Aller au contenu principal

Confidentialité

À propos des témoins

Les témoins essentiels font fonctionner ce site. Les témoins d’analyse facultatifs nous aident à comprendre ce qui fonctionne, activés seulement si vous acceptez.

LIBRARY
General practiceExtension of timePractice article

EOT claims expert or lawyer? What to do before you hire one

An EOT claims expert's or a construction lawyer's time goes furthest when they are called before the notice deadline runs and handed the executed contract, every schedule update as a native file, and a dated record of events. A lawyer answers entitlement, notice and forum. A delay expert answers whether the event delayed completion, and by how many days. A quantum expert prices the money. None of them can make a late notice timely or create records that were never kept.

Reviewed 10 nov. 202612 min read8 sources

Disponible en anglais seulement Cet article n'a pas encore été traduit. Les délais, le droit à réclamation et la procédure décrits ici touchent au droit, et une traduction automatique constituerait un risque de crédibilité plutôt qu'une commodité : l'original anglais est donc servi intégralement jusqu'à ce qu'une traduction révisée existe.

At a glance

General practice
Last reviewed
10 November 2026
Class
Practical page. Getting ready to brief a construction lawyer, delay expert or quantum expert
Scope
Jurisdiction-neutral, with pointers for Australia (including Western Australia), Canada, England and Wales and the United States
Not legal advice
Storia is software. This page does not provide or recommend legal, expert or consulting services
§ 00

Key facts

  1. 01

    Do this first

    Serve any notice that is due. The clock runs whether or not an adviser has been engaged, and no expert can make a late notice timely.

  2. 02

    Who answers what

    Lawyer: entitlement, notice, forum and clocks. Delay expert: critical path and days. Quantum expert: the money.

  3. 03

    When to bring in the delay expert

    Early on a large or disputed claim, while the records can still be improved. The records you keep decide which analysis methods remain open.

  4. 04

    What to hand over

    The executed contract and amendments, the baseline and every update as native files, notices with proof of service, RFIs, instructions, daily reports, minutes and cost records.

  5. 05

    The first question to ask an expert

    Is any part of the fee tied to the outcome? In Canada, a success-linked fee is what signals bias, while prior work on the project is survivable.

  6. 06

    The rules differ by forum

    Alberta's courts allow one expert per subject matter unless the court orders otherwise. A BC arbitration report must carry a statutory certification. Australian courts expect the expert's reasoning to be exposed.

Before you hire an EOT claims expert or a construction lawyer, do three things. Serve any notice that is due, because no expert can make a late one timely. Collect the executed contract and every schedule update as native files. And build a dated list of events with a record reference against each. Then choose the adviser by the question you need answered: a lawyer for entitlement, notice and forum; a delay expert for whether the event delayed completion and by how many days; a quantum expert for the money.

This page is for project managers, commercial managers and owners' representatives. It is not legal advice, and Storia does not provide legal, expert or consulting services: it is software. On an AS 4000 contract in Perth or elsewhere in Western Australia, start with the WA section below: cl 34 sets the clocks, and s 16 of the WA Security of Payment Act can disapply a time bar on contracts from 1 August 2022.

§ 01

Who does what, and when you need each

AdviserThe question they answerWhen you usually need oneWhat they cannot do
Construction lawyerDoes the contract give the right, was notice valid, which forum, and which escalation and limitation clocks are runningA missed or doubtful notice, a rejected claim, a release you are asked to sign, any step up the dispute ladderProve the critical path or price the delay
Delay or programming expertDid the event delay completion through the critical path, and by how many days, net of float and your own delaysA large or disputed claim, and any claim heading to adjudication, arbitration or courtMake a late notice timely, or create records that were never kept
Quantum expertWhat the delay cost, priced for the weeks the effect was felt, with nothing counted twiceWhen money is claimed on top of timeTurn a time-only event into a money event
Claims consultantOrganising the record, the chronology and the claim document, and sometimes analysis during the worksOften during the works, before anyone is sure there is a disputeBe assumed independent later: in Canada, a fee tied to the result is what signals bias (see the questions below)

The split is this library's working description, not a rule; firms combine the roles in different ways. (Opinion.)

Some claims cannot be proved without the expert. In Amatea/Grimberg JV v Secretary of the Navy1, No. 24-1006 (Fed. Cir., 25 June 2025) (nonprecedential), a US federal constructive acceleration claim failed for want of expert critical-path analysis of the alleged delay drivers (acceleration in the United States).

Check how many experts the forum allows before you retain two. In Alberta's Court of King's Bench a party may call one expert per subject matter unless the court orders otherwise, so separate schedule and quantum experts may need leave (Alberta arbitration and forum). Quebec allows one expert report per discipline unless the court authorises more (Quebec vs common-law Canada). In Australia, the library draws a directional lesson from a case it could not verify: qualify each expert in their own discipline, delay or quantum (records and expert evidence in Australia).

§ 02

When to call: before the notice clock runs out

Do not hold a notice back while you look for an expert or a lawyer: the clock runs whether or not anyone has been engaged. A valid notice can be short, provided it identifies the event, states the entitlement claimed, arrives in time and reaches the person the contract names. Across the decisions in this library, notice is the cheapest element of a claim to get right and the one on which entitlement is most often lost. In Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC2 [2022] DIFC CA 016, a DIFC decision on the FIDIC 1999 Red Book, persuasive but not binding elsewhere, the contractor lost its extension of time although the employer had caused 306 of the 325 days of delay. The delay notice templates give letters for AS 4000, FIDIC 2017 and CCDC 2.

FormThe clock, as the library states itRead
FIDIC 2017 SC 20.2.128 days from when you became aware, or should have, as published commentary summarises itNotice and time bars
CCDC 2 – 2020 GC 6.5.410 Working Days from the commencement of the delay, not from awarenessCanada, Ontario
AS 4000-1997 cl 34.2 and 34.3A delay notice promptly, then a written claim within 28 calendar days of when you should reasonably have become aware of the causation, as secondary summaries give itAustralia
AIA A201–2017 §15.1.3.121 days from the event or first recognition, whichever is later; a Claim goes by certified or registered mail or courier (§1.6.2)United States
NEC4 ECC cl 61.3 and JCT 2024NEC4: 8 weeks from awareness, a hard bar with one exception. JCT 2024: "forthwith", and on the printed wording probably not a condition precedent (the library's inference)England and Wales

Form-default positions. Amendment to notice clauses is normal on major projects, and the executed contract governs.

If the deadline has already passed, the library's working rule is to serve the notice now, say it is late and why, and take advice (readiness checklist).

On an AS 4000 contract in Western Australia

Principals commonly amend cl 34 (a survey the library cites found the EOT clause amended in 76% of contracts; its full publication was not located), so start from the executed contract, then check which edition it is built on: AS 4000:2025 superseded AS 4000-1997 in 2025, and the library has not read the 2025 text. On the 1997 form the clocks are those in the table above. The 2025 edition reportedly softens the notice trigger to "as soon as reasonably practicable", which principals are expected to amend back.

Western Australia is one of two Australian jurisdictions where a statute can disapply an EOT time bar. On contracts for WA construction work entered on or after 1 August 2022, s 16 of the Building and Construction Industry (Security of Payment) Act 2021 (WA) lets an adjudicator, court, arbitrator or expert determiner declare a notice-based time bar of no effect for a particular entitlement, where compliance was not reasonably possible or would be unreasonably onerous. The Australian notice page, last reviewed 26 September 2026, records no decision applying it (AustLII searched to about June 2026). Also raise with a lawyer the Superintendent's duty to exercise any unilateral power to extend honestly and impartially (extension of time in Australia). Australian standard forms predominantly route disputes to arbitration, so check the executed dispute clause before you brief anyone (records and expert evidence in Australia).

When to bring the delay expert in

Early. The how-to guide's advice for a large or disputed claim: bring in a delay analyst while the records can still be improved. The records a project keeps decide which delay analysis methods it can run, and that set closes long before anyone knows there is a dispute (records and evidence). An expert briefed while the works are live can still change what gets recorded: statused updates, native files, a narrative for every logic change. (Inference.)

After the event, the SCL Protocol (paragraph 11.8) recommends agreeing the method with the other side before significant work starts; failing to consult might count on costs (delay analysis methods compared).

§ 03

What to have ready

An expert's first days are usually spent finding and dating documents. (Opinion.) Hand them over already found and dated.

ItemWhy it matters
The executed contract, with every amendment and the particular or special conditionsThe amended clause decides the claim, not the printed form
The baseline and every schedule update, as native files, with narratives and the acceptance correspondenceA PDF programme cannot be interrogated for logic, constraints or float, so it supports no CPM-based method
Notices and correspondence, in date order, with proof of serviceProves notice and when the event occurred. Notice must come from the party claiming
RFI and submittal logs, dated on both sidesResponse time is how design-caused delay is proved
Directions, instructions and change orders, including any release wordingA signed release can settle the delay you meant to claim
Daily reports, site diaries and manpower returnsThey fix when the impact began. Record what was prevented, not only what was done
Meeting minutes and monthly reportsThe contemporaneous narrative
Cost records by periodMoney is priced for the weeks the effect was felt
Your dated chronology, one record reference per entry, and a list of what is missingLets the expert test the facts instead of searching for them

The item-by-item version is the EOT claim readiness checklist. In White Constructions [2019] NSWSC 1166 both parties' delay experts were rejected, and the site diary recorded what was done, not what was prevented and why (records and expert evidence in Australia).

§ 04

What to ask an expert before you engage them

Rules on an expert's duties differ by forum, and most courts and tribunals expect expert opinion to be independent of the party that pays for it. (Opinion.)

§ 05

What you can do yourself first

Much of the preparation is project administration, not expert work, and you can do it while you arrange advice. (Opinion.)

  1. Read the executed contract and pull the extension of time, notice, programme and dispute clauses onto one page (how to write an EOT claim, step 1).
  2. Serve the notice, and any separate money notice the contract requires.
  3. Run groups 1 to 3 of the readiness checklist the week the delay starts.
  4. Build the chronology: date-ordered facts, each tied to a record reference, with argument kept out.
  5. List your own delays in the same window. The other side will (concurrent delay).
  6. Do not sign away the delay. Read change orders and payment releases for full-and-final wording (change order releases).
§ 06

Where Storia fits

Storia does the finding and dating described above. It reads the record where it lives, in Aconex, SharePoint, Outlook and Primavera P6, reads every page with scans included, and "holds the moved activity against the documents that caused it, and writes the delay report" (Schedule Intelligence). From that record it dates each event, cites its page, and assembles an editable claim narrative with labelled exhibits, "ready for your expert and counsel" (Claims and Dispute Resolution). It does not give legal advice or decide entitlement, and it does not replace your expert or lawyer: their opinion is what the claim rests on. To see the draft on your own project, book a demo.

§ 07

Frequently asked questions

Do I need a lawyer or a delay expert?

They answer different questions: a lawyer, whether the contract gives the right, whether the notice was valid and where the claim will be decided; a delay expert, whether the event delayed completion through the critical path, and by how many days. A missed notice or a release is a lawyer's question first; a disputed number of days is an expert's. Many disputed claims need both. (Opinion.)

When should I bring in an EOT claims expert?

On a large or disputed claim, while the works are still running and the records can still be improved. Serve any notice that is due in the meantime: in Panther the contractor lost its extension of time on notice alone.

Can the consultant who helped us during the project be our expert?

In Canada, prior work on the project did not make the expert biased in Walsh v TTC; a fee tied to the claim's success is what signals bias. Elsewhere, check the forum's independence rules with your lawyer first.

I have an AS 4000 contract in Perth. What should I check before calling a lawyer?

The executed cl 34 and its amendments; which edition of AS 4000 the contract is built on; whether the delay notice and, on the 1997 form, the 28-day written claim went in on time; and whether the contract is for WA construction work entered on or after 1 August 2022, when WA's s 16 began to apply. Bring the notices, Superintendent's directions and programme updates.

Can I do the delay analysis myself?

For a small claim during the works you can prepare one while you take advice, and a simple analysis on clean records beats a sophisticated one on reconstructed schedules. (Opinion.) For a large or disputed claim, or anything heading to a tribunal, the analysis is expert work, and some claims fail without it.

Notes

Sources and authorities

8 cited
  1. 1
    Amatea/Grimberg JV v Secretary of the NavyNo. 24-1006 (Fed. Cir., 25 June 2025) (nonprecedential), US Court of Appeals for the Federal Circuit

    A constructive acceleration claim failed because there was no expert critical-path analysis of the alleged delay drivers. A Contracting Officer's grant of a time extension and release of liquidated damages does not establish excusable delay for the contractor's own affirmative claim.

    Justia

  2. 2
    Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC[2022] DIFC CA 016 (judgment 12 May 2023), DIFC Court of Appeal

    The contractor lost its extension of time on notice grounds despite the employer having caused 306 of the 325 days of delay. A valid notice may be short and to the point, provided it identifies the event, states the entitlement claimed, arrives within the 28 days and reaches the Engineer.

    DIFC Courts

  3. 3
    White Burgess Langille Inman v Abbott and Haliburton Co Ltd2015 SCC 23, Supreme Court of Canada

    Expert independence, impartiality and the absence of bias are a threshold admissibility question at the qualification stage, not merely a matter of weight. The expert's duty is to give "fair, objective, and non-partisan opinion evidence". The threshold is low: an expert is excluded only where unable or unwilling to comply, and residual concerns go to weight.

    Chercher sur CanLII

  4. 4
    Walsh Construction Company of Canada v Toronto Transit Commission2024 ONSC 2782, Ontario Superior Court of Justice

    Required a clear and rational expert opinion based on contemporaneous records, tolerating reasoned departures from AACE RP 29R-03. A bias challenge to the contractor's expert failed despite the expert's retention during the project; the decisive factor was whether compensation was tied to the success of the claim. A critique-only defence left the court with a single opinion on quantum.

    Chercher sur CanLII

  5. 5
    Arbitration Act (British Columbia)SBC 2020, c 2, s 35

    An expert appointed by one or more parties or by the arbitral tribunal has a duty to assist the tribunal and is not to be an advocate for any party, and must certify in any report that the expert is aware of that duty, has made the report in conformity with it, and will testify in conformity with it.

    Chercher sur CanLII

  6. 6
    Thomas Barnes & Sons plc (in administration) v Blackburn with Darwen Borough Council[2022] EWHC 2598 (TCC), Technology and Construction Court

    At [110]: "it would be wrong to proceed on the basis that, because the SCL Protocol identifies six commonly used methods of delay analysis, an expert is only allowed to choose one such method". A manifestly inappropriate method, or a material unexplained departure from the stated method, goes to the weight of the expert's opinion.

    Find Case Law

  7. 7
    Makita (Australia) Pty Ltd v Sprowles[2001] NSWCA 305, (2001) 52 NSWLR 705, NSW Court of Appeal

    Sets four requirements for admissible expert opinion: the expert's specialised knowledge must be identified, the opinion must be wholly or substantially based on it, the facts and assumptions must be stated, and the reasoning must be exposed, showing how the specialised knowledge applies to the facts to produce the opinion.

    Chercher sur AustLII

  8. 8
    Chartered Institute of Arbitrators, Guideline on the Use of AI in ArbitrationMarch 2025, updated September 2025

    Article 7 requires disclosure where AI use may affect the evidence or the outcome, extends expressly to party-appointed experts at Article 7.3, and permits adverse inferences and costs consequences for non-disclosure.

    Guideline

General information, not legal advice. Reviewed 10 nov. 2026. Spotted an error? info@storiatechnologies.com

Newsletter · monthly

The notice brief

One email a month on claims, notices and the cases that decided them.

One email a month. Unsubscribe in one click. We never share your address.

The notice briefIssue 01 · sample

This month: three notice clocks and their judgments.

  1. 01
    Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
  2. 02
    Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
  3. 03
    Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou…

Each issue links to the full articles in the Storia Library.

Avant d'engager un expert en réclamations de prolongation · Storia