Claim deadline register: construction notice, payment and limitation periods
A register of the claim deadlines this library records for Ontario, British Columbia, United States federal contracts, England and Wales and FIDIC 2017: notices of delay and claims, payment and adjudication steps, liens and limitation periods. Each row gives the instrument and clause, the event that starts the clock, the period, what missing it does, how far the rule has been verified, and the library page that states it.
Disponible solo en inglés Este artículo aún no se ha traducido. Los plazos, el derecho a reclamar y el procedimiento descritos aquí rozan lo jurídico, y una traducción automática sería un riesgo de credibilidad más que una comodidad: por eso se sirve el original inglés íntegro hasta que exista una traducción revisada.
At a glance
- 24 November 2026
- Tool. A reference register of claim deadlines
- Ontario, British Columbia, United States (federal), England and Wales, FIDIC 2017
- Default periods. The executed contract, its amendments and the governing law decide the deadline
Key facts
- 01
What it lists
Contract notice periods, statutory payment and adjudication steps, lien periods and limitation periods, one table per regime.
- 02
Evidence levels
Each row says whether the rule was read in an official source, rests on this library only, or comes from a licensed standard form that was not read.
- 03
Standard forms
CCDC, AIA, JCT, NEC4 and FIDIC rows give the printed default. Projects routinely amend them.
- 04
To get a date
Use the claim deadline calculator.
Every claim deadline this library records for Ontario, British Columbia, US federal contracts, England and Wales and FIDIC 2017, in one table per regime. Each row links to the page that states the rule and says how far it has been verified. To turn a row into a date, use the claim deadline calculator.
How to read the register
The trigger is the event that starts the clock, in the words of the source. The period is counted from the day after it, or, for a step due before an event, counted back from it. A waiting period ends before you may act: act from the day after it ends. A window gives both ends. Where the library advises working to a shorter period, the period cell says so, and where a rule applies only to some contracts, the condition is shown under the period. Cut-offs, such as costs incurred more than 20 days before a notice, are stated in words. The consequence says what missing the deadline does to the right the row covers: a lien row that bars the lien does not, on its own, bar the debt.
The evidence column has four values. Read in an official source: the statute or regulation was read in an official consolidation or the enacting text. Library only: the period is stated on a library page but was not re-read in an official source. Standard form: the printed default of a licensed form, which projects routinely amend. No fixed date: the rule has no period you can count, is a cut-off rather than a clock, or has no trigger stated in the library; the row then also says whether it was read in an official source or rests on the library only.
The register
| Deadline | Instrument and clause | Trigger | Period | Consequence | Evidence | Library |
|---|---|---|---|---|---|---|
Notice of delay (claim for extension of Contract Time)
| CCDC 2 – 2020, GC 6.5.4 | the commencement of the delay | 10 working days (last day) | Time barThe claim itself. There is nothing left to bring | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Waiting period before requesting an extension for the Consultant's failure to furnish instructions
| CCDC 2 – 2020, GC 6.5.5 | demand for instructions, where no schedule was made under GC 2.2.12 | 10 working days (a waiting period: act from the day after it ends) | Not a time bar | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Subcontractor notice of claim for extension of subcontract time
| CCA 1 – 2021 | Not stated | 7 working days (last day) | Probably a time bar | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Application to extend the Contract Time
| OPSS.MUNI 100 (November 2019), GC 3.06.01 | the expiration of the Contract Time | 15 calendar days (counted back from the event) | Probably a time bar | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Application for extension of Contract Time on MTO form PH-CC-756
| OPSS.PROV 100 (April 2023), GC 3.06 | the need for the extension becomes evident | No fixed period (promptly) | Probably a time barA contractor that writes a well-drafted letter instead of form PH-CC-756 has not applied for anything | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Notice of intention to claim a change in Contract Price
| CCDC 2 – 2020, GC 6.6.1 | intention to claim a change in Contract Price | No fixed period (promptly) | Unsettled | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Compensation Request after cost-estimate submission
| OPSS.PROV 100 (April 2023), GC 3.14 | cost-estimate submission | 10 calendar days (last day) | Unsettled | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Unresolved change-order pricing
| OPSS.PROV 100 (April 2023), GC 3.14 | Not stated | 10 business days (last day) | Unsettled | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Verbal notice of a potential claim situation
| OPSS.MUNI 100 (November 2019), GC 3.13.03 | becoming aware of a potential claim situation | No fixed period (promptly) | Unsettled | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Written Notice of Intent to Claim
| OPSS.MUNI 100 (November 2019), GC 3.13.03 | the commencement of any part of the Work affected | 7 calendar days (last day) | Probably a time bar | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
Detailed claim
| OPSS.MUNI 100 (November 2019), GC 3.13.03 | completion of the work affected | 30 calendar days (last day) | Probably a time barFailure to provide sufficient information within 30 days after completion is a failure to provide notice of the claim at all (Ross-Clair, 2016 ONCA 205) | Standard formCheck your executed contract. | Clock A: contractual notice, and why it is the only one that decides entitlement |
| Payment of the determined amount | Construction Act, RSO 1990, c C.30 (as amended by 2024, c. 20, Sched. 4), s 13.19(2) | the determination being communicated to the parties to the adjudication | 15 calendar days (last day); the library advises working to 10 calendar days15 days under the Act as amended by 2024, c. 20, Sched. 4; 10 days is the pre-2026 figure, and the 2026 regime attaches to the contract date. The library page says diarise 10 as prudence. | Time barInterest from the due date at the prejudgment rate or the higher contractual rate (s 13.19(3)) | Read in an official source | How an Ontario EOT adjudication actually runs |
| Owner's written notice of deficiency in an invoice | Construction Act, RSO 1990, c C.30 (as amended by Bill 216, Sch 4), s 6.1 | receipt of the invoice | 7 calendar days (last day) | Time barThe invoice is deemed to be a proper invoice | Library onlyCheck before relying on it. | How prompt payment changed the leverage on a delay claim |
| Owner's prompt payment of a proper invoice | Construction Act, RSO 1990, c C.30 (as amended), Part I.1 | the proper invoice | 28 calendar days (last day) | Time bar | No fixed dateLibrary only | How prompt payment changed the leverage on a delay claim |
| Owner's Notice of Annual Release of Holdback (Form 6) | Construction Act, RSO 1990, c C.30 (as amended by Bill 216, Sch 4 and Bill 60, Sch 2), ss 26 to 27.1 | each contract anniversary | 14 calendar days (last day)Contracts running more than one year entered into on or after 1 January 2026; for earlier contracts (other than those under the former Construction Lien Act), from the second contract anniversary after 1 January 2026 (s 87.4(4)). Pre-2026 P3 project agreements with a special purpose entity are exempt. | Unsettled | Library onlyCheck before relying on it. | How prompt payment changed the leverage on a delay claim |
| Payment of annually released holdback | Construction Act, RSO 1990, c C.30 (as amended by Bill 216, Sch 4 and Bill 60, Sch 2), ss 26 to 27.1 | publication of the Notice of Annual Release of Holdback | Window: opens once 60 calendar days have run in full, closes on day 74Contracts running more than one year entered into on or after 1 January 2026; for earlier contracts (other than those under the former Construction Lien Act), from the second contract anniversary after 1 January 2026 (s 87.4(4)). Pre-2026 P3 project agreements with a special purpose entity are exempt. | Unsettled | Library onlyCheck before relying on it. | How prompt payment changed the leverage on a delay claim |
| Cascade of released holdback to subcontractors | Construction Act, RSO 1990, c C.30 (as amended by Bill 216, Sch 4 and Bill 60, Sch 2), ss 26 to 27.1 | receipt of the released holdback | 14 calendar days (last day) | Unsettled | Library onlyCheck before relying on it. | How prompt payment changed the leverage on a delay claim |
| Notice of adjudication, contract dispute | Construction Act, RSO 1990, c C.30 (as amended to 2026), s 13.5(3) | the date on which the contract is completed, abandoned or terminated | 90 calendar days (last day)Only for contracts entered into on or after 1 January 2026 (the 2026 regime); check the contract date first. | Time barAdjudication of a contract dispute is unavailable; the claim survives and must be litigated or arbitrated instead | Library onlyCheck before relying on it. | How an Ontario EOT adjudication actually runs |
| Notice of adjudication, subcontract dispute | Construction Act, RSO 1990, c C.30 (as amended to 2026), s 13.5(3.1) | the earliest of contract completion, abandonment or termination, certification of subcontract completion under s 33, and the date the subcontractor last supplied services or materials | 90 calendar days (last day)Only for contracts entered into on or after 1 January 2026 (the 2026 regime); check the contract date first. | Time barAdjudication unavailable; the claim survives | Library onlyCheck before relying on it. | How an Ontario EOT adjudication actually runs |
| Objection to the adjudicator's jurisdiction | Construction Act, RSO 1990, c C.30 (as amended to 2026), s 13.12.1 | the party first making submissions, or the matter being raised | Raise the objection before the adjudicator: at first submissions, or as soon as the matter is raised. | Time barA jurisdictional objection not raised before the adjudicator cannot ground judicial review unless the failure was justified | No fixed dateLibrary only | What actually became adjudicable on 1 January 2026 |
| Adjudicator's determination | Construction Act, RSO 1990, c C.30 (as amended to 2026) | Not stated | 30 calendar days (last day) | Not a time bar | No fixed dateLibrary only | How an Ontario EOT adjudication actually runs |
| Correction of a slip in a determination | Construction Act, RSO 1990, c C.30 (as amended to 2026), s 13.17.1 | Not stated | 5 calendar days (last day) | Unsettled | No fixed dateLibrary only | How an Ontario EOT adjudication actually runs |
| Motion for leave to seek judicial review of a determination | Construction Act, RSO 1990, c C.30 (as amended by 2024, c. 20, Sched. 4), s 13.18(2) | the determination is communicated | 35 calendar days (last day); the library advises working to 30 calendar days35 days under the Act as amended by 2024, c. 20, Sched. 4; 30 days is the pre-2026 figure, and the 2026 regime attaches to the contract date. The library page says diarise 30 as prudence: the five days lost are unrecoverable. | Time bara missed leave deadline is fatal | Read in an official source | How an Ontario EOT adjudication actually runs |
Notice of dispute after the Consultant's finding
| CCDC 2 – 2020, GC 8.3.2 | receipt of the Consultant's finding | 15 working days (last day) | Not a time barUsually nothing. The periods are minimums, not cut-offs | Standard formCheck your executed contract. | Clock B: staged ADR, which is a floor rather than a ceiling |
Reply to the notice of dispute
| CCDC 2 – 2020, GC 8.3.2 | receipt of the notice of dispute | 10 working days (last day) | Not a time barUsually nothing. The periods are minimums, not cut-offs | Standard formCheck your executed contract. | Clock B: staged ADR, which is a floor rather than a ceiling |
Negotiation period before the Project Mediator is requested
| CCDC 2 – 2020, GC 8.3.4 | receipt of the reply | 10 working days (a waiting period: act from the day after it ends) | Not a time bar | Standard formCheck your executed contract. | Clock B: staged ADR, which is a floor rather than a ceiling |
Appointment of the Project Mediator
| CCDC 2 – 2020, GC 8.3.1 | award of the contract | 20 working days (last day) | Not a time bar | Standard formCheck your executed contract. | Clock B: staged ADR, which is a floor rather than a ceiling |
Negotiation, then mediation if unresolved
| OPSS.MUNI 100 (November 2019), GC 3.13.04–.05 | the opinion | 30 calendar days (window closes) | Not a time barUsually nothing. The periods are minimums, not cut-offs | Standard formCheck your executed contract. | Clock B: staged ADR, which is a floor rather than a ceiling |
Mediator's review to complete
| OPSS.MUNI 100 (November 2019), GC 3.13.04–.05 | the opinion | 90 calendar days (window closes) | Not a time barUsually nothing. The periods are minimums, not cut-offs | Standard formCheck your executed contract. | Clock B: staged ADR, which is a floor rather than a ceiling |
Notice of arbitration
| OPSS.MUNI 100 (November 2019), GC 3.14.01–.02 | the opinion | 60 calendar days (last day) | UnsettledUsually nothing. The periods are minimums, not cut-offs | Standard formCheck your executed contract. | Clock B: staged ADR, which is a floor rather than a ceiling |
Arbitration hearing to commence
| OPSS.MUNI 100 (November 2019), GC 3.14.01–.02 | appointment of the arbitrator | 90 calendar days (last day) | Not a time bar | Standard formCheck your executed contract. | Clock B: staged ADR, which is a floor rather than a ceiling |
Preservation of a lien
| Construction Act, RSO 1990, c C.30 (as amended to 2026), s 31 | Not stated | 60 calendar days (last day) | Time barMissing the 60-day preservation date or the 90-day perfection date destroys the security. It does not destroy the claim. | No fixed dateLibrary only | The lien clocks: 60 days to preserve, 90 to perfect, and the 7-day notice of termination |
Perfection of a lien
| Construction Act, RSO 1990, c C.30 (as amended to 2026), s 36 | Not stated | 90 calendar days (last day) | Time barMissing the 60-day preservation date or the 90-day perfection date destroys the security. It does not destroy the claim. | No fixed dateLibrary only | The lien clocks: 60 days to preserve, 90 to perfect, and the 7-day notice of termination |
| Publication of notice of termination | Construction Act, RSO 1990, c C.30 (as amended by Bill 60, Sch 2), s 31(6)–(8) | termination | 7 calendar days (last day)Only for contracts entered into on or after 1 January 2026 (the 2026 regime); check the contract date first. | Unsettled | Library onlyCheck before relying on it. | The lien clocks: 60 days to preserve, 90 to perfect, and the 7-day notice of termination |
Basic limitation period
| Limitations Act, 2002, SO 2002, c 24, Sch B, s 4 | the day on which the claim was discovered | 2 years (last day) | Time bara proceeding shall not be commenced in respect of a claim after the second anniversary of the day on which the claim was discovered | Library onlyCheck before relying on it. | The basic period is two years from discovery, and discovery has four limbs |
| Ultimate limitation period | Limitations Act, 2002, SO 2002, c 24, Sch B, s 15 | the day the act or omission on which the claim is based took place | 15 years (last day) | Time bar | Library onlyCheck before relying on it. | The basic period is two years from discovery, and discovery has four limbs |
| Deadline | Instrument and clause | Trigger | Period | Consequence | Evidence | Library |
|---|---|---|---|---|---|---|
Notice of delay (claim for extension of Contract Time)
| CCDC 2 – 2020, GC 6.5.4 | the commencement of the delay | 10 working days (last day) | Probably a time barNothing on that event, subject to waiver, estoppel and the purposive BC reading of notice | Standard formCheck your executed contract. | Contractual notice, the condition-precedent clocks |
Extension of time notice
| BC MOTI Major Works General Conditions (version 2026-04-01), GC 44.03 | the occurrence or the detection of the event | 14 calendar days (last day) | Probably a time barNothing on that event, subject to waiver, estoppel and the purposive BC reading of notice | Standard formCheck your executed contract. | Contractual notice, the condition-precedent clocks |
Waiting period before requesting an extension for the Consultant's failure to furnish instructions
| CCDC 2 – 2020, GC 6.5.5 | demand for instructions | 10 working days (a waiting period: act from the day after it ends) | Not a time bar | Standard formCheck your executed contract. | The periods you are actually working to |
Notice of a supervening event (P3 project agreement)
| Penticton Regional Hospital Patient Care Tower Project Agreement (6 April 2016), Infrastructure BC, s 8.2(a) | the applicant Has Knowledge that a supervening event has caused an entitlement | 5 business days (last day) | Probably a time barNothing on that event, subject to waiver, estoppel and the purposive BC reading of notice | Standard formCheck your executed contract. | Contractual notice, the condition-precedent clocks |
Supporting details of a supervening event
| Penticton Regional Hospital Patient Care Tower Project Agreement (6 April 2016), Infrastructure BC, s 8.2(b) | delivery of the notice | 10 business days (last day) | Probably a time bar | Standard formCheck your executed contract. | Contractual notice, the condition-precedent clocks |
Changed condition notice
| BC MOTI Major Works General Conditions (version 2026-04-01), GC 41.01 | Not stated | 7 calendar days (last day) | Probably a time barNothing on that event, subject to waiver, estoppel and the purposive BC reading of notice | Standard formCheck your executed contract. | Contractual notice, the condition-precedent clocks |
Default notice period where no period is stated
| BC MOTI Major Works General Conditions (version 2026-04-01), GC 37.07 | Not stated | 7 calendar days (last day) | Probably a time bar | Standard formCheck your executed contract. | Contractual notice, the condition-precedent clocks |
| Written notice of damage to a municipality or regional district | Local Government Act, RSBC 2015, c 1, s 736 | the date the damage was sustained | 2 months (last day) | Unsettleda municipality or regional district is in no case liable for damages unless written notice | Read in an official source | Statutory preconditions to suing. The ones British Columbia does not have |
| Contractor's notice of suspension for failure to pay holdback into the holdback account | Builders Lien Act, SBC 1997, c 45, s 5(7) | the contractor's notice of suspension | 10 calendar days (a waiting period: act from the day after it ends)Only where the owner must keep a holdback account: not where s 5(8) exempts it (government, government corporations, designated public bodies, contracts under $100,000). | Not a time bar | Read in an official source | The holdback, the holdback account, and the exemption nobody expects |
Meeting on the supervening event, then dispute resolution
| Penticton Regional Hospital Patient Care Tower Project Agreement (6 April 2016), Infrastructure BC, s 8.2(h) | Not stated | 15 business days (last day) | Not a time bar | Standard formCheck your executed contract. | Contractual notice, the condition-precedent clocks |
| Serve expert report | Supreme Court Civil Rules (BC), Rule 11-6 | the trial date | 84 calendar days (counted back from the event) | Unsettled | Read in an official source | The procedural clocks, and how the whole set interacts |
| Serve responding expert report | Supreme Court Civil Rules (BC), Rule 11-6 | the trial date | 42 calendar days (counted back from the event) | Unsettled | Read in an official source | The procedural clocks, and how the whole set interacts |
| Dormant proceeding: notice required before proceeding | Supreme Court Civil Rules (BC), Rule 22-4(4) | the last step taken in the proceeding | 1 year (last day) | Not a time barcannot proceed without notice under Rule 22-4(4) | Read in an official source | The procedural clocks, and how the whole set interacts |
| File a claim of lien | Builders Lien Act, SBC 1997, c 45, s 20 | a certificate of completion, or the head contract completed, abandoned or terminated, or the improvement completed or abandoned | 45 calendar days (last day) | Time barLien extinguished (s 22) | Read in an official source | The Builders Lien Act clocks: conditions of a security remedy |
Holdback period
| Builders Lien Act, SBC 1997, c 45, s 8 | certificate of completion, otherwise head contract or improvement completion | 55 calendar days (last day) | Time barPayment out discharges liens unless a lien was filed or proceedings commenced | Read in an official source | The Builders Lien Act clocks: conditions of a security remedy |
| Certifier issues a certificate of completion on request | Builders Lien Act, SBC 1997, c 45, s 7 | the request | 10 calendar days (last day) | Not a time barThe court may declare completion. The certifier is personally liable | Read in an official source | The Builders Lien Act clocks: conditions of a security remedy |
| Commence the lien action and register a certificate of pending litigation | Builders Lien Act, SBC 1997, c 45, s 33 | the date the lien was filed | 1 year (last day) | Time barthe lien is extinguished if either step is missed (s 33(5)) | Read in an official source | The Builders Lien Act clocks: conditions of a security remedy |
| Commence the action after a notice to commence | Builders Lien Act, SBC 1997, c 45, s 33 | service of the notice to commence | 21 calendar days (last day) | Time barLien extinguished | Read in an official source | The Builders Lien Act clocks: conditions of a security remedy |
| Trust action (s 10 statutory construction trust) | Builders Lien Act, SBC 1997, c 45, s 14 | the head contract being completed, abandoned or terminated | 1 year (last day) | Time bar | Read in an official source | The trust clock, a one-year limitation that runs from an event you may not hear about |
| Basic limitation period | Limitation Act, SBC 2012, c 13, s 6(1) | the day the claim is discovered | 2 years (last day) | Time bar | Read in an official source | What the Limitation Act actually provides |
| Ultimate limitation period | Limitation Act, SBC 2012, c 13, s 21(1) | the day the act or omission on which the claim is based took place | 15 years (last day) | Time bar | Read in an official source | What the Limitation Act actually provides |
| Deadline | Instrument and clause | Trigger | Period | Consequence | Evidence | Library |
|---|---|---|---|---|---|---|
Written notice of the causes of delay to the Contracting Officer
| FAR 52.249-10, Default (Fixed-Price Construction), 52.249-10(b)(2) | the beginning of any delay | 10 calendar days (last day)Read the clause as incorporated in your contract: the FAR Overhaul is mid-flight and class-deviated text may apply. | UnsettledRelief from default termination and delay damages under 52.249-10(b) is conditioned on the notice | Read in an official source | FAR: notice, cost cut-offs, and the final-payment backstop |
Cost cut-off before written notice of a constructive change
| FAR 52.243-4, Changes, 52.243-4(d) | the written notice | Costs incurred more than 20 days before the written notice are not recoverable, except for an adjustment based on defective specifications. A look-back cut-off, not a filing deadline. | Not a time barA cost cut-off, not an entitlement bar | No fixed dateRead in an official source | FAR's notice-vs-cost-cutoff distinction |
Cost cut-off before written notice of a suspension
| FAR 52.242-14, Suspension of Work, 52.242-14(c) | the written notice | Costs incurred more than 20 days before the written notice are not allowed. A look-back cut-off, not a filing deadline; it does not apply to a claim resulting from a suspension order. | Not a time barA cost cut-off, not an entitlement bar | No fixed dateRead in an official source | FAR: notice, cost cut-offs, and the final-payment backstop |
Initiate a Claim (including a request for additional Contract Time)
| AIA A201-2017, §15.1.3.1 | the later of the event giving rise to the Claim and the claimant first recognizing the condition | 21 calendar days (last day) | Time barMiss it and the Claim is contractually time-barred. | Standard formCheck your executed contract. | The §15.1.3.1/.2 split: new in 2017, and it changes which regime applies |
Assert the right to an equitable adjustment
| FAR 52.243-4, Changes, 52.243-4(e) | the change order or the (b) notice | 30 calendar days (last day)Read the clause as incorporated in your contract: the FAR Overhaul is mid-flight and class-deviated text may apply. | Unsettled | Library onlyCheck before relying on it. | FAR: notice, cost cut-offs, and the final-payment backstop |
No proposal after final payment
| FAR 52.243-4, Changes, 52.243-4(f) | final payment | No proposal or claim after final payment. Final payment is a cut-off, not the start of a clock: assert the adjustment before it. | Time barNo proposal or claim after final payment | No fixed dateLibrary only | FAR: notice, cost cut-offs, and the final-payment backstop |
Assert the suspension claim
| FAR 52.242-14, Suspension of Work, 52.242-14(c) | the suspension ends | No fixed period (promptly) | Time barno claim survives final payment | No fixed dateRead in an official source | FAR: notice, cost cut-offs, and the final-payment backstop |
Notice of differing site conditions
| FAR 52.236-2, Differing Site Conditions, 52.236-2(a), (c) | encountering the condition, before the conditions are disturbed | No fixed period (promptly) | Probably a time barno adjustment without it | No fixed dateLibrary only | FAR: notice, cost cut-offs, and the final-payment backstop |
No differing-site-conditions request after final payment
| FAR 52.236-2, Differing Site Conditions, 52.236-2(d) | final payment | No request for an adjustment under this clause after final payment. Final payment is a cut-off, not the start of a clock. | Time barno claim survives final payment under any of the three clauses | No fixed dateLibrary only | FAR: notice, cost cut-offs, and the final-payment backstop |
| Submit the claim to the Contracting Officer (CDA limitation period) | Contract Disputes Act, as implemented by FAR 33.206, FAR 33.206 | accrual: when all events that fix the alleged liability were known or should have been known (FAR 33.201) | 6 years (last day) | Time bar | Library onlyCheck before relying on it. | The CDA layer: six years, $100,000, and when the clock starts |
| Deadline | Instrument and clause | Trigger | Period | Consequence | Evidence | Library |
|---|---|---|---|---|---|---|
Notice by Contractor of delay to progress
| JCT Design and Build Contract 2024, cl 2.24 | delay to progress becomes reasonably apparent | No fixed period (promptly) | Not a time bar | Standard formCheck your executed contract. | On the printed JCT 2024 wording, time has no time bar, but the money notice can forfeit |
Employer's request for further information on a delay notice
| JCT Design and Build Contract 2024, cl 2.24.4 | receipt of the required particulars or of a notice of a material change | 14 calendar days (last day) | Unsettled | Standard formCheck your executed contract. | Template D. Reply to an Employer's cl 2.24.4 request for further information |
Employer's decision fixing a later Completion Date
| JCT Design and Build Contract 2024, cl 2.25.2 | Not stated | 8 weeks (last day) | Not a time barIf the Employer misses that period, there is no deemed grant. | Standard formCheck your executed contract. | On the printed JCT 2024 wording, time has no time bar, but the money notice can forfeit |
Employer's review of the Completion Date after practical completion
| JCT Design and Build Contract 2024 | practical completion | 12 weeks (last day) | Not a time bar | Standard formCheck your executed contract. | On the printed JCT 2024 wording, time has no time bar, but the money notice can forfeit |
Loss and expense notice
| JCT Design and Build Contract 2024, cl 4.21 Relevant Matter (loss and expense notice clause of the executed contract) | it becomes apparent that regular progress is or will be materially affected by a Relevant Matter | No fixed period (promptly) | Probably a time barOn the Scottish SBC 2016 in FES (persuasive), the notice was a condition precedent to loss and expense; likely the same under DB 2024 (Inference.) | Standard formCheck your executed contract. | Which notice, under which form |
Contractor notifies a compensation event
| NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 61.3 | the Contractor becoming aware of the event | 8 weeks (last day) | Time barthe Prices, the Completion Date and the Key Dates are not changed | Standard formCheck your executed contract. | NEC4 clause 61.3 is a hard bar, with one exception and a two-step safety valve |
Project Manager replies to a compensation event notification
| NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 61.4 | the Contractor's notification of the compensation event | 1 week (last day) | Not a time bar | Standard formCheck your executed contract. | NEC4 clause 61.3 is a hard bar, with one exception and a two-step safety valve |
Deemed acceptance of a compensation event after notice of the Project Manager's failure
| NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 61.4 | the Contractor's notice of the Project Manager's failure to reply | 2 weeks (a waiting period: act from the day after it ends) | Not a time bartreated as acceptance that the event is a compensation event | Standard formCheck your executed contract. | NEC4 clause 61.3 is a hard bar, with one exception and a two-step safety valve |
Contractor submits quotations for a compensation event
| NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 62.3 | the instruction to submit quotations | 3 weeks (last day) | Unsettled | Standard formCheck your executed contract. | NEC4 cl 61.4 and 62.6: silence becomes acceptance only if you say so |
Deemed acceptance of a quotation after notice of the Project Manager's failure
| NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 62.6 | the Contractor's notice of the Project Manager's failure to reply to the quotation | 2 weeks (a waiting period: act from the day after it ends) | Not a time bar | Standard formCheck your executed contract. | NEC4 clause 61.3 is a hard bar, with one exception and a two-step safety valve |
Project Manager replies to a quotation
| NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 62.3 | submission of the quotation | 2 weeks (last day) | Not a time bar | Standard formCheck your executed contract. | NEC4 cl 61.4 and 62.6: silence becomes acceptance only if you say so |
Early warning
| NEC4 ECC (June 2017, amended January 2019, October 2020, January 2023), cl 15.1 | becoming aware of a matter that could affect cost, time or quality | No fixed period (promptly) | Not a time barthe compensation event is then assessed as if the warning had been given | Standard formCheck your executed contract. | The early warning is not the compensation event notification |
| Notice of intention to refer a dispute to adjudication | Housing Grants, Construction and Regeneration Act 1996, as amended by LDEDCA 2009 Part 8, s.108 | Not stated | No fixed period | Not a time bar | No fixed dateRead in an official source | Any EOT dispute can be referred at any time, and the certificate can be reopened |
| Adjudicator's decision | Housing Grants, Construction and Regeneration Act 1996, as amended by LDEDCA 2009 Part 8, s.108 | referral | 28 calendar days (last day)Contracts entered into on or after 1 October 2011 (the current text). | Unsettled | Read in an official source | Any EOT dispute can be referred at any time, and the certificate can be reopened |
| Deadline | Instrument and clause | Trigger | Period | Consequence | Evidence | Library |
|---|---|---|---|---|---|---|
Notice of Claim (extension of time under Sub-Clause 8.5, or additional payment)
| FIDIC Conditions of Contract, Second Edition 2017 (2022 reprint), Red, Yellow and Silver Books, Sub-Clause 20.2.1 | the claiming Party became aware, or should have become aware, of the event or circumstance | 28 calendar days (last day) | Time barExpress bar: no extension, no additional payment. | Standard formCheck your executed contract. | Which notice, under which form |
Engineer gives notice that a Notice of Claim is late
| FIDIC Conditions of Contract, Second Edition 2017 (2022 reprint), Red, Yellow and Silver Books, Sub-Clause 20.2.2 | Not stated | 14 calendar days (last day) | Time barthe Notice is deemed valid | Standard formCheck your executed contract. | FIDIC 2017 Sub-Clause 20.2.1: the 28-day Notice of Claim |
Fully detailed Claim
| FIDIC Conditions of Contract, Second Edition 2017 (2022 reprint), Red, Yellow and Silver Books, Sub-Clause 20.2.4 | the claiming Party became aware, or should have become aware, of the event | 84 calendar days (last day) | Probably a time barWithout the legal-basis statement, the Notice of Claim is reported to lapse, subject to the Engineer notifying the lapse within 14 days | Standard formCheck your executed contract. | FIDIC 2017 Sub-Clause 20.2.4: the fully detailed Claim at 84 days |
Engineer's agreement or determination of a Claim
| FIDIC Conditions of Contract, Second Edition 2017 (2022 reprint), Red, Yellow and Silver Books, Sub-Clause 3.7 | Not stated | 42 calendar days (last day) | Not a time barfailure to determine is a deemed rejection, referable to the DAAB | Standard formCheck your executed contract. | Why deemed acceptance matters more than the length of the period |
What is not here yet
Alberta, Quebec and Australia are covered on their own library pages, but not every statute behind their deadlines has been read in an official source, so they are not in the register yet.
Where Storia fits
A register tells you which clocks exist. Storia keeps the record that shows when each one started and when you acted: it reads the project record where it lives and builds a dated chain of events, every paragraph cited to its page. See Claims and Dispute Resolution or book a demo.
General information, not legal advice. Reviewed 24 nov 2026. Spotted an error? info@storiatechnologies.com
The notice brief
One email a month on claims, notices and the cases that decided them.
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Modelos de aviso de retraso para AS 4000, FIDIC 2017 y CCDC 2Un aviso de retraso deja constancia a tiempo de un solo hecho: que algo ha retrasado, o…
Each issue links to the full articles in the Storia Library.