Claim deadline calculator: notice, payment, lien and limitation dates
A claim deadline is a contractual or statutory day by which something must be done, or the right it protects is lost or weakened: a notice of delay, a payment response, a lien, an adjudication step or a limitation period. This calculator takes the event that starts the clock and, for a statutory rule with a fixed period, returns the date, with the rule, its source in this library, and how far the result can be trusted. Standard-form clauses show the form's default period instead. It covers Ontario, British Columbia, United States federal contracts, England and Wales and FIDIC 2017.
Reviewed 24 nov 20266 min read0 sources
Disponible solo en inglés Este artículo aún no se ha traducido. Los plazos, el derecho a reclamar y el procedimiento descritos aquí rozan lo jurídico, y una traducción automática sería un riesgo de credibilidad más que una comodidad: por eso se sirve el original inglés íntegro hasta que exista una traducción revisada.
At a glance
General practice
Last reviewed
24 November 2026
Class
Tool. A deadline calculator for project managers, contract administrators and claims teams
Jurisdiction
Ontario, British Columbia, United States (federal), England and Wales, FIDIC 2017
Not legal advice
The executed contract, its amendments and the governing law decide the deadline. Check before relying on a date
§ 00
Key facts
01
What you enter
The regime, the deadline, and the date of the event that starts the clock, such as the commencement of a delay or the receipt of an invoice.
02
What you get
The last day to act, the earliest day for a waiting period, or both ends of a window; where the library advises an earlier date, that cautious date first and the statutory date beneath. Then the rule in words, the clause or section, which contracts it applies to, what missing it does, and a link to the library page that states it.
03
How days are counted
The day after the trigger is day 1. Holidays are not applied to the date: where a statute excludes them or moves a deadline that falls on one, the result says so next to the date.
04
Statutes and standard forms
Statutory deadlines with a fixed period and a trigger date you can enter get a date. Standard-form clauses (CCDC, AIA, JCT, NEC4, FIDIC) show the form's default period instead, because they are routinely amended, so FIDIC gives no date at all.
05
How far to trust it
Each result says whether the rule was read in an official source, rests on this library only, or comes from a licensed form that was not read.
Pick the regime, pick the deadline, enter the date of the event that starts the clock, and for a statutory rule with a fixed period the calculator gives you the date, the rule behind it, and a link to the page in this library that states it. Add the date to your calendar the day the event happens: a notice served late can cost the claim however good the rest of the record is.
§ 01
Calculate a deadline
This deadline gives no date to compute, so no trigger date is needed.
Standard form
Notice of delay (claim for extension of Contract Time)
Form default10 working days
Check your executed contract: these clauses are often amended.
Rule
Within 10 working days after the commencement of the delay.
From the library: "CCDC 2 – 2020 GC 6.5.4 gives 10 Working Days from the commencement of the delay, not from its effect."
Instrument and clause
CCDC 2 – 2020, GC 6.5.4
Trigger
the commencement of the delay
Consequence
Time bar. The claim itself. There is nothing left to bring
Counting
Working Days, a CCDC defined term: they exclude Saturdays, Sundays and holidays (eot-delay-notice-templates); the holiday calendar is not stated. Runs from the commencement of the delay, not from its effect or from awareness. One notice suffices for a continuing cause.
Flags
amendments common
Read in the librarySection: Clock A: contractual notice, and why it is the only one that decides entitlement
This reads the rule as the Storia library states it. It is not legal advice.
§ 02
How the calculator counts
The day of the triggering event is not counted: the next day is day 1. A period in calendar days adds that many days. A period in working or business days counts Monday to Friday only and does not exclude public holidays: for a last day that errs early, which is the cautious reading, but for an earliest day it can be too early, and the result says which. No dated statutory row uses working or business days today; they appear in standard-form clauses, which get no date.
A period in months or years ends on the same date in the later month or year. Where that date does not exist (31 January plus one month), it ends on the last day of that month.
Some rules are waiting periods rather than deadlines: nothing may be done until a period has run, such as a suspension "on 10 days' notice". The calculator gives the day after the period ends, the first day on which the whole period has run, and labels it "Earliest day to act, counting the full period". Where the rule is a window ("not less than 60 and not later than 74 days"), it gives both days: the window opens the day after the first period ends and closes on the last day of the second.
Where the library page tells you to work to a shorter period than the statute gives, such as the 30 days it advises for an Ontario leave motion that the Act now allows 35 days for, the date shown is the earlier one, labelled "Last day to act (cautious)", with the statutory date and the reason beneath it. Where a rule applies only to some contracts, such as Ontario's 2026 regime, the condition is shown directly under the date.
Holidays are never applied to the date. Where the library records that a statute excludes them or moves a deadline that falls on one, the note sits next to the date: the Housing Grants, Construction and Regeneration Act 1996 s 116 for England and Wales, and the Legislation Act, 2006 s 89 for Ontario. British Columbia's Interpretation Act has not yet been read in an official source for this calculator, so BC dates carry no holiday note: check whether the last day falls on a holiday.
Rules that run backwards from a later event, such as a step due a set number of days before a hearing, and cut-offs, such as costs incurred more than 20 days before a notice, are shown in words without a date. A deadline whose trigger the library does not state gets no date. Trigger dates must fall between 1900 and 2200; anything else shows "Not a valid date".
§ 03
How far to trust each result
Every result carries one of four labels.
Label
What it means
What to do
Read in an official source
The statute or regulation was read in an official consolidation or the enacting text
Use the date where one is given, and still check the executed contract for anything stricter
Library only
The period is stated on a library page, but the statute was not re-read in an official source
Treat the date as provisional and check the statute before relying on it
Standard form
A CCDC, AIA, JCT, NEC4 or FIDIC clause, shown with the form's default period
Check your executed contract and its supplementary conditions: these clauses are often amended
No fixed date
The rule says "as soon as practicable", "promptly" or a reasonable time, it is a cut-off rather than a clock, or the trigger is not stated or is not a date you can enter
Act at once and keep a dated record of when you became aware
§ 04
What the calculator does not do
It does not read your contract, and it does not apply holiday calendars. Standard forms are amended on most projects, and the amendment usually moves exactly the deadline you are looking up. It does not decide whether a missed deadline bars the claim: that depends on the wording, the forum and the facts, which the linked library page explains. It does not give legal advice.
Alberta, Quebec and Australia are not in the calculator yet. Their deadlines are in the library, but the statutes behind them have not all been read in an official source. They will be added once they are.
§ 05
Where Storia fits
The calculator gives you the day. Storia keeps the record that proves you met it: it reads the project record where it lives, dates each event, and assembles the chain of events with every paragraph cited to its page, so the date a notice went out and the event that started the clock can be shown, not argued. See Claims and Dispute Resolution or book a demo.
§ 06
Frequently asked questions
Is the date the calculator gives me binding?
No. It is the date the rule produces on its default wording, counted as described above. The executed contract, any amendment and the governing law decide the actual deadline.
Why do standard-form clauses not get a date?
Because the clause in your contract is often not the printed clause. Owners and contractors routinely change notice periods, recipients and triggers in supplementary conditions. The calculator shows the default period so you know what to look for.
What happens if the last day falls on a weekend or a holiday?
Weekends are skipped only when the period is in working or business days. Holidays are never applied. Where the library records a statutory holiday rule (England and Wales HGCRA s 116, Ontario Legislation Act, 2006 s 89), the result says so next to the date, and the real date may be later than shown. British Columbia rows carry no holiday note yet.
Can I add the deadline to my calendar?
Yes. Every result with a date has an "Add to calendar" button that downloads an all-day event on the date shown: the cautious date where there is one, the closing day of a window. Its description gives the opening day of a window or the statutory date behind a cautious one, which contracts the rule applies to, the rule, the counting note (with any holiday rule), the flags, the source and any warning.
Where do the deadlines come from?
From the pages of this library, each of which cites its sources. The claim deadline register lists every deadline the calculator uses, with its source and evidence level.