Notice and time bars in Canada
Canadian courts enforce construction notice clauses as conditions precedent, and the owner need not prove prejudice. Under CCDC 2 – 2020 GC 6.5.4 the contractor has 10 Working Days from the commencement of the delay not from its effect, to give Notice in Writing, and an insufficient notice is treated as no notice at all.
Disponible en anglais seulement Cet article n'a pas encore été traduit. Les délais, le droit à réclamation et la procédure décrits ici touchent au droit, et une traduction automatique constituerait un risque de crédibilité plutôt qu'une commodité : l'original anglais est donc servi intégralement jusqu'à ce qu'une traduction révisée existe.
At a glance
- Procedure
- Canada, common-law provinces
- CCDC 2 – 2020, GC 6.5 and GC 6.6
- Excludes Quebec
Key facts
- 01
The short answer
Notice is where a Canadian delay claim dies more often than at any other point. On procedure Canada sits close to England and is strict, on one point it is stricter. The owner does not have to show it was prejudiced by the late or missing notice.
- 02
The main-contract clock
CCDC 2 – 2020 GC 6.5.4, Notice in Writing of the cause of delay to the Consultant not later than 10 Working Days after the commencement of the delay. Not from awareness, not from the effect. One notice suffices for a continuing cause.
- 03
The money clock
CCDC 2 – 2020 GC 6.6.1, "timely" Notice in Writing of intent to claim, with no fixed period. Time and money are separate notices on the same form.
- 04
The subcontract clock
The CCA 1 subcontract runs 7 Working Days three fewer than the main contract. A general contractor is therefore administering two unaligned clocks.
- 05
Read the SCs first
Supplementary conditions almost universally amend GC 6.5, and usually tighten it. The exception is the OAA/OGCA Agreed-to Recommended Supplementary Conditions for CCDC 2-2020, which contain no supplementary condition amending GC 6.5 at all.
- 06
Sufficiency, not just timing
Ross-Clair, 2016 ONCA 205, a claim submission must in substance prove the claim in the submission itself. An inadequate claim is not a late claim, it is a non-existent claim.
- 07
What it costs
Elite Construction CAD 4.1M in delay and extras dismissed on summary judgment for a missed 10-working-day notice, affirmed on appeal.
- 08
Verification status
No Canadian judgment and no consolidated statutory text was read in original form for this page. Every citation and section number rests on independent secondary sources and needs checking before pleading.
Canada is the strictest of the major common-law construction jurisdictions on notice, and notice is the element on which Canadian delay claims most often die. On procedure Canada sits close to England. On one point it goes further. A notice provision can bar a claim even without express "failing which" wording, and the owner does not have to prove it was prejudiced by the failure.
The main form is the CCDC 2 – 2020 Stipulated Price Contract1, still current as at August 2026. There is no 2025 or 2026 update to CCDC 2. It runs two separate notice clocks: GC 6.5.4 for time and GC 6.6.1 for money. The time clock is the harsh one, because it starts at the commencement of the delay rather than at the contractor's awareness of it.
The doctrinal anchor is Technicore Underground Inc v Toronto (City)2 2012 ONCA 597: strict compliance, and the owner need not prove prejudice. An English or Australian practitioner arriving on a Canadian job should assume that the arguments that soften a time bar elsewhere. The owner knew anyway, the owner suffered nothing, the clause does not say the claim is lost, are weaker here than at home.
This page covers Canada's common-law provinces. Quebec is civil law and is carved out entirely: it has no time at large, no concurrent-delay doctrine, a three-year prescription running from fin des travaux, and art 2884 C.c.Q. forbidding any conventional prescription period at all. Start instead at notice and time bars in Quebec.
Why notice is where a Canadian delay claim dies
A Canadian delay claim is lost at the notice gate more often than at causation, quantum or expert evidence. The reason is structural: notice compliance is a condition precedent, so it can be decided on the documents without trying the delay, and Canadian courts have shown a real appetite to do exactly that. The largest reported loss is Elite Construction Inc v Canada (Attorney General)3 CAD 4.1M, gone on summary judgment.
There is no statutory relief. No Canadian province or territory has a statute addressing construction delay claims as such. No statutory extension-of-time entitlement, no statutory concurrency rule, no statutory delay-analysis standard. Nor does this corpus record any Canadian statutory power to declare a notice-based time bar unfair and of no effect, a power that exists in parts of Australia. Canada is contract and common law all the way down.
The claim was never tested on its merits. Nobody decided whether the contractor was in fact delayed, by whom, or for how long. That is the characteristic shape of a Canadian delay loss.
The CCDC 2 – 2020 clocks: 10 Working Days for time, "timely" for money
CCDC 2 – 2020 imposes two distinct notices. GC 6.5.4 requires Notice in Writing of the cause of delay to the Consultant not later than 10 Working Days after the commencement of the delay, and one Notice suffices for a continuing cause. GC 6.6.1 requires "timely" Notice in Writing of intent to claim money, with no fixed period. Giving one does not give the other.
Two features of GC 6.5.4 catch experienced people out.
The clock runs from commencement of the delay, not from awareness of it. Compare the trigger in the forms a visiting practitioner is likely to know: FIDIC 2017 runs from when the Party became aware or should have become aware. JCT 2024 from when delay becomes "reasonably apparent". NEC4 from when the Contractor becomes aware of the event. Under CCDC 2 – 2020 the contractor can be time-barred before it knew there was anything to notify. A late supplier shipment, a soil condition encountered by another trade, an approval that quietly went unissued. Each starts the clock on the day the delay begins, not on the day its effect surfaces in the programme.
"Working Days" is a defined term excluding Saturdays, Sundays and holidays, so the calendar window is roughly two weeks. That sounds generous, and it is not, once the first point is applied to it.
There is a third mechanic worth knowing. GC 6.5.5 provides that where the Consultant fails to furnish instructions and no schedule was made under ¶2.2.12 of GC 2.2, no request for extension may be made until 10 Working Days after demand for instructions. A waiting period, not a deadline, and it presupposes that a demand was actually made.
| Instrument | Time notice | Money notice |
|---|---|---|
| CCDC 2 – 2020 | GC 6.5.4, 10 Working Days after the commencement of the delay, to the Consultant. One notice for a continuing cause | GC 6.6.1, "timely" Notice in Writing of intent to claim, no fixed period |
| CCDC 2 – 2020, GC 6.5.5 | No request for extension for the Consultant's failure to instruct until 10 Working Days after demand for instructions | – |
| CCA 1 subcontract | 7 Working Days, three fewer than the main contract | Not recorded in this corpus |
| CCDC 2 + OAA/OGCA supplementary conditions | Unchanged, no SC amends GC 6.5 | SC 6.6.1 adds "and the Consultant" to the recipients |
Layer: form-default. These are the printed positions of the standard documents, not the position on any executed contract, supplementary conditions almost universally amend GC 6.5, and the executed contract governs. This row set rests on secondary sources. The contract text was not read in original form for this corpus.
The CCA 1 subcontract clock is 7 Working Days, three fewer than the main contract
The CCA 1 – 2021 subcontract4 gives the subcontractor 7 Working Days, against the 10 Working Days that CCDC 2 – 2020 GC 6.5.4 gives the general contractor under the main contract. The gap is deliberate. It exists so the general contractor can receive, digest and pass on a subcontractor's delay notice inside its own window. But it is routinely missed by both sides.
For the subcontractor, the practical consequence is that any diary rule built from the main contract is three working days too slow. Roughly a calendar week separates the two clocks, and it is the week in which a subcontract delay claim is most often lost.
For the general contractor, the consequence is administrative: a project runs at least two unaligned notice clocks in opposite directions, plus the "timely" money notice under GC 6.6.1, which has no fixed period at all and therefore no diary entry to set. A contractor who treats "the notice period" as a single number on a CCDC project is running the wrong system.
Read the supplementary conditions before the general conditions
Analysing a Canadian delay claim from the printed general conditions alone is a form-default exercise, not an answer. GC 6.5 is almost universally amended by supplementary conditions on real projects, and the amendments usually tighten the notice regime rather than loosen it. Owner-drafted packages are where shortened contractual limitation periods and no-damage-for-delay clauses live, and no Canadian statute prohibits the latter, federally, provincially or territorially.
There is one significant exception, and it is the interesting kind. The OAA/OGCA Agreed-to Recommended Supplementary Conditions for CCDC 2-20205 current version 15 March 2024 (R00), issued with OAA Practice Tip PT.23.11, contain no supplementary condition amending GC 6.5 at all. The 10 Working Days notice, the causes of delay and the delay-cost recovery all stand unamended in the leading Ontario industry-negotiated package.
The significance is the absence. The two bodies that negotiate the Ontario market standard looked at GC 6.5 and left it alone. What the package does touch nearby matters too: SC 6.6.1 clarifies the money-claim notice and adds "and the Consultant" to the recipients, so on an OAA/OGCA-supplemented CCDC 2 a GC 6.6 money notice must go to the Consultant as well as the Owner. A contractor who notices only the Owner has not complied.
The working rule for any Canadian project: find the supplementary conditions, read GC 6.5 and GC 6.6 as amended, and build the diary from that text, never from the printed form and never from memory of the last job.
Notice as a condition precedent. And the owner need not prove prejudice
Canadian courts enforce contractual notice provisions as conditions precedent to maintaining the claim in court. Doyle Construction Co v Carling O'Keefe Breweries of Canada Ltd6 1988 CanLII 2844 (BCCA) states the proposition, and the rule is pan-Canadian across the common-law provinces. But the strictness of enforcement is not uniform, and the divergence is worth pleading. Ontario is strict: a claim can be barred without proof of prejudice to the owner. British Columbia is purposive instead of strict: BC courts ask what the notice clause was for, and whether the owner was deprived, in substance and in good time, of the opportunity the clause exists to protect, namely to investigate, mitigate, price or substitute (W A Stephenson Construction (Western) Ltd v Metro Canada Ltd7, (1987), 27 CLR 113 (BCSC), and Foundation Co of Canada Ltd v United Grain Growers Ltd8, (1997), 91 BCAC 254 (BCCA), and CIMIC, discussed further below), subject to Northland Kaska's limit, also discussed below, that the contractor's intention to claim must still have been unequivocal. And BC does not apply one notice answer across a whole contract: a delay claim can die on notice while a differing-conditions or quantity claim on the same facts survives. A BC notice defence is a materially weaker starting position for an owner than the same defence in Ontario, and a claimant should say so explicitly rather than concede the point by silence.
★ Alberta should not be added to that list without a qualification. The Alberta authority is Dilcon Construction Ltd v ANC Developments Inc9 2000 ABCA 223, carried in the corpus for strict notice, but CONFLICT, because a substantial source attributes to the same judgment an implied term that the owner will give the contractor uninterrupted possession of the site, a prevention-adjacent holding indexed under possession rather than notice. Both may be true of the same judgment. Since no Alberta appellate authority beyond 2000 ABCA 223 treating a notice-of-claim clause as a condition precedent was located, ★ Alberta may have no appellate condition-precedent authority at all, and the party order in the style of cause is itself CONFLICT between sources, the neutral citation being the only agreed element.
Two features make Canada harsher than England on the same facts.
First, the clause does not need to spell out the consequence. Corpex (1977) Inc v The Queen in right of Canada10 1982 CanLII 213 (SCC) holds that a notice provision can bar a claim even without express "failing which" language. The drafting argument that a bare "shall give notice within X days" imposes an obligation but no forfeiture is a much weaker argument in Canada than it is in London.
Second, prejudice is irrelevant. Technicore, 2012 ONCA 597, requires strict compliance and holds that the owner need not prove prejudice. This is the single most important thing for a visiting practitioner to absorb. The instinct to argue that the owner knew, that the owner participated in the recovery meetings, that the owner suffered nothing it would not have suffered anyway. That instinct is worth very little at the Canadian notice gate.
The corpus records three recognised exceptions: actual knowledge, waiver, and rights independently preserved under the applicable provincial Construction Act. All three are fact-heavy and none is reliable.
Sufficiency, not just timing. An inadequate claim is a non-existent claim
Timing is only half the gate. The other half is content, and it is the half that surprises people. A notice served inside the window but thin on causation, schedule impact and quantum basis may be treated not as a defective notice but as no notice at all. The authority is Ross-Clair v Canada (Attorney General)11 2016 ONCA 205, (2016) 347 OAC 177, an Ontario Court of Appeal decision on a standard-form government contract, reviewed on a correctness standard.
The contractor had submitted a claim for extras of $1,437,976. The owner did not say the claim was late. It said the supporting information was insufficient. The Court of Appeal held that a claim submission must contain sufficient particulars. The contractor must in substance prove its claim to the other side in the submission itself. And that sufficiency is a threshold requirement, so insufficient detail extinguishes the right to claim entirely.
Failure to provide sufficient information within 30 days after completion is a failure to provide notice of the claim at all.
The distinction is worth stating flatly, because it changes what a notice has to contain. An inadequate claim is not a late claim. It is a non-existent claim. A late claim invites arguments about waiver, knowledge and relief. A non-existent claim invites none, because there is nothing to relieve against.
The practical consequence for a CCDC 2 – 2020 delay notice is that the causation narrative, the schedule impact and the quantum basis must be inside the notice window, not supplied later when the analyst has finished. Ten Working Days from the commencement of the delay is not long to produce that, which is precisely why the notice file has to be built as the job runs rather than assembled when the claim is conceived. The GC number of the clause construed in Ross-Clair is unverified in this corpus, the proposition is not.
What does not count as notice, and what can save a late one
Complaint is not notice. Northland Kaska Corp v R12 2001 BCSC 929 puts it as directly as it can be put: "the grumblings of a contractor are not sufficient to constitute notice." Site-meeting minutes recording dissatisfaction, an email chain about a late approval, a progress report with a red schedule line. None of these is the contractual notice, and none becomes one because the owner read it.
Three things can rescue a claim, and each has a limit worth knowing before it is relied on: waiver by conduct, on Colautti Construction Ltd v Ottawa (City)13 1984 CanLII 1969 (ONCA), actual knowledge read in context, on CIMIC Morningstar Investments Ltd v Chandos Construction Ltd14 2026 BCCA 2, which must be handled with care. And the Canadian good-faith line.
| Route | What it is | The limit |
|---|---|---|
| Waiver by conduct | Colautti, 1984 CanLII 1969 (ONCA), the owner had repeatedly paid for unauthorised extras, and could not then insist on the formality | It is a course-of-conduct finding, fact-heavy and specific to the party who did the paying. It is also the pleading of choice on ostensible authority, since no Canadian appellate decision addresses whether a CCDC Consultant can bind an Owner to an extra |
| Actual knowledge, read in context | CIMIC Morningstar, 2026 BCCA 2: an arbitrator read a 10-day notice requirement in context, found actual knowledge from emails, meetings and schedule updates, applied the prevention principle and awarded CAD 6.47M | It is a leave decision on an arbitral award. It confirms curial deference to an arbitrator's contextual reading. It does not restate the doctrine, the underlying award is not public, and it displaces neither Technicore nor Elite. Do not present it as a softening of Canadian notice law |
| Good faith | Bhasin, Callow and Wastech. An owner administering an extension-of-time clause is exercising a contractual discretion, which must be exercised reasonably and consistently with the purpose for which it was conferred | No Canadian case deciding an extension-of-time refusal on this basis was located for this corpus. The argument is structurally sound and has no English equivalent, but it is untested |
Layer: jurisdictional. Colautti is Ontario appellate and Northland Kaska is British Columbia first instance. CIMIC is a British Columbia leave decision on an arbitral award, not an appellate statement of doctrine. All three rest on secondary sources. No judgment was read in original form for this corpus.
The good-faith line is the one to watch. Bhasin v Hrynew15 2014 SCC 71 established the organising principle of good faith and the duty of honest performance, C.M. Callow Inc v Zollinger16 2020 SCC 45 extended it to knowingly misleading a counterparty on matters directly linked to performance, and Wastech Services Ltd v Greater Vancouver Sewerage and Drainage District17 2021 SCC 7 brought contractual discretion within it. An owner who sits on a valid extension application to force acceleration is exercising exactly that kind of discretion. The argument has not yet been run in a reported Canadian delay case. It remains the most promising untested route, and it is uniquely Canadian. An English contractor has nothing comparable to plead.
Ontario adds a layer, and it is where the reported law sits
Ontario is where most of the reported Canadian notice law comes from, and it adds three things to the pan-Canadian position rather than replacing it. First, it pairs strict timing with strict content. Ross-Clair and Technicore are both Ontario Court of Appeal decisions. Second, it splits its reading of "within X days" between notice clauses, which are hard bars, and ADR-staging clauses, which are minimum periods rather than cut-offs. Third, it is the only Canadian jurisdiction where a contractual limitation period may lawfully be shortened, which is why the owner's supplementary conditions matter more there than anywhere else.
Ontario also has date-keyed public-sector clocks that look nothing like CCDC: OPSS municipal and provincial general conditions, and Infrastructure Ontario project agreements whose Delay, Compensation and Relief Event notice periods are project-specific and were not surfaced in this corpus. Read the specific project agreement. Do not assume a day count. The detail sits on the Ontario notice and time bars page and the Ontario delay claim clocks page, and is not duplicated here.
One Ontario development is often misread as a rescue and is not. Since 1 January 2026, section 13.5 of the Construction Act and O. Reg. 264/25, s 1918 make a request for an extension of time to complete the work adjudicable. The section number is given as s 19 by most sources and as s 19.1 by one, a minor unresolved conflict. But only as a supporting matter reasonably necessary to a subsequent determination on a prescribed payment dispute, not on P3 projects, and not on contracts predating 1 January 2026. A contractor cannot commence a freestanding adjudication for a declaration of time entitlement, and adjudication does not reopen a contractual notice bar. No Canadian equivalent of that ancillary head exists anywhere else in the country.
For the doctrine sitting behind all of this (the four-element entitlement test, the Canadian approach to apportionment, and where else a Canadian delay claim fails), start at the Canadian extension of time hub. For the mechanism as it operates across regimes, and the safety valves that FIDIC and NEC4 build in and CCDC does not, see notice and time bars generally. Where the argument is that the owner's own conduct has put time at large, see the prevention principle and time at large in Canada, noting that no Ontario authority on the prevention principle or time at large was located at all.
Sources and authorities
- *Verification, unless noted
No Canadian judgment or consolidated statutory text was read in original form for this corpus. The citation, section number and holding rest on independent secondary sources. Verify on CanLII or the consolidated statute before pleading.
- 1CCDC 2 – 2020 Stipulated Price ContractCanadian Construction Documents Committee, GC 6.5 (Delays) and GC 6.6
GC 6.5.4 bars any extension for delay unless Notice in Writing of the cause of delay is given to the Consultant not later than 10 Working Days after the commencement of the delay. One Notice suffices for a continuing cause. GC 6.5.5 bars a request for extension arising from the Consultant's failure to furnish instructions until 10 Working Days after demand for instructions. GC 6.6.1 requires "timely" Notice in Writing of intent to claim money, with no fixed period. CCDC 2 – 2020 remains current as at August 2026, there is no 2025 or 2026 update.
- 2Technicore Underground Inc v Toronto (City)2012 ONCA 597, Court of Appeal for Ontario
Strict compliance with a contractual notice provision is required, and the owner need not prove prejudice from the failure to give notice. The leading Canadian statement of the no-prejudice rule.
- 3Elite Construction Inc v Canada (Attorney General)2021 ONSC 562 (Pinto J), aff'd 2021 ONCA 803 (MacPherson, Simmons and Nordheimer JJA)
A CAD 4.1M delay and extras claim dismissed on summary judgment for failure to give written notice of an intention to claim additional compensation or damages within ten working days of the date the neglect or delay first occurred. The condition-precedent analysis is the motion judge's. The Court of Appeal dismissed the appeal on the availability of summary judgment, on the absence of any waiver of the strict contractual notice requirements, and on there being "no room" for quantum meruit or unjust enrichment where the parties were operating under a contract.
- 4CCA 1 – 2021 Stipulated Price SubcontractCCA 1 – 2021, Canadian Construction Association Stipulated Price Subcontract
The subcontractor's delay notice period is 7 Working Days, three fewer than the 10 Working Days the main contract gives the general contractor under CCDC 2 – 2020 GC 6.5.4.
- 5OAA/OGCA Agreed-to Recommended Supplementary Conditions for CCDC 2-2020Ontario Association of Architects and Ontario General Contractors Association, version 15 March 2024 (R00), issued with OAA Practice Tip PT.23.11
The package contains no supplementary condition amending GC 6.5 (Delays) the 10 Working Days notice, the causes of delay and the delay-cost recovery stand unamended. SC 6.6.1 clarifies the money-claim notice and adds "and the Consultant" to the recipients, SC 8.3.9–8.3.13 permit the Consultant to join an arbitration as a full party.
- 6Doyle Construction Co v Carling O'Keefe Breweries of Canada Ltd1988 CanLII 2844 (BCCA), Court of Appeal for British Columbia
Contractual notice is a condition precedent to maintaining the claim in court.
- 7W A Stephenson Construction (Western) Ltd v Metro Canada Ltd(1987), 27 CLR 113 (BCSC)
Meeting minutes documenting the contractor's concerns about delay and access were sufficient notice without formal written notice inside the contractual period. Form of notice is unimportant. Substance and the owner's actual or constructive knowledge control. The owner waived strict compliance by its own conduct, its objection being "purely technical" because it had all necessary information in good time.
- 8Foundation Co of Canada Ltd v United Grain Growers Ltd(1997), 91 BCAC 254 (BCCA)
Cited in the British Columbia case law on notice and apportionment for its purposive treatment of what a notice clause is for, whether the owner was deprived, in substance and in good time, of the opportunity to investigate, mitigate, price or substitute that the clause exists to protect.
- 9Dilcon Construction Ltd v ANC Developments Inc2000 ABCA 223, Court of Appeal of Alberta
Carried in the corpus as authority that Alberta enforces contractual notice strictly, so that failure to give the contractual notice bars the delay claim. The corpus records a CONFLICT: a substantial source attributes to the same judgment an implied term that the owner will give the contractor uninterrupted possession of the site, a prevention-adjacent holding indexed under possession rather than notice. Both may be true of the same judgment, and since no Alberta appellate authority beyond this decision treating a notice-of-claim clause as a condition precedent was located, Alberta may have no appellate condition-precedent authority at all. The party order in the style of cause is a further recorded CONFLICT. The neutral citation is agreed.
- 10Corpex (1977) Inc v The Queen in right of Canada1982 CanLII 213 (SCC), Supreme Court of Canada
A notice provision can bar a claim even without express "failing which" language. The absence of a stated forfeiture consequence is not an answer to the bar.
- 11Ross-Clair v Canada (Attorney General)2016 ONCA 205, (2016) 347 OAC 177, Court of Appeal for Ontario
A claim submission must contain sufficient particulars, the contractor must in substance prove its claim to the other side in the submission itself. Sufficiency is a threshold requirement: "failure to provide sufficient information within 30 days after completion is a failure to provide notice of the claim at all." The claim was for $1,437,976 in extras. Standard of review on appeal was correctness, the contract being a standard-form government contract. The GC number of the clause construed is unverified in this corpus.
- 12Northland Kaska Corp v R2001 BCSC 929, Supreme Court of British Columbia
"The grumblings of a contractor are not sufficient to constitute notice." Complaint, however contemporaneous and however loud, is not the contractual notice: the contractor's intention to claim must have been unequivocal. This is the limit on British Columbia's purposive approach to notice: substance and good-time knowledge can save a claim, but only where what the owner actually had made the intention to claim clear.
- 13Colautti Construction Ltd v Ottawa (City)1984 CanLII 1969 (ONCA), Court of Appeal for Ontario
The main exception to strict enforcement, waiver by conduct, where the owner had repeatedly paid for unauthorised extras. It is also the pleading of choice on ostensible authority, no Canadian appellate decision having addressed whether a CCDC Consultant can bind an Owner to an extra.
- 14CIMIC Morningstar Investments Ltd v Chandos Construction Ltd2026 BCCA 2, Court of Appeal for British Columbia
Leave to appeal an arbitral award refused. The arbitrator had read a 10-day written notice requirement in context, found the owner had actual knowledge from emails, meetings and schedule updates, applied the prevention principle and awarded CAD 6.47M. It is a leave decision on an arbitral award: it confirms curial deference to an arbitrator's contextual reading, it does not restate the doctrine, and the underlying award is not public. Do not deploy it as an appellate statement of Canadian notice law.
- 15Bhasin v Hrynew2014 SCC 71, Supreme Court of Canada
The organising principle of good faith and the duty of honest performance in contract.
- 16C.M. Callow Inc v Zollinger2020 SCC 45, Supreme Court of Canada
Extends the duty of honest performance. A party may not knowingly mislead its counterparty about matters directly linked to the performance of the contract.
- 17Wastech Services Ltd v Greater Vancouver Sewerage and Drainage District2021 SCC 7, Supreme Court of Canada
A contractual discretion must be exercised reasonably and consistently with the purpose for which it was conferred. No Canadian case deciding an EOT refusal on this basis was located for this corpus, the argument is structurally available and untested.
- 18Construction Act (Ontario), s 13.5, and O. Reg. 264/25, s 19Ontario, the regulation applies to contracts entered into on or after 1 January 2026
A request for an extension of time to complete the work is adjudicable only as a supporting matter reasonably necessary to a subsequent determination on a prescribed payment dispute. Not on P3 projects, and not on contracts predating 1 January 2026. Adjudication does not reopen a contractual notice bar. The section number is preferred as s 19, one firm reports s 19.1 (minor conflict).
General information, not legal advice. Reviewed 10 sept. 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou…
Each issue links to the full articles in the Storia Library.