Ontario
Browse1
Articles28
- Extension of timeA contractual instrument that moves the completion date because the works were delayed by an event that was not the contractor's risk, relieving liability for late-completion damages. Whether the same event also pays for the…Reviewed Oct 13, 2026
- Concurrent delayConcurrent delay is where an employer-risk event and a contractor-risk event both drive the same period of critical overrun. It is settled law nowhere. On one four-week fact pattern the answer runs from four weeks of time and no…Reviewed Oct 13, 2026
- Notice and time barsA notice clause is a time bar where the contract makes the extension of time conditional on serving notice within a stated period. Under FIDIC 2017 Sub-Clause 20.2.1 and NEC4 clause 61.3 failure forfeits entitlement outright.…Reviewed Oct 13, 2026
- Delay analysis methods compared: which one your records can supportA delay analysis method is the technique used to prove that a qualifying event delayed completion. The SCL Delay and Disruption Protocol, 2nd Edition (February 2017) tabulates six commonly used methods at paragraph 11.5: impacted…Reviewed Oct 13, 2026
- Prolongation and delay costsAn extension of time and compensation are separate gateways: winning the time does not win the money. Prolongation cost is assessed for the period when the effect of the employer risk event was actually felt, not the overrun at…Reviewed Aug 7, 2026
- Records and evidence for an EOT claimThe records a project keeps decide which delay analysis methods it can run, and that set closes long before anyone knows there is a dispute. The SCL Delay and Disruption Protocol, 2nd Edition (February 2017) names six record…Reviewed Oct 13, 2026
- Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay, the work, and that you claim the time. AS 4000 wants a prompt cl 34.2 delay notice, then a written cl 34.3 claim within 28 days of…Reviewed Oct 13, 2026
- How to write an EOT claim, step by stepAn extension of time claim succeeds when it proves, on the contract's own terms and inside its deadlines, four things: a qualifying cause of delay that was not the contractor's risk, that it delayed completion and not merely…Reviewed Oct 13, 2026
- EOT claim checklist: is your extension of time claim ready to submit?An extension of time claim is ready when a stranger to the project could check every assertion in it against a dated record. That means seven things are in place: the contract basis, a notice served in time to the right person,…Reviewed Oct 13, 2026
- Extension of time in CanadaCanadian delay and extension-of-time law is almost entirely common law and contract. No province or territory has a statute addressing construction delay as such. On procedure Canada is close to England and strict, on remedy it…Reviewed Sep 10, 2026
- Delay regimes by Canadian province: what changes at the borderNo Canadian province or territory has a statute addressing construction delay as such, so delay law is common law and contract everywhere. What changes at the border is the machinery around the claim: whether a limitation period…Reviewed Sep 8, 2026
- Notice and time bars in CanadaCanadian courts enforce construction notice clauses as conditions precedent, and the owner need not prove prejudice. Under CCDC 2 – 2020 GC 6.5.4 the contractor has 10 Working Days from the commencement of the delay not from its…Reviewed Sep 10, 2026
- Concurrent delay in CanadaCanadian courts treat delays as concurrent where delays to co-critical and co-controlling activities overlap, and they apportion time and money alike. On remedy that is closer to the United States than to England, which awards a…Reviewed Oct 13, 2026
- Liquidated damages and the penalty rule in CanadaCanada has not adopted Cavendish Square v Makdessi. A delay liquidated damages clause is enforceable only if the rate is a genuine pre-estimate of loss, and is separately vulnerable to an unconscionability challenge. Where the…Reviewed Sep 8, 2026
- Prevention principle and time at large in CanadaIn Canada an owner that has prevented the contractor from completing on time cannot insist on liquidated damages, and where no extension is granted the completion date can fall away. Perini Pacific is the anchor, but the domestic…Reviewed Sep 10, 2026
- Prolongation and delay costs in CanadaCanadian law compensates delay through two routes: the contract's own reimbursement clause and damages for breach. Extended site overhead, unabsorbed head-office overhead, equipment standby and acceleration are all recoverable in…Reviewed Sep 8, 2026
- Extension of time in OntarioOntario is the only Canadian jurisdiction where an extension of time is adjudicable, and the only one where a commercial contract may lawfully shorten or exclude a limitation period. Both turn on the contract date. A delay claim…Reviewed Sep 10, 2026
- Ontario delay claim clocksOntario runs five independent clocks on a delay claim: contractual notice, adjudication, lien, holdback and limitation. Each has a different trigger, a different character in law and a different consequence for being missed, and…Reviewed Sep 10, 2026
- Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is gone, and the owner need not prove prejudice. Content counts as much as timing. An insufficient claim submission is treated as no notice…Reviewed Sep 10, 2026
- Prompt payment and adjudication in OntarioSince 1 January 2026 Ontario is the only Canadian jurisdiction where an extension of time can be adjudicated. And only as an ancillary head, only where reasonably necessary to a money determination, not on P3 projects, and not on…Reviewed Sep 10, 2026
- Limitation periods and claim accrual in OntarioOntario gives a delay claim two years from discovery under the Limitations Act, 2002, with a fifteen-year long-stop. Uniquely in Canada, section 22 lets commercial parties to a business agreement extend, shorten, suspend or…Reviewed Aug 8, 2026
- Liens, holdback and security for a delay claim in OntarioAn Ontario construction lien secures a delay claim only in part. The line is price versus damages: extended-duration equipment and extra labour caused by owner default are lienable. Overhead, lost profit on other jobs and general…Reviewed Sep 10, 2026
- VariationsA change to the contract scope, instructed under the contract's own change power, valued by the contract's pricing machinery. Whether an item is a variation is a question of contract construction, not of fairness, and proving it…Reviewed Oct 13, 2026
- What counts as a variationA variation is a change to the design, quality or quantity of the works as defined by the contract documents, instructed under the contract's change mechanism. Whether an item qualifies is a question of construing the contract,…Reviewed Oct 13, 2026
- Written instruction and waiverA variation is compensable only if instructed, in writing, by the named person, before the cut-off. Whether an unwritten instruction can still be paid for depends entirely on the regime: England enforces the formality, Australia…Reviewed Oct 13, 2026
- Constructive and deemed variationsConstructive change is a United States doctrine: work beyond the contract requirements, ordered expressly or impliedly by the government. No doctrine of that name exists elsewhere: England, Canada, Australia and FIDIC use deemed…Reviewed Oct 13, 2026
- Valuation and the pricing ladderAlmost every construction contract values a variation by climbing a ladder (contract rates, then adjusted rates, then a fair valuation, then daywork) and a party may not skip a rung because it prefers the answer further up. NEC4…Reviewed Sep 26, 2026
- Change order releases and reservation of rightsElement 5 of the variation claim, and the one with no extension-of-time analogue: the impact claim you meant to bring at the end has already been released by the change orders you signed along the way. Impact claims die in signed…Reviewed Oct 6, 2026
The notice brief
One email a month on claims, notices and the cases that decided them.
The notice briefIssue 01 · sample
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Delay notice templates for AS 4000, FIDIC 2017 and CCDC 2A delay notice puts one fact on the record in time: that something has delayed, or will delay,…
Each issue links to the full articles in the Storia Library.