Colombie-Britannique
Browse1
Articles33
- Prolongation de délaiUn instrument contractuel qui déplace la date d'achèvement parce que les travaux ont été retardés par un événement qui ne relevait pas du risque de l'entrepreneur, le libérant de sa responsabilité pour les dommages d'achèvement…Reviewed 13 oct. 2026
- Retards concomitantsIl y a retard concomitant lorsqu'un événement relevant du risque du maître de l'ouvrage et un événement relevant du risque de l'entrepreneur causent tous deux la même période de dépassement critique. Ce point n'est réglé nulle…Reviewed 13 oct. 2026
- Notice and time barsA notice clause is a time bar where the contract makes the extension of time conditional on serving notice within a stated period. Under FIDIC 2017 Sub-Clause 20.2.1 and NEC4 clause 61.3 failure forfeits entitlement outright.…Reviewed 13 oct. 2026
- Méthodes d'analyse de retard comparées : laquelle vos documents peuvent étayerUne méthode d'analyse de retard est la technique employée pour prouver qu'un événement ouvrant droit a retardé l'achèvement. Le SCL Delay and Disruption Protocol, 2nd Edition (February 2017) présente sous forme de tableau six…Reviewed 13 oct. 2026
- Prolongation and delay costsAn extension of time and compensation are separate gateways: winning the time does not win the money. Prolongation cost is assessed for the period when the effect of the employer risk event was actually felt, not the overrun at…Reviewed 7 août 2026
- Records and evidence for an EOT claimThe records a project keeps decide which delay analysis methods it can run, and that set closes long before anyone knows there is a dispute. The SCL Delay and Disruption Protocol, 2nd Edition (February 2017) names six record…Reviewed 13 oct. 2026
- Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou retardera, les travaux, et que vous réclamez le délai. L'AS 4000 exige un avis de retard sans délai au titre de la cl 34.2, puis une demande…Reviewed 13 oct. 2026
- Comment rédiger une demande de prolongation de délaiUne demande de prolongation de délai aboutit lorsqu'elle prouve, selon les termes mêmes du contrat et dans ses délais, quatre choses : une cause de retard ouvrant droit qui ne relevait pas du risque de l'entrepreneur, le fait…Reviewed 13 oct. 2026
- Liste de contrôle avant une demande de prolongationUne demande de prolongation de délai est prête lorsqu'une personne étrangère au projet pourrait vérifier chacune de ses affirmations au regard d'une pièce datée. Cela suppose que sept éléments soient en place : le fondement…Reviewed 13 oct. 2026
- Prolongation de délai au CanadaLe droit canadien du retard et de la prolongation de délai relève presque entièrement de la common law et du contrat. Aucune province ni aucun territoire n'a de loi traitant du retard de construction comme tel. Sur la procédure,…Reviewed 10 sept. 2026
- Delay regimes by Canadian province: what changes at the borderNo Canadian province or territory has a statute addressing construction delay as such, so delay law is common law and contract everywhere. What changes at the border is the machinery around the claim: whether a limitation period…Reviewed 8 sept. 2026
- Notice and time bars in CanadaCanadian courts enforce construction notice clauses as conditions precedent, and the owner need not prove prejudice. Under CCDC 2 – 2020 GC 6.5.4 the contractor has 10 Working Days from the commencement of the delay not from its…Reviewed 10 sept. 2026
- Concurrent delay in CanadaCanadian courts treat delays as concurrent where delays to co-critical and co-controlling activities overlap, and they apportion time and money alike. On remedy that is closer to the United States than to England, which awards a…Reviewed 13 oct. 2026
- Liquidated damages and the penalty rule in CanadaCanada has not adopted Cavendish Square v Makdessi. A delay liquidated damages clause is enforceable only if the rate is a genuine pre-estimate of loss, and is separately vulnerable to an unconscionability challenge. Where the…Reviewed 8 sept. 2026
- Prevention principle and time at large in CanadaIn Canada an owner that has prevented the contractor from completing on time cannot insist on liquidated damages, and where no extension is granted the completion date can fall away. Perini Pacific is the anchor, but the domestic…Reviewed 10 sept. 2026
- Prolongation and delay costs in CanadaCanadian law compensates delay through two routes: the contract's own reimbursement clause and damages for breach. Extended site overhead, unabsorbed head-office overhead, equipment standby and acceleration are all recoverable in…Reviewed 8 sept. 2026
- Extension of time in British ColumbiaBritish Columbia is the birthplace of Canadian delay doctrine and the jurisdiction that has done least with it since. It supplies the national anchors on prevention, notice, acceleration and total cost, then goes quiet for twenty…Reviewed 8 sept. 2026
- British Columbia Delay Claim ClocksEvery deadline that can end a British Columbia delay claim, grouped by the clock it belongs to and by its character in law, contractual condition precedent, statutory precondition, limitation period, or condition of a security…Reviewed 8 sept. 2026
- Notice and Time Bars in British ColumbiaBritish Columbia enforces construction notice provisions purposively rather than mechanically. A BC court asks what the clause was for and whether the owner was actually deprived of it, in substance and in good time. That is…Reviewed 10 sept. 2026
- Prevention and Time at Large in British ColumbiaBritish Columbia supplies both Canadian prevention anchors and the strongest candidate for a Canadian judgment actually finding time at large, Hawl-Mac (1985). That proposition contradicts most national commentary, rests on a…Reviewed 8 sept. 2026
- Concurrent Delay and Apportionment in British ColumbiaBritish Columbia apportions concurrent delay as a damages exercise rather than an entitlement exercise. There is no Malmaison, no dominant cause and no first-in-time in BC. The province has both precise day-by-day apportionment…Reviewed 8 sept. 2026
- Prolongation, Acceleration and Quantum in British ColumbiaBritish Columbia's delay-quantum philosophy is actual cost, proved. Head-office overhead runs on Shore & Horwitz rather than a formula, total cost is available as a last resort through the W A Stephenson gateway, and the province…Reviewed 8 sept. 2026
- Limitation Periods and Claim Accrual in British ColumbiaIn British Columbia the deadline that kills a delay claim is almost always a Builders Lien Act deadline, not a Limitation Act one. The Act gives two years from discovery, the lien, holdback and trust clocks expire far sooner, and…Reviewed 8 sept. 2026
- Liens, Holdback and the Statutory Trust in British ColumbiaBritish Columbia's Builders Lien Act creates two trusts, a 10% holdback, a 45-day lien filing period and a separate lien on the holdback fund. Together they, not the Limitation Act, set the deadlines that decide whether a delayed…Reviewed 8 sept. 2026
- Prompt Payment and Adjudication, British ColumbiaBritish Columbia has no prompt payment and no construction adjudication. The Construction Prompt Payment Act received Royal Assent on 27 November 2025 and is not in force as at 8 September 2026, no adjudication authority has been…Reviewed 8 sept. 2026
- Arbitration, Experts and Forum in British ColumbiaBritish Columbia decides most large delay disputes in confidential arbitration, and the Arbitration Act permits appeal only on a question of law. Because contract interpretation is mixed fact and law, an arbitrator's reading of…Reviewed 8 sept. 2026
- Public Works and Infrastructure, British ColumbiaBritish Columbia's public construction owners allocate delay differently from one another and from CCDC 2. The MOTI Major Works General Conditions give time but not money for abnormal weather, the Site C contract excludes flood…Reviewed 8 sept. 2026
- AvenantsUne modification de l'étendue contractuelle des travaux, ordonnée en vertu du pouvoir de modification que le contrat prévoit lui-même, et évaluée par la mécanique de prix que le contrat fournit. Savoir si un poste est un avenant…Reviewed 13 oct. 2026
- What counts as a variationA variation is a change to the design, quality or quantity of the works as defined by the contract documents, instructed under the contract's change mechanism. Whether an item qualifies is a question of construing the contract,…Reviewed 13 oct. 2026
- Written instruction and waiverA variation is compensable only if instructed, in writing, by the named person, before the cut-off. Whether an unwritten instruction can still be paid for depends entirely on the regime: England enforces the formality, Australia…Reviewed 13 oct. 2026
- Constructive and deemed variationsConstructive change is a United States doctrine: work beyond the contract requirements, ordered expressly or impliedly by the government. No doctrine of that name exists elsewhere: England, Canada, Australia and FIDIC use deemed…Reviewed 13 oct. 2026
- Valuation and the pricing ladderAlmost every construction contract values a variation by climbing a ladder (contract rates, then adjusted rates, then a fair valuation, then daywork) and a party may not skip a rung because it prefers the answer further up. NEC4…Reviewed 26 sept. 2026
- Change order releases and reservation of rightsElement 5 of the variation claim, and the one with no extension-of-time analogue: the impact claim you meant to bring at the end has already been released by the change orders you signed along the way. Impact claims die in signed…Reviewed 6 oct. 2026
The notice brief
One email a month on claims, notices and the cases that decided them.
The notice briefIssue 01 · sample
This month: three notice clocks and their judgments.
- 01Notice and time bars in OntarioIn Ontario a contractual notice of delay is a condition precedent: miss it and the claim is…
- 02Notice and time bars in AustraliaAustralian EOT time bars are enforceable conditions precedent everywhere, subject to the…
- 03Modèles d'avis de retard pour l'AS 4000, le FIDIC 2017 et le CCDC 2Un avis de retard consigne un seul fait, en temps utile : qu'un événement a retardé, ou…
Each issue links to the full articles in the Storia Library.