Bill 30 (2024) came into force 1 April 2025.

    Chercher sur CanLII

  3. 2
    Public Works ActRSA 2000, c P-46 (Alberta)

    Governs Alberta provincial Crown public works. Section 14(3) requires notice of a claim within 45 days, by registered mail, specifying nature and amount. Section 14.3(2), added by Bill 30 (2024) and in force 1 April 2025, excludes from adjudication changes or delays to a construction schedule, completion or milestone dates, and disputes over relief events, designated changes in law, remedial actions and force majeure events.

    Chercher sur CanLII

  4. 3
    Graham Construction and Engineering Inc v Alberta (Infrastructure)2021 ABQB 184, Court of Queen's Bench of Alberta

    Strict compliance with the Public Works Act s 14(3) notice, 45 days, by registered mail, specifying the nature and amount of the claim, is mandatory on a provincial public work. Seventeen claimants who used the statutory form were paid, thirty-two, including Graham, were shut out.

    Chercher sur CanLII

  5. 4
    CCDC 2 – 2020 Stipulated Price ContractCCDC 2 – 2020, GC 6.5 Delays, GC 6.5.4 and GC 6.6.1

    GC 6.5.4 requires notice in writing of a claim for extension of the Contract Time within 10 Working Days of the commencement of the delay. GC 6.6.1 requires timely notice of a claim for money, with no fixed period. CCDC 2 – 2020 remains current, no 2025 or 2026 update exists.

  6. 5
    Alberta Infrastructure Construction Management AgreementAlberta Infrastructure CM Agreement, Schedules 19, 20 and 21

    Schedule 19 Relief Events require prompt written notice, mitigation and records, and give relief only for time impact beyond 10 Business Days and costs exceeding $10,000. Force majeure requires notice within 5 Business Days and either party may terminate if the event exceeds 120 days. Recorded as single-source, the Agreement itself was not read.

  7. 6
    City of Calgary Standard General ConditionsVersion 2.0, 31 October 2022, Articles 4.5(1), 5.3(1), 6.2(5) and 7.2

    Article 6.2(5) provides that an extension request arising from delay by the City's Design Professional will not be considered unless the delay is more than 14 Days. Article 7.2 requires immediate notice on becoming aware the Scheduled Operational Date will not be met. Articles 4.5(1) and 5.3(1) require another contractor's defects to be reported within one Business Day. Single-source, one reading.

  8. 7
    Alberta Transportation General Specifications and Specification Amendments for Highway and Bridge Construction, Edition 16 (2019)Edition 16 (2019), ss 1.2.39, 1.2.43 and 1.2.57

    Section 1.2.39 governs adjustment of completion dates for force majeure events, differing site conditions and Department-caused delays, s 1.2.43 is a seasonal or prolonged shutdown clause, s 1.2.57 refers claims and dispute resolution out to a 1997 government document. No notice-of-claim day count was extractable and the reading is single-source.

  9. 8
    ACA SC CCDC2-2020, Alberta Construction Association supplementary conditionsACA SC CCDC2 – 2020, Alberta Construction Association

    Whether the package amends GC 6.5 Delays could not be established and is recorded as the top Alberta verification gap. The file is distributed as a.docx and the site was unreachable. A 2021 Advisory discusses Ready-for-Takeover and GC 5.4.5 holdback release and is silent on GC 6.5, which is weak evidence rather than a finding.

  10. 9
    Dilcon Construction Ltd v ANC Developments Inc2000 ABCA 223, Court of Appeal of Alberta

    Recorded in the corpus as the Alberta authority for strict enforcement of a contractual notice provision. A conflict is recorded: a substantial source attributes to the same judgment an implied term of uninterrupted possession of the site, a prevention-adjacent holding. Sources also reverse the party order in the style of cause. The neutral citation is agreed.

    Chercher sur CanLII

  11. 10
    Tempo Alberta Electrical Contractors Co Ltd v Man-Shield Construction Inc2023 ABKB 44, Court of King's Bench of Alberta

    Partial summary judgment of $678,261 on the payment claim. The general contractor's delay and staffing backcharge failed for want of written notice and an opportunity to cure, delay damages were expressly reserved for trial.

    Chercher sur CanLII

  12. 11
    Prompt Payment and Construction Lien Forms RegulationAlta Reg 51/2002 or Alta Reg 23/2022. The corpus does not resolve which

    Carries the prescribed prompt-payment notices, Forms 1 to 5. The corpus records it as unverified whether the forms sit in Alta Reg 51/2002 or in Alta Reg 23/2022.

  13. 12
    Welcome Homes Construction Inc v Atlas Granite Inc2024 ABKB 301, Court of King's Bench of Alberta

    Lien rights and adjudication are independent processes, and an adjudicator's determination may be filed as an order of the court.

    Chercher sur CanLII

  14. 13
    Court of Justice ActCourt of Justice Act (Alberta), s 9(1)(i), chapter number not recorded in the corpus

    Cross-referenced by the Public Works Act adjudication regime as the source of the monetary cap on adjudication of a provincial public works dispute. Commentary reads the cross-reference as $200,000, the prescribed Alberta Court of Justice civil limit has been $100,000 since 1 August 2023. The corpus records the figure as unresolved.

  15. 14
    ATB Financial v DLM Oilfield Enterprises Ltd2020 ABQB 562, Court of Queen's Bench of Alberta

    The statutory construction trust arises only on payments received after a Certificate of Substantial Performance. A project terminated or abandoned before that certificate has no trust at all.

    Chercher sur CanLII

  16. 15
    Builders' Lien ActRSA 2000, c B-7 (Alberta), the name and chapter before 29 August 2022

    The predecessor name and chapter of the Prompt Payment and Construction Lien Act. Renamed by Bill 37, the Builders' Lien (Prompt Payment) Amendment Act, 2020, in force 29 August 2022, with the chapter letter changing from B-7 to P-26.4. Every Alberta lien and delay authority before that date cites c B-7.

    Chercher sur CanLII

  17. 16
    Krupp Canada Inc v JV Driver Projects Inc2014 ABQB 259, Court of Queen's Bench of Alberta

    Delay damages form part of a lien only where they relate directly to the work that is the subject of the lien, lost productivity on the liened project yes, inability to work elsewhere no. The corpus records a conflict on the holding and there is no Alberta appellate resolution.

    Chercher sur CanLII

  18. 17
    Limitations ActLimitations Act (Alberta), the corpus does not record a chapter number

    Section 3(1)(a) sets a two-year basic period running from a three-limb discovery test that includes whether the injury warrants bringing a proceeding, and a ten-year ultimate period. Section 7(1) permits the parties to agree to extend a limitation period, s 7(2) makes an agreement purporting to shorten one invalid.

    Chercher sur CanLII

  19. 18
    Living Waters v UFA2025 ABKB 319, Court of King's Bench of Alberta, recorded in the corpus as single-source and unverified

    The ten-year ultimate limitation period runs from the discrete, first actionable breach rather than from a continuing or later-crystallising state of affairs. The corpus records only this short style of cause. The full party names were not captured.

    Chercher sur CanLII

  20. 19
    Lafarge Canada Inc v Edmonton (City)2013 ABCA 376, Court of Appeal of Alberta

    Limitation periods apply to arbitration, and commencing a court action does not stop time running for the purposes of an arbitration.

    Chercher sur CanLII

  21. 20
    Arbitration ActArbitration Act (Alberta), the corpus does not record a chapter number

    Section 44(2) and (2.1) permit an appeal from an arbitral award on a question of law with permission. Section 46(1) sets 30 days from receipt of the award to commence the appeal.

  22. 21
    Frog Lake First Nation v 2250657 Alberta Ltd2025 ABKB 206, Court of King's Bench of Alberta

    The 30-day period to commence an appeal from an arbitral award runs to the clerk's FILED stamp, not to the moment of submission. The court's inherent discretion to extend is exercised sparingly and only in the most obvious cases of unfairness, and bureaucratic filing delay is not enough.

    Chercher sur CanLII

  23. 22
    Quanta Canada Holdings II ULC v Bremar Construction Ltd2024 ABKB 317, Court of King's Bench of Alberta

    Permission to appeal an arbitral award on an $8,137,116 delay-and-defects claim refused: delay causation is mixed fact and law, so no question of law arises under Arbitration Act s 44(2).

    Chercher sur CanLII

  24. 23
    Alberta Rules of CourtAlberta Rules of Court, rr 4.31, 4.33, 5.34, 5.35, 5.36, 5.37, 8.4, 8.16

    Rule 4.31 permits dismissal for inordinate and inexcusable delay causing significant prejudice, with prejudice presumed on long delay. Rule 4.33 is the drop-dead rule, dismissal where three or more years pass without a significant advance, mandatory once triggered. Rules 5.34 to 5.37 and 8.4 govern expert reports and sequencing, r 8.16(1) limits a party to one expert per subject matter unless the Court orders otherwise, and is recorded as single-source.

  25. 24
    Peters v Countryside Masonry Inc2025 ABKB 713, Court of King's Bench of Alberta

    A construction claim of approximately $4 million was struck for inordinate delay in prosecution. That construction litigation is complex is not an excuse for failing to advance the action.

    Chercher sur CanLII

General information, not legal advice. Reviewed 9 août 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou…

Each issue links to the full articles in the Storia Library.

Les délais d'une réclamation pour retard en Alberta · Storia